CN107938681A - 混凝土集水井后做法 - Google Patents

混凝土集水井后做法 Download PDF

Info

Publication number
CN107938681A
CN107938681A CN201711198689.3A CN201711198689A CN107938681A CN 107938681 A CN107938681 A CN 107938681A CN 201711198689 A CN201711198689 A CN 201711198689A CN 107938681 A CN107938681 A CN 107938681A
Authority
CN
China
Prior art keywords
sump
baffle
mould
hung
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711198689.3A
Other languages
English (en)
Inventor
魏仁明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201711198689.3A priority Critical patent/CN107938681A/zh
Publication of CN107938681A publication Critical patent/CN107938681A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

本发明涉及集水井施工领域,具体是一种混凝土集水井后做法;包括集水井吊模,所述集水井吊模包括挡板、挡板内支撑和挡板顶部支撑,挡板有多块并合围呈集水井截面形状,在挡板内部环绕设置挡板内支撑,在合围后的挡板顶部交叉设置挡板顶部支撑;沿集水井外边线棱廓破凿结构垫层;向下挖深结构地层并至集水井底面厚度;将加工好的集水井吊模吊放至挖深的集水坑中,并继续挖深至集水井设计深度,将集水井吊模沉入设计标高,集水井吊模内用混凝土封底,集水井吊模外侧采用混凝土填充。本装置可以确保集水坑的尺寸不变形,避免模板在浇注过程中出现的“上浮”现象,从而保证集水井施工质量。

Description

混凝土集水井后做法
技术领域
本发明涉及集水井施工领域,具体是一种混凝土集水井后做法。
背景技术
集水井外壁一般采用砖胎膜,而集水井的做法一般采用吊模或者底部封堵的整体筒模。但对于地下结构底板施工完成或安装竣工后,在后续施工过程或使用过程中才发现渗漏水而需要后期补做集水井不适用。
发明内容
本发明的目的在于,提供一种适用于集水井后期补做施工并且能保证集水井施工质量的后做法施工方法。
为了达到上述目的,本发明是这样实现的:
一种混凝土集水井后做法,包括集水井吊模,所述集水井吊模包括挡板、挡板内支撑和挡板顶部支撑,挡板有多块并合围呈集水井截面形状,在挡板内部环绕设置挡板内支撑,在合围后的挡板顶部交叉设置挡板顶部支撑,还包括如下施工步骤:
步骤1、沿集水井外边线棱廓破凿结构垫层;
步骤2、向下挖深结构地层并至集水井底面厚度;
步骤3、将加工好的集水井吊模吊放至挖深的集水坑中,
步骤4、并继续挖深至集水井设计深度,
步骤5、将集水井吊模沉入设计标高,
步骤6、集水井吊模内采用10~20cm厚的C20混凝土封底,集水井吊模外侧采用混凝土填充;
步骤7、集水井施工。
由于地下结构底板施工完成或安装竣工后,在后续施工过程或使用过程中才发现渗漏水而需要后期补做集水井,考虑到已完成结构的返工影响以及传统集水井施工过程中放置的模板盒易收到混凝土的挤压,从而造成集水井结构尺寸不符、混凝土不密实而渗水、后期拆模不便等不利影响,本装置可以确保集水坑的尺寸不变形,避免模板在浇注过程中出现的“上浮”现象,从而保证集水井施工质量。
附图说明
图1为本施工方法中,集水井吊模的俯视图。
图2为本施工方法中,集水井吊模的侧视图。
图3为本施工方法示意图。
具体实施方式
以下通过具体实施例进一步说明本发明。
如图1、图2所示,一种混凝土集水井后做法,包括集水井吊模,所述集水井吊模包括挡板1、挡板内支撑2和挡板顶部支撑3,挡板1有多块并合围呈集水井截面形状,在挡板1内部环绕设置挡板内支撑2,在合围后的挡板1顶部交叉设置挡板顶部支撑3。
如图3所示,还包括如下施工步骤:
步骤1、沿集水井外边线外扩破凿结构垫层;
步骤2、向下挖深结构地层并至集水井底面厚度;
步骤3、将加工好的集水井吊模吊放至挖深的集水坑中,
步骤4、并继续挖深至深度H,
步骤5、将集水井吊模沉入设计标高,
步骤6、集水井吊模内采用10~20cm厚的C20混凝土封底,集水井吊模外侧采用混凝土填充;
步骤7、集水井施工。
由于地下结构底板施工完成或安装竣工后,在后续施工过程或使用过程中才发现渗漏水而需要后期补做集水井,考虑到已完成结构的返工影响以及传统集水井施工过程中放置的模板盒易收到混凝土的挤压,从而造成集水井结构尺寸不符、混凝土不密实而渗水、后期拆模不便等不利影响,本装置可以确保集水坑的尺寸不变形,避免模板在浇注过程中出现的“上浮”现象,从而保证集水井施工质量。

Claims (1)

1.一种混凝土集水井后做法,其特征是:包括集水井吊模,所述集水井吊模包括挡板、挡板内支撑和挡板顶部支撑,挡板有多块并合围呈集水井截面形状,在挡板内部环绕设置挡板内支撑,在合围后的挡板顶部交叉设置挡板顶部支撑,还包括如下施工步骤:
步骤1、沿集水井外边线棱廓破凿结构垫层;
步骤2、向下挖深结构地层并至集水井底面厚度;
步骤3、将加工好的集水井吊模吊放至挖深的集水坑中,
步骤4、并继续挖深至集水井设计深度,
步骤5、将集水井吊模沉入设计标高,
步骤6、集水井吊模内采用10~20cm厚的C20混凝土封底,集水井吊模外侧采用混凝土填充;
步骤7、集水井施工。
CN201711198689.3A 2017-11-26 2017-11-26 混凝土集水井后做法 Pending CN107938681A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711198689.3A CN107938681A (zh) 2017-11-26 2017-11-26 混凝土集水井后做法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711198689.3A CN107938681A (zh) 2017-11-26 2017-11-26 混凝土集水井后做法

Publications (1)

Publication Number Publication Date
CN107938681A true CN107938681A (zh) 2018-04-20

Family

ID=61949865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711198689.3A Pending CN107938681A (zh) 2017-11-26 2017-11-26 混凝土集水井后做法

Country Status (1)

Country Link
CN (1) CN107938681A (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101245602A (zh) * 2008-03-13 2008-08-20 王形 坑中坑支护体系的施工工艺
CN102888847A (zh) * 2012-10-19 2013-01-23 中国二十二冶集团有限公司 电梯井局部深基坑免降水施工方法
CN103015456A (zh) * 2011-09-21 2013-04-03 五冶集团上海有限公司 地下混凝土构筑物基础底板中的坑中坑快速支模法
CN203049588U (zh) * 2013-01-15 2013-07-10 龙元建设集团股份有限公司 坑中坑筒模
CN203924085U (zh) * 2014-07-01 2014-11-05 中铁城建集团第二工程有限公司 一种应用于集水井的沉井结构
CN104975607A (zh) * 2015-07-22 2015-10-14 中建八局第二建设有限公司 近海区局部深基坑止水槽施工方法
CN107059904A (zh) * 2017-03-17 2017-08-18 中国华冶科工集团有限公司 一种地下管廊积水井开挖方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101245602A (zh) * 2008-03-13 2008-08-20 王形 坑中坑支护体系的施工工艺
CN103015456A (zh) * 2011-09-21 2013-04-03 五冶集团上海有限公司 地下混凝土构筑物基础底板中的坑中坑快速支模法
CN102888847A (zh) * 2012-10-19 2013-01-23 中国二十二冶集团有限公司 电梯井局部深基坑免降水施工方法
CN203049588U (zh) * 2013-01-15 2013-07-10 龙元建设集团股份有限公司 坑中坑筒模
CN203924085U (zh) * 2014-07-01 2014-11-05 中铁城建集团第二工程有限公司 一种应用于集水井的沉井结构
CN104975607A (zh) * 2015-07-22 2015-10-14 中建八局第二建设有限公司 近海区局部深基坑止水槽施工方法
CN107059904A (zh) * 2017-03-17 2017-08-18 中国华冶科工集团有限公司 一种地下管廊积水井开挖方法

Similar Documents

Publication Publication Date Title
CN107700496B (zh) 深基坑的逆顺结合施工方法
CN103255772A (zh) 优化深基坑换撑施工顺序的施工方法
CN103382722B (zh) 地下水压较大的预留集水井处混凝土基础底板恢复方法
CN105350555B (zh) 一种降水井的快速施工方法
CN103498486A (zh) 一种采用套管对后浇带降水管井实施封堵的方法
CN102995642B (zh) 水下混凝土灌注防浮浆隔水装置
CN107938681A (zh) 混凝土集水井后做法
CN102345287A (zh) 大直径现浇薄壁混凝土复合桩的施工方法及专用成孔器
CN203695883U (zh) 上箱砂芯固定结构
CN208152063U (zh) 一种超高渗透系数砂卵地层地下水控制系统
CN204676551U (zh) 后插式钢筋笼灌注桩的振捣装置
CN217204017U (zh) 一种地下连续墙分幅处预埋灌浆结构
CN105804690A (zh) 地浸工艺钻孔逆向注水泥浆装置
CN107268639A (zh) 防杆洞塌方设备
CN108487229A (zh) 一种强岩溶地基预注浆处理后人工成孔方法
CN205224589U (zh) 楼层洞孔封堵吊模结构
CN108729669A (zh) 一种墙体预埋线盒一次安装模具
JP2012062660A (ja) 場所打ちコンクリート杭の杭頭処理方法および杭頭処理装置
CN207245193U (zh) 一种混凝土浇筑设备
CN204920205U (zh) 窗框固定桩的施工工装
CN104975878B (zh) 隧道排水沟施工方法
CN205369279U (zh) 一种用于快速施作降水井的管体装置
CN103821525B (zh) 高水位地质条件下电缆隧道快速施工方法
CN109208605A (zh) 一种循环坐底式混凝土侧壁浇筑方法
CN110409415A (zh) 一种湿陷性土或溶陷性土地基的处理方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420