CN108069215A - Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method - Google Patents
Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method Download PDFInfo
- Publication number
- CN108069215A CN108069215A CN201611040587.4A CN201611040587A CN108069215A CN 108069215 A CN108069215 A CN 108069215A CN 201611040587 A CN201611040587 A CN 201611040587A CN 108069215 A CN108069215 A CN 108069215A
- Authority
- CN
- China
- Prior art keywords
- earth
- stone
- container
- cubic metre
- track
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004575 stone Substances 0.000 title claims abstract description 130
- 230000005540 biological transmission Effects 0.000 title claims abstract description 15
- 238000000034 method Methods 0.000 title claims abstract description 12
- 239000004576 sand Substances 0.000 claims abstract description 30
- 238000009434 installation Methods 0.000 claims 2
- 239000007788 liquid Substances 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 4
- 239000002689 soil Substances 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000004806 packaging method and process Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000004140 cleaning Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G35/00—Mechanical conveyors not otherwise provided for
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G65/00—Loading or unloading
- B65G65/23—Devices for tilting and emptying of containers
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G67/00—Loading or unloading vehicles
- B65G67/02—Loading or unloading land vehicles
- B65G67/24—Unloading land vehicles
- B65G67/30—Unloading land vehicles using transportable tipping apparatus
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G67/00—Loading or unloading vehicles
- B65G67/60—Loading or unloading ships
- B65G67/606—Loading or unloading ships using devices specially adapted for bulk material
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65G—TRANSPORT OR STORAGE DEVICES, e.g. CONVEYORS FOR LOADING OR TIPPING, SHOP CONVEYOR SYSTEMS OR PNEUMATIC TUBE CONVEYORS
- B65G2201/00—Indexing codes relating to handling devices, e.g. conveyors, characterised by the type of product or load being conveyed or handled
- B65G2201/04—Bulk
- B65G2201/045—Sand, soil and mineral ore
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Aviation & Aerospace Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention belongs to cubic metre of earth and stone transmission technique field more particularly to cubic metre of earth and stone transmitting devices and cubic metre of earth and stone transmission method.Container equipped with the cubic metre of earth and stone is transported to a cubic meter transmitting device by container car.In cubic metre of earth and stone transmitting device, the initial position of delivery vehicle is in the front end of track, turning support is articulated on delivery vehicle, container equipped with the cubic metre of earth and stone is transferred on turning support by the first transfer device, container is sent to the end of track by delivery vehicle, turning support overturning is made the cubic metre of earth and stone in container be poured into sand mud ship by driving mechanism, and the container that the second transfer device makes to topple over after the cubic metre of earth and stone leaves turning support, so as to which the cubic metre of earth and stone in building site is transferred to sand mud ship.Cubic metre of earth and stone transport vehicle is travelled in building site, and container car travels on off-site, and cubic metre of earth and stone transport vehicle delivers the cubic metre of earth and stone in building site, the cubic metre of earth and stone is loaded into the container of container car again, building site isolates with road, need not also be cleaned when container car sets out at building site, easy to operate, road keeps clean.
Description
Technical field
The invention belongs to cubic metre of earth and stone transmission technique field more particularly to cubic metre of earth and stone transmitting devices and cubic metre of earth and stone transmission method.
Background technology
Effectively to administer the phenomenon that city cubic metre of earth and stone transport vehicle pollutes road, the environment of neat and tidy is safeguarded, policy is clear and definite
Regulation building site vehicle forbids road on band soil.Specifically, cubic metre of earth and stone transport vehicle is when sailing out of construction site, it is necessary to take measures clear
Car body is swept, wheel is cleaned, forbids tire belt Ni Shang roads.Work will can just be left through over cleaning by carrying the haulage vehicle of the cubic metre of earth and stone
Ground, then travel to precalculated position, this is troublesome in poeration.At this point, the cubic metre of earth and stone will be by sand mud ship water transport to other positions, in existing skill
There is no the technology that the cubic metre of earth and stone on haulage vehicle is transmitted to sand mud ship in art, this is a urgent problem to be solved.
The content of the invention
It is an object of the invention to provide a kind of cubic meter of transmitting devices, it is intended to which solution is difficult to pass through the cubic metre of earth and stone in building site
Existing transport vehicle is transferred to the technical issues of sand mud ship.
The present invention is achieved in that a cubic meter transmitting device, including:
For containing the container of the cubic metre of earth and stone;
Its end is located at the track of the top of a sand mud ship;
Run on the delivery vehicle on the track;
It is articulated on the delivery vehicle and is used to support the turning support of the container;
For the container that the cubic metre of earth and stone is housed to be transferred to the first transfer device of the turning support;
It is installed on the delivery vehicle and for being turned over described in the driving when the delivery vehicle runs on the end of the track
The frame that asks is overturn so that the cubic metre of earth and stone in the container is poured into the driving mechanism in the sand mud ship;And
For making to topple over the second transfer device that the container after the cubic metre of earth and stone leaves the turning support.
Further, the container includes bottom plate and several coaming plates arranged on the edge of the bottom plate, the bottom plate
An accommodating chamber is enclosed with the coaming plate, the end that the coaming plate is away from the bottom plate is enclosed a receiving port, described
Coaming plate offers the mouth that comes down in torrents, and a dodge gate is equipped at the mouth that comes down in torrents.
Further, further include that the mounting bracket component of the track is installed and be used to support the mounting bracket component
Support leg.
Further, the mounting bracket component includes the first mounting bracket, the branch arranged on the end of first mounting bracket
Bar, be articulated in first mounting bracket end the second mounting bracket and be connected to the strut and second mounting bracket it
Between anchor chain, the track includes the first rail for being installed on first mounting bracket and is installed on second mounting bracket
Second rail, the end of first rail are concordant with second mounting bracket in first mounting bracket with the front end of second rail
When it is adjacent.
Further, the delivery vehicle includes vehicle frame, is installed on the vehicle frame and rolls and be installed on the track
Wheel and for driving the actuating unit that the vehicle frame is moved along the track, the vehicle frame has toward before the track
The first end at end and the second end toward the end of the track.
Further, the turning support includes the supporting rack for being used to support the container, and support frame as described above has pivot
The pivot joint end for being connected to the second end and the free end compared with the pivot joint end, the turning support, which further includes, to be set
In the linking arm of the free end and for the container to be fixedly connected on to the locking mechanism on support frame as described above.
Further, the driving mechanism is hydraulic cylinder, and the hydraulic cylinder includes cylinder barrel and is slidably mounted on the cylinder barrel
Piston rod, the side wall of the cylinder barrel is articulated in the linking arm, and the end of the piston rod is articulated in the first end.
Further, jack is offered on the side wall of the container, the locking mechanism includes being installed on the support
Linear drives part on frame and by the mobile bolt to be plugged in the jack of linear drives part driving.
Another object of the present invention is to provide a kind of cubic meter of transmission method, comprise the following steps:
Above-mentioned cubic metre of earth and stone transmitting device is provided, the delivery vehicle is located at the front end of the track, provides sand mud ship, in building site
It the cubic metre of earth and stone transport vehicle of interior traveling and is travelled and in off-site for delivering the container car of the container;
The cubic metre of earth and stone in building site is transferred on the cubic metre of earth and stone transport vehicle, the cubic metre of earth and stone transport vehicle is by the cubic metre of earth and stone thereon
It is transferred in the container of the container car, the container car leaves building site and travelled again to cubic metre of earth and stone transmission dress by road
Put place;
The container equipped with the cubic metre of earth and stone is transferred to the turning support by first transfer device;The delivery vehicle
Operation to the end of the track, the driving mechanism drives the turning support to overturn the cubic metre of earth and stone so that in the container
It is poured into the sand mud ship, the driving mechanism drives the turning support to reset;Second transfer device makes to topple over soil
The container after the cubic meter of stone leaves the turning support and is transferred on the container car, and the delivery vehicle is run to the rail
The front end in road.
Further, the track has the trunkful position arranged successively, empty van position and topples over position, first transfer device
Arranged on the trunkful position, second transfer device is arranged on the empty van position, and the container car is divided into delivering equipped with native stone
The trunkful container car of the container of side and the empty van container car for delivering the empty container, the both sides of the track
Region is respectively formed the trunkful parking stall for being useful for parking the trunkful container car and the sky for parking the empty van container car
Case parking stall.
The present invention has the technical effect that the container equipped with the cubic metre of earth and stone is transported to native stone by container car compared with the prior art
Square transmitting device.In cubic metre of earth and stone transmitting device, the initial position of delivery vehicle is articulated with overturning on the front end of track, delivery vehicle
Container equipped with the cubic metre of earth and stone is transferred on turning support by bracket, the first transfer device, and container is sent to rail by delivery vehicle
Turning support overturning is made the cubic metre of earth and stone in container be poured into sand mud ship by the end in road, driving mechanism, and the second transfer device makes
Topple over the container after the cubic metre of earth and stone and leave turning support, so as to which the cubic metre of earth and stone in building site is transferred to sand mud ship.
In cubic metre of earth and stone transmission method, cubic metre of earth and stone transport vehicle is travelled in building site, and container car travels on off-site, the cubic metre of earth and stone
Transport vehicle delivers the cubic metre of earth and stone in building site, then the cubic metre of earth and stone is loaded into the container of container car, and building site isolates with road, container car
It travels on road and finally reaches harbour, so as to which the container equipped with the cubic metre of earth and stone is transported to a cubic meter transmitting device, the cubic metre of earth and stone passes
The cubic metre of earth and stone is transmitted on sand mud ship by defeated device.It need not also be cleaned when container car sets out at building site, easy to operate, road is kept
Totally.
Description of the drawings
Fig. 1 is the assembling schematic diagram of cubic metre of earth and stone transmitting device provided in an embodiment of the present invention;
Fig. 2 is the dress of container, delivery vehicle, turning support and the driving mechanism applied in the cubic metre of earth and stone transmitting device of Fig. 1
With schematic diagram;
Fig. 3 is the operating diagram of the cubic metre of earth and stone transmitting device of Fig. 1;
Fig. 4 is the operating diagram of another angle of the cubic metre of earth and stone transmitting device of Fig. 3.
Specific embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, it is right
The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and
It is not used in the restriction present invention.
It please refers to Fig.1 to Fig.4, cubic metre of earth and stone transmitting device 100 provided in an embodiment of the present invention, including being used to contain the cubic metre of earth and stone
200 container 10;Its end is located at the track 20 of the top of a sand mud ship 102;Run on the delivery vehicle 30 on track 20;Pivot
It is connected on delivery vehicle 30 and is used to support the turning support 40 of container 10;For 10 turns of the container of the cubic metre of earth and stone 200 will to be equipped with
Move to the first transfer device 50 of turning support 40;It is installed on delivery vehicle 30 and for running on track 20 in delivery vehicle 30
During end turning support 40 is driven to overturn so that the cubic metre of earth and stone 200 in container 10 is poured into the driving mechanism in sand mud ship 102
60;And for making to topple over the second transfer device 70 that the container 10 after the cubic metre of earth and stone 200 leaves turning support 40.
Container 10 equipped with the cubic metre of earth and stone 200 is transported to cubic meter transmitting device 100 by container car 101.It is passed in the cubic metre of earth and stone
In defeated device 100, the initial position of delivery vehicle 30 is articulated with turning support 40 on the front end of track 20, delivery vehicle 30, and first
Container 10 equipped with the cubic metre of earth and stone 200 is transferred on turning support 40 by transfer device 50, and delivery vehicle 30 transmits container 10
To the end of track 20, the overturning of turning support 40 is made the cubic metre of earth and stone 200 in container 10 be poured into sand mud ship by driving mechanism 60
102, the container 10 that the second transfer device 70 makes to topple over after the cubic metre of earth and stone 200 leaves turning support 40, so as to by the native stone in building site
Side 200 is transferred to sand mud ship 102.
The cubic metre of earth and stone 200 can be remaining mud, dregs or sandstone.Track 20 is heavy rail, can bear larger power.
Further, container 10 include bottom plate 11 and several coaming plates 12 arranged on the edge of bottom plate 11, bottom plate 11 with
Coaming plate 12 is enclosed an accommodating chamber 13, and the end that coaming plate 12 is away from bottom plate 11 is enclosed a receiving port 14, and coaming plate 12 is opened
Equipped with the mouth 15 that comes down in torrents, a dodge gate 16 is equipped at the mouth 15 that comes down in torrents.The container 10 easily makes, and structural strength is good, dodge gate 16
Folding is arranged at the mouth 15 that comes down in torrents.The mouth 15 that comes down in torrents is arranged on the end of container 10, and dodge gate 16 is articulated in the top edge of tilt port.
When driving mechanism 60 drives the overturning of turning support 40, dodge gate 16 can automatically open, and the cubic metre of earth and stone 200 in container 10 can come down in torrents
It goes out.
Further, further include for attachment rail 20 mounting bracket component 80 and be used to support the branch of mounting bracket component 80
Support leg 85.Mounting bracket component 80 may be employed I-steel, Fang Tong, channel steel or other section bars and make, and mounting bracket component 80 is for branch
Support track 20.Two rows of support legs 85 are disposed with along the length direction of mounting bracket component 80, support leg 85 makes mounting bracket component 80 inclined
Predetermined altitude from the ground.Preferably, support leg 85 is hydraulic leg, can provide enough support forces, reliable operation.
Further, mounting bracket component 80 includes the first mounting bracket 81, the strut arranged on the end of the first mounting bracket 81
82nd, it is articulated in the second mounting bracket 83 of the end of the first mounting bracket 81 and is connected between 82 and second mounting bracket 83 of strut
Anchor chain 84, track 20 include the first rail 21 being installed on the first mounting bracket 81 and the second rail being installed on the second mounting bracket 83
22, the front end of the end of the first rail 21 and the second rail 22 is adjacent when the first mounting bracket 81 is concordant with the second mounting bracket 83.
In use, anchor chain 84 tenses, the first mounting bracket 81 is concordant with the second mounting bracket 83, before the end of the first rail 21 and the second rail 22
It holds adjacent, is travelled for delivery vehicle 30.When not in use, rotate at the second mounting bracket 83 to strut 82, this is compact-sized, uses
It is convenient.
Further, the end of track 20 is equipped with the limited block 86 that delivery vehicle 30 is avoided to plunge off the tracks 20, allows transmission
Vehicle 30 is limited in 20 end of track when travelling to the end of track 20, driving mechanism 60 drives turning support 40 to overturn with the soil that comes down in torrents
The cubic meter of stone 200.Specifically, limited block 86 is arranged on the end of the second mounting bracket 83.
Further, delivery vehicle 30 includes vehicle frame 31, is installed on vehicle frame 31 and rolls the wheel being installed on track 20
32 and for driving the actuating unit (not shown) that vehicle frame 31 is moved along track 20, vehicle frame 31 has toward the front end of track 20
First end 31a and the second end 31b toward the end of track 20.The structure easily makes, convenient for running on track
To transmit container 10 on 20.Actuating unit can be the motor or other actuating units that driving wheel 32 rotates.
Further, turning support 40 includes the supporting rack 41 for being used to support container 10, and supporting rack 41, which has, to be articulated in
The pivot joint end 41a and the free end 41b compared with pivot joint end 41a of the second end 31b, turning support 40, which further includes, to be arranged on
The linking arm 42 of free end 41b and for container 10 to be fixedly connected on to the locking mechanism (not shown) on supporting rack 41.
Container 10 is fixed on turning support 40 by locking mechanism, and driving mechanism 60 drives turning support 40 to overturn or reset, so as to
Realize the overturning or reset of container 10.Preferably, supporting rack 41 is distributed with linking arm 42 in L fonts, which is easily worked,
Structural strength is good.
Further, driving mechanism 60 is hydraulic cylinder, and hydraulic cylinder includes cylinder barrel 61 and is slidably mounted on the piston of cylinder barrel 61
Bar 62, the side wall of cylinder barrel 61 are articulated in linking arm 42, and the end of piston rod 62 is articulated in first end 31a.The structure easily fills
With with operation.When piston rod 62 gradually stretches out in cylinder barrel 61, turning support 40 is gradually overturn, the cubic metre of earth and stone in container 10
200 come down in torrents in sand mud ship 102.When piston rod 62 gradually bounces back to cylinder barrel 61, turning support 40 is gradually reset on vehicle frame 31.
Preferably, the pivot joint axis between the pivot joint end 41a of supporting rack 41 and the second end 31b of vehicle frame 31, cylinder barrel 61 are with being connected
Pivot joint axis between arm 42, the end of piston rod 62 are parallel with the pivot joint axis between the first end 31a of vehicle frame 31, should
Structure is easily assembled, can allow driving mechanism 60 drive turning support 40 overturn so that the cubic metre of earth and stone 200 in container 10 come down in torrents in
Sand mud ship 102.
Further, jack (not shown) is offered on the side wall of container 10, locking mechanism includes being installed on supporting rack
It linear drives part (not shown) on 41 and is driven by linear drives part mobile to be plugged in the bolt (not shown) in jack.It should
Structure is easily worked and controls.Specifically, four ends of 10 bottom plate 11 of container are respectively equipped with a jack, are set on supporting rack 41
There are four linear drives part, four linear drives parts correspond driving bolts and are inserted in four jacks, so as to by container
10 are fixed on turning support 40.The corresponding bolt of linear drives part driving resets, you can container 10 is located away from turning support
40.Preferably, linear drives part is hydraulic cylinder.
Further, the first transfer device 50 and the second transfer device 70 are gantry crane.By taking the first transfer device 50 as an example
Illustrate, the first transfer device 50 includes being installed on the supporting rod 51 on mounting bracket component 80, the spandrel girder on supporting rod 51
It 52 and is slidably mounted on along the length direction of spandrel girder 52 on spandrel girder 52 and for capturing the hanger 53 of container 10 and being used for
The straight line driving mechanism (not shown) that hanger 53 is driven to move, the first transfer device 50 will completely be equipped with the cubic metre of earth and stone on container car 101
200 container 10 is transferred on the turning support 40 of the delivery vehicle 30 of 20 front end of track.The knot of second transfer device 70
Structure can refer to the first transfer device 50, and empty container 10 is transferred on container car 101a by the second transfer device 70.It can manage
Xie Di, the first transfer device 50 and the second transfer device 70 can also be other transmitting mechanicals.
Further, cubic metre of earth and stone transmitting device 100 further includes the operating room 91 that operator controls each dynamical element.Operation
Room 91 and the front end of track 20 are oppositely arranged, and member easy to operation observes all parts working condition.Cubic metre of earth and stone transmitting device 100 is also
Generating set 92 including being used to provide stand-by power supply is providing electric energy without electric situation.
It please refers to Fig.1 to Fig.4, cubic metre of earth and stone transmission method provided in an embodiment of the present invention comprises the following steps:It provides above-mentioned
Cubic metre of earth and stone transmitting device 100, delivery vehicle 30 are located at the front end of track 20, the cubic metre of earth and stone for provide sand mud ship 102, travelling in building site
It transport vehicle (not shown) and is travelled and in off-site for delivering the container car 101 of container 10.The cubic metre of earth and stone transport vehicle can be
Dump truck, excavator or other cubic meters of transport vehicles.
The cubic metre of earth and stone 200 in building site is transferred on cubic meter transport vehicle, cubic metre of earth and stone transport vehicle is by 200 turns of the cubic metre of earth and stone thereon
It moves in the container 10 of container car 101, container car 101 leaves building site and travelled again to cubic metre of earth and stone transmitting device 100 by road
Place.Preferably, building site is equipped with enclosure wall, and to distinguish inside and outside building site, cubic metre of earth and stone transport vehicle is travelled in building site, and container car 101 travels
In off-site, the cubic metre of earth and stone 200 is transferred in the container 10 of container car 101 by cubic metre of earth and stone transport vehicle, and building site isolates with road.
Container 10 equipped with the cubic metre of earth and stone 200 is transferred to turning support 40 by the first transfer device 50;Delivery vehicle 30 is run
To the end of track 20, driving mechanism 60 drives turning support 40 to overturn so that the cubic metre of earth and stone 200 in container 10 is poured into sand
In mud ship 102, driving mechanism 60 drives turning support 40 to reset;Second transfer device 70 makes to topple over the packaging after the cubic metre of earth and stone 200
Case 10 leaves turning support 40 and is transferred on container car 101, and delivery vehicle 30 is run to the front end of track 20.The step is repeated,
The cubic metre of earth and stone 200 in building site is transmitted to sand mud ship 102 by cubic metre of earth and stone transport vehicle, container car 101, cubic metre of earth and stone transmitting device 100.
In cubic metre of earth and stone transmission method, cubic metre of earth and stone transport vehicle is travelled in building site, and container car 101 travels on off-site, soil
Cubic meter of stone transport vehicle delivers the cubic metre of earth and stone 200 in building site, then the cubic metre of earth and stone 200 is loaded into the container 10 of container car 101, building site with
Road is isolated, and container car 101 travels on road and finally reaches harbour, so as to which the container 10 equipped with the cubic metre of earth and stone 200 be transported to
The cubic metre of earth and stone 200 is transmitted on sand mud ship 102 by cubic metre of earth and stone transmitting device 100, cubic metre of earth and stone transmitting device 100.Container car 101 is in work
Being located in when setting out need not also clean, easy to operate, and road keeps clean.
Further, track 20 has the trunkful position 20a, the empty van position 20b that arrange successively and topples over a 20c, the first transfer
Mechanism 50 is arranged on trunkful position 20a, and the second transfer device 70 is arranged on empty van position 20b, and container car is divided into delivering equipped with the cubic metre of earth and stone
Container 10 trunkful container car 101 and empty van container car 101a for delivering empty container 10, the both sides of track 20
Region, which is respectively formed, is useful for the trunkful parking stall for parking trunkful container car 101 and the empty van for parking empty van container car 101a
Parking stall.For the program convenient for arrangement two groups of container cars 101,101a, the fully loaded trunkful goods for having the cubic metre of earth and stone 200 is parked on trunkful parking stall
The empty van container car 101a of empty container 10, two groups of container cars 101,101a and the cubic metre of earth and stone are parked in cabinet vehicle 101, empty van parking stall
Cooperating, work efficiency are high simultaneously for transmitting device 100.
Further, container car 101,101a are the container car that can load two containers 10.First transfer device 50 will
Container 10 close to the trunkful container car 101 of trunkful position 20a is moved on the turning support 40 of delivery vehicle 30.Then, it is full
Case container car 101 is moved another container 10 close to trunkful position 20a.Meanwhile delivery vehicle 30 is from the front end of track 20
Start to move.Delivery vehicle 30 is run to the end of track 20, and driving mechanism 60 drives turning support 40 to overturn so that container 10
The interior cubic metre of earth and stone 200 is poured into sand mud ship 102, and driving mechanism 60 drives turning support 40 to reset.Then, delivery vehicle 30 moves
To empty van position 20b, the container 10 that the second transfer device 70 makes to topple over after the cubic metre of earth and stone 200 leaves turning support 40 and is transferred to sky
On case container car 101a, delivery vehicle 30 is run to the front end of track 20.First transfer device 50 is by 101 another collection of trunkful container car
Vanning 10 is moved on the turning support 40 of delivery vehicle 30, and the cubic metre of earth and stone 200 of the container 10 is poured into sand mud ship 102.Together
When, empty van container car 101a movements are by another room close to empty van position 20b.Delivery vehicle 30 is moved to empty van position 20b, the
Two transfer devices 70 make container 10 be transferred on empty van container car 101a.Thus by two casees cubic metres of earth and stone 200 by trunkful container car
101 container 10 is transmitted to sand mud ship 102, and two empty containers 10 are transferred on empty van container car 101a, with again
It is secondary that the cubic metre of earth and stone 200 in building site is transferred to harbour.It is to be appreciated that container car 101,101a are that can load one or more packagings
The container car of case 10, situation are similar.
Further, sand mud ship 102 can configure multiple cubic meters of transmitting devices 100 and container car 101,101a, make simultaneously
Industry improves efficiency of transmission.
The foregoing is merely a prefered embodiment of the invention, is not intended to limit the invention, it is all the present invention spirit and
All any modification, equivalent and improvement made within principle etc., should all be included in the protection scope of the present invention.
Claims (10)
1. cubic meter transmitting device, which is characterized in that including:
For containing the container of the cubic metre of earth and stone;
Its end is located at the track of the top of a sand mud ship;
Run on the delivery vehicle on the track;
It is articulated on the delivery vehicle and is used to support the turning support of the container;
For the container that the cubic metre of earth and stone is housed to be transferred to the first transfer device of the turning support;
It is installed on the delivery vehicle and for driving the overturning support when the delivery vehicle runs on the end of the track
Frame is overturn so that the cubic metre of earth and stone in the container is poured into the driving mechanism in the sand mud ship;And
For making to topple over the second transfer device that the container after the cubic metre of earth and stone leaves the turning support.
2. as described in claim 1 cubic meter of transmitting device, which is characterized in that the container includes bottom plate and arranged on described
Several coaming plates of the edge of bottom plate, the bottom plate are enclosed an accommodating chamber with the coaming plate, and the coaming plate is away from described
The end of bottom plate is enclosed a receiving port, and the coaming plate offers the mouth that comes down in torrents, a dodge gate is equipped at the mouth that comes down in torrents.
3. as described in claim 1 cubic meter of transmitting device, which is characterized in that further include to install the installation of the track
Frame component and the support leg for being used to support the mounting bracket component.
4. as claimed in claim 3 cubic meter of transmitting device, which is characterized in that the mounting bracket component includes the first installation
Frame, arranged on the end of first mounting bracket strut, be articulated in first mounting bracket end the second mounting bracket
And the anchor chain between the strut and second mounting bracket is connected to, the track includes being installed on first mounting bracket
The first rail and the second rail for being installed on second mounting bracket, the front end of the end of first rail and second rail in
First mounting bracket is adjacent when concordant with second mounting bracket.
5. such as Claims 1-4 any one of them cubic metre of earth and stone transmitting device, which is characterized in that the delivery vehicle include vehicle frame,
It is installed on the vehicle frame and rolls the wheel that is installed on the track and for the vehicle frame to be driven to be moved along the track
Actuating unit, the vehicle frame has toward the first end of the front end of the track and toward the end of the track
The second end.
6. as claimed in claim 5 cubic meter of transmitting device, which is characterized in that the turning support includes being used to support described
The supporting rack of container, support frame as described above, which has, is articulated in the pivot joint end of the second end and compared with the pivot joint end
Free end, the turning support further include arranged on the free end linking arm and for by the container fix connect
The locking mechanism being connected on support frame as described above.
7. as claimed in claim 6 cubic meter of transmitting device, which is characterized in that the driving mechanism be hydraulic cylinder, the liquid
Cylinder pressure includes cylinder barrel and is slidably mounted on the piston rod of the cylinder barrel, and the side wall of the cylinder barrel is articulated in the linking arm, described
The end of piston rod is articulated in the first end.
8. cubic metre of earth and stone transmitting device as claimed in claim 6, which is characterized in that offered on the side wall of the container slotting
Hole, the locking mechanism include being installed on linear drives part on support frame as described above and by the linear drives part drive it is mobile with
The bolt being plugged in the jack.
9. cubic meter transmission method, which is characterized in that comprise the following steps:
Such as claim 1 to 8 any one of them cubic metre of earth and stone transmitting device is provided, before the delivery vehicle is located at the track
End, the cubic metre of earth and stone transport vehicle that provide sand mud ship, travels in building site and travels and in off-site for delivering the container
Container car;
The cubic metre of earth and stone in building site is transferred on the cubic metre of earth and stone transport vehicle, the cubic metre of earth and stone transport vehicle shifts the cubic metre of earth and stone thereon
To the container of the container car, the container car leaves building site and is travelled again to the cubic metre of earth and stone transmitting device by road
Place;
The container equipped with the cubic metre of earth and stone is transferred to the turning support by first transfer device;The delivery vehicle operation
To the end of the track, the driving mechanism drives the turning support overturning so that the cubic metre of earth and stone in the container is toppled over
In in the sand mud ship, the driving mechanism drives the turning support to reset;Second transfer device makes to topple over the cubic metre of earth and stone
The container afterwards leaves the turning support and is transferred on the container car, and the delivery vehicle is run to the track
Front end.
10. as claimed in claim 9 cubic meter of transmission method, which is characterized in that the track has the trunkful arranged successively
Position, empty van position are arranged on the trunkful position with toppling over position, first transfer device, and second transfer device is arranged on the empty van
Position, the container car are divided into delivering the trunkful container car for the container that the cubic metre of earth and stone is housed and for delivering described in sky
The empty van container car of container, the two side areas of the track are respectively formed the trunkful for being useful for parking the trunkful container car and stop
Parking stall and the empty van parking stall for parking the empty van container car.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611040587.4A CN108069215A (en) | 2016-11-11 | 2016-11-11 | Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611040587.4A CN108069215A (en) | 2016-11-11 | 2016-11-11 | Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108069215A true CN108069215A (en) | 2018-05-25 |
Family
ID=62161587
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611040587.4A Pending CN108069215A (en) | 2016-11-11 | 2016-11-11 | Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108069215A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110342282A (en) * | 2019-08-02 | 2019-10-18 | 徐州易尚饰家装饰工程有限责任公司 | A kind of automobile-used easing gear of transport |
CN113460720A (en) * | 2021-06-24 | 2021-10-01 | 中车齐齐哈尔车辆有限公司 | Unloading device and unloading method |
Citations (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060018735A1 (en) * | 2004-06-24 | 2006-01-26 | Paceco Corp. | Cargo container scanning crane |
US20070110551A1 (en) * | 2003-09-16 | 2007-05-17 | Barry Leonard D | Container dump truck and oblique transfer system |
US20070217894A1 (en) * | 2006-03-15 | 2007-09-20 | Hong Tian | Container transportation carrier and container transportation system |
CN201472216U (en) * | 2009-05-12 | 2010-05-19 | 王东文 | Automatic pulling device for rear board of self-dump truck |
US20120087768A1 (en) * | 2005-09-28 | 2012-04-12 | Barry Leonard D | Go-between container transfer and system |
CN202368434U (en) * | 2011-12-19 | 2012-08-08 | 天津立中合金集团有限公司 | Turnover device for rear cover of carriage of dumper |
CN102774588A (en) * | 2012-08-13 | 2012-11-14 | 广西新波环保科技有限责任公司 | Garbage briquetting equipment |
CN202829009U (en) * | 2012-07-25 | 2013-03-27 | 中交天航南方交通建设有限公司 | Rotary unloading type barging platform |
CN203306770U (en) * | 2013-05-10 | 2013-11-27 | 上海宝冶集团有限公司 | Bulk material unloading platform for wharf |
EP2810822A2 (en) * | 2013-06-04 | 2014-12-10 | Fliegl jun., Josef | Transfer trolley |
CN104724518A (en) * | 2015-03-04 | 2015-06-24 | 东南大学 | High-pile wharf bulk cargo self-unloading platform |
CN104875662A (en) * | 2014-02-27 | 2015-09-02 | 江苏卡威专用汽车制造有限公司 | Multipurpose side-turnover dumper |
CN105129274A (en) * | 2015-07-17 | 2015-12-09 | 武汉电力设备厂 | Lump coal boxing system and method |
CN105217331A (en) * | 2014-06-03 | 2016-01-06 | 王同建 | A kind of mobile container positioning machine |
CN205240797U (en) * | 2015-12-28 | 2016-05-18 | 王飞 | Pier material shipment equipment for tipper |
CN105645133A (en) * | 2016-01-25 | 2016-06-08 | 海宁三易科技有限公司 | Automatic locating and unloading device |
CN206203297U (en) * | 2016-11-11 | 2017-05-31 | 深圳市兴德诚投资有限公司 | Cubic metre of earth and stone transmitting device |
-
2016
- 2016-11-11 CN CN201611040587.4A patent/CN108069215A/en active Pending
Patent Citations (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070110551A1 (en) * | 2003-09-16 | 2007-05-17 | Barry Leonard D | Container dump truck and oblique transfer system |
US20060018735A1 (en) * | 2004-06-24 | 2006-01-26 | Paceco Corp. | Cargo container scanning crane |
US20120087768A1 (en) * | 2005-09-28 | 2012-04-12 | Barry Leonard D | Go-between container transfer and system |
US20070217894A1 (en) * | 2006-03-15 | 2007-09-20 | Hong Tian | Container transportation carrier and container transportation system |
CN201472216U (en) * | 2009-05-12 | 2010-05-19 | 王东文 | Automatic pulling device for rear board of self-dump truck |
CN202368434U (en) * | 2011-12-19 | 2012-08-08 | 天津立中合金集团有限公司 | Turnover device for rear cover of carriage of dumper |
CN202829009U (en) * | 2012-07-25 | 2013-03-27 | 中交天航南方交通建设有限公司 | Rotary unloading type barging platform |
CN102774588A (en) * | 2012-08-13 | 2012-11-14 | 广西新波环保科技有限责任公司 | Garbage briquetting equipment |
CN203306770U (en) * | 2013-05-10 | 2013-11-27 | 上海宝冶集团有限公司 | Bulk material unloading platform for wharf |
EP2810822A2 (en) * | 2013-06-04 | 2014-12-10 | Fliegl jun., Josef | Transfer trolley |
CN104875662A (en) * | 2014-02-27 | 2015-09-02 | 江苏卡威专用汽车制造有限公司 | Multipurpose side-turnover dumper |
CN105217331A (en) * | 2014-06-03 | 2016-01-06 | 王同建 | A kind of mobile container positioning machine |
CN104724518A (en) * | 2015-03-04 | 2015-06-24 | 东南大学 | High-pile wharf bulk cargo self-unloading platform |
CN105129274A (en) * | 2015-07-17 | 2015-12-09 | 武汉电力设备厂 | Lump coal boxing system and method |
CN205240797U (en) * | 2015-12-28 | 2016-05-18 | 王飞 | Pier material shipment equipment for tipper |
CN105645133A (en) * | 2016-01-25 | 2016-06-08 | 海宁三易科技有限公司 | Automatic locating and unloading device |
CN206203297U (en) * | 2016-11-11 | 2017-05-31 | 深圳市兴德诚投资有限公司 | Cubic metre of earth and stone transmitting device |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110342282A (en) * | 2019-08-02 | 2019-10-18 | 徐州易尚饰家装饰工程有限责任公司 | A kind of automobile-used easing gear of transport |
CN110342282B (en) * | 2019-08-02 | 2020-12-15 | 徐州易尚饰家装饰工程有限责任公司 | Unloading device for transport vehicle |
CN113460720A (en) * | 2021-06-24 | 2021-10-01 | 中车齐齐哈尔车辆有限公司 | Unloading device and unloading method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206203297U (en) | Cubic metre of earth and stone transmitting device | |
CN106927371B (en) | Descaling gantry crane | |
CN107128847A (en) | A kind of multi-functional side fork Ju Shi Operation Vans | |
CN104343263A (en) | Rotary lifting type three-dimensional garage | |
CN102433853B (en) | Trailer type sand elimination machine for railway | |
CN103374974B (en) | Sludge clearing grab bucket vehicle | |
CN108069215A (en) | Cubic metre of earth and stone transmitting device and cubic metre of earth and stone transmission method | |
CN102041757B (en) | Working method of self-propelled mortar vehicle | |
CN105089311A (en) | Arc hanging type vertical garage | |
CN202968018U (en) | Folding type installation forklift | |
CN109707407B (en) | Mortar tank truck, auxiliary transfer device of mortar tank truck and tunnel construction transportation method | |
CN206537986U (en) | Cubic metre of earth and stone transmitting device | |
CN203558748U (en) | Wheeled crane | |
CN107604776B (en) | Convenient beam transverse crane for railway track construction | |
CN206091438U (en) | Flexible rod -type stereo garage is dodged to two -layer vertical nothing | |
CN206091437U (en) | Flexible rod -type stereo garage is dodged to two -layer horizontal nothing | |
CN101187266B (en) | Automobile transverse transportation device | |
CN108341284A (en) | Cubic metre of earth and stone transmitting device | |
CN201614655U (en) | Drainage box culvert dredging device | |
CN102502418A (en) | Special equipment and method for turning container door | |
CN101323269A (en) | Tank-carrying hydraulic automatic discharging vehicle | |
CN203062217U (en) | Lifting mounting vehicle of fully-mechanized coal mining equipment | |
CN106192624B (en) | The nonstandard section of track of railway bridge erecting machine single line operation storing unit and method nearby | |
CN215104960U (en) | Self-walking self-retracting guardrail special installation vehicle | |
CN201002929Y (en) | Small-sized road maintenance machinery hoisting transporting vehicle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20180628 Address after: 518000 -1, 88 Xinghai Road, Nanshan District, Shenzhen, Guangdong. Applicant after: Chen Wei Address before: 518000 -1, 88 Xinghai Road, Nanshan District, Shenzhen, Guangdong. Applicant before: Shenzhen City Hing Tak Investment Company Limited |