CN106284077A - A kind of tubular arch sections installs measurement and positioning device and construction method - Google Patents

A kind of tubular arch sections installs measurement and positioning device and construction method Download PDF

Info

Publication number
CN106284077A
CN106284077A CN201610602534.0A CN201610602534A CN106284077A CN 106284077 A CN106284077 A CN 106284077A CN 201610602534 A CN201610602534 A CN 201610602534A CN 106284077 A CN106284077 A CN 106284077A
Authority
CN
China
Prior art keywords
tubular arch
arch sections
sections
tubular
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610602534.0A
Other languages
Chinese (zh)
Inventor
陈开桥
杜操
杨秀娟
刘翔
蒋本俊
许鑫
李施展
藕长洪
杨蒙
何盟盟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
7th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
7th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 7th Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN201610602534.0A priority Critical patent/CN106284077A/en
Publication of CN106284077A publication Critical patent/CN106284077A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to Bridge Construction field, disclose a kind of tubular arch sections and measurement and positioning device and a kind of tubular arch sections installation measurement and positioning construction method are installed, be included in the upstream of each tubular arch sections, downstream lateral symmetry arranges reflection paster, angle between reflection paster and tubular arch sections arch rib stringcourse is that this tubular arch sections arch rib installs angle, coordinates total powerstation to complete measurement by reflection paster and makes each tubular arch sections be accurately positioned.The present invention can be precisely controlled tubular arch sections and install, and measures used time shortening, and measurement data is stable, need not survey crew construction operation on arch rib, security risk is low, it is possible in real time carries out long-term observation to setting up rib-lifting section, provides data support for tubular arch closure.

Description

A kind of tubular arch sections installs measurement and positioning device and construction method
Technical field
The present invention relates to Bridge Construction field, be specifically related to tubular arch sections is installed, measure, position and execute Work.
Background technology
Steel tube arch is applicable to river valley, mountain area and complicated landform more, and bridge site district landform is precipitous, and tubular arch sections is installed and surveyed Amount location general measuring method is, when every sections rib-hoisting, survey crew is by foot hands platform to arch rib top surface structure Disposing little prism measurement and positioning on point, operation process security risk is big, and the stability influence that survey crew holds up prism placed in the middle is measured Precision, and measure every time need to judge arch rib stably safety after could measure operation on arch rib, longevity of service, efficiency are low.
Summary of the invention
The technical problem to be solved is to provide a kind of tubular arch sections and installs measurement and positioning device and a kind of steel Pipeline overhead lifting sections installs measurement and positioning construction method, and it has can be precisely controlled the installation of tubular arch sections, measures used time shortening, measures Data stabilization, it is not necessary to survey crew is construction operation on arch rib, security risk is low, it is possible to enter setting up rib-lifting section in real time Row long-term observation, provides the feature of data support for tubular arch closure.
For solving above-mentioned technical problem, the invention provides a kind of tubular arch sections and measurement and positioning device is installed, including: anti- Penetrate paster;
The upstream of each tubular arch sections, downstream lateral symmetry arrange described reflection paster, the work surface court of reflection paster To total powerstation observation station position, the angle between reflection paster work surface and tubular arch sections arch rib stringcourse is this tubular arch sections Arch rib angle is installed, the reflection tubular arch sections front end surface distance one that is secured to of paster on each tubular arch sections Causing, before installation, each reflection paster being positioned on each tubular arch sections of the same side is in same level height, described steel pipe Arch sections front end is the one end towards arch bridge center.
Above-mentioned base case is carried out preferred technical scheme is, the concrete fixed position of described reflection paster is that symmetry sets At the arch rib stringcourse of the both sides, upstream and downstream being placed in tubular arch sections lower chord tube;Or,
The concrete fixed position of described reflection paster is the both sides, upstream and downstream being symmetricly set in tubular arch sections lower chord tube At arch rib stringcourse, the reflection tubular arch sections front end surface distance that is secured to of paster on each tubular arch sections for 1mm~ 1500mm。
The technical scheme improving such scheme is, also includes: antirust thin plate;Described reflection paster is by described anti- Rust thin plate is arranged on described tubular arch sections.
It is that described antirust thin plate is square that such scheme is made further preferred technical scheme.
Technical scheme more preferably is, described antirust thin plate surrounding more described reflection paster width goes out 5mm.
Present invention also offers a kind of tubular arch sections and measurement and positioning construction method is installed, use above-mentioned tubular arch sections Measurement and positioning device is installed, comprises the following steps:
A, determine the arch rib stringcourse of each tubular arch sections;
B, the arch rib calculating each tubular arch sections install angle, the location three-dimensional of each tubular arch sections is sat when installing Mark;
C, arrange on each tubular arch sections described tubular arch sections install measurement and positioning device;
D, by step C arrange tubular arch sections install measurement and positioning device coordinate total powerstation complete measure, according to The location three-dimensional coordinate of tubular arch sections, makes each tubular arch sections be accurately positioned.
It is that described step A is for divide midpoint according to tubular arch sections lower chord tube that said method is made preferred technical scheme In tubular arch sections front end, determine arch rib stringcourse.
Method more preferably is, becomes the linear and pre-arch of bridge to lift each steel when value calculates installation according to described step B The location three-dimensional coordinate of pipeline overhead lifting sections, the arch rib of each tubular arch sections to be installed install angle.
The beneficial effects of the present invention is:
Realizing measurement and positioning by the symmetrical reflection paster being fixed on rib-lifting section both sides in the present invention, sighting condition is good, Be conducive to measurement data stable, install it is thus possible to be precisely controlled tubular arch sections;Need not survey crew construct on arch rib work Industry so that measure job safety risk low, measures efficiency and is greatly improved;Can see for a long time setting up rib-lifting section in real time Survey, provide data support for tubular arch closure.
Accompanying drawing explanation
Fig. 1 is the structural representation of the embodiment of the present invention.
Fig. 2 is the tubular arch sections cross section structure enlarged diagram being mounted with to reflect paster in the embodiment of the present invention.
Wherein, 1-reflects paster, and 2-winds up pipe, 3-lower chord tube, the arch rib stringcourse on 4-lower chord tube, 5-sections splicing line, The arch rib of α-tubular arch sections installs angle.
Detailed description of the invention
By technological means and effect that the present invention by reach predetermined goal of the invention taked being expanded on further, below in conjunction with attached Figure and preferred embodiment, install measurement and positioning device to a kind of tubular arch sections proposed according to the present invention and a kind of employing should Tubular arch sections installs detailed description of the invention and the work of the tubular arch sections installation measurement and positioning construction method of measurement and positioning device It is described in detail as principle.
As shown in Figure 1 and Figure 2, the tubular arch sections that the present embodiment is introduced installs measurement and positioning device, including: reflection patch Sheet 1.Reflection paster 1 concrete set-up mode be: in the upstream of each tubular arch sections, downstream lateral symmetry reflection paster is set 1, the work surface of reflection paster 1, towards total powerstation observation station position, reflects paster 1 work surface and tubular arch sections arch rib stringcourse 3 Between the arch rib that angle is this tubular arch sections angle α is installed, the reflection paster 1 on each tubular arch sections is secured to Tubular arch sections front end surface distance is consistent, before installation, and each reflection paster 1 being positioned on each tubular arch sections of the same side It is in same level height.Tubular arch sections front end is the one end towards arch bridge center.
Reflection paster 1 in the present embodiment is arranged on tubular arch sections by antirust thin plate.For antirust thin steel Plate, it is preferred that use square antirust sheet metal, for square steel-sheet size, it is preferred that use surrounding than reflection paster 1 width goes out the square antirust sheet metal of 5mm, conveniently makes sheet metal be welded on arch rib.Antirust thin plate in the present embodiment uses It it is the square sheet metal having gone up paint.
In the present embodiment reflect paster 1 concrete fixed position as in figure 2 it is shown, tubular arch sections includes: the pipe 2 that winds up, under String pipe 3.At the arch rib stringcourse 4 of the both sides, upstream and downstream that reflection paster 1 is symmetricly set in tubular arch sections lower chord tube 3.For reflection The tubular arch sections front end surface distance that paster 1 is secured to, preferably 1mm~1500mm, the present embodiment uses 50mm。
Present invention also offers a kind of tubular arch sections and measurement and positioning construction method is installed, use above-mentioned tubular arch sections to pacify Dress measurement and positioning device, comprises the following steps:
A, determine the arch rib stringcourse of each tubular arch sections.Preferably, midpoint can be divided according to tubular arch sections lower chord tube Arch rib stringcourse is determined in tubular arch sections front end.
B, calculate each tubular arch sections arch rib install angle α.Preferably, according to becoming the linear and pre-arch of bridge to lift value When calculating installation, the location three-dimensional coordinate of each tubular arch sections, the arch rib of each tubular arch sections to be installed install angle α.
C, arrange on each tubular arch sections above-mentioned tubular arch sections install measurement and positioning device.In the present embodiment, adopt With the square sheet metal of a size of 60 × 60 × 3mm as reflection paster 1 carrier, preferred dimension be 50 × 50mm square instead Penetrate paster 1, select tubular arch sections bottom both sides, arch rib upstream and downstream arch rib stringcourse at as reflection paster, place is set. Concrete grammar is, in each tubular arch sections front end, it is preferred that in tubular arch sections front end apart from its front end surface 1mm~ 1500mm, it is furthermore preferred that the present embodiment uses the upper of the lower chord tube 3 at distance front end surface 50mm of tubular arch sections front end Trip, both sides, downstream, be positioned at the position of arch rib stringcourse 4, is symmetrically welded the square sheet metal of 60 × 60 × 3mm, square sheet metal with should Angle between tubular arch sections arch rib stringcourse 4 is that arch rib installs angle α, by square sheet metal japanning.Steel tube arch rib sections hangs Before dress, reflection paster 1 is arranged on the square sheet metal having gone up paint, and reflects the central point of paster 1 and the upper side of paint Shape sheet metal central point overlap, made paint square sheet metal surrounding than reflection paster 1 wide go out 5mm.Before installation, it is positioned at same Each reflection paster 1 on each tubular arch sections of side is in same level height.Tubular arch sections front end is towards arch bridge The one end at center.
D, by step C arrange tubular arch sections install measurement and positioning device coordinate total powerstation complete measure, survey During discharge observation, sight line is the most vertical with steel plate surface, according to the location three-dimensional coordinate of tubular arch sections, makes each tubular arch sections essence Determine position.
It should be noted last that, above detailed description of the invention only in order to technical scheme to be described and unrestricted, Although the present invention being described in detail with reference to example, it will be understood by those within the art that, can be to the present invention Technical scheme modify or equivalent, without deviating from the spirit and scope of technical solution of the present invention, it all should be contained In the middle of scope of the presently claimed invention.

Claims (8)

1. a tubular arch sections installs measurement and positioning device, it is characterised in that including: reflection paster;
The upstream of each tubular arch sections, downstream lateral symmetry arrange described reflection paster, and the work surface of reflection paster is towards entirely Instrument observation station of standing position, the arch that angle is this tubular arch sections between reflection paster work surface and tubular arch sections arch rib stringcourse Rib installs angle, and the tubular arch sections front end surface distance that the reflection paster on each tubular arch sections is secured to is consistent, peace Before dress, each reflection paster being positioned on each tubular arch sections of the same side is in same level height, and described tubular arch saves Duan Qianduan is the one end towards arch bridge center.
2. tubular arch sections as claimed in claim 1 installs measurement and positioning device, it is characterised in that the tool of described reflection paster Body fixed position is at the arch rib stringcourse of the both sides, upstream and downstream being symmetricly set in tubular arch sections lower chord tube;Or, described reflection patch The concrete fixed position of sheet is at the arch rib stringcourse of the both sides, upstream and downstream being symmetricly set in tubular arch sections lower chord tube, each steel The tubular arch sections front end surface distance that reflection paster on pipeline overhead lifting sections is secured to is 1mm~1500mm.
3. tubular arch sections as claimed in claim 2 installs measurement and positioning device, it is characterised in that also include: antirust thin plate; Described reflection paster is arranged on described tubular arch sections by described antirust thin plate.
4. tubular arch sections as claimed in claim 3 installs measurement and positioning device, it is characterised in that the described antirust thin plate side of being Shape.
5. tubular arch sections as claimed in claim 4 installs measurement and positioning device, it is characterised in that described antirust thin plate surrounding More described reflection paster width goes out 5mm.
6. a tubular arch sections installs measurement and positioning construction method, it is characterised in that use in claim 1 to 5 any one Tubular arch sections described in Xiang installs measurement and positioning device, comprises the following steps:
A, determine the arch rib stringcourse of each tubular arch sections;
B, calculate each tubular arch sections arch rib install angle, install time each tubular arch sections location three-dimensional coordinate;
C, arrange on each tubular arch sections described tubular arch sections install measurement and positioning device;
D, by step C arrange tubular arch sections install measurement and positioning device coordinate total powerstation complete measure, according to steel pipe The location three-dimensional coordinate of arch sections, makes each tubular arch sections be accurately positioned.
7. tubular arch sections as claimed in claim 6 installs measurement and positioning construction method, it is characterised in that described step A is Divide midpoint in tubular arch sections front end according to tubular arch sections lower chord tube, determine arch rib stringcourse.
Tubular arch sections the most as claimed in claims 6 or 7 installs measurement and positioning construction method, it is characterised in that described step B According to become the linear and pre-arch of bridge lift the location three-dimensional coordinate of each tubular arch sections when value calculates installation, each steel to be installed The arch rib of pipeline overhead lifting sections installs angle.
CN201610602534.0A 2016-07-27 2016-07-27 A kind of tubular arch sections installs measurement and positioning device and construction method Pending CN106284077A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610602534.0A CN106284077A (en) 2016-07-27 2016-07-27 A kind of tubular arch sections installs measurement and positioning device and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610602534.0A CN106284077A (en) 2016-07-27 2016-07-27 A kind of tubular arch sections installs measurement and positioning device and construction method

Publications (1)

Publication Number Publication Date
CN106284077A true CN106284077A (en) 2017-01-04

Family

ID=57662830

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610602534.0A Pending CN106284077A (en) 2016-07-27 2016-07-27 A kind of tubular arch sections installs measurement and positioning device and construction method

Country Status (1)

Country Link
CN (1) CN106284077A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107860376A (en) * 2017-11-07 2018-03-30 中国化学工程第三建设有限公司 A kind of measurement and positioning method of the tripod of large-scale indirect cool tower cone segments
CN107988908A (en) * 2017-06-27 2018-05-04 宝鸡中铁宝桥天元实业发展有限公司 The total assembling method of tubular arch
CN109214099A (en) * 2018-09-20 2019-01-15 中建三局基础设施建设投资有限公司 A kind of arch rib steel pipe location Calculation and construction method
CN109612429A (en) * 2018-12-27 2019-04-12 郑州市第建筑工程集团有限公司 A kind of 3-D positioning method of the segment beam end prestress pipe based on total station
CN110331666A (en) * 2019-07-02 2019-10-15 武船重型工程股份有限公司 A kind of high-altitude steel lagging jack segment located lateral method of adjustment
CN112525091A (en) * 2020-11-04 2021-03-19 中铁大桥局第七工程有限公司 Construction method integrating installation, positioning and monitoring of steel box truss arch bridge
CN113502731A (en) * 2021-07-06 2021-10-15 中铁大桥局集团有限公司 Steel pipe arch bridge arch rib closure structure and closure method
CN113931067A (en) * 2020-07-13 2022-01-14 中铁宝桥集团有限公司 Space multidimensional angle control method for inward-inclined basket arch bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201731881U (en) * 2010-07-14 2011-02-02 腾达建设集团股份有限公司 Bridge arch rib vertical rotation deviation measurement device
KR20130126381A (en) * 2012-05-11 2013-11-20 주식회사 장헌산업 Construction method of arch rib in arch bridge
CN103711080A (en) * 2013-12-26 2014-04-09 中国一冶集团有限公司 Method for locating arch ribs of steel tube arch bridge through coordinate correlation method
CN103821088A (en) * 2014-02-13 2014-05-28 中铁四局集团第四工程有限公司 Intelligent measurement construction method for positioning arch rib of long railway tunnel
CN103981810A (en) * 2014-05-20 2014-08-13 中铁十局集团有限公司 Steel tube arch main arch splicing and supporting system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201731881U (en) * 2010-07-14 2011-02-02 腾达建设集团股份有限公司 Bridge arch rib vertical rotation deviation measurement device
KR20130126381A (en) * 2012-05-11 2013-11-20 주식회사 장헌산업 Construction method of arch rib in arch bridge
CN103711080A (en) * 2013-12-26 2014-04-09 中国一冶集团有限公司 Method for locating arch ribs of steel tube arch bridge through coordinate correlation method
CN103821088A (en) * 2014-02-13 2014-05-28 中铁四局集团第四工程有限公司 Intelligent measurement construction method for positioning arch rib of long railway tunnel
CN103981810A (en) * 2014-05-20 2014-08-13 中铁十局集团有限公司 Steel tube arch main arch splicing and supporting system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何旭辉: "澜沧江桥提篮钢管拱安装测量控制探讨", 《中国高新技术企业》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107988908A (en) * 2017-06-27 2018-05-04 宝鸡中铁宝桥天元实业发展有限公司 The total assembling method of tubular arch
CN107860376A (en) * 2017-11-07 2018-03-30 中国化学工程第三建设有限公司 A kind of measurement and positioning method of the tripod of large-scale indirect cool tower cone segments
CN107860376B (en) * 2017-11-07 2020-12-04 中国化学工程第三建设有限公司 Measuring and positioning method for tripod of large-scale intercooling tower cone section
CN109214099A (en) * 2018-09-20 2019-01-15 中建三局基础设施建设投资有限公司 A kind of arch rib steel pipe location Calculation and construction method
CN109612429A (en) * 2018-12-27 2019-04-12 郑州市第建筑工程集团有限公司 A kind of 3-D positioning method of the segment beam end prestress pipe based on total station
CN110331666A (en) * 2019-07-02 2019-10-15 武船重型工程股份有限公司 A kind of high-altitude steel lagging jack segment located lateral method of adjustment
CN113931067A (en) * 2020-07-13 2022-01-14 中铁宝桥集团有限公司 Space multidimensional angle control method for inward-inclined basket arch bridge
CN112525091A (en) * 2020-11-04 2021-03-19 中铁大桥局第七工程有限公司 Construction method integrating installation, positioning and monitoring of steel box truss arch bridge
CN112525091B (en) * 2020-11-04 2022-07-08 中铁大桥局第七工程有限公司 Construction method integrating installation, positioning and monitoring of steel box truss arch bridge
CN113502731A (en) * 2021-07-06 2021-10-15 中铁大桥局集团有限公司 Steel pipe arch bridge arch rib closure structure and closure method

Similar Documents

Publication Publication Date Title
CN106284077A (en) A kind of tubular arch sections installs measurement and positioning device and construction method
CN104631419B (en) The method of monitoring foundation ditch top horizontal movement
CN103114732A (en) Cast steel penetration pipe node space positioning method
CN107806205A (en) A kind of mounting structure and installation method of unlined steel dome
CN107090775A (en) A kind of full framing space beam-ends cable guide pipe construction localization method
CN206235329U (en) Device for drilling, positioning and paying-off in blasting operation
CN106123849A (en) The monitoring method of Vault settlement and monitoring element thereof in a kind of bored tunnel
CN109443327A (en) A kind of distribution method of SURVEYING CONTROL NETWORK
CN103759719A (en) Point location tooling and method for measuring datum point for detecting installation accuracy of circular track beam
CN106223623A (en) Steel construction box arched roof truss installation method
CN108612075A (en) A method of monitoring deep basal pit horizontal displacement
CN115387221A (en) High pier line type control method for high altitude area
CN102966254B (en) Arrangement method for measuring tower used for construction of stub matching method
CN104501727A (en) Measurement method of short circular-arc radius sample plate
CN205785225U (en) A kind of device for cartridge type steel storage tank reverse installation process squareness measurement
CN102967237A (en) Multifunctional measuring apparatus for erecting main cable strand of suspension bridge
CN104390630A (en) Method for measuring and estimating overall inclination of external floating-roof storage tank
CN203702139U (en) Hole digging cast-in-place pile pore-forming quality detection device
CN106197390A (en) A kind of spheroid centre of sphere coordinate location device
CN105716511A (en) Bridge static load test deflection dial indicator measuring and connecting device
CN106949886B (en) Rapid positioning device and positioning method for subway tunnel engineering line measuring point positions
CN210513117U (en) Pole gradient measuring tool
CN106123873B (en) Upright projection positioning measuring device positions cultellation construction method
RU126123U1 (en) DEVICE FOR DETERMINING THE PLANNED ALTITUDE POSITION OF UNDERGROUND PIPELINES
CN205742129U (en) A kind of vertical ship lift balance weight track Fast Installation adjusting apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104

RJ01 Rejection of invention patent application after publication