JPS63156120A - Construction for cast-in-place form of slope - Google Patents
Construction for cast-in-place form of slopeInfo
- Publication number
- JPS63156120A JPS63156120A JP30084886A JP30084886A JPS63156120A JP S63156120 A JPS63156120 A JP S63156120A JP 30084886 A JP30084886 A JP 30084886A JP 30084886 A JP30084886 A JP 30084886A JP S63156120 A JPS63156120 A JP S63156120A
- Authority
- JP
- Japan
- Prior art keywords
- anchor
- slope
- cast
- thickness
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 238000005507 spraying Methods 0.000 claims abstract description 6
- 238000000034 method Methods 0.000 claims description 6
- 229910000831 Steel Inorganic materials 0.000 abstract description 15
- 230000003014 reinforcing effect Effects 0.000 abstract description 15
- 239000010959 steel Substances 0.000 abstract description 15
- 239000004570 mortar (masonry) Substances 0.000 abstract description 12
- 238000005266 casting Methods 0.000 abstract description 5
- 239000004568 cement Substances 0.000 abstract description 2
- 239000008267 milk Substances 0.000 abstract description 2
- 210000004080 milk Anatomy 0.000 abstract description 2
- 235000013336 milk Nutrition 0.000 abstract description 2
- 238000009415 formwork Methods 0.000 description 18
- 238000005452 bending Methods 0.000 description 5
- 238000009434 installation Methods 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 3
- 230000002265 prevention Effects 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000006260 foam Substances 0.000 description 2
- PCHJSUWPFVWCPO-UHFFFAOYSA-N gold Chemical compound [Au] PCHJSUWPFVWCPO-UHFFFAOYSA-N 0.000 description 2
- 239000010931 gold Substances 0.000 description 2
- 229910052737 gold Inorganic materials 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 229920003002 synthetic resin Polymers 0.000 description 2
- 239000000057 synthetic resin Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 208000000260 Warts Diseases 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000007797 corrosion Effects 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000003292 diminished effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 201000010153 skin papilloma Diseases 0.000 description 1
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は、切り土性面、盛土法面等、崩壊や崩落のおそ
れがある法面を保護する現場打ち法枠工法に関する。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a cast-in-place frame construction method for protecting slopes that are at risk of collapsing or collapsing, such as cut earth surfaces and embankment slopes.
現場打ち法枠工法(フリーフレーム工法、ストロングフ
レーム工法)は、近年種々の災害防止工事に採用され、
多様化の傾向がある。主に採用されている防止工事は、
急傾斜地崩壊防止工事、地すべり工事、新設道路及びダ
ム構造物等の法面防護工事等であり、これらの工事にお
いては、抑止力としてアンカー力を導入した使用例が増
加している。Cast-in-place frame construction methods (free frame construction method, strong frame construction method) have been adopted in recent years for various disaster prevention construction works.
There is a tendency towards diversification. The prevention works that are mainly adopted are:
These include collapse prevention work on steep slopes, landslide work, slope protection work for new roads and dam structures, etc. In these works, the use of anchor force as a deterrent is increasing.
一般に土木工事で用いられるコンクリートの強度は昭和
55年度、土木学会で採択されたコンクリート標準示方
書によっているが、現場打ち法枠工法(モルタル及びコ
ンクリート吹付はフレーム工法)も同等品とみなし、そ
の設計にあたっては、上記コンクリート標準示方書に示
された許容応力度を採用することが多い。Generally, the strength of concrete used in civil engineering works is based on the concrete standard specification adopted by the Japan Society of Civil Engineers in 1981, but the cast-in-place frame method (the frame method for mortar and concrete spraying) is also considered to be equivalent, and its design In this regard, the allowable stress level shown in the above-mentioned concrete standard specifications is often adopted.
この種の工法は今後需要が増々多くなることが予想され
ている。Demand for this type of construction method is expected to increase in the future.
ところが、今回の改正で特殊現場打ち法枠工法(フリー
フレーム工法、ストロングフレーム工法)の設計規準強
度が下記第1表の如く大幅に低減される見通しとなった
。However, with this revision, the design standard strength of special cast-in-place frame construction methods (free frame construction method, strong frame construction method) is expected to be significantly reduced as shown in Table 1 below.
上記第1表の許容応力度に基づいて導入可能なアンカー
荷重を計算すると、曲げ圧縮応力のみを考慮して最大2
0 ton程度、剪断応力を併せて考慮すると、15t
on程度まで低下する。この値は従来に比しかなり低い
ため、本工法と組合わせた利点が薄れ、このままだと、
施工範囲が限定されるおそれがある。Calculating the anchor load that can be introduced based on the allowable stress levels in Table 1 above, the maximum 2
Approximately 0 ton, 15 ton when considering shear stress
It decreases to about on level. Since this value is considerably lower than conventional methods, the advantage of combining it with this construction method will be diminished, and if it continues as it is,
The scope of construction may be limited.
そこで、本発明の主たる目的は、経済的に採算がとれ、
アンカー荷重を太き(することができる現場打ち法枠工
法を提供することにある。Therefore, the main purpose of the present invention is to provide an economically viable and
The objective is to provide a cast-in-place frame construction method that can increase the anchor load.
上記目的を達成するため、本発明は、法面地山上に、吹
付は工法で法枠を構築し、法枠の適宜箇所にアンカーを
打設する現場打ち法枠工法において、上記法枠を構築す
る際、アンカー打設部の幅及び厚みのうち少なくとも厚
みを他の部分より厚くしたことを特徴とする。In order to achieve the above-mentioned object, the present invention constructs the above-mentioned slope frame using the cast-in-place method of constructing the slope frame on the slope ground using the spraying method and driving anchors at appropriate locations on the slope. In this case, at least the width and thickness of the anchor driving part is made thicker than other parts.
法枠は、法面の状況に応じて種々の形態を選択し、法面
に溝を切るか、あるいぼ型枠を配置組み立て溝内又は型
枠内にモルタル又はコンクリートを吹付けて構築する。Various forms of slope frames are selected depending on the situation of the slope, and they are constructed by cutting grooves in the slope, or by arranging and assembling certain wart forms and spraying mortar or concrete into the grooves or formwork.
形態は例えば地すべりが予想されるときは、法枠を井桁
又は斜格子とし、局部的な崩壊に過ぎないときは縦枠の
み、又は横枠のみとしてもよい。For example, when a landslide is expected, the legal frame may be a parallel girder or diagonal lattice, and when the collapse is only localized, only vertical frames or only horizontal frames may be used.
法枠を井桁又は斜格子に組むときは、その交差部をアン
カー打設部として選び、縦枠のみ又は横枠のみの場合は
、法面の状況をみて、適宜箇所にアンカー打設部を形成
する。When assembling the slope into a parallel girder or diagonal lattice, select the intersection of the two as the anchor placement area.If there are only vertical or horizontal frames, consider the slope condition and form the anchor placement area at the appropriate location. do.
アンカー打設部の厚み及び幅は、従来、他の部分と同じ
寸法に形成されていたが、本発明においては、他の部分
よりも厚(形成され、法枠及びアンカーの耐力向上が図
られる。Conventionally, the thickness and width of the anchor driving part were formed to be the same as other parts, but in the present invention, the thickness and width of the anchor driving part are formed to be thicker than other parts, so that the strength of the legal frame and the anchor is improved. .
また、必要に応じて溝内又は型枠内に鉄筋又はPC鋼よ
り線を敷設し、法枠の耐力を向上させてもよく、アンカ
ー打設部の幅を広くして支持面圧を小さくしてもよい。In addition, if necessary, reinforcing bars or prestressed steel strands may be laid in the groove or formwork to improve the strength of the framework, and the width of the anchoring part may be widened to reduce the support surface pressure. It's okay.
アンカーを打設し、緊張すると、法面より反作用として
分布荷重や集中荷重を受け、法枠の各梁に曲げモーメン
トが生じる。この曲げモーメントはアンカー打設点直下
で最も大きくなり、この曲げモーメントによりアンカー
打設部の裏面に引張力が生じるが、本発明においてはア
ンカー打設部の厚みが他の部分よりも厚く形成されてい
るため、その部分の断面係数が大きく、裏面に生じる引
張応力が小さくなる。したがって、アンカーの耐力を高
めることができ、適用範囲を更に広くすることができる
。When anchors are installed and tensioned, each beam of the slope receives a distributed or concentrated load as a reaction from the slope, and a bending moment is generated in each beam of the slope. This bending moment is greatest immediately below the anchor driving point, and this bending moment generates a tensile force on the back surface of the anchor driving part, but in the present invention, the thickness of the anchor driving part is formed thicker than other parts. Therefore, the section modulus of that part is large, and the tensile stress generated on the back surface is small. Therefore, the strength of the anchor can be increased and the range of application can be further expanded.
以下、図面を参照して実施例を説明する。 Examples will be described below with reference to the drawings.
本発明においては法枠及びアンカー打設部の形態を法面
の状況に合わせて種々採ることができる。In the present invention, various forms of the slope frame and the anchor driving portion can be adopted depending on the situation of the slope.
第1図に示す例は、法枠1を井桁に組み、梁la、lb
の公差部をアンカー打設部2としたもので、地すべりが
予想される法面に適用される。In the example shown in Fig. 1, the slope frame 1 is assembled into a parallel girder, and the beams la, lb
The tolerance part is set as the anchor driving part 2, and is applied to slopes where landslides are expected.
図示例ではアンカー打設部2の幅が梁1a、1bの幅よ
りも大きくされ支持面が広くされるとともに、厚みHが
他の部分1a、lbの厚みhより厚く、すなわち、他の
部分1a、lbより深く構築され、厚くされている。In the illustrated example, the width of the anchor driving part 2 is larger than the width of the beams 1a and 1b to widen the support surface, and the thickness H is thicker than the thickness h of the other parts 1a and lb, that is, the width of the anchor driving part 2 is larger than that of the beams 1a and 1b. , lb. are built deeper and thicker.
また、図示例は、法枠1の構築に当って型枠4を金網で
形成し、埋め殺しとしたものであるが、これに限るもの
ではなく、型枠4を耐水性段ボール、エキスバンドメタ
ル、合成樹脂発泡体、コンクリート板等により形成して
もよい。型枠4内には、図にもみられるように必要に応
じて鉄筋又はPC鋼より線4a、・・・を上下左右に配
し、長手方向に生じた引張力をこれら鉄筋又はPC鋼よ
り線4a、・・・に分担させて受は持たせるようにして
もよい。また、法枠1の構築にあたっては、アンカー鋼
棒3aのガイドとしてアンカー打設部2の中心位置に補
強管5を埋設することが望しい。In addition, in the illustrated example, the formwork 4 is formed of wire mesh and filled in when constructing the legal frame 1, but the formwork 4 is not limited to this, and the formwork 4 is made of water-resistant cardboard, expanded metal , synthetic resin foam, concrete plate, etc. As can be seen in the figure, within the formwork 4, reinforcing bars or PC steel stranded wires 4a,... are arranged on the top, bottom, left and right as needed, and the tensile force generated in the longitudinal direction is transferred to these reinforcing bars or PC steel stranded wires. 4a, . . . may share the role of Uke. Further, in constructing the legal frame 1, it is desirable to bury a reinforcing pipe 5 at the center of the anchor driving portion 2 as a guide for the anchor steel rod 3a.
施工に際しては、例えば次の順序によることができる。The construction can be carried out in the following order, for example.
(1) まず、金網から成る型枠4を法面R上に配置
し、井桁に組み上げるとともにアンカー打設部2の厚み
Hが他の部分1a、lbの厚みhよりも厚くなるように
交差部の真下をアンカー打設部2の形態となるように四
角形状に掘り下げる。(1) First, the formwork 4 made of wire mesh is placed on the slope R, and assembled into a cross section, and the intersection is made so that the thickness H of the anchor driving part 2 is thicker than the thickness h of the other parts 1a and lb. Dig into a rectangular shape directly below to form the anchor driving part 2.
(2) もし必要ならば、補助アンカーを用いて型枠
4を法面R上に固定し、次いで型枠4内に鉄筋又はPC
鋼より線4aを上下、左右に配筋する。(2) If necessary, use auxiliary anchors to fix the formwork 4 on the slope R, and then install reinforcing bars or PC in the formwork 4.
Steel stranded wires 4a are arranged vertically and horizontally.
(3) このようにしてアンカー打設部2が組み上が
ったら、その中心位置に補強管5を配設し、次いで吹付
は工法にてモルタル又はコンクリート6を型枠4内に打
設する。打設の際鉄筋又はPC!ijlより線4 a
+ ・・・に高周波バイブロを取り付け、バイブロの振
動で、打設したモルタル又はコンクリート6を均一に押
し固めてもよい。(3) Once the anchor installation part 2 is assembled in this way, the reinforcing pipe 5 is arranged at its center position, and then mortar or concrete 6 is poured into the formwork 4 using the spraying method. Reinforcement or PC when pouring! ijl strand 4 a
A high-frequency vibro may be attached to +..., and the placed mortar or concrete 6 may be uniformly compacted by the vibration of the vibro.
(4)アンカー打設部2においては、モルタル又はコン
クリート6の吹付は量を多くし、次いで、人力又はコン
ポにより、第1図にみられる角柱形状となるように形を
整える。他の部分1a、lbについても同様の手段で形
を整えてもよい。(4) In the anchor placement part 2, a large amount of mortar or concrete 6 is sprayed, and then the shape is shaped into the prismatic shape shown in FIG. 1 by hand or by a component. The other portions 1a and lb may also be shaped by similar means.
(5)上記のようにして法枠1の構築が終了したらアン
カー打設を行なう。(5) After completing the construction of the legal frame 1 as described above, cast the anchor.
(6)まず、補強管5を介してすべり面の深部に達する
までアンカ一孔を削孔し、次いでアンカー鋼棒3aを孔
内に挿入し、定着部にセメントミルク又はモルタルを注
入して固定する。約4週間程度の養生期間を置いてアン
カー頭部を座金3b、及びナンド3Cでアンカー打設部
2に締付け、アンカー鋼棒3aを緊張状態で固定する。(6) First, drill an anchor hole through the reinforcing pipe 5 until it reaches the deep part of the sliding surface, then insert the anchor steel rod 3a into the hole, and inject cement milk or mortar into the anchoring part to fix it. do. After a curing period of about 4 weeks, the anchor head is tightened to the anchor driving part 2 with a washer 3b and a pad 3C, and the anchor steel rod 3a is fixed under tension.
次いでアンカー頭部を保護するため、頭部をモルタル又
はコンクリートにより埋設する。Next, to protect the anchor head, the head is buried in mortar or concrete.
以上は、アンカー打設部を他の部分より深くして厚みを
大きくとった例であるが、法面が岩盤のように硬い場合
は、第2図のA矢視で示すように、アンカー打設部2の
高さを他の部分1a、lbの高さよりも高くし、厚みを
大きくとることもできる。The above is an example of making the anchor driving part deeper and thicker than other parts, but if the slope is hard like rock, anchor driving should be done as shown by arrow A in Figure 2. It is also possible to make the height of the installation part 2 higher than the height of the other parts 1a and lb, and to make it thicker.
また、B矢視で示すように、両者を併用してもよい。Moreover, as shown in arrow B, both may be used together.
上記実施例は梁の厚みに対し、アンカー打設部の厚みを
不連続的に大きくとった例であるが、第3図に示すよう
に連続させてもよい。この例は井桁を構成する各梁1a
、lbの高さを漸近的に高くし、最終的にアンカー打設
部2の厚みを他の部分1a、lbよりも厚くした例であ
る。この例においては、アンカー打設部2と梁1a、l
bとの間に応力集中が起り難り<、また各梁1a、1b
の断面積が曲げモーメントの増加に伴って増加するため
、曲げに対し、強い抵抗力を示す。Although the above embodiment is an example in which the thickness of the anchor driving portion is made discontinuously larger than the thickness of the beam, it may be made continuous as shown in FIG. In this example, each beam 1a constituting the parallel
, lb are increased asymptotically, and the thickness of the anchor driving part 2 is finally made thicker than the other parts 1a and lb. In this example, the anchor installation part 2 and the beams 1a, l
It is difficult for stress concentration to occur between the beams 1a and 1b.
Since the cross-sectional area of the material increases as the bending moment increases, it exhibits strong resistance to bending.
第4図はラジアル方向に等しい強度を持たせるため、ア
ンカー打設部2の形状を円柱形状とし、他の部分1a、
lbよりも高くした例である。この例では、第5図及び
第6図にみられるように、スパイラル筋7を補強管5と
同心に配し、割裂等の防止が図られている。In Fig. 4, in order to have equal strength in the radial direction, the shape of the anchor driving part 2 is cylindrical, and the other parts 1a,
This is an example where it is higher than lb. In this example, as shown in FIGS. 5 and 6, the spiral reinforcement 7 is arranged concentrically with the reinforcing tube 5 to prevent splitting and the like.
施工にあたっては、まず井桁を構成する梁1a。In construction, the first thing to do is to build the beam 1a that will make up the crossbeam.
1b及びその交点となるアンカー打設部2の外形を縁取
るように型枠を第5図にみられる破線に沿って配し、次
いでアンカー打設部2の中心に補強管5及びスパイラル
筋7を配した後、梁1a、1bの上下、左右に鉄筋又は
pc鋼より線4a、・・・を配して枠組みを構成する。1b and the intersection thereof, a formwork is placed along the broken line shown in FIG. After placing the beams 1a and 1b, reinforcing bars or PC steel wires 4a, etc. are placed above and below, on the left and right sides of the beams 1a and 1b to form a framework.
型枠を構成する材料は、耐水性段ボール、合成樹脂発泡
体、コンクリート板、木型等いずれであってもよい。実
施例ではアンカー打設部2の高さが他の部分1a、lb
よりも高くされているため、型枠も他の部分よりも高く
しておくことが望しい。The material constituting the formwork may be water-resistant cardboard, synthetic resin foam, concrete board, wooden mold, or the like. In the embodiment, the height of the anchor driving part 2 is different from that of the other parts 1a and lb.
Since it is higher than the other parts, it is desirable that the formwork is also higher than the other parts.
次いで、上方より型枠に向けてモルタル又はコンクリー
ト6を吹付け、法枠1を構築する。法枠1の上面をコテ
等で均らした後、アンカーを打設する。アンカーの打設
は前実施例と同様であるため、ここではその説明を省略
する。Next, mortar or concrete 6 is sprayed from above toward the formwork to construct the legal frame 1. After leveling the upper surface of the legal frame 1 with a trowel or the like, anchors are driven. Since the anchor placement is the same as in the previous embodiment, the explanation thereof will be omitted here.
第7図及び第8図は、法面Rの状態が局部的な崩壊に過
ぎない場合に適用した例であり、この実施例では、法枠
1が縦枠のみで構成され、適宜箇所にアンカー打設部2
が設けられる。縦枠1. 1との間は、法面Rを覆うよ
うにして金WI8と、その金網8を押え付けるように横
に追わした複数の鉄筋又はPC鋼より線9.・・・によ
り抑止力が持たせられる。アンカー打設部2は、第7図
にみられるように角柱に形成してもよく、第8図のよう
に楕円柱に形成してもよい。いずれの場合においても他
の部分よりも高く形成される。7 and 8 are examples applied when the condition of the slope R is only a local collapse. In this example, the slope frame 1 is composed of only vertical frames, and anchors are placed at appropriate locations. Casting part 2
is provided. Vertical frame 1. 1 and 1, there is a gold WI8 covering the slope R, and a plurality of reinforcing bars or PC steel stranded wires 9 placed laterally to press down the wire mesh 8. ... provides a deterrent effect. The anchor driving portion 2 may be formed into a square column as shown in FIG. 7, or may be formed into an elliptical column as shown in FIG. In either case, it is formed higher than other parts.
施工に際しては、例えば次の順序によることができる。The construction can be carried out in the following order, for example.
(1)まず、抑止を必要とする法面Rに沿って金!ii
8を敷設し、その上から鉄筋又はPC鋼より線9、・・
・を横方向に這わせる。ここで用いられる鉄筋又はPC
鋼より線9.・・・は、雨水に晒されるため、できれば
、腐食しないようにシースしたものが望しい。
・
(2)次いで、法面Rの縦方向の所定位置に金網からな
る型枠4.4及び型枠に沿って鉄筋又はpc鋼より線6
.・・・を配設する。アンカー打設部2となる位置には
、図示されていないが、アンカー3のガイドとなる補強
管を予め立設しておく。(1) First, there is gold along the slope R that requires deterrence! ii
8, and then reinforcing bars or PC steel stranded wires 9,...
・Crawl horizontally. Rebar or PC used here
Steel strand9. ... is exposed to rainwater, so if possible, it is desirable to have a sheath to prevent corrosion.
・(2) Next, a formwork 4.4 made of wire mesh is placed at a predetermined position in the vertical direction of the slope R, and reinforcing bars or PC steel stranded wires 6 are placed along the formwork.
.. ... will be installed. Although not shown, a reinforcing tube that serves as a guide for the anchor 3 is previously installed upright at a position that will become the anchor installation portion 2 .
(3) このようにして枠組みが組み上がったら、型
枠4.4内にモルタルまたはコンクリート6を吹付は法
枠1を構築する。(3) Once the framework is assembled in this way, mortar or concrete 6 is sprayed into the formwork 4.4 to construct the legal framework 1.
(4)法枠1の上面及び側面をコテ等で均らし、特にア
ンカー打設部2においては、第7図にみられるように角
柱又は第8図にみられるように楕円柱となるように形を
整える。(4) Level the top and side surfaces of the legal frame 1 using a trowel or the like, especially in the anchor driving part 2, so that it becomes a square column as shown in Fig. 7 or an elliptical column as shown in Fig. 8. Adjust the shape.
(5)次いでモルタル又はコンクリートの強度発現を待
って、アンカー3の打設を行なう。この打設は前実施例
と同様の手段で行なう。(5) Next, wait for the strength of the mortar or concrete to develop, and then cast the anchor 3. This casting is carried out in the same manner as in the previous embodiment.
以上の手順により法枠1を構築し、崩壊のおそれがある
法面を保護する。The slope 1 is constructed using the above procedure to protect the slope that is at risk of collapse.
従来より下回る許容応力度が新たに設定されても、本発
明方法によれば、従来に劣らぬアンカー耐力を経済的に
得ることができ、適用範囲を拡げることができる。Even if an allowable stress level lower than the conventional method is newly set, according to the method of the present invention, it is possible to economically obtain an anchor proof strength comparable to that of the conventional method, and the range of application can be expanded.
第1図は、本発明の一実施例を示した部分切欠き斜視図
、第2図は、第1図の変形例を示した斜視図、第3図及
び第4図は本発明の他の実施例を示した斜視図、第5図
は第4図の枠組みを示した平面図、第6図は第5図の正
面図、第7図及び第8図は本発明の具体的構成を縦枠の
みに適した斜視図である。
1・・・法枠、la、lb・・・梁、2・・・アンカー
打設部、3・・・アンカー、3a・・・アンカー鋼棒、
3b・・・座金、3C・・・ナンド、4・・・型枠、4
a・・・鉄筋又はPC!!4より線、5・・・補強管、
6・・・モルタル又はコンクリート、7・・・スパイラ
ル筋、8・・・金網、9・・・鉄筋又はpc鋼より線、
R・・・法面、H・・・アンカー打設部の厚み、h・・
・梁(他の部分)の厚み。
特許出願人 ライト工業株式会社
代 理 人 弁理士 永井義久
第1図
第2図
第4図
第5図
第7図
第8図FIG. 1 is a partially cutaway perspective view showing one embodiment of the present invention, FIG. 2 is a perspective view showing a modification of FIG. 1, and FIGS. 3 and 4 show other embodiments of the invention. FIG. 5 is a plan view showing the framework of FIG. 4, FIG. 6 is a front view of FIG. 5, and FIGS. 7 and 8 are longitudinal views showing the specific structure of the present invention. FIG. 4 is a perspective view suitable for frames only; 1... Law frame, la, lb... beam, 2... anchor driving part, 3... anchor, 3a... anchor steel bar,
3b...Washer, 3C...Nand, 4...Formwork, 4
a...Reinforcing steel or PC! ! 4 stranded wire, 5... reinforcing pipe,
6...Mortar or concrete, 7...Spiral reinforcement, 8...Wire mesh, 9...Reinforcement bar or PC steel stranded wire,
R...Slope surface, H...Thickness of anchor installation part, h...
・Thickness of the beam (other parts). Patent applicant: Light Kogyo Co., Ltd. Representative: Yoshihisa Nagai, patent attorney Figure 1 Figure 2 Figure 4 Figure 5 Figure 7 Figure 8
Claims (1)
の適宜箇所にアンカーを打設する現場打ち法枠工法にお
いて、上記法枠を構築する際、アンカー打設部の幅及び
厚みのうち少くとも厚みを他の部分より厚くしたことを
特徴とする現場打ち法枠工法。(1) In the cast-in-place method, in which a slope is constructed using the spraying method on top of the slope and anchors are driven at appropriate locations on the slope, when constructing the slope, it is necessary to A cast-in-place frame construction method characterized by making at least the width and thickness thicker than other parts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30084886A JPS63156120A (en) | 1986-12-17 | 1986-12-17 | Construction for cast-in-place form of slope |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30084886A JPS63156120A (en) | 1986-12-17 | 1986-12-17 | Construction for cast-in-place form of slope |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS63156120A true JPS63156120A (en) | 1988-06-29 |
Family
ID=17889845
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30084886A Pending JPS63156120A (en) | 1986-12-17 | 1986-12-17 | Construction for cast-in-place form of slope |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63156120A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02200916A (en) * | 1989-01-30 | 1990-08-09 | Kensetsu Kiso Eng Kk | Slope surface protecting structure and its operation method |
JPH02213521A (en) * | 1989-02-14 | 1990-08-24 | Takayoshi Fujiwara | Normal plane protection work by mainly using |
JPH0328420A (en) * | 1989-06-26 | 1991-02-06 | Shuji Shimizu | Slope protection method |
JPH05112944A (en) * | 1991-10-21 | 1993-05-07 | Kensetsu Kiso Eng Co Ltd | Slope protective structure |
JP2002309584A (en) * | 2001-04-11 | 2002-10-23 | Sango:Kk | Frame for forming slope protection frame and method for constructing slope protection frame using the same |
JP2007100344A (en) * | 2005-10-03 | 2007-04-19 | Okabe Co Ltd | Method for grating crib work |
JP2009052392A (en) * | 2007-07-30 | 2009-03-12 | Hayashi Kensetsu Kk | Method for reinforcing mortar sprayed layer |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54118602A (en) * | 1978-03-06 | 1979-09-14 | Yuuji Kawai | Method of executing slope face protective construction |
JPS5938425A (en) * | 1982-08-26 | 1984-03-02 | Makoto Kaneuji | Cutting work of slope |
JPS59199916A (en) * | 1983-06-27 | 1984-11-13 | Kensetsu Kiso Eng Kk | Slope protection work |
-
1986
- 1986-12-17 JP JP30084886A patent/JPS63156120A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54118602A (en) * | 1978-03-06 | 1979-09-14 | Yuuji Kawai | Method of executing slope face protective construction |
JPS5938425A (en) * | 1982-08-26 | 1984-03-02 | Makoto Kaneuji | Cutting work of slope |
JPS59199916A (en) * | 1983-06-27 | 1984-11-13 | Kensetsu Kiso Eng Kk | Slope protection work |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02200916A (en) * | 1989-01-30 | 1990-08-09 | Kensetsu Kiso Eng Kk | Slope surface protecting structure and its operation method |
JPH02213521A (en) * | 1989-02-14 | 1990-08-24 | Takayoshi Fujiwara | Normal plane protection work by mainly using |
JPH0328420A (en) * | 1989-06-26 | 1991-02-06 | Shuji Shimizu | Slope protection method |
JPH05112944A (en) * | 1991-10-21 | 1993-05-07 | Kensetsu Kiso Eng Co Ltd | Slope protective structure |
JP2002309584A (en) * | 2001-04-11 | 2002-10-23 | Sango:Kk | Frame for forming slope protection frame and method for constructing slope protection frame using the same |
JP2007100344A (en) * | 2005-10-03 | 2007-04-19 | Okabe Co Ltd | Method for grating crib work |
JP2009052392A (en) * | 2007-07-30 | 2009-03-12 | Hayashi Kensetsu Kk | Method for reinforcing mortar sprayed layer |
JP4588084B2 (en) * | 2007-07-30 | 2010-11-24 | 林建設株式会社 | Reinforcement method of mortar spray layer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100958014B1 (en) | Construction method of steel composite girder bridge | |
KR20090013528A (en) | The prestressed tunnel support structure | |
CN102418387A (en) | Post-tensioning external prestressed steel beam and pre-tensioning prestressed superposed beam combined building structure system and construction technology thereof | |
KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
KR20210009014A (en) | The stress loss prevention system in case of cutting pile-head in pre-stressed concrete pile of pre-tensioning system | |
JPS63156120A (en) | Construction for cast-in-place form of slope | |
KR102104932B1 (en) | Precast modular system retaining wall | |
KR101521946B1 (en) | Enlarged capital of steel framed reinforced concrete column | |
JP2004100157A (en) | Retaining wall structure and its construction method | |
KR101157607B1 (en) | Prestressed steel composite girder with prestressed non-introducing portions provided at both ends of lower flange casing concrete, manufacturing method thereof, and Rahmen structure and construction method thereof | |
JP3118210B2 (en) | Building structures using piles as pillars | |
KR102111153B1 (en) | Retaining Wall Panel Structure using PC Strand | |
JP6817589B1 (en) | How to build pile support structure | |
KR101483865B1 (en) | Construction Method of Underground Structure using Composite Wale | |
JP2641182B2 (en) | Slope stabilization method and slope expansion method | |
US10077539B1 (en) | Wall and retaining members and fluidizing installation of retaining members | |
JPH0237442B2 (en) | DOROKAKUFUKUKOHO | |
KR20200004087A (en) | Method constructing the reinforcing materials to the minus moment of continuous girder | |
KR100380907B1 (en) | Precast concrete segment for arch type culvert and construction method using this segment | |
CN1079468C (en) | Ribbed retaining wall and columned retaining wall | |
KR102353664B1 (en) | Removal Pre-Stressed Beam and Construction Methods thereof | |
JP7270412B2 (en) | Reinforcement structure of masonry building | |
JP2592438B2 (en) | Overhang structure | |
CN118273365A (en) | Side slope supporting structure adjacent to highway and supporting method | |
KR101045315B1 (en) | Prestressed concrete panel with prestress non-introducing portions provided in both slope ends, manufacturing method thereof, precasted Rahmen and construction method thereof using the same |