CN107988908A - The total assembling method of tubular arch - Google Patents

The total assembling method of tubular arch Download PDF

Info

Publication number
CN107988908A
CN107988908A CN201710500688.3A CN201710500688A CN107988908A CN 107988908 A CN107988908 A CN 107988908A CN 201710500688 A CN201710500688 A CN 201710500688A CN 107988908 A CN107988908 A CN 107988908A
Authority
CN
China
Prior art keywords
total
arch rib
assembled
arch
preassembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710500688.3A
Other languages
Chinese (zh)
Inventor
彭飞
张秉钧
胡刚
宋朴
巫丽凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRBBG Tycoon Industrial Development Co Ltd
Original Assignee
CRBBG Tycoon Industrial Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRBBG Tycoon Industrial Development Co Ltd filed Critical CRBBG Tycoon Industrial Development Co Ltd
Priority to CN201710500688.3A priority Critical patent/CN107988908A/en
Publication of CN107988908A publication Critical patent/CN107988908A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention discloses a kind of total assembling method of tubular arch.The total assembling method of tubular arch provided by the invention is included according to preassembled computer software setting-out gathered data, total place of spelling has been surveyed using the setting-out of total powerstation, theodolite and spirit level measuring apparatus progress truss arch rib on flat steel plate, and arch rib position and steel pipe interface position are set and lean on shelves;Step S2, sets the cushion block of not equal altitude in ground steel plate, ensures the requirement of truss arch rib plane and facade line style;Step S3, the position location of ring flange and arch rib diagonal brace built in the case that casts anchor on corresponding moulding bed position releasing arch rib, interface, ensures the total assembled splicing accuracy of arch rib, reduces always assembled error;Step S4, is detected total assembled fetalism, examining report is provided after detection is qualified.The present invention improves manufacture, sets up precision, realizes design idea, equipment is simple, and blanking is easily purchased, and can reuse;Difficulty of construction is reduced, improves production efficiency, improves economic benefit.

Description

The total assembling method of tubular arch
Technical field
The present invention relates to the total assembling technique field of truss tubular arch, more particularly to a kind of total assembling method of tubular arch.
Background technology
Steel pipe arch bridge is as a kind of type of bridge with span ability is big, bearing capacity is high, cost economic, maintenance charge With the distinctive technical advantage such as low, handsome in appearance, become one of indispensable structure type of modern architecture bridge.With the modern times The variation of Bridge Design, the span of steel pipe arch bridge is increasing, and difficulty of construction is also higher and higher, this to steel pipe arch bridge especially The manufacture of truss steel pipe arch bridge and erection precision are one very big " challenges ".
Original technique:Using arch rib unit making-preassembling-sanding-application-transport in factory.
The process that bridge location is set up.Since truss tubular arch unit sectional dimension is larger, the highway component conveying that transfinites is of high cost, It is more dangerous in transportational process, and well damage is painted to steel box-girder surface.Since transit route is longer, component deforms upon Possibility it is very big, directly affect component set up precision.
Solve the above problems therefore, it is necessary to provide a kind of total assembling method of new tubular arch.
The content of the invention
In order to solve the above technical problems, the present invention provides a kind of total assembling method of tubular arch, bridge space line style is converted For the flat linearity effectively controlled, production efficiency is improved, manufacture cost and security risk is reduced, improves truss steel pipe arch bridge bridge Position set up precision, ensure that the design line style of bridge, make appearance it is more beautiful, smooth-going.
The present invention provides a kind of total assembling method of tubular arch, includes the following steps:
Step S1, according to preassembled computer software setting-out gathered data, theory state is pressed assembled segment is needed The plane coordinates size for keeping flat the point that on the table, needs are controlled has arranged form, and ground sample is established on Department service bench and is sat Mark system, makes the workbench in workshop have the function of to detect, position, clamp, assembling, and total spelling place has been surveyed on flat steel plate and has been utilized Total powerstation, theodolite and spirit level measuring apparatus carry out the setting-out of truss arch rib, and arch rib position and steel pipe interface position are set Shelves are rested against, using the method for the horizontal assembling of arch rib, and tire fetalism is assembled, welded, repaired using arch rib;
Step S2, sets the cushion block of not equal altitude in ground steel plate, ensures the requirement of truss arch rib plane and facade line style, On ground sample coordinate assembling table, base area sample coordinate points can reflect that camber, sunpender on arch rib control point link center The detection coordinates numerical value of bonding wire between the exact position of line, segment, and check the total length and flatness of component;
Step S3, the positioning of ring flange and arch rib diagonal brace built in the case that casts anchor on corresponding moulding bed position releasing arch rib, interface Position, ensures the total assembled splicing accuracy of arch rib, reduces total assembled error, when steel pipes with straight is assembled, butt weld is placed in flat On the inside of yoke plate;The adjacent longitudinal seam size that staggers is more than 200mm;
Step S4, is detected total assembled fetalism, examining report is provided after detection is qualified;
Step S5, component is by the assembled parallel spot welding of line, always again into equidirectional symmetrical welding, and pass through after assembled all components After crossing Non-Destructive Testing, rechecked again by fetalism setting-out position, bridge location is installed into position line, bridge location measurement position line in component On mark, tire inspection is carried out out after meeting the requirements, component goes out tire after the assay was approved;After arch rib is detected a flaw, tire progress is returned again Review, after meeting the requirements, gas flame cuttiug, reconditioning are carried out according to the prefabricated segment length of steel lagging jack, and carry out sanding, application, specifically, In the range of the 50mm of butt weld both ends and web member contact site is without application, and is protected;
Step S6, goes out tire rear part and is transported to bridge location by sanding, application using heavy-load automobile and is lifted;
Step S7, carries out comprehensive repetition measurement to total assembled fetalism and is modified again, ensures that the precision of total assembled fetalism will Ask, be ready for the total consolidation service of next round;Lifting rib-lifting section is transported using heavy-load automobile, is transported to bridge location, Cable crane is coordinated to carry out rib-hoisting, set up.
Preferably, the arch rib preassembling is carried out using the pattern of prosposition " 3+1 ";Each pre-splicing 4 lifting elements, it is pre-splicing A segment is reserved after dress as reset section, participates in next preassembling.
Preferably, the method for the arch rib preassembling, includes the following steps:
Put first steel lagging jack lifting elements successively on preassembling moulding bed, pre-control geometric accuracy when putting, puts Accurate adjustment again afterwards;
After first unit preassembling is in place, complete detection geometric accuracy and interface precision are then interim fixed;
Second, third and the 4th lifting elements are put successively, and detect, adjust and fix temporarily accordingly;
The geometric accuracy and matching precision of one preassembling round of complete detection, then need to carry out if there is off-gage phenomenon Corresponding adjustment;
After each corner is all met the requirements, each interface installs two groups and matches connector temporarily;
Rod piece is numbered, in order to install;
Disintegrate, in addition to reset unit gives over to the benchmark of preassembling next time, remaining lifting elements is transported to beam strorage area storage.
Preferably, the preassembled computer software is Atuo CAD.
Preferably, in step plays S4, the component detection is included in the appearance and size progress to unit member before tire Detection, participates in total assembled after meeting the requirements.
The total assembling method of tubular arch provided by the invention carries out truss arch rib 1 according to design drawing requirement using computer software:1 Full-scale setting-out.The setting-out coordinate points of steel truss arch rib are gathered according to software setting-out and are arranged, by measuring apparatus total Spell the arch rib line style that place releases actual Cheng Qiao (facade line style is converted into plane curve);Arch rib is carried out according to the line style of releasing Total assembled, welding, the finishing of unit, anchor box unit and ring flange unit, ensure the connection required precision between arch rib unit;Can To utilize existing place, equipment near bridge location, the top-bottom chord that processing and fabricating in factory is completed, web member, ring flange, anchor case etc. Unit member is sent to total assembled place, and the complex space line style of the total assembling technique of truss tubular arch is converted into flat linearity Total consolidation service is carried out, not only increases making precision, is also effectively guaranteed the production efficiency and bridge location arch of truss tubular arch The connection precision set up between rib unit, while risk in transit, difficulty of construction and the manufacture cost of the component that transfinites are reduced, reach Truss tubular arch line style is beautiful, the requirement of smooth-going.
Brief description of the drawings
Fig. 1 is the steel tube arch rib setting-out schematic diagram of the total assembling method of tubular arch provided by the invention;
Fig. 2 is the steel tube arch rib sectional drawing of the total assembling method of tubular arch provided by the invention.
Embodiment
Below in conjunction with drawings and embodiments, the invention will be further described.
Please refer to Fig.1 and Fig. 2, Fig. 1 be the total assembling method of tubular arch provided by the invention steel tube arch rib setting-out schematic diagram; Fig. 2 is the steel tube arch rib sectional drawing of the total assembling method of tubular arch provided by the invention.
The total assembling method of tubular arch includes the following steps:
Step S1, according to preassembled computer software setting-out gathered data, theory state is pressed assembled segment is needed The plane coordinates size for keeping flat the point that on the table, needs are controlled has arranged form, and ground sample is established on Department service bench and is sat Mark system, makes the workbench in workshop have the function of to detect, position, clamp, assembling, and total spelling place has been surveyed on flat steel plate and has been utilized Total powerstation, theodolite and spirit level measuring apparatus carry out the setting-out of truss arch rib, and arch rib position and steel pipe interface position are set Shelves are rested against, using the method for the horizontal assembling of arch rib, and tire fetalism is assembled, welded, repaired using arch rib;
Step S2, sets the cushion block of not equal altitude in ground steel plate, ensures the requirement of truss arch rib plane and facade line style, On ground sample coordinate assembling table, base area sample coordinate points can reflect that camber, sunpender on arch rib control point link center The detection coordinates numerical value of bonding wire between the exact position of line, segment, and check the total length and flatness of component;
Step S3, the positioning of ring flange and arch rib diagonal brace built in the case that casts anchor on corresponding moulding bed position releasing arch rib, interface Position, ensures the total assembled splicing accuracy of arch rib, reduces total assembled error, when steel pipes with straight is assembled, butt weld is placed in flat On the inside of yoke plate;The adjacent longitudinal seam size that staggers is more than 200mm;
Step S4, is detected total assembled fetalism, examining report is provided after detection is qualified;
Step S5, component is by the assembled parallel spot welding of line, always again into equidirectional symmetrical welding, and pass through after assembled all components After crossing Non-Destructive Testing, rechecked again by fetalism setting-out position, bridge location is installed into position line, bridge location measurement position line in component On mark, tire inspection is carried out out after meeting the requirements, component goes out tire after the assay was approved;After arch rib is detected a flaw, tire progress is returned again Review, after meeting the requirements, gas flame cuttiug, reconditioning are carried out according to the prefabricated segment length of steel lagging jack, and carry out sanding, application, specifically, In the range of the 50mm of butt weld both ends and web member contact site is without application, and is protected;
Step S6, goes out tire rear part and is transported to bridge location by sanding, application using heavy-load automobile and is lifted;
Step S7, carries out comprehensive repetition measurement to total assembled fetalism and is modified again, ensures that the precision of total assembled fetalism will Ask, be ready for the total consolidation service of next round;Lifting rib-lifting section is transported using heavy-load automobile, is transported to bridge location, Cable crane is coordinated to carry out rib-hoisting, set up.
Preferably, the arch rib preassembling is carried out using the pattern of prosposition " 3+1 ";Each pre-splicing 4 lifting elements, it is pre-splicing A segment is reserved after dress as reset section, participates in next preassembling.
Preferably, the method for the arch rib preassembling, includes the following steps:
Put first steel lagging jack lifting elements successively on preassembling moulding bed, pre-control geometric accuracy when putting, puts Accurate adjustment again afterwards;
After first unit preassembling is in place, complete detection geometric accuracy and interface precision are then interim fixed;
Second, third and the 4th lifting elements are put successively, and detect, adjust and fix temporarily accordingly;
The geometric accuracy and matching precision of one preassembling round of complete detection, then need to carry out if there is off-gage phenomenon Corresponding adjustment;
After each corner is all met the requirements, each interface installs two groups and matches connector temporarily;
Rod piece is numbered, in order to install;
Disintegrate, in addition to reset unit gives over to the benchmark of preassembling next time, remaining lifting elements is transported to beam strorage area storage.
Preferably, the preassembled computer software is Atuo CAD.
Preferably, in step plays S4, the component detection is included in the appearance and size progress to unit member before tire Detection, participates in total assembled after meeting the requirements.
Refer to list below;Respectively arch rib segmentation mouth coordinate parameters table, crossbeam central coordinate of circle parameter list, the stull center of circle Coordinate parameters table, arch rib coordinate parameters table.
The technical measures of preassembling of the present invention, including:
1) establishment of preassembling technique guiding book will be with preassembling operation reasonable, simple and direct economy for principle, preassembling Detection to accomplish overall scientific, strong operability, the moulding bed of preassembling is designed in addition to fulcrum requirement is met, while to consider basis Firm, influence of the rigidity of stent to preassembling precision, while to consider the elasticity after the selection and moulding bed load-bearing of benchmark The influence to benchmark is deformed, in order to avoid influence of the stent load-bearing to benchmark, detection benchmark must individually be located at steady outside stent On the basis of Gu.
2) preassembling is carried out in strict accordance with the order of technological requirement, putting for first lifting elements will be in strict accordance with datum line Aligned, as the benchmark of other cell locations.
3) during subsequent cell preassembling, not only to consider, with first segment matches precision and with respect to geometric accuracy, also to carry out Overall measurement, to avoid the accumulation of error.
4) often increase the preassembling of a lifting elements, then complete detection is wanted, to provide foundation for follow-up preassembling.
5) after a preassembling totally detects qualification, the unwrapping wire of position baseline and interim matching connector can be carried out Installment work.
The total assembling method of tubular arch provided by the invention carries out truss arch rib 1 according to design drawing requirement using computer software:1 Full-scale setting-out.The setting-out coordinate points of steel truss arch rib are gathered according to software setting-out and are arranged, by measuring apparatus total Spell the arch rib line style that place releases actual Cheng Qiao (facade line style is converted into plane curve);Arch rib is carried out according to the line style of releasing Total assembled, welding, the finishing of unit, anchor box unit and ring flange unit, ensure the connection required precision between arch rib unit;Can To utilize existing place, equipment near bridge location, the top-bottom chord that processing and fabricating in factory is completed, web member, ring flange, anchor case etc. Unit member is sent to total assembled place, and the complex space line style of the total assembling technique of truss tubular arch is converted into flat linearity Total consolidation service is carried out, not only increases making precision, is also effectively guaranteed the production efficiency and bridge location arch of truss tubular arch The connection precision set up between rib unit, while risk in transit, difficulty of construction and the manufacture cost of the component that transfinites are reduced, reach Truss tubular arch line style is beautiful, the requirement of smooth-going.
The foregoing is merely the embodiment of the present invention, is not intended to limit the scope of the invention, every to utilize this hair The equivalent structure or equivalent flow shift that bright specification and accompanying drawing content are made, is directly or indirectly used in other relevant skills Art field, is included within the scope of the present invention.

Claims (5)

1. a kind of total assembling method of tubular arch, it is characterised in that include the following steps:
Step S1, according to preassembled computer software setting-out gathered data, is kept flat assembled segment is needed by theory state On the table, the plane coordinates size of point needs controlled has arranged form, and ground sample coordinate system is established on Department service bench, The workbench in workshop had the function of to detect, positioned, clamp, assembling, total spelling place has been surveyed whole station is utilized on flat steel plate Instrument, theodolite and spirit level measuring apparatus carry out the setting-out of truss arch rib, and arch rib position and steel pipe interface position are set and leaned on Shelves, using the method for the horizontal assembling of arch rib, and tire fetalism is assembled, welded, repaired using arch rib;
Step S2, sets the cushion block of not equal altitude in ground steel plate, ensures the requirement of truss arch rib plane and facade line style, on ground On sample coordinate assembling table, base area sample coordinate points can reflect that camber, sunpender on arch rib control point link center line The detection coordinates numerical value of bonding wire between exact position, segment, and check the total length and flatness of component;
Step S3, the position location of ring flange and arch rib diagonal brace built in the case that casts anchor on corresponding moulding bed position releasing arch rib, interface, Ensure the total assembled splicing accuracy of arch rib, reduce total assembled error, when steel pipes with straight is assembled, butt weld is placed in lateral plate Side;The adjacent longitudinal seam size that staggers is more than 200mm;
Step S4, is detected total assembled fetalism, examining report is provided after detection is qualified;
Step S5, component always again into equidirectional symmetrical welding after assembled all components, and pass through nothing by the assembled parallel spot welding of line After damage detection, rechecked again by fetalism setting-out position, bridge location installation position line, bridge location measurement position line are drawn on component Go out, tire inspection is carried out out after meeting the requirements, component goes out tire after the assay was approved;After arch rib is detected a flaw, tire is returned again and is checked, After meeting the requirements, gas flame cuttiug, reconditioning are carried out according to the prefabricated segment length of steel lagging jack, and carries out sanding, application, specifically, docking In the range of the 50mm of weld seam both ends and web member contact site is without application, and is protected;
Step S6, goes out tire rear part and is transported to bridge location by sanding, application using heavy-load automobile and is lifted;
Step S7, carries out comprehensive repetition measurement to total assembled fetalism and is modified again, ensures the required precision of total assembled fetalism, accurate It is standby to carry out the total consolidation service of next round;Lifting rib-lifting section is transported using heavy-load automobile, transports to bridge location, coordinates cable Rope, which is hung, to carry out rib-hoisting, sets up.
2. the total assembling method of tubular arch according to claim 1, it is characterised in that the arch rib preassembling uses prosposition " 3 + 1 " pattern carries out;Each pre-splicing 4 lifting elements, reserve a segment after preassembling and are used as reset section, participate in next Preassembling.
3. the total assembling method of tubular arch according to claim 1, it is characterised in that the method for the arch rib preassembling, bag Include following steps:
Put first steel lagging jack lifting elements successively on preassembling moulding bed, pre-control geometric accuracy when putting, after putting again Precision adjustment;
After first unit preassembling is in place, complete detection geometric accuracy and interface precision are then interim fixed;
Second, third and the 4th lifting elements are put successively, and detect, adjust and fix temporarily accordingly;
The geometric accuracy and matching precision of one preassembling round of complete detection, then need to carry out corresponding if there is off-gage phenomenon Adjustment;
After each corner is all met the requirements, each interface installs two groups and matches connector temporarily;
Rod piece is numbered, in order to install;
Disintegrate, in addition to reset unit gives over to the benchmark of preassembling next time, remaining lifting elements is transported to beam strorage area storage.
4. the total assembling method of tubular arch according to claim 1, it is characterised in that the preassembled computer software is Atuo CAD。
5. the total assembling method of tubular arch according to claim 1, it is characterised in that in step plays S4, the component detection The appearance and size of unit member is detected before being included in tire, is participated in after meeting the requirements total assembled.
CN201710500688.3A 2017-06-27 2017-06-27 The total assembling method of tubular arch Pending CN107988908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710500688.3A CN107988908A (en) 2017-06-27 2017-06-27 The total assembling method of tubular arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710500688.3A CN107988908A (en) 2017-06-27 2017-06-27 The total assembling method of tubular arch

Publications (1)

Publication Number Publication Date
CN107988908A true CN107988908A (en) 2018-05-04

Family

ID=62029625

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710500688.3A Pending CN107988908A (en) 2017-06-27 2017-06-27 The total assembling method of tubular arch

Country Status (1)

Country Link
CN (1) CN107988908A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109214099A (en) * 2018-09-20 2019-01-15 中建三局基础设施建设投资有限公司 A kind of arch rib steel pipe location Calculation and construction method
CN109505266A (en) * 2018-12-07 2019-03-22 中铁局集团厦门建设工程有限公司 A kind of sleeping splicing method in the scene of tubular arch
CN109815640A (en) * 2019-03-19 2019-05-28 中国十九冶集团有限公司 Method for erecting ground tire of curved-surface steel box bridge
CN110144809A (en) * 2019-05-21 2019-08-20 安徽伟宏钢结构集团股份有限公司 A kind of bridge arch rib production method
CN110725212A (en) * 2019-10-24 2020-01-24 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN111395533A (en) * 2020-03-30 2020-07-10 中铁二局第一工程有限公司 Multi-mechanism resultant force air overturning construction method for large-span arc-shaped latticed shell structure
CN114438899A (en) * 2022-02-28 2022-05-06 中铁大桥科学研究院有限公司 Linear control method of hexagonal basket arch
CN115365690A (en) * 2021-05-19 2022-11-22 南通振华重型装备制造有限公司 Construction method of large-scale steel bridge S690 high-strength steel large-section box type arch rib
CN115422645B (en) * 2022-09-22 2024-02-02 北京首钢建设集团有限公司 Three-dimensional measurement space coordinate conversion method for large-span deformed steel truss structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120133328A (en) * 2011-05-31 2012-12-10 우혁근 Span Structure having Half-slab Precast Panel and Constructing Method of Bridge using such Span Structure
CN105586834A (en) * 2016-02-26 2016-05-18 江苏中铁山桥重工有限公司 Bridge beam arch rib section manufacturing process
CN105740560A (en) * 2016-02-03 2016-07-06 中铁一局集团有限公司 Simulation assembling method used for continuous assembling construction of steel pipe arch rib segment bed jig method
CN106284077A (en) * 2016-07-27 2017-01-04 中铁大桥局第七工程有限公司 A kind of tubular arch sections installs measurement and positioning device and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120133328A (en) * 2011-05-31 2012-12-10 우혁근 Span Structure having Half-slab Precast Panel and Constructing Method of Bridge using such Span Structure
CN105740560A (en) * 2016-02-03 2016-07-06 中铁一局集团有限公司 Simulation assembling method used for continuous assembling construction of steel pipe arch rib segment bed jig method
CN105586834A (en) * 2016-02-26 2016-05-18 江苏中铁山桥重工有限公司 Bridge beam arch rib section manufacturing process
CN106284077A (en) * 2016-07-27 2017-01-04 中铁大桥局第七工程有限公司 A kind of tubular arch sections installs measurement and positioning device and construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
付平: "准朔黄河特大桥钢管拱预拼装施工技术", 《价值工程》 *
王建军等: "200t级钢管拱肋节段卧式制作工艺", 《西部交通科技》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109214099A (en) * 2018-09-20 2019-01-15 中建三局基础设施建设投资有限公司 A kind of arch rib steel pipe location Calculation and construction method
CN109214099B (en) * 2018-09-20 2023-06-09 中建三局基础设施建设投资有限公司 Arch rib steel pipe positioning and construction method
CN109505266A (en) * 2018-12-07 2019-03-22 中铁局集团厦门建设工程有限公司 A kind of sleeping splicing method in the scene of tubular arch
CN109815640A (en) * 2019-03-19 2019-05-28 中国十九冶集团有限公司 Method for erecting ground tire of curved-surface steel box bridge
CN110144809A (en) * 2019-05-21 2019-08-20 安徽伟宏钢结构集团股份有限公司 A kind of bridge arch rib production method
CN110725212A (en) * 2019-10-24 2020-01-24 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN110725212B (en) * 2019-10-24 2021-03-16 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN111395533A (en) * 2020-03-30 2020-07-10 中铁二局第一工程有限公司 Multi-mechanism resultant force air overturning construction method for large-span arc-shaped latticed shell structure
CN115365690A (en) * 2021-05-19 2022-11-22 南通振华重型装备制造有限公司 Construction method of large-scale steel bridge S690 high-strength steel large-section box type arch rib
CN114438899A (en) * 2022-02-28 2022-05-06 中铁大桥科学研究院有限公司 Linear control method of hexagonal basket arch
CN115422645B (en) * 2022-09-22 2024-02-02 北京首钢建设集团有限公司 Three-dimensional measurement space coordinate conversion method for large-span deformed steel truss structure

Similar Documents

Publication Publication Date Title
CN107988908A (en) The total assembling method of tubular arch
CN108049302B (en) A kind of manufacturing method of full welding steel case and full bolt truss combined bridge lower edge steel box-girder
CN104060523B (en) A kind of ultra-large type bridge box beam component, jig frame special and its assemble method
CN105401732B (en) A kind of assemble method of nuclear power station large-sized steel construction module
CN109459311A (en) A kind of experimental provision for simulating pipe ring stress deformation in tunnel under different stress conditions
CN103321296B (en) Annular double-layer truss and manufacture method thereof
CN107498269B (en) A kind of large-scale ship reception chamber manufacturing method suitable for dry type ship compartment room
CN103821372A (en) Method for installing trusses with different heights
CN107100309B (en) A kind of construction method for the large-scale multi-angular cantilever frame of integral hoisting
CN101967886A (en) Assembly and installation methods of steel containment vessel of nuclear power station
CN108103938A (en) A kind of double deck module solid trial assembly method of large steel girder
CN107825083A (en) A kind of wedge bracket structure construction technology
CN209400324U (en) A kind of experimental provision for simulating pipe ring stress deformation in tunnel under different stress conditions
CN202382696U (en) Pipe straightness detection device
CN102518204B (en) Buddha ceremonial canopy and manufacturing method thereof
CN111232154B (en) One-time hoisting, positioning and mounting process for liquefied gas carrier liquid cargo unit
CN102877595A (en) Method for manufacturing large-size and large-span steel truss
CN111691681A (en) Method for mounting outer frame cylinder structure of diagonal steel pipe grid column
CN111335178A (en) Small-curve-radius steel box girder bridge girder erection machine and erection construction method
CN107964864A (en) A kind of trapezoidal bending component of gradual change and manufacture method of anchoringwire in vivo
CN107825077A (en) It is a kind of to rise self-propulsion type platform leg building technology certainly
CN105382491A (en) Machining, manufacturing and inspection method of arc-shaped steel pipe column
CN115059308A (en) Large-span hyperbolic reducing inverted triangular pipe truss assembling method
CN205152802U (en) Improve structure of arched bridge strength nature skeleton building -site preparation precision
CN114043171B (en) Manufacturing method of curve cable tower steel anchor box

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180504