CN107939420A - The construction method filled after two backing of bored tunnel assembled - Google Patents

The construction method filled after two backing of bored tunnel assembled Download PDF

Info

Publication number
CN107939420A
CN107939420A CN201710720494.4A CN201710720494A CN107939420A CN 107939420 A CN107939420 A CN 107939420A CN 201710720494 A CN201710720494 A CN 201710720494A CN 107939420 A CN107939420 A CN 107939420A
Authority
CN
China
Prior art keywords
beans gravel
section
grouting
assembled
behind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710720494.4A
Other languages
Chinese (zh)
Inventor
王一
李宝文
孟祥友
任建
胡伟
李嵩
李东
赵婷婷
徐小龙
魏凤东
马雪松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Beijing Railway Construction Co of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Beijing Railway Construction Co of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201710720494.4A priority Critical patent/CN107939420A/en
Publication of CN107939420A publication Critical patent/CN107939420A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • E21D11/386Sealing means positioned between adjacent lining members inflatable sealing means

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The construction method filled after two backing of bored tunnel assembled belongs to railway traffic engineering technical field of construction.It is characterized in that:After the assembly for completing each endless tube piece, carry out hydraulic reclamation beans gravel to the gap between prefabricated pipe section behind and branch structure at the beginning of main track and construct;The order of hydraulic reclamation beans gravel for from the bottom to top, it is symmetrical;Install bellows seal additional in pipe ring termination, Dong Bishang is withstood on after air sac sealing inflation, when equipment moves forward, air bag deflation, mounting base drives air bag reach;It is using cement mortar that the beans gravel gap filling of ring prefabricated pipe section filling behind is full after 20 rings are completed in assembly, closed-loop is formed, longitudinally every hole slip casting during grouting, per one hole of five rings note;Every 20 ring carries out once circumferential closure, and circumferential direction closure uses chemical grouting.The present invention can control ground settlement, strengthen the waterproof ability in assembled tunnel, prevent duct piece float upward and sidesway, and low easy to construction, safe, short time limit, cost.

Description

The construction method filled after two backing of bored tunnel assembled
Technical field
The invention belongs to railway traffic engineering technical field of construction, is adopted more particularly to one kind applied to Bored Section of Metro With the tunnel of the lining construction of assembled two, the construction party being filled to gap of the prefabricated pipe section behind between branch structure at the beginning of main track Method.
Background technology
Available data shows that bored tunnel fabricated construction has been implemented and applied in Japan and the Soviet Union.It is domestic at present right Shield-bored tunnels fabricated construction studies comparative maturity, but to the research that bored tunnel assembled two serves as a contrast also in a step Section.Domestic tunnel machine is mainly reflected in shield and TBM (being suitable for lithostratigraphy) tunnel construction technology, its outstanding feature To use prefabricated pipe section component as two lining structures, so as to improve construction efficiency with reducing project cost.
Bored tunnel assembled two serves as a contrast and gap is left between prefabricated pipe section and just lining, is timely carried out behind after the completion of assembled Filling is a highly important process, its construction effect mainly has following three aspects:
1st, gap is filled in time, is supported section of jurisdiction surrounding rock body, is efficiently controlled ground settlement.
2nd, first waterproof barrier of the slurries condensed as construction tunnel, strengthens the waterproof ability in assembled tunnel.
3rd, stablizing and making section of jurisdiction integrated with first branch for early stage is provided for section of jurisdiction, prevents duct piece float upward and sidesway, and can be really The final of assembled tunnel is protected to stablize.
The content of the invention
Difficulty of construction is reduced at the same time in order to reach the effect above, and it is an object of the invention to provide a kind of Bored Section of Metro The construction method filled after two backing of main track assembled.
In order to achieve the above object, the construction filled after two backing of Bored Section of Metro main track assembled provided by the invention Method includes the following steps carried out in order:
1) after the assembly for completing each endless tube piece, using the beans gravel pack system (3) in pipe sheet assembling equipment by pre- The radial grouting hole (5) of tubulation on piece to prefabricated pipe section (1) behind with main track at the beginning of gap between branch structure (2) carry out hydraulic reclamation beans Gravel is constructed;Beans gravel is transported to beans gravel pump (10) through belt feeder (11), is filled by compressed air to section of jurisdiction behind, hydraulic reclamation beans The order of gravel for from the bottom to top, it is symmetrical.
2) to prevent that beans gravel overflows when synchronously noting beans gravel, in pipe ring termination installation bellows seal, air sac sealing Dong Bishang is withstood on after inflation, when pipe sheet assembling equipment moves forward, air bag deflation, mounting base drives air bag reach.
3) after 20 rings of assembled completion, filling system (4) injects water behind by radial grouting hole (5) to prefabricated pipe section (1) Mud, it is using cement mortar that the beans gravel gap filling of ring prefabricated pipe section filling behind is full, form closed-loop, grouting sequence For from the bottom to top, it is symmetrical, longitudinally every hole slip casting, (per one hole of tricyclic note, the backfill of vault block beans gravel is difficult, slurries during grouting Mobility is larger, per one hole of five rings note).When pore pressure force of being in the milk reaches 0.2MPa~0.3MPa, grout hole stopping slip casting, and after Continuous perfusion 5min can terminate.
4) since grouting serous fluid pressure is larger, to prevent that slurries are excessive by section of jurisdiction front end, close measure, every 20 ring need to be increased Carry out once circumferential closure (just branch and section of jurisdiction radial clearance);Since common grouting material grouting setting time is difficult to control, expand It is big to dissipate scope, it is difficult to quick closure is formed, and chemical grouting material has setting time controllable small with range of scatter, can quickly seal The advantages of closing, so using chemical grouting.
The beans gravel pack system mainly by beans gravel pack pot (9), beans gravel belt feeder (11), beans gravel pump (10) and The part such as air compressor machine (8) forms.
The filling system is mainly made of grouting pump (12), agitator tank (14).Drive is separately configured in slip casting trolley (13) Dynamic portion (15), can automatic moving as needed.
The close measure uses chemical grouting.
Highly it is not less than 100mm during the airbag aeration, unaerated is highly 60mm.
The construction method filled after two backing of Bored Section of Metro main track assembled provided by the invention can fill in time Gap between section of jurisdiction and just lining, supports section of jurisdiction surrounding rock body, efficiently controls ground settlement;Simultaneously coagulated slurries are used as and apply First of waterproof barrier in work tunnel, strengthens the waterproof ability in assembled tunnel;For section of jurisdiction provide early stage stablize and make section of jurisdiction with First branch integration, prevents duct piece float upward and sidesway, it is ensured that the final of assembled tunnel is stablized;And easy to construction, security it is higher, Short time limit, construction cost are low.
Brief description of the drawings
Fig. 1 serves as a contrast horizontal sectional schematic diagram for metro built by mining method assembled two.
Fig. 2 is beans gravel pack system schematic.
Fig. 3 is filling system schematic diagram.
Fig. 4 is prefabricated pipe section side portion structure diagram.
Fig. 5, Fig. 6 are beans gravel pipe ring faces end head plugging measure schematic diagram.
The meaning of digital representation in figure:1st, prefabricated pipe section;2nd, the first branch structure of main track;3rd, beans gravel pack system;4th, slip casting System;5th, injected hole;6th, inflated condition air bag;7th, deflation status air bag;8th, air compressor machine;9th, beans gravel pack pot;10th, beans gravel pump; 11st, chad stone belt feeder;12nd, grouting pump;13rd, slip casting trolley;14th, agitator tank;15th, driving unit;16th, mounting base
Embodiment
Below in conjunction with the accompanying drawings with specific embodiment to two backing of Bored Section of Metro main track assembled provided by the invention after The construction method of filling is described in detail.The component identical with prior art uses identical label, and omits and it is carried out Explanation.
Now illustrated by taking certain Bored Section of Metro engineering as an example:As shown in Figure 1, two lining structure of section breaks for the shape of a hoof Face, assembled by the first to the 6th prefabricated pipe section, there are gap between prefabricated pipe section and the first branch structure of main track need to carry out behind Filling.
As shown in Figs. 1-5, the work side applied is filled after two backing of Bored Section of Metro main track assembled provided in this embodiment Method includes the following steps carried out in order:
1) after the assembly for completing each endless tube piece, using the beans gravel pack system (3) in pipe sheet assembling equipment by pre- The radial grouting hole (5) of tubulation on piece to prefabricated pipe section (1) behind with main track at the beginning of gap between branch structure (2) carry out hydraulic reclamation beans Gravel is constructed;Beans gravel is transported to beans gravel pump (10) through belt feeder (11), is filled by compressed air to section of jurisdiction behind, hydraulic reclamation beans The order of gravel for from the bottom to top, it is symmetrical.
2) to prevent that beans gravel overflows when synchronously noting beans gravel, in pipe ring termination installation bellows seal, air sac sealing Dong Bishang is withstood on after inflation, when pipe sheet assembling equipment moves forward, air bag deflation, mounting base drives air bag reach.
3) after 20 rings of assembled completion, filling system (4) injects water behind by radial grouting hole (5) to prefabricated pipe section (1) Mud, it is using cement mortar that the beans gravel gap filling of ring prefabricated pipe section filling behind is full, form closed-loop, grouting sequence For from the bottom to top, it is symmetrical, longitudinally every hole slip casting, (per one hole of tricyclic note, the backfill of vault block beans gravel is difficult, slurries during grouting Mobility is larger, per one hole of five rings note).When pore pressure force of being in the milk reaches 0.2MPa~0.3MPa, grout hole stopping slip casting, and after Continuous perfusion 5min can terminate.
4) since grouting serous fluid pressure is larger, to prevent that slurries are excessive by section of jurisdiction front end, close measure, every 20 ring need to be increased Carry out once circumferential closure (just branch and section of jurisdiction radial clearance);Since common grouting material grouting setting time is difficult to control, expand It is big to dissipate scope, it is difficult to quick closure is formed, and chemical grouting material has setting time controllable small with range of scatter, can quickly seal The advantages of closing, so using chemical grouting.
5) the assembled progress according to section of jurisdiction, slip casting of following up in time, completes whole work progress.

Claims (3)

1. the construction method filled after a kind of two backing of Bored Section of Metro main track assembled, it is characterised in that including following step Suddenly:
1) after the assembly for completing each endless tube piece, prefabricated pipe is passed through using the beans gravel pack system (3) in pipe sheet assembling equipment The radial grouting hole (5) of on piece to prefabricated pipe section (1) behind with main track at the beginning of gap between branch structure (2) carry out hydraulic reclamation beans gravel Construction;Beans gravel is transported to beans gravel pump (10) through belt feeder (11), is filled by compressed air to section of jurisdiction behind, hydraulic reclamation beans gravel Order for from the bottom to top, it is symmetrical;
2) install bellows seal additional in pipe ring termination, Dong Bishang, when pipe sheet assembling equipment moves forward, gas are withstood on after air sac sealing inflation Capsule is deflated, and mounting base drives air bag reach;
3) after 20 rings of assembled completion, filling system (4) injects cement mortar behind by radial grouting hole (5) to prefabricated pipe section (1), It is using cement mortar that the beans gravel gap filling of ring prefabricated pipe section filling behind is full, closed-loop is formed, grouting sequence is served as reasons Under it is supreme, symmetrical, longitudinally every hole slip casting during grouting, per one hole of five rings note;Pore pressure force to be in the milk reach 0.2MPa~ During 0.3MPa, grout hole stops slip casting, and continues perfusion 5min and terminate;
4) every 20 ring carries out once circumferential closure, and circumferential direction closure is positioned at just branch and section of jurisdiction radial clearance;Circumferential direction closure is using chemistry Grouting.
2. according to the construction method filled after two backing of Bored Section of Metro assembled described in claim 1, its feature exists In:The beans gravel pack system (3) includes beans gravel pack pot (9), beans gravel belt feeder (11), beans gravel pump (10) and pneumatics Machine (8).
3. according to the construction method filled after two backing of Bored Section of Metro assembled described in claim 1, its feature exists In:The filling system (4) includes grouting pump (12), agitator tank (14) forms;Drive division is separately configured in slip casting trolley (13) (15), can automatic moving.
CN201710720494.4A 2017-08-21 2017-08-21 The construction method filled after two backing of bored tunnel assembled Pending CN107939420A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710720494.4A CN107939420A (en) 2017-08-21 2017-08-21 The construction method filled after two backing of bored tunnel assembled

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710720494.4A CN107939420A (en) 2017-08-21 2017-08-21 The construction method filled after two backing of bored tunnel assembled

Publications (1)

Publication Number Publication Date
CN107939420A true CN107939420A (en) 2018-04-20

Family

ID=61928617

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710720494.4A Pending CN107939420A (en) 2017-08-21 2017-08-21 The construction method filled after two backing of bored tunnel assembled

Country Status (1)

Country Link
CN (1) CN107939420A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109505634A (en) * 2019-01-28 2019-03-22 山东科技大学 Emergency type water-impervious airbag apparatus and its application method in tunnel
CN109578017A (en) * 2018-12-28 2019-04-05 中国电建集团贵阳勘测设计研究院有限公司 A kind of quick liner structure of speciality light section hydraulic tunnel and its construction method
CN109707410A (en) * 2019-01-16 2019-05-03 交通运输部公路科学研究所 Wisdom sensing type tunnel-liner support structural system
CN110242331A (en) * 2019-07-29 2019-09-17 西南交通大学 A method of pipe-plate lining ring anti-floating is assisted for the anti-floating system in shield tunnel and using it
CN111173537A (en) * 2020-01-07 2020-05-19 中铁十八局集团有限公司 Large-scale supplementary grouting method between duct piece and surrounding rock for tunnel construction by TBM method
CN111322089A (en) * 2020-02-28 2020-06-23 西南交通大学 Vault prefabricated assembled tunnel and construction method
CN111456758A (en) * 2020-06-03 2020-07-28 中国水利水电第十工程局有限公司 Double-shield TBM pipe back supporting method for dealing with rock burst
CN113565536A (en) * 2021-07-24 2021-10-29 郑州大学 Mud gushing prevention and control device for tunnel lining drilling and installation method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009102945A (en) * 2007-10-25 2009-05-14 Ohbayashi Corp Water conduction structure preventing flow inhibition of groundwater and method and back-filling material preventing flow inhibition of groundwater
CN102562146A (en) * 2012-03-07 2012-07-11 深圳市市政工程总公司 Construction gap filling method and device for shield through air pushing section
CN103510964A (en) * 2013-07-31 2014-01-15 中铁隧道集团有限公司 Method for performing backfill grouting on pea gravel by adoption of shield type TBM in construction process
CN105626096A (en) * 2015-12-31 2016-06-01 中交一公局第三工程有限公司 Pea gravel hydraulic filling construction process for TBM
CN105649650A (en) * 2014-12-03 2016-06-08 中铁十八局集团有限公司 Back pea gravel blow filling grouting construction method for single-shield hard rock roadheader after installing TBM pipe piece
CN106089245A (en) * 2016-06-25 2016-11-09 中交公局第三工程有限公司 A kind of delay grouting method after single shield TBM wall

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009102945A (en) * 2007-10-25 2009-05-14 Ohbayashi Corp Water conduction structure preventing flow inhibition of groundwater and method and back-filling material preventing flow inhibition of groundwater
CN102562146A (en) * 2012-03-07 2012-07-11 深圳市市政工程总公司 Construction gap filling method and device for shield through air pushing section
CN103510964A (en) * 2013-07-31 2014-01-15 中铁隧道集团有限公司 Method for performing backfill grouting on pea gravel by adoption of shield type TBM in construction process
CN105649650A (en) * 2014-12-03 2016-06-08 中铁十八局集团有限公司 Back pea gravel blow filling grouting construction method for single-shield hard rock roadheader after installing TBM pipe piece
CN105626096A (en) * 2015-12-31 2016-06-01 中交一公局第三工程有限公司 Pea gravel hydraulic filling construction process for TBM
CN106089245A (en) * 2016-06-25 2016-11-09 中交公局第三工程有限公司 A kind of delay grouting method after single shield TBM wall

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109578017A (en) * 2018-12-28 2019-04-05 中国电建集团贵阳勘测设计研究院有限公司 A kind of quick liner structure of speciality light section hydraulic tunnel and its construction method
CN109707410A (en) * 2019-01-16 2019-05-03 交通运输部公路科学研究所 Wisdom sensing type tunnel-liner support structural system
CN109505634A (en) * 2019-01-28 2019-03-22 山东科技大学 Emergency type water-impervious airbag apparatus and its application method in tunnel
CN109505634B (en) * 2019-01-28 2023-10-17 山东科技大学 Emergency type anti-seepage water-air bag device in tunnel and application method thereof
CN110242331A (en) * 2019-07-29 2019-09-17 西南交通大学 A method of pipe-plate lining ring anti-floating is assisted for the anti-floating system in shield tunnel and using it
CN110242331B (en) * 2019-07-29 2024-03-26 西南交通大学 Anti-floating device for shield tunnel and method for assisting segment lining ring anti-floating by adopting anti-floating device
CN111173537B (en) * 2020-01-07 2022-05-03 中铁十八局集团有限公司 Large-scale supplementary grouting method between duct piece and surrounding rock for tunnel construction by TBM method
CN111173537A (en) * 2020-01-07 2020-05-19 中铁十八局集团有限公司 Large-scale supplementary grouting method between duct piece and surrounding rock for tunnel construction by TBM method
CN111322089A (en) * 2020-02-28 2020-06-23 西南交通大学 Vault prefabricated assembled tunnel and construction method
CN111456758B (en) * 2020-06-03 2021-05-14 中国水利水电第十工程局有限公司 Double-shield TBM pipe back supporting method for dealing with rock burst
CN111456758A (en) * 2020-06-03 2020-07-28 中国水利水电第十工程局有限公司 Double-shield TBM pipe back supporting method for dealing with rock burst
CN113565536A (en) * 2021-07-24 2021-10-29 郑州大学 Mud gushing prevention and control device for tunnel lining drilling and installation method
CN113565536B (en) * 2021-07-24 2023-10-27 郑州大学 Device for preventing and controlling mud and sand burst of tunnel lining drilling and mounting method

Similar Documents

Publication Publication Date Title
CN107939420A (en) The construction method filled after two backing of bored tunnel assembled
CN107191197B (en) Shield segment and construction method thereof in tunnel through mine method by shield air pushing
CN102121395B (en) Method for integrated comprehensive management of gas in low-permeability single coal bed
WO2021120991A1 (en) Method for reconstructing shield tunnel for mining construction
CN103899323B (en) A kind of construction method of shield crossing rail yard
CN106948833A (en) Pin-connected panel service channel structure and its construction method
CN106884655B (en) A kind of two-way reinforcement means of gob side entry driving coal column
CN104453930B (en) Tunnel initial lining construction device and method
CN105240024B (en) A kind of method of parallel shield method enlarging construction subway station
CN105201518B (en) Disassembling method is received in a kind of major diameter slurry balance shield hole
CN106050245A (en) Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method
CN109505634A (en) Emergency type water-impervious airbag apparatus and its application method in tunnel
CN103195390A (en) Mining-coal bed nearly horizontal gas extraction borehole sealing method
CN106121722A (en) A kind of method quickly constructing fire dam
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN105888673A (en) Deep-hole plastic pipe high-pressure grouting anti-explosion device in soft water-rich surrounding rock and operation method
CN209430219U (en) Emergency type water-impervious airbag apparatus in tunnel
CN103291354B (en) Floor rock roadway layer-crossing pressure relief drilling filling and reinforcing method
CN214499063U (en) Supplementary quick backfill system of two shield TBM crack rock segment bags
CN103993902A (en) Gas extraction drilled hole two-step grouting hole sealing method
CN110939404A (en) Hydraulic joint cutting pressure relief device and method for coal mine tunnel broken surrounding rock roof
CN102337859B (en) Coal field drill hole leak blocking system
CN108868827A (en) Km deep-well high-ground stress combination of steel rope injection hole sealing device and method for sealing
CN113756868B (en) Geotechnical engineering underground side wall construction method
CN111594199A (en) Construction method for wall back backfilling of double-shield TBM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420