CN1079468C - Ribbed retaining wall and columned retaining wall - Google Patents

Ribbed retaining wall and columned retaining wall Download PDF

Info

Publication number
CN1079468C
CN1079468C CN 97101434 CN97101434A CN1079468C CN 1079468 C CN1079468 C CN 1079468C CN 97101434 CN97101434 CN 97101434 CN 97101434 A CN97101434 A CN 97101434A CN 1079468 C CN1079468 C CN 1079468C
Authority
CN
China
Prior art keywords
retaining wall
barricade
skeleton
rubble
net structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 97101434
Other languages
Chinese (zh)
Other versions
CN1190146A (en
Inventor
肖炳成
汤小刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shiyan City Planning & Construction Design Inst
Original Assignee
Shiyan City Planning & Construction Design Inst
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shiyan City Planning & Construction Design Inst filed Critical Shiyan City Planning & Construction Design Inst
Priority to CN 97101434 priority Critical patent/CN1079468C/en
Publication of CN1190146A publication Critical patent/CN1190146A/en
Application granted granted Critical
Publication of CN1079468C publication Critical patent/CN1079468C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The present invention relates to a reinforced retaining wall and a columned retaining wall, which has a technical scheme that a reinforcing steel bar frame in a reticular structure or a reinforced concrete column or beam frame in a reticular structure are added to a retaining wall body in the supporting construction of side slopes, and a columned retaining wall in a type of a reinforced retaining wall is formed. The addition of the reinforced concrete column or beam has a restricting function on the retaining wall body, so that the wall body has a strong capacity for deformation. Therefore, the integral shear strength and rigidity of the retaining wall are improved, and furthermore, the capacities for resisting slip and overturn of the retaining wall are improved.

Description

A kind of reinforced retaining wall and strutting barricade
The invention belongs to the barricade in the slope support engineering of civil works, particularly a kind of reinforced retaining wall and strutting barricade.
Usually the supporting barricade that adopts in engineering grouts two types of rubble barricade and steel concrete barricades.Grout the rubble barricade and belong to rigid retaining wall, material compressive strength height, the body of wall shear resistance is low, and integral rigidity is poor, easily produces the part under external force and collapses; The steel concrete barricade, material resistance to compression, shear strength are higher, the body of wall good integrity, rigidity is big, but wall stability is lower, the cost height.
The purpose of this invention is to provide a kind of reinforced retaining wall and strutting barricade, this barricade rigidity is big, good integrity, and cross dimensions is little, has stronger antiskid and moves, resists the ability of inclining and carrying out.
Technical scheme of the present invention is: add the bar frame structural skeleton in rubble, the rectangular slab of stone barricade body grouting of slope support engineering, or reinforced concrete post space truss structure skeleton, form reinforcement or strutting barricade.
Reinforced retaining wall is to arrange reinforcing bar in length and breadth at interval grouting in the rubble barricade body of slope support engineering, extends upward from the basis and forms fastening net structure skeleton, and the net structure skeleton anchors into the ground certain depth, resists the shoe that inclines, antiskid to move ability to increase reinforced retaining wall.
The net structure cross-section of its skeleton shape of above-mentioned reinforced retaining wall is consistent with the barricade cross sectional shape of design be generally up-narrow and down-wide trapezoidal.
The strutting barricade is grouting in mao factory's barricade at slope support engineering, arrange reinforced concrete post at interval in length and breadth, extend upward the fastening concrete column net structure skeleton of formation from the basis, the space truss structure skeleton anchors into the ground certain depth, resists the shoe that inclines, antiskid to move ability to increase the strutting barricade.
The net structure cross-section of its skeleton of above-mentioned strutting barricade forms consistent with the barricade cross sectional shape that designs, and is generally up-narrow and down-wide trapezoidal.
Advantage of the present invention is: owing to add netted structural skeleton of reinforcing bar or reinforced concrete post net structure skeleton in the rubble barricade grouting of slope support engineering, form reinforced retaining wall or strutting barricade.Reinforcing bar that adds or reinforced concrete post have played effect of contraction and the ground anchorage effect to body of wall, make body of wall have stronger deformability, thereby improve the globality of barricade, shear strength and rigidity, and then realized that the antiskid that strengthens barricade moves, the anti-ability of inclining and carrying out.
Further describe the present invention below in conjunction with accompanying drawing.
Fig. 1 grouts the lateral plan of rubble barricade for reinforcement.
Fig. 2 is the front view of the barricade of Fig. 1.
Fig. 3 grouts the side view of rubble barricade for strutting.
Among Fig. 1,2, foundation trench 1 is lower than ground, the degree of depth is as the criterion with the design soil supporting layer, in foundation trench 1, water the C10 concrete cushion, discharge lateral stressed reinforcing bar and longitudinal stress reinforcing bar at regular intervals, form horizontal tectonics muscle 2, plug or anchor into vertical applied force reinforcing bar 3 by design at the width of foundation trench 1 then, the junction welding or the colligation of above-mentioned reinforcing bar.After treating that concrete cushion reaches certain intensity, on concrete cushion, grout contain above-mentioned reinforcing bar grout rubble body 4, when grouting rubble (about 1~1.5 meter) to the first row of horizontal muscle height, stop to grout rubble, lay horizontal tectonics muscle 2, horizontal tectonics muscle 2 and 3 colligations of vertical applied force reinforcing bar or welding.At this moment, tamp with being higher than the cement mortar that grouts the rubble one-level between horizontal tectonics muscle 2 and vertical applied force reinforcing bar 3 and rubble.When continuing to grout ashlar, stop to grout rubble, spread second row of horizontal structure muscle 2, so repeatedly, grout the construction of rubble barricade up to reinforcement and finish to second row of horizontal structure muscle worker height.So just in above-mentioned barricade, form a net structure skeleton, in manufacturing process, the cross sectional shape of the net structure cage of reinforcement in the barricade should be provided with barricade cross sectional shape unanimity, be generally up-narrow and down-wide trapezoidal.
Fig. 3,4 strutting grout the rubble barricade: promptly each steel bar stress that grouts the net structure skeleton in the rubble barricade at above-mentioned reinforcement is changed to reinforced concrete post or beam and forms strutting and grout the rubble barricade.Its reinforced concrete post cross sectional shape is a rectangle.
Strutting grouts the concrete construction sequence of rubble barricade:
Strutting grouts rubble barricade construction sequence:
A, unwrapping wire: the strutting by design grouts the rubble barricade axially at the ground unwrapping wire;
B, dig foundation trench: grout rubble barricade section key dimension by the strutting of design and dig foundation trench on ground, the degree of depth is as the criterion to dig the design soil supporting layer;
C, build bed course: insert the reinforced concrete post reinforcing bar;
Before grouting rubble, in foundation trench, water the C10 concrete cushion, thickness is by designing requirement, and is general>100mm.Before the concreting bed course, fixedly the reinforced concrete post reinforcing bar inserts it into basic degree, and with support that vertical reinforcement is in place;
D, grout ashlar
Treat that concrete cushion reaches certain intensity, on concrete cushion, grout ashlar behind the reinforced concrete post assembling reinforcement;
E, build first floor reinforced concrete post and reinforced concrete beam
Grout and promptly stop to grout rubble after the ashlar height reaches first floor reinforced concrete beam top mark height, set up first floor steel concrete beam steel, outside the reinforced concrete post body of wall, be situated between then and steel concrete top surface of the beam and body of wall outside formwork concreting then, make the formation of first floor reinforced concrete post and beam;
F, treat that first floor reinforced concrete post and beam reach certain intensity after, promptly begin to grout second layer ashlar, after second layer ashlar height reach a certain height, set up second layer steel concrete beam steel, then at steel concrete, make with two layers of reinforced concrete post and beam to form, so repeatedly, grout the construction of rubble barricade until whole strutting and finish.
Reinforcement or strutting are mainly considered by grouting on the random ashlar in the said method, but principle also is applicable to and is grouting woollen stone, reinforcement or strutting in the rubble concrete, or reinforcement or strutting anchor in the ground to improve barricade whole gonosome and rigidity or antiskid moves, the anti-shoe ability of inclining in the steel concrete.
F, treat that first floor reinforced concrete post and beam reach certain intensity after, promptly begin to grout second layer ashlar, after second layer ashlar height reach a certain height, set up second layer steel concrete beam steel, at reinforced concrete post wall outer side and steel concrete top surface of the beam and wall outer side formwork, concreting makes with two layers of reinforced concrete post and beam to form then, so repeatedly, grouting the construction of rubble bumping post until whole strutting finishes.
Reinforcement or strutting are mainly considered but principle also is applicable to and is grouting woollen stone by grouting on the random ashlar in the said method, reinforcement or strutting in the rubble concrete, or reinforcement or strutting anchor in the ground to improve barricade whole gonosome and rigidity or antiskid moves, the anti-shoe ability of inclining in the steel concrete.

Claims (4)

1, a kind of reinforced retaining wall is characterized in that grouting in the rubble in slope support engineering, arranges reinforcing bar in length and breadth at interval, extends upward from the basis and forms fastening net structure skeleton, and the net structure skeleton anchors into the ground certain depth.
2,, it is characterized in that net structure cross-section of its skeleton shape is consistent with the barricade cross sectional shape of design according to the described reinforced retaining wall of claim 1.
3, a kind of strutting barricade, it is characterized in that grouting in the rubble barricade body at slope support engineering, arrange reinforced concrete post, beam at interval in length and breadth, extend upward with the basis and form fastening concrete column, weir shape structural skeleton that the net structure skeleton anchors into the ground certain depth.
4, according to the described strutting barricade of claim 3, it is characterized in that net structure cross-section of its skeleton shape is consistent with the retaining wall cross sectional shape, be generally up-narrow and down-wide trapezoidal.
CN 97101434 1997-02-01 1997-02-01 Ribbed retaining wall and columned retaining wall Expired - Fee Related CN1079468C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 97101434 CN1079468C (en) 1997-02-01 1997-02-01 Ribbed retaining wall and columned retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 97101434 CN1079468C (en) 1997-02-01 1997-02-01 Ribbed retaining wall and columned retaining wall

Publications (2)

Publication Number Publication Date
CN1190146A CN1190146A (en) 1998-08-12
CN1079468C true CN1079468C (en) 2002-02-20

Family

ID=5165733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 97101434 Expired - Fee Related CN1079468C (en) 1997-02-01 1997-02-01 Ribbed retaining wall and columned retaining wall

Country Status (1)

Country Link
CN (1) CN1079468C (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100516382C (en) * 2007-06-18 2009-07-22 于明江 Finishing construction method for sandstone hilly land house foundation
CN107503362A (en) * 2017-09-21 2017-12-22 武汉市政工程设计研究院有限责任公司 A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN112343005A (en) * 2020-11-18 2021-02-09 深圳金煌建设工程有限公司 Water conservancy construction ramp protection structure and protection method

Also Published As

Publication number Publication date
CN1190146A (en) 1998-08-12

Similar Documents

Publication Publication Date Title
CA2306130C (en) Reinforced retaining wall
US6050749A (en) Concrete masonry unit for reinforced retaining wall
AU2007100294A5 (en) Earth Retention and Piling Systems
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
CN104790429A (en) Integral prestress reinforced earth retaining wall construction method
CN111749288B (en) Load-reducing heightening structure of existing retaining wall and construction method thereof
CN112982432A (en) Prestressed concrete foundation pit supporting structure and construction method
CN1167857C (en) Foundation pit side-wall flexible support method
US5123777A (en) Construction elements
CN113389220A (en) Rock slope non-excavation road shoulder retaining wall and construction method thereof
CN1079468C (en) Ribbed retaining wall and columned retaining wall
CN112227391A (en) Ecological steel sheet pile island-building cofferdam and construction method
JP3804943B2 (en) Reinforced earth structure and wall block
CN214883846U (en) High embankment light retaining wall of filling
KR100750703B1 (en) A vegetation block and a method for constructing the cut ground using
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
JP3914073B2 (en) Dry block, molding frame, molding method, reinforced soil structure using dry block
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
JP3818939B2 (en) Reinforced soil structure, embankment reinforcement and reinforced soil block
JP2787806B2 (en) Earth retaining wall
JPS63156120A (en) Construction for cast-in-place form of slope
JP3836443B2 (en) Road widening retaining wall construction method and concrete building block used for it
CN220117273U (en) Prefabricated assembled prestressing force retaining wall
CN218374009U (en) Ecological assembled retaining wall structure that can plant
KR102665377B1 (en) Structure Improved Concrete Panel Retaining Wall and Its Construction Method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee