CN108049495A - 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法 - Google Patents

全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法 Download PDF

Info

Publication number
CN108049495A
CN108049495A CN201711386620.3A CN201711386620A CN108049495A CN 108049495 A CN108049495 A CN 108049495A CN 201711386620 A CN201711386620 A CN 201711386620A CN 108049495 A CN108049495 A CN 108049495A
Authority
CN
China
Prior art keywords
layers
escalator
staircase
construction
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711386620.3A
Other languages
English (en)
Inventor
于义翔
郭世江
胡利
樊开威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Ke Zhu Construction Management Co Ltd
Foshan Vanke Properties Development Co Ltd
Original Assignee
Guangdong Ke Zhu Construction Management Co Ltd
Foshan Vanke Properties Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Ke Zhu Construction Management Co Ltd, Foshan Vanke Properties Development Co Ltd filed Critical Guangdong Ke Zhu Construction Management Co Ltd
Priority to CN201711386620.3A priority Critical patent/CN108049495A/zh
Publication of CN108049495A publication Critical patent/CN108049495A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

本发明公开了一种全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,包括以下步骤:N层电梯间、楼梯间主体结构层;N‑1层电梯间、楼梯间拆模施工层;N‑2层电梯间、楼梯间支顶止水层;N‑5层电梯间、楼梯间管线安装层;N‑6层电梯间、楼梯间天花腻子层;N‑8层电梯间地砖铺贴层;N‑9层电梯间砌筑层;N‑10层电梯间门施工层;N‑11层楼梯间施工层。该全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,保证了全现浇外墙高层住宅电梯间、楼梯间施工作业,各专业工种都能穿插连续作业,既缩短了施工总工期,提高了工效,又提升了项目工程管理的精细化水平。

Description

全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法
技术领域
本发明涉及建筑施工领域,尤其涉及一种全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法。
背景技术
传统施工组织推进现场作业一般采用,第一步主体施工完成,第二步外立面作业,第三步外架拆除,第四步装修作业进场,至今在工程中仍在沿用。
传统施工组织形式基本为从单一时间轴上进行现场组织,即同一时间无法同时进行多项工作安排,从而使得时间效用未能最大化被利用。
传统施工组织多为传统建造工艺(木模、砌筑、脚手架、湿作业等)下的形式,无法实现现行采用新型建造体系(铝模、智能爬架、预制墙板、全现浇外墙、干法施工等)带来的提效的优势。
发明内容
本发明的目的在于提供一种全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,该全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,保证了全现浇外墙高层住宅电梯间、楼梯间施工作业,各专业工种都能穿插连续作业,既缩短了施工总工期,提高了工效,又提升了项目工程管理的精细化水平。
其技术方案如下:
全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,包括以下步骤:
N层电梯间、楼梯间主体结构层:高层住宅的电梯间、楼梯间主体结构从第1层逐层向顶层进行电梯间、楼梯间主体结构施工作业;
N-1层电梯间、楼梯间拆模施工层:当电梯间、楼梯间主体结构在进行第N层施工作业时,第N-1层的电梯间、楼梯间主体结构施工作业已完成,第N-1层进行穿插电梯间、楼梯间拆模施工作业;
N-2层电梯间、楼梯间支顶止水层:当第N-1层进行电梯间、楼梯间拆模施工作业时,第N-2层的电梯间、楼梯间拆模施工作业已完成,第N-2层进行穿插电梯间、楼梯间支顶止水施工作业;
N-5层电梯间、楼梯间管线安装层:当第N-2层进行电梯间、楼梯间支顶止水施工作业时,第N-5层的电梯间、楼梯间支顶止水施工作业已完成,第N-5层进行穿插电梯间、楼梯间管线安装施工作业;
N-6层电梯间、楼梯间天花腻子层:当第N-5层进行电梯间、楼梯间管线安装施工作业时,第N-6层的电梯间、楼梯间管线安装施工作业已完成,第N-6层进行穿插电梯间、楼梯间天花腻子施工作业;
N-8层电梯间地砖铺贴层:当第N-6层进行电梯间、楼梯间天花腻子施工作业时,第N-8层的电梯间、楼梯间天花腻子施工作业已完成,第N-8层进行穿插电梯间地砖铺贴施工作业;
N-9层电梯间砌筑层:当第N-8层进行电梯间地砖铺贴施工作业时,第N-9层的电梯间地砖铺贴施工作业已完成,第N-9层进行穿插电梯间砌筑施工作业;
N-10层电梯间门施工层:当第N-9层进行电梯间砌筑施工作业时,第N-10层的电梯间砌筑施工作业已完成,第N-10层进行穿插电梯间门施工作业;
N-11层楼梯间施工层:当第N-10层进行电梯间门施工作业时,第N-11层的电梯间门施工作业已完成,第N-11层进行穿插楼梯间施工作业。
所述N-5层电梯间、楼梯间管线安装层包括N-5层电梯间管线安装,所述N-5层电梯间管线安装包括以下步骤:
N-5层电梯间墙板嵌缝修补;
N-5层电梯间墙板线盒及线管安装;
N-5层电梯间消防设备布线;
N-5层电梯间消防通风口百叶安装;
N-5层电梯间照明、插座穿引线;
N-5层电梯间天花吊杆龙骨安装。
所述N-5层电梯间、楼梯间管线安装层还包括N-5层楼梯间管线安装,所述N-5层楼梯间管线安装包括以下步骤:
N-5层楼梯间墙板嵌缝修补;
N-5层楼梯间墙板线盒及线管安装;
N-5层楼梯间消防设备布线;
N-5层楼梯间照明、插座穿引线。
所述N-5层电梯间、楼梯间管线安装层还包括N-5层管道井管线安装,所述N-5层管道井管线安装包括以下步骤:
N-5层管道井墙板嵌缝修补;
N-5层管道井墙板线盒及线管安装;
N-5层管道井强弱电线槽安装;
N-5层管道井给排水管安装。
所述N-6层电梯间、楼梯间天花腻子层包括N-6层电梯间天花腻子、N-6层安装楼梯间门框,所述N-6层电梯间天花腻子包括以下步骤:
N-6层电梯间防火门框安装、塞缝;
N-6层电梯间照明、插座穿线及调试;
N-6层电梯间消火栓安装;
N-6层电梯间天花吊顶封板;
N-6层电梯间天花装修一、二遍腻子层。
所述N-6层安装楼梯间门框包括以下步骤:
N-6层楼梯间防火门框安装、塞缝;
N-6层楼梯间照明、插座穿线及调试。
所述N-8层电梯间地砖铺贴包括以下步骤:
N-8层电梯间地砖施工;
N-8层地砖成品保护。
所述N-9层电梯间砌筑包括以下步骤:
N-9层电梯井钢筋切割,放中线;
N-9层电梯井搭架轨道安装。
所述N-10层电梯间门施工层包括以下步骤:N-10层电梯间电梯门、门框安装;
N-10层电梯间墙砖及门边收口。
所述N-11层楼梯间施工层包括以下步骤:
N-11层楼梯间拆除临卫往主体结构楼层上移;N-11层楼梯间防滑砖及砂浆找平;
N-11层楼梯间天花、墙面第一遍腻子;
N-11层楼梯间天花、墙面第二遍腻子;
N-11层楼梯间腻子打磨、验收。
需要说明的是:
前述“N”代表电梯间、楼梯间主体结构施工作业层;
“N-1层电梯间、楼梯间拆模施工层”表示当高层住宅的电梯间、楼梯间主体结构在进行第2层施工作业时,2-1层电梯间、楼梯间拆模施工层表示为:1层电梯间、楼梯间拆模施工层,即表示高层住宅的第1层进行电梯间、楼梯间拆模施工作业;
“N-5层电梯间、楼梯间管线安装施工层”表示当高层住宅的电梯间、楼梯间主体结构在进行第6层施工作业时,6-5层电梯间、楼梯间管线安装施工层表示为:1层电梯间、楼梯间管线安装施工层,即表示高层住宅的第1层进行电梯间、楼梯间管线安装施工作业。
下面对本发明的优点或原理进行说明:
1、本全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,细化到每一层需进行穿插施工的工作项;其目的在于明确施工全过程中自下而上的施工工序流水组织和技术要求,既缩短了施工总工期,提高了工效,又提升了项目工程管理的精细化水平;
当高层住宅的电梯间、楼梯间主体结构在进行第N层施工作业时,此时高层住宅第N-1层即可穿插进行电梯间、楼梯间拆模施工作业,高层住宅第N-2层即可穿插进行电梯间、楼梯间支顶止水施工作业,高层住宅第N-5层即可穿插进行电梯间、楼梯间管线安装施工作业,高层住宅第N-6层即可穿插进行电梯间、楼梯间天花腻子施工作业,高层住宅第N-8层即可穿插进行电梯间地砖铺贴施工作业,高层住宅第N-9层即可穿插进行电梯间砌筑施工作业,高层住宅第N-10层即可穿插进行电梯间门施工作业,高层住宅第N-11层即可穿插进行楼梯间施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层电梯间、楼梯间施工,各专业工种都能穿插连续作业,确保高层住宅各楼层全穿插施工作业,缩短了施工总工期,提高了工效;
为实现电梯间、楼梯间穿插施工,该电梯间、楼梯间穿插施工梳理了过程中标志性的节点,便于宏观把控;该电梯间、楼梯间穿插施工相比传统施工组织形式,可操作强,进一步减少了主观误差;
该电梯间、楼梯间穿插施工实现了有效结合铝模、智能爬架、预制墙板、全现浇外墙、干法施工等先进工艺,前瞻性高,为建筑行业创造了附加价值,是行业未来发展的主流。
2、按各施工作业内容进一步细分流水段,优化劳动力安排,降低对单一工种劳动力数量的突击性需求,做到科学、有序、连贯,保证各专业工种都能穿插连续作业。
具体实施方式
下面对本发明的实施例进行详细说明。
全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,包括以下步骤:
N层电梯间、楼梯间主体结构层:高层住宅的电梯间、楼梯间主体结构从第1层逐层向顶层进行电梯间、楼梯间主体结构施工作业;
N-1层电梯间、楼梯间拆模施工层:当电梯间、楼梯间主体结构在进行第N层施工作业时,第N-1层的电梯间、楼梯间主体结构施工作业已完成,第N-1层进行穿插电梯间、楼梯间拆模施工作业;
N-2层电梯间、楼梯间支顶止水层:当第N-1层进行电梯间、楼梯间拆模施工作业时,第N-2层的电梯间、楼梯间拆模施工作业已完成,第N-2层进行穿插电梯间、楼梯间支顶止水施工作业;
N-5层电梯间、楼梯间管线安装层:当第N-2层进行电梯间、楼梯间支顶止水施工作业时,第N-5层的电梯间、楼梯间支顶止水施工作业已完成,第N-5层进行穿插电梯间、楼梯间管线安装施工作业;
N-6层电梯间、楼梯间天花腻子层:当第N-5层进行电梯间、楼梯间管线安装施工作业时,第N-6层的电梯间、楼梯间管线安装施工作业已完成,第N-6层进行穿插电梯间、楼梯间天花腻子施工作业;
N-8层电梯间地砖铺贴层:当第N-6层进行电梯间、楼梯间天花腻子施工作业时,第N-8层的电梯间、楼梯间天花腻子施工作业已完成,第N-8层进行穿插电梯间地砖铺贴施工作业;
N-9层电梯间砌筑层:当第N-8层进行电梯间地砖铺贴施工作业时,第N-9层的电梯间地砖铺贴施工作业已完成,第N-9层进行穿插电梯间砌筑施工作业;
N-10层电梯间门施工层:当第N-9层进行电梯间砌筑施工作业时,第N-10层的电梯间砌筑施工作业已完成,第N-10层进行穿插电梯间门施工作业;
N-11层楼梯间施工层:当第N-10层进行电梯间门施工作业时,第N-11层的电梯间门施工作业已完成,第N-11层进行穿插楼梯间施工作业。
其中,全现浇外墙高层住宅全穿插施工提效方法,包括以下步骤:
N层主体结构施工层:高层住宅的主体结构从第1层逐层向顶层进行主体结构施工作业;
N-1层拆模施工层:当主体结构在进行第N层施工作业时,第N-1层的主体结构施工作业已完成,第N-1层进行穿插拆模施工作业;
N-2层支顶止水施工层:当第N-1层进行拆模施工作业时,第N-2层的拆模施工作业已完成,第N-2层进行穿插支顶止水施工作业;
N-3层内墙板施工层:当第N-2层进行支顶止水施工作业时,第N-3层的支顶止水施工作业已完成,第N-3层进行穿插内墙板施工作业;
N-4层给排水安装施工层:当第N-3层进行内墙板施工作业时,第N-4层的内墙板施工作业已完成,第N-4层进行穿插给排水安装施工作业;
N-5层管线安装施工层:当第N-4层进行给排水安装施工作业时,第N-5层的给排水安装施工作业已完成,第N-5层进行穿插管线安装施工作业;
N-6层天花腻子施工层:当第N-5层进行管线安装施工作业时,第N-6层的管线安装施工作业已完成,第N-6层进行穿插天花腻子施工作业;
N-7层厨卫墙砖铺贴施工层:当第N-6层进行天花腻子施工作业时,第N-7层的天花腻子施工作业已完成,第N-7层进行穿插厨卫墙砖铺贴施工作业;
N-8层台地砖铺贴施工层:当第N-7层进行厨卫砖铺贴施工作业时,第N-8层的厨卫砖铺贴施工作业已完成,第N-8层进行穿插台地砖铺贴施工作业;
N-9层内墙面第一遍腻子施工层:当第N-8层进行台地砖铺贴施工作业时,第N-9层的台地砖铺贴施工作业已完成,第N-9层进行穿插内墙面第一遍腻子施工作业;
N-10层内墙面第二遍腻子施工层:当第N-9层进行内墙面第一遍腻子施工作业时,第N-10层的内墙面第一遍腻子施工作业已完成,第N-10层进行穿插内墙面第二遍腻子施工作业;
N-11层楼梯间施工层:当第N-10层进行穿插第二遍腻子施工作业时,第N-11层的第二遍腻子施工作业已完成,第N-11层进行穿插楼梯间施工作业;
全现浇外墙高层住宅厨卫穿插施工提效方法,包括以下步骤:
N层厨卫主体结构施工层:高层住宅的厨卫主体结构从第1层逐层向顶层进行厨卫主体结构施工作业;
N-1层厨卫拆模施工层:当厨卫主体结构在进行第N层施工作业时,第N-1层的厨卫主体结构施工作业已完成,第N-1层进行穿插厨卫拆模施工作业;
N-2层厨卫支顶止水施工层:当第N-1层进行厨卫拆模施工作业时,第N-2层的厨卫拆模施工作业已完成,第N-2层进行穿插厨卫支顶止水施工作业;
N-3层厨卫内墙板施工层:当第N-2层进行厨卫支顶止水施工作业时,第N-3层的厨卫支顶止水施工作业已完成,第N-3层进行穿插厨卫内墙板施工作业;
N-4层厨卫给排水安装层:当第N-3层进行厨卫内墙板施工作业时,第N-4层的厨卫内墙板施工作业已完成,第N-4层进行穿插厨卫给排水安装施工作业;
N-5层厨卫管线安装层:当第N-4层进行厨卫给排水安装施工作业时,第N-5层的厨卫给排水安装施工作业已完成,第N-5层进行穿插厨卫管线安装施工作业;
N-6层厨卫天花腻子层:当第N-5层进行厨卫管线安装施工作业时,第N-6层的厨卫管线安装施工作业已完成,第N-6层进行穿插厨卫天花腻子施工作业;
N-7层厨卫墙砖铺贴层:当第N-6层进行厨卫天花腻子施工作业时,第N-7层的厨卫天花腻子施工作业已完成,第N-7层进行穿插厨卫墙砖铺贴施工作业;
N-8层厨卫台地砖铺贴层:当第N-7层进行厨卫墙砖铺贴施工作业时,第N-8层的厨卫墙砖铺贴施工作业已完成,第N-8层进行穿插厨卫台地砖铺贴施工作业;
N-9层厨卫门框基层安装:当第N-8层进行穿插厨卫台地砖铺贴施工作业时,第N-9层的厨卫台地砖铺贴施工作业已完成,第N-9层进行穿插厨卫门框基层安装施工作业;
N-10层厨卫淋浴设备安装:当第N-9层进行厨卫门框基层安装施工作业时,第N-10层的厨卫门框基层安装施工作业已完成,第N-10层进行穿插厨卫淋浴设备安装施工作业;
全现浇外墙高层住宅厅房穿插施工提效方法,包括以下步骤:
N层厅房主体结构层:高层住宅的厅房主体结构从第1层逐层向顶层进行厅房主体结构施工作业;
N-1层厅房拆模施工层:当厅房主体结构在进行第N层施工作业时,第N-1层的厅房主体结构施工作业已完成,第N-1层进行穿插厅房拆模施工作业;
N-2层厅房支顶止水层:当第N-1层进行厅房拆模施工作业时,第N-2层的厅房拆模施工作业已完成,第N-2层进行穿插厅房支顶止水施工作业;
N-3层厅房内墙板施工层:当第N-2层进行厅房支顶止水施工作业时,第N-3层的厅房支顶止水施工作业已完成,第N-3层进行穿插厅房内墙板施工作业;
N-4层厅房给排水安装:当第N-3层进行厅房内墙板施工作业时,第N-4层的厅房内墙板施工作业已完成,第N-4层进行穿插厅房给排水安装施工作业;
N-5层厅房管线安装层:当第N-4层进行厅房给排水安装施工作业时,第N-5层的厅房给排水安装施工作业已完成,第N-5层进行穿插厅房管线安装施工作业;
N-6层厅房天花腻子层:当第N-5层进行厅房管线安装施工作业时,第N-6层的厅房管线安装施工作业已完成,第N-6层进行穿插厅房天花腻子施工作业;
N-8层厅房台地砖铺贴层:当第N-6层进行厅房天花腻子施工作业时,第N-8层的厅房天花腻子施工作业已完成,第N-8层进行穿插厅房台地砖铺贴施工作业;
N-9层厅房内墙面第一遍腻子层:当第N-8层进行厅房台地砖铺贴施工作业时,第N-9层的厅房台地砖铺贴施工作业已完成,第N-9层进行穿插厅房内墙面第一遍腻子施工作业;
N-10层厅房内墙面第二遍腻子层:当第N-9层进行厅房内墙面第一遍腻子施工作业时,第N-10层的厅房内墙面第一遍腻子施工作业已完成,第N-10层进行穿插厅房内墙面第二遍腻子施工作业;
全现浇外墙高层住宅室外穿插施工提效方法,包括以下步骤:
N层室外主体结构施工层:高层住宅的室外主体结构从第1层逐层向顶层进行室外主体结构施工作业;
N-1层室外拆模施工层:当室外主体结构在进行第N层施工作业时,第N-1层的室外主体结构施工作业已完成,第N-1层进行穿插室外拆模施工作业;
N-2层室外支顶止水施工层:当第N-1层进行室外拆模施工作业时,第N-2层的室外拆模施工作业已完成,第N-2层进行穿插室外支顶止水施工作业;
N-3层阳台护栏安装:当第N-2层进行室外支顶止水施工作业时,第N-3层的室外支顶止水施工作业已完成,第N-3层进行穿插阳台护栏安装作业;
N-4层阳台给排水安装:当第N-3层进行阳台护栏安装作业时,第N-4层的阳台护栏安装作业已完成,第N-4层进行穿插阳台给排水安装施工作业;
N-5层阳台管线安装:当第N-4层进行阳台给排水安装施工作业时,第N-5层的阳台给排水安装施工作业已完成,第N-5层进行穿插阳台管线安装施工作业;
N-8层阳台地砖铺贴:当第N-5层进行阳台管线安装施工作业时,第N-8层的阳台管线安装施工作业已完成,第N-8层进行穿插阳台地砖铺贴施工作业;
N层主体结构施工层包括以下步骤:
N层结构放线;
N层墙柱钢筋绑扎;
N层结构拉缝安装;
N层墙柱内水电安装;
N层铝模板安装;
N层梁板钢筋绑扎;
N层砼施工;
N层墙根部水平拉缝安装;
N层结构放线包括以下步骤:
N层结构定位放线;
N层钢筋定位筋焊接;
N层墙根部模板找平;
N层结构拉缝安装包括以下步骤:
N层竖向结构拉缝安装;
N层横向结构拉缝安装;
所述N层铝模板安装包括以下步骤:
N层墙柱铝模拼装;
N层墙柱模板清理、加固调整到位;
N层梁板铝模拼装;
N层梁板模板清理;
N层梁板钢筋绑扎包括以下步骤:
N层梁钢筋绑扎;
N层止水节、底盒预埋;
N层板底筋绑扎;
N层水电管线预埋;
N层板面筋安装;
N层防雷接地;
N层砼施工包括以下步骤:
N层模板表面浇筑前淋水;
N层楼板水平度控制;
N层卫生间结构找坡1%;
N-1层拆模施工层包括以下步骤:
N-1层室外安全防护;
N-1层墙柱模板拆除;
N-1层梁、楼面模板拆除;
N-1层垃圾清理;
N-1层墙柱内侧螺杆洞封堵;
N-1层室外修整;
N-1层结构内墙的实测并标注打磨修补点;
N-1层室外安全防护包括以下步骤:
N-1层室外水平安全兜网设置;
N-1层室外防漏浆遮蔽;
N-1层室外修整包括N-1层阳台修整,N-1层阳台修整包括以下步骤:
N-1层阳台反坎修整;
N-1层阳台结构打磨修整;
N-1层阳台天花修平;
N-1层室外修整还包括N-1层空调板修整,N-1层空调板修整包括以下步骤:
N-1层空调飘板部位打磨;
N-1层空调飘板部位修补;
N-1层室外修整还包括N-1层外窗修整,N-1层外窗修整包括以下步骤:
N-1层窗洞打磨;
N-1层窗洞修补;
N-1层室外修整还包括N-1层外墙面修整,N-1层外墙面修整包括以下步骤:
N-1层外墙螺杆洞封堵;
N-1层外墙墙面实测并标注打磨修补点;
N-1层外墙墙面打磨修补;
N-1层外墙墙面涂料第一遍腻子;
N-1层外墙墙面涂料第二遍腻子;
N-2层支顶止水施工层包括N-2层室内支顶止水层、N-2层阳台止水施工、N-2层空调板止水施工、N-2层外窗止水施工,N-2层室内支顶止水层包括以下步骤:
N-2层结构内墙的打磨;
N-2层结构内墙的修补;
N-2层墙板放线;
N-2层层间止水;
N-2层结构闭水,楼板预留临时供水排水、临电孔接管;
N-2层卫生间反坎电线管接管;
N-2层卫生间防水反坎浇筑;
N-2层卫生间排水管安装;
N-2层卫生间结构闭水;
N-2层卫生间管井墩子浇筑;
N-2层立杆拆除;
N-2层阳台止水施工包括以下步骤:
N-2层阳台给水管预埋安装;
N-2层阳台外墙涂料第一遍腻子;
N-2层阳台排水立管安装;
N-2层阳台临时地漏安装;
N-2层空调板止水施工包括以下步骤:
N-2层空调板立管周边腻子施工;
N-2层空调板内立管安装;
N-2层空调百叶安装;
N-2层新风系统外侧安装;
N-2层外窗止水施工包括以下步骤:
N-2层外窗窗框安装;
N-2层外窗防雷铁片焊接;
N-2层外窗窗框塞缝;
N-2层外窗玻璃、外窗扇安装;
N-3层内墙板施工层包括N-3层墙板安装,N-3层墙板安装包括以下步骤:
N-3层安装内墙板;
N-3层层间止水;
N-3层厨房烟道安装,消防立管安装,临时卫生间安装;
N-3层烟道防水反坎封堵。
N-3层内墙板施工层还包括N-3层阳台护栏安装,N-3层阳台护栏安装包括以下步骤:
N-3层安装栏杆;
N-3层栏杆防雷接地;
N-4层给排水安装施工层包括以下步骤:
N-4层卫生间给排水安装;
N-4层洗漱间给排水安装;
N-4层厨房给排水安装;
N-4层厅房给排水安装;
N-4层阳台给排水安装;
N-4层卫生间给排水安装包括以下步骤:
N-4层卫生间防水反坎;
N-4层卫生间给水管安装;
N-4层卫生间排水横支管安装;
N-4层洗漱间给排水安装包括以下步骤:
N-4层洗漱间给水管安装;
N-4层洗漱间排水横支管安装;
N-4层厨房给排水安装包括以下步骤:
N-4层厨房给水管安装;
N-4层厨房煤气管道安装;
N-4层厅房给排水安装包括以下步骤:
N-4层室内天花水泥腻子;
N-4层客厅给水管安装;
N-4层客厅天花放线;
N-4层阳台给排水安装包括以下步骤:
N-4层阳台天花水泥腻子;
N-4层阳台给水管安装;
N-4层阳台煤气管道安装;
N-5层管线安装施工层包括以下步骤:
N-5层卫生间管线安装;
N-5层洗漱间管线安装;
N-5层厨房管线安装;
N-5层房间管线安装;
N-5层客厅管线安装;
N-5层电梯间管线安装;
N-5层楼梯间管线安装;
N-5层管道井管线安装;
N-5层阳台管线安装;
N-5层卫生间管线安装包括以下步骤:
N-5层卫生间墙板嵌缝修补;
N-5层卫生间墙板线盒及线管安装;
N-5层卫生间隐蔽试水;
N-5层卫生间照明、插座穿引线;
N-5层卫生间天花吊杆;
N-5层洗漱间管线安装包括以下步骤:
N-5层洗漱间墙板嵌缝修补;
N-5层洗漱间墙板线盒及线管安装;
N-5层洗漱间照明、插座穿引线;
N-5层洗漱间天花吊杆龙骨安装;
N-5层厨房管线安装包括以下步骤:
N-5层厨房墙板嵌缝修补;
N-5层厨房墙板线盒及线管安装;
N-5层厨房止回阀安装;
N-5层厨房天花吊杆;
N-5层房间管线安装包括以下步骤:
N-5层房间墙板嵌缝修补;
N-5层房间墙板线盒及线管安装;
N-5层房间照明、插座穿引线;
N-5层客厅管线安装包括以下步骤:
N-5层客厅墙板嵌缝修补;
N-5层客厅墙板线盒及线管安装;
N-5层客厅照明、插座穿引线;
N-5层客厅天花吊杆龙骨安装;
N-5层电梯间管线安装包括以下步骤:
N-5层电梯间墙板嵌缝修补;
N-5层电梯间墙板线盒及线管安装;
N-5层电梯间消防设备布线;
N-5层电梯间消防通风口百叶安装;
N-5层电梯间照明、插座穿引线;
N-5层电梯间天花吊杆龙骨安装。
N-5层楼梯间管线安装包括以下步骤:
N-5层楼梯间墙板嵌缝修补;
N-5层楼梯间墙板线盒及线管安装;
N-5层楼梯间消防设备布线;
N-5层楼梯间照明、插座穿引线;
N-5层管道井管线安装包括以下步骤:
N-5层管道井墙板嵌缝修补;
N-5层管道井墙板线盒及线管安装;
N-5层管道井强弱电线槽安装;
N-5层管道井给排水管安装;
N-5层阳台管线安装包括以下步骤:
N-5层阳台墙板嵌缝修补;
N-5层阳台墙板线盒及线管安装;
N-5层阳台照明、插座穿引线;
N-6层天花腻子施工层包括以下步骤:
N-6层卫生间天花腻子;
N-6层洗漱间天花腻子;
N-6层厨房天花腻子;
N-6层房间天花腻子;
N-6层客厅天花腻子;
N-6层安装管道井门框;
N-6层电梯间天花腻子;
N-6层安装楼梯间门框;
N-6层卫生间天花腻子包括以下步骤:
N-6层卫生间天花高压水枪拉毛;
N-6层卫生间照明、插座穿线及调试;
N-6层卫生间地面防水,湿区墙面防水;
N-6层洗漱间天花腻子包括以下步骤:
N-6层洗漱间天花高压水枪拉毛;
N-6层洗漱间照明、插座穿线及调试;
N-6层洗漱间天花装修一、二遍腻子层;
N-6层洗漱间天花吊顶封板;
N-6层厨房天花腻子包括以下步骤:
N-6层厨房天花高压水枪拉毛;
N-6层厨房照明、插座穿线及调试;
N-6层房间天花腻子包括以下步骤:
N-6层房间天花保温板安装;
N-6层房间照明、插座穿线及调试;
N-6层房间天花装修一、二遍腻子层;
N-6层客厅天花腻子包括以下步骤:
N-6层客厅照明、插座穿线及调试;
N-6层客厅天花装修一、二遍腻子层;
N-6层客厅入户门框安装;
N-6层客厅入户门框塞缝、收口;
N-6层客厅天花吊顶封板;
N-6层安装管道井门框包括以下步骤:
N-6层管道井防火门框安装;
N-6层管道井防火门框收口;
N-6层电梯间天花腻子包括以下步骤:
N-6层电梯间防火门框安装、塞缝;
N-6层电梯间照明、插座穿线及调试;
N-6层电梯间消火栓安装;
N-6层电梯间天花吊顶封板;
N-6层电梯间天花装修一、二遍腻子层;
N-6层安装楼梯间门框包括以下步骤:
N-6层楼梯间防火门框安装、塞缝;
N-6层楼梯间照明、插座穿线及调试;
N-7层厨卫墙砖铺贴施工层包括以下步骤:
N-7层卫生间墙砖铺贴;
N-7层洗漱间墙砖铺贴;
N-7层厨房墙砖铺贴;
N-8层台地砖铺贴施工层包括以下步骤:
N-8层卫生间地砖铺贴;
N-8层洗漱间地砖铺贴;
N-8层厨房地砖铺贴;
N-8层房间台地砖铺贴;
N-8层客厅地砖铺贴;
N-8层电梯间地砖铺贴;
N-8层阳台地砖铺贴;
N-8层卫生间地砖铺贴以下步骤:
N-8层卫生间门槛,卫生间挡水石施工;
N-8层卫生间地砖施工;
N-8层卫生间地砖成品保护;
N-8层卫生间铝扣板天花安装;
N-8层洗漱间地砖铺贴以下步骤:
N-8层洗漱间地砖施工;
N-8层洗漱间地砖成品保护;
N-8层厨房地砖铺贴以下步骤:
N-8层厨房地砖施工;
N-8层厨房门槛石;
N-8层厨房地砖成品保护;
N-8层厨房烟道井安装软管;
N-8层厨房铝扣板天花安装;
N-8层房间台地砖铺贴以下步骤:
N-8层房间窗台砖铺贴;
N-8层房间门槛砖施工;
N-8层客厅地砖铺贴以下步骤:
N-8层客厅地砖施工;
N-8层客厅入户门槛石施工;
N-8层客厅地砖成品保护;
N-8层电梯间地砖铺贴以下步骤:
N-8层电梯间地砖施工;
N-8层地砖成品保护;
N-8层阳台地砖铺贴以下步骤:
N-8层阳台地砖施工;
N-8层阳台地砖成品保护;
N-9层内墙面一遍腻子层包括以下步骤:
N-9层厅房内墙面一遍腻子;
N-9层厨卫门框基层安装;
N-9层电梯间砌筑;
N-9层管道井门施工;
N-9层厅房内墙面一遍腻子以下步骤:
N-9层房间、客厅墙面修角;
N-9层房间、客厅墙面第一遍腻子;
N-9层房间门框基层安装;
N-9层厨卫门框基层安装以下步骤:
N-9层卫生间门框基层安装;
N-9层厨房门框基层安装;
N-9层电梯间砌筑以下步骤:
N-9层电梯井钢筋切割,放中线;
N-9层电梯井搭架轨道安装。
N-9层管道井门施工以下步骤:
N-9层管道井防火门框安装;
N-9层管道井防火门框收口;
N-10层内墙面二遍腻子层包括以下步骤:
N-10层厅房内墙面二遍腻子;
N-10层厨卫淋浴设备安装;
N-10层电梯间门施工;
N-10层厅房内墙面二遍腻子包括以下步骤:
N-10层房间、客厅墙面第二遍腻子;
N-10层房间、客厅天花打磨;
N-10层房间、客厅墙面打磨;
N-10层厨卫淋浴设备安装包括以下步骤:
N-10层卫生间淋浴杆安装;
N-10层卫生间淋浴屏安装;
N-10层卫生间淋浴屏打胶;
N-10层洗漱间天花打磨;
N-10层电梯间门施工包括以下步骤:
N-10层电梯间电梯门、门框安装;
N-10层电梯间墙砖及门边收口;
N-11层楼梯间施工层包括以下步骤:
N-11层楼梯间拆除临卫往主体结构楼层上移;
N-11层楼梯间防滑砖及砂浆找平;
N-11层楼梯间天花、墙面第一遍腻子;
N-11层楼梯间天花、墙面第二遍腻子;
N-11层楼梯间腻子打磨、验收;
本全现浇外墙高层住宅全穿插施工提效方法还包括地下室施工层,地下室施工层包括以下步骤:
地下室墙面腻子施工;
配电房、发电机房安装;
生活水泵房、消防水泵房、消防控制中心、风机房安装;
智能化控制中心、智能化系统安装;
通水、通电、消防水电风系统安装调试;
金刚砂地坪;
地下室墙面一、二遍面漆;
固化地坪;
车位划线;
全现浇外墙高层住宅主体封顶后全穿插施工提效方法,包括以下步骤:
主体结构封顶;
机房施工:主体结构封顶后开始进行屋面结构机房施工作业;
爬架及施工电梯拆除:屋面结构、机房施工作业完成后,开始爬架及施工电梯拆除;
电梯安装:爬架拆除、施工电梯拆除完成后,住宅电梯开始安装,电梯安装完后进行电梯调试;
拆除塔吊:拆除爬架施工作业完成后开始拆除塔吊;
室外园林施工:拆除塔吊施工作业完成后,开始室外园林施工作业开始;
外墙吊篮施工:拆除塔吊施工作业完成后,住宅外墙收尾工程、外墙吊篮施工作业开始施工;
漆面施工:外墙吊篮施工完成后,开始进行住宅各层的漆面施工作业;
收纳安装:住宅各层的漆面施工作业完成后,住宅各层的收纳设备安装开始施工作业;
台面灯具安装:住宅各层的收纳设备安装完成后,住宅各层的台面灯具开始安装施工作业;
门及二遍面漆施工:住宅各层的台面灯具开始安装施工作业完成后,住宅各层的门及二遍面漆开始施工作业;
木地板安装:住宅各层的门及二遍面漆开始施工作业完成后,住宅各层的木地板安装施工作业开始;
五金设备安装及住宅保洁:住宅各层的木地板安装施工作业完成后,住宅各层进行五金设备安装及住宅保洁施工作业;
室外园林施工包括以下步骤:
园林基层施工;
园林乔木种植;
园林基建砌筑;
园林灌木施工;
园林地被施工;
园林草皮施工;
园林绿化养护;
漆面施工包括室内漆面施工,室内漆面施工包括以下步骤:
室内天花机械喷涂底漆、修补;
室内天花第一遍面漆施工;
室内天花第二遍面漆施工;
漆面施工还包括室外漆面施工,室外漆面施工包括以下步骤:
阳台、空调板、外窗、外墙面底漆;
阳台、空调板、外窗、外墙面第一遍面漆;
阳台、空调板、外窗、外墙面第二遍面漆;
阳台、空调板、外窗、外墙面第一次清洗;
阳台、空调板、外窗、外墙面第二次清洗;
电梯调试包括以下步骤:
电梯智能化设备安装;
电梯安装调试;
电梯智能化设备调试;
收纳安装包括以下步骤:
洁柜安装;
镜柜安装;
橱柜安装;
消防通风口百叶安装;
台面灯具安装包括以下步骤:
卫生间、房间、电梯间低窗护栏安装;
客厅智能化设备开始调试;
卫生间、洗漱间、厨房台面安装;
卫生间、厨房、房间户内门框安装;
厨房、电梯间、楼梯间、阳台灯具安装;
房间、客厅细部整改;
开关面板安装;
门及二遍面漆施工包括以下步骤:
卫生间、厨房、房间门扇安装;
卫生间马桶安装;
房间、客厅、电梯间墙面二遍面漆施工;
开关面板安装;
卫生间、厨房、房间门贴脸安装;
管道井、电梯间、楼梯间防火门门扇安装;
五金设备安装及住宅保洁包括以下步骤:
厨电安装;
卫生间、洗漱间、厨房五金安装;
室内、室外初保洁;
室内打胶;
卫生间、洗漱间、厨房墙地砖勾缝;
室内打胶包括以下步骤:
卫生间、洗漱间、厨房台面打胶;
客厅入户门门框外边打胶;
电梯间、楼梯间门框边打胶。
本实施例具有如下优点:
1、本全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,细化到每一层需进行穿插施工的工作项;其目的在于明确施工全过程中自下而上的施工工序流水组织和技术要求,既缩短了施工总工期,提高了工效,又提升了项目工程管理的精细化水平;
当高层住宅的电梯间、楼梯间主体结构在进行第N层施工作业时,此时高层住宅第N-1层即可穿插进行电梯间、楼梯间拆模施工作业,高层住宅第N-2层即可穿插进行电梯间、楼梯间支顶止水施工作业,高层住宅第N-5层即可穿插进行电梯间、楼梯间管线安装施工作业,高层住宅第N-6层即可穿插进行电梯间、楼梯间天花腻子施工作业,高层住宅第N-8层即可穿插进行电梯间地砖铺贴施工作业,高层住宅第N-9层即可穿插进行电梯间砌筑施工作业,高层住宅第N-10层即可穿插进行电梯间门施工作业,高层住宅第N-11层即可穿插进行楼梯间施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层电梯间、楼梯间施工,各专业工种都能穿插连续作业,确保高层住宅各楼层全穿插施工作业,缩短了施工总工期,提高了工效;
为实现电梯间、楼梯间穿插施工,该电梯间、楼梯间穿插施工梳理了过程中标志性的节点,便于宏观把控;该电梯间、楼梯间穿插施工相比传统施工组织形式,可操作强,进一步减少了主观误差;
该电梯间、楼梯间穿插施工实现了有效结合铝模、智能爬架、预制墙板、全现浇外墙、干法施工等先进工艺,前瞻性高,为建筑行业创造了附加价值,是行业未来发展的主流。
2、本全现浇外墙高层住宅全穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,当高层住宅的主体结构在进行第N层施工作业时,此时,高层住宅第N-1层即可穿插进行拆模施工作业,高层住宅第N-2层即可穿插进行支顶止水施工作业,高层住宅第N-3层即可穿插进行内墙板施工作业,高层住宅第N-4层即可穿插进行给排水安装施工作业,高层住宅第N-5层即可穿插进行管线安装施工作业,高层住宅第N-6层即可穿插进行天花腻子施工作业,高层住宅第N-7层即可穿插进行厨卫墙砖铺贴施工作业,高层住宅第N-8层即可穿插进行台地砖铺贴施工作业,高层住宅第N-9层即可穿插进行内墙面第一遍腻子施工作业,高层住宅第N-10层即可穿插进行内墙面第二遍腻子施工作业,高层住宅第N-11层即可穿插进行楼梯间施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层各专业工种都能穿插连续作业,确保高层住宅各楼层全穿插施工作业,缩短了施工总工期,提高了工效。
3、全现浇外墙高层住宅厨卫穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,当高层住宅的厨卫主体结构在进行第N层施工作业时,第N-1层的厨卫主体结构施工作业已完成,此时,高层住宅第N-1层即可穿插进行厨卫拆模施工作业,高层住宅第N-2层即可穿插进行厨卫支顶止水施工作业,高层住宅第N-3层即可穿插进行厨卫内墙板施工作业,高层住宅第N-4层即可穿插进行厨卫给排水安装施工作业,高层住宅第N-5层即可穿插进行厨卫管线安装施工作业,高层住宅第N-6层即可穿插进行厨卫天花腻子施工作业,高层住宅第N-7层即可穿插进行厨卫墙砖铺贴施工作业,高层住宅第N-8层即可穿插进行厨卫台地砖铺贴施工作业,高层住宅第N-9层即可穿插进行厨卫门框基层安装施工作业,高层住宅第N-10层即可穿插进行厨卫淋浴设备安装施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层厨卫施工各专业工种都能穿插连续作业,确保高层住宅各楼层厨卫穿插施工作业,缩短了施工总工期,提高了工效。
4、全现浇外墙高层住宅厅房穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,当高层住宅的厅房主体结构在进行第N层施工作业时,此时高层住宅第N-1层即可穿插进行厅房拆模施工作业,高层住宅第N-2层即可穿插进行厅房支顶止水施工作业,高层住宅第N-3层即可穿插进行厅房内墙板施工作业,高层住宅第N-4层即可穿插进行厅房给排水安装施工作业,高层住宅第N-5层即可穿插进行厅房管线安装施工作业,高层住宅第N-6层即可穿插进行厅房天花腻子施工作业,高层住宅第N-8层即可穿插进行厅房台地砖铺贴施工作业,高层住宅第N-9层即可穿插进行厅房内墙面第一遍腻子施工作业,高层住宅第N-10层即可穿插进行厅房内墙面第二遍腻子施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层厅房施工各专业工种都能穿插连续作业,确保高层住宅各楼层厅房穿插施工作业,缩短了施工总工期,提高了工效。
5、全现浇外墙高层住宅室外穿插施工提效方法是一种工序组织管理技术,以结构层数为划分依据,当高层住宅的室外主体结构在进行第N层施工作业时,此时高层住宅第N-1层即可穿插进行室外拆模施工作业,高层住宅第N-2层即可穿插进行室外支顶止水施工作业,高层住宅第N-3层即可穿插进行阳台护栏安装施工作业,高层住宅第N-4层即可穿插进行阳台给排水安装施工作业,高层住宅第N-5层即可穿插进行阳台管线安装施工作业,高层住宅第N-8层即可穿插进行阳台地砖铺贴施工作业;依此类推使得时间效用最大化被利用,实现了高层住宅各楼层室外施工各专业工种都能穿插连续作业,确保高层住宅各楼层室外穿插施工作业,缩短了施工总工期,提高了工效。
6、按各施工作业内容进一步细分流水段,优化劳动力安排,降低对单一工种劳动力数量的突击性需求,做到科学、有序、连贯,保证各专业工种都能穿插连续作业。
7、本全现浇外墙高层住宅全穿插施工提效方法,还包括地下室施工层的施工作业,使该全穿插施工范围涵盖到室内、室外、地下室等方面,实现了室内、室外与地下室同步施工,进一步缩短了施工总工期,提高了工效。
8、全现浇外墙高层住宅主体封顶后全穿插施工提效方法是一种工序组织管理技术,以高层住宅主体封顶后各施工部位为划分依据;该高层住宅主体封顶后全穿插施工的范围进一步涵盖高层住宅主体封顶后室内、室外、地下室、园林等部分,是真正意义上的高层住宅的全方位穿插施工,细化到需进行穿插施工的第一个工作项,包括室内、室外、地下室、园林;其目的在于明确高层住宅主体封顶后施工全过程的施工工序流水组织和技术要求,既缩短了施工总工期,提高了工效。
以上仅为本发明的具体实施例,并不以此限定本发明的保护范围;在不违反本发明构思的基础上所作的任何替换与改进,均属本发明的保护范围。

Claims (10)

1.全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,包括以下步骤:
N层电梯间、楼梯间主体结构层:高层住宅的电梯间、楼梯间主体结构从第1层逐层向顶层进行电梯间、楼梯间主体结构施工作业;
N-1层电梯间、楼梯间拆模施工层:当电梯间、楼梯间主体结构在进行第N层施工作业时,第N-1层的电梯间、楼梯间主体结构施工作业已完成,第N-1层进行穿插电梯间、楼梯间拆模施工作业;
N-2层电梯间、楼梯间支顶止水层:当第N-1层进行电梯间、楼梯间拆模施工作业时,第N-2层的电梯间、楼梯间拆模施工作业已完成,第N-2层进行穿插电梯间、楼梯间支顶止水施工作业;
N-5层电梯间、楼梯间管线安装层:当第N-2层进行电梯间、楼梯间支顶止水施工作业时,第N-5层的电梯间、楼梯间支顶止水施工作业已完成,第N-5层进行穿插电梯间、楼梯间管线安装施工作业;
N-6层电梯间、楼梯间天花腻子层:当第N-5层进行电梯间、楼梯间管线安装施工作业时,第N-6层的电梯间、楼梯间管线安装施工作业已完成,第N-6层进行穿插电梯间、楼梯间天花腻子施工作业;
N-8层电梯间地砖铺贴层:当第N-6层进行电梯间、楼梯间天花腻子施工作业时,第N-8层的电梯间、楼梯间天花腻子施工作业已完成,第N-8层进行穿插电梯间地砖铺贴施工作业;
N-9层电梯间砌筑层:当第N-8层进行电梯间地砖铺贴施工作业时,第N-9层的电梯间地砖铺贴施工作业已完成,第N-9层进行穿插电梯间砌筑施工作业;
N-10层电梯间门施工层:当第N-9层进行电梯间砌筑施工作业时,第N-10层的电梯间砌筑施工作业已完成,第N-10层进行穿插电梯间门施工作业;
N-11层楼梯间施工层:当第N-10层进行电梯间门施工作业时,第N-11层的电梯间门施工作业已完成,第N-11层进行穿插楼梯间施工作业。
2.如权利要求1所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-5层电梯间、楼梯间管线安装层包括N-5层电梯间管线安装,所述N-5层电梯间管线安装包括以下步骤:
N-5层电梯间墙板嵌缝修补;
N-5层电梯间墙板线盒及线管安装;
N-5层电梯间消防设备布线;
N-5层电梯间消防通风口百叶安装;
N-5层电梯间照明、插座穿引线;
N-5层电梯间天花吊杆龙骨安装。
3.如权利要求1所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-5层电梯间、楼梯间管线安装层还包括N-5层楼梯间管线安装,所述N-5层楼梯间管线安装包括以下步骤:
N-5层楼梯间墙板嵌缝修补;
N-5层楼梯间墙板线盒及线管安装;
N-5层楼梯间消防设备布线;
N-5层楼梯间照明、插座穿引线。
4.如权利要求1所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-5层电梯间、楼梯间管线安装层还包括N-5层管道井管线安装,所述N-5层管道井管线安装包括以下步骤:
N-5层管道井墙板嵌缝修补;
N-5层管道井墙板线盒及线管安装;
N-5层管道井强弱电线槽安装;
N-5层管道井给排水管安装。
5.如权利要求1所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-6层电梯间、楼梯间天花腻子层包括N-6层电梯间天花腻子、N-6层安装楼梯间门框,所述N-6层电梯间天花腻子包括以下步骤:
N-6层电梯间防火门框安装、塞缝;
N-6层电梯间照明、插座穿线及调试;
N-6层电梯间消火栓安装;
N-6层电梯间天花吊顶封板;
N-6层电梯间天花装修一、二遍腻子层。
6.如权利要求1所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-6层安装楼梯间门框包括以下步骤:
N-6层楼梯间防火门框安装、塞缝;
N-6层楼梯间照明、插座穿线及调试。
7.如权利要求6所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-8层电梯间地砖铺贴包括以下步骤:
N-8层电梯间地砖施工;
N-8层地砖成品保护。
8.如权利要求6所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-9层电梯间砌筑包括以下步骤:
N-9层电梯井钢筋切割,放中线;
N-9层电梯井搭架轨道安装。
9.如权利要求6所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-10层电梯间门施工层包括以下步骤:
N-10层电梯间电梯门、门框安装;
N-10层电梯间墙砖及门边收口。
10.如权利要求1至9任一项所述的全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法,其特征在于,所述N-11层楼梯间施工层包括以下步骤:
N-11层楼梯间拆除临卫往主体结构楼层上移;
N-11层楼梯间防滑砖及砂浆找平;
N-11层楼梯间天花、墙面第一遍腻子;
N-11层楼梯间天花、墙面第二遍腻子;
N-11层楼梯间腻子打磨、验收。
CN201711386620.3A 2017-12-20 2017-12-20 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法 Pending CN108049495A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711386620.3A CN108049495A (zh) 2017-12-20 2017-12-20 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711386620.3A CN108049495A (zh) 2017-12-20 2017-12-20 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法

Publications (1)

Publication Number Publication Date
CN108049495A true CN108049495A (zh) 2018-05-18

Family

ID=62130362

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711386620.3A Pending CN108049495A (zh) 2017-12-20 2017-12-20 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法

Country Status (1)

Country Link
CN (1) CN108049495A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158974A (zh) * 2019-06-10 2019-08-23 张杨 一种高层装配式建筑结构的全穿插施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100948255B1 (ko) * 2009-08-12 2010-03-18 주식회사 에스에이치텍 고 단열 방음의 발포 스치로폼 블럭을 이용한 그린하우스 시공방법, 고 단열 방음의 발포 스치로폼 블럭 및 고 단열 방음의 발포 스치로폼 천장패널
CN101818574A (zh) * 2010-03-23 2010-09-01 南通宏华建筑安装有限公司 自稳型高强薄壁管内模现浇空心板施工方法
CN103174293A (zh) * 2011-12-23 2013-06-26 五冶集团上海有限公司 空心楼板自稳式内模安装方法
CN103216102A (zh) * 2013-05-02 2013-07-24 江苏华江建设集团有限公司 钢管柱内混凝土导管导入浇筑的施工方法
CN103774846A (zh) * 2012-10-26 2014-05-07 甘肃省建设投资(控股)集团总公司 一种建筑工程窗间隔断柱的施工方法
CN106121231A (zh) * 2016-06-21 2016-11-16 中天建设集团有限公司天津分公司 一种高层建筑穿插流水施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100948255B1 (ko) * 2009-08-12 2010-03-18 주식회사 에스에이치텍 고 단열 방음의 발포 스치로폼 블럭을 이용한 그린하우스 시공방법, 고 단열 방음의 발포 스치로폼 블럭 및 고 단열 방음의 발포 스치로폼 천장패널
CN101818574A (zh) * 2010-03-23 2010-09-01 南通宏华建筑安装有限公司 自稳型高强薄壁管内模现浇空心板施工方法
CN103174293A (zh) * 2011-12-23 2013-06-26 五冶集团上海有限公司 空心楼板自稳式内模安装方法
CN103774846A (zh) * 2012-10-26 2014-05-07 甘肃省建设投资(控股)集团总公司 一种建筑工程窗间隔断柱的施工方法
CN103216102A (zh) * 2013-05-02 2013-07-24 江苏华江建设集团有限公司 钢管柱内混凝土导管导入浇筑的施工方法
CN106121231A (zh) * 2016-06-21 2016-11-16 中天建设集团有限公司天津分公司 一种高层建筑穿插流水施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110158974A (zh) * 2019-06-10 2019-08-23 张杨 一种高层装配式建筑结构的全穿插施工方法

Similar Documents

Publication Publication Date Title
Weeks et al. The Secretary of the Interior's Standards for the Treatment of Historic Properties: With Guidelines for Preserving, Rehabilitating, Restoring & Reconstructing Historic Buildings
Grimmer The Secretary of the Interior's standards for the treatment of historic properties: With guidelines for preserving, rehabilitating, restoring & reconstructing historic buildings
CN103510631B (zh) 一种室内隔音施工结构及其施工方法
CN106121231A (zh) 一种高层建筑穿插流水施工方法
CN108049496A (zh) 全现浇外墙高层住宅全穿插施工提效方法
CN106285074A (zh) 一种物流园区的设计规范
CN110158974A (zh) 一种高层装配式建筑结构的全穿插施工方法
CN103321393B (zh) 内墙抹灰施工方法
CN104695706A (zh) Aac砌块自由加载墙施工工法
CN108049495A (zh) 全现浇外墙高层住宅电梯间、楼梯间穿插施工提效方法
CN108104257A (zh) 全现浇外墙高层住宅厅房穿插施工提效方法
CN108086714A (zh) 全现浇外墙高层住宅厨卫穿插施工提效方法
CN108104472A (zh) 全现浇外墙高层住宅室外穿插施工提效方法
CN104372877B (zh) 高大垂直石材水幕墙施工工法
Davies et al. Architect's illustrated pocket dictionary
CN108104278A (zh) 全现浇外墙高层住宅主体封顶后全穿插施工提效方法
CN109989554A (zh) 一种高层建筑用装配式管道井及其制备方法和安装方法
CN114934588A (zh) 一种建筑施工用高效穿插流水施工方法
CN103422671B (zh) 建筑工程施工用集成工艺样板房的施工方法
CN108252518A (zh) 高层住宅新型建造体系总控工期下的施工方法
CN209025491U (zh) 一种由废旧集装箱改造的箱式房
Goldoni et al. Palazzo Sartoretti in Reggiolo
Elkodousy Office center in Izyum city of Kharkiv region
CN114809635A (zh) 一种全装配整体式混凝土剪力墙高层住宅穿插施工方法
Yue Analysis on The Main Points and Importance of Construction Technology of Construction Civil Engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180518

RJ01 Rejection of invention patent application after publication