CN107816629A - Permanent support and rubber film sealed gas cabinet provided with same - Google Patents

Permanent support and rubber film sealed gas cabinet provided with same Download PDF

Info

Publication number
CN107816629A
CN107816629A CN201711046897.1A CN201711046897A CN107816629A CN 107816629 A CN107816629 A CN 107816629A CN 201711046897 A CN201711046897 A CN 201711046897A CN 107816629 A CN107816629 A CN 107816629A
Authority
CN
China
Prior art keywords
support
piston
permanent support
cabinet
cabinet plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711046897.1A
Other languages
Chinese (zh)
Other versions
CN107816629B (en
Inventor
曹宝平
刘红娟
杨永
周华
齐蕊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Capital Engineering & Research Inc Ltd
Beijing Jingcheng Zeyu Energy Environmental Protection Engineering Technology Co ltd
Original Assignee
Capital Engineering & Research Inc Ltd
Beijing Jingcheng Zeyu Energy Environmental Protection Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Capital Engineering & Research Inc Ltd, Beijing Jingcheng Zeyu Energy Environmental Protection Engineering Technology Co ltd filed Critical Capital Engineering & Research Inc Ltd
Priority to CN201711046897.1A priority Critical patent/CN107816629B/en
Publication of CN107816629A publication Critical patent/CN107816629A/en
Application granted granted Critical
Publication of CN107816629B publication Critical patent/CN107816629B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17BGAS-HOLDERS OF VARIABLE CAPACITY
    • F17B1/00Gas-holders of variable capacity
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17BGAS-HOLDERS OF VARIABLE CAPACITY
    • F17B1/00Gas-holders of variable capacity
    • F17B1/02Details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a permanent support and a rubber membrane sealed gas tank provided with the permanent support, relates to a gas tank for recovering gas in iron and steel enterprises, the permanent support comprises a central support, a plurality of radial beams and a plurality of circumferential beams, the central support is vertically arranged and fixedly connected at the center of a cabinet bottom plate of the rubber membrane sealed gas cabinet, the plurality of radial beams are radially arranged on the periphery of the central support, each radial beam is radially arranged along the rubber membrane sealed gas cabinet, a stand column with a plurality of intervals is arranged below each radial beam, each stand column is vertically arranged, the top end of each stand column is fixedly connected with the corresponding radial beam, the bottom end of each stand column is fixedly connected with the cabinet bottom plate, each circumferential beam is horizontally arranged in a ring shape, the plurality of circumferential beams are sequentially arranged from inside to outside by taking the central support as the center of a circle and are fixedly connected with the radial beams, and intervals are arranged between every two adjacent circumferential beams.

Description

Permanent support and the rubber film sealing gas chamber for being provided with permanent support
Technical field
The present invention relates to the gas chamber that iron and steel enterprise is used for coal-gas recovering, more particularly to a kind of permanent support and it is provided with forever The rubber film sealing gas chamber of long support.
Background technology
The necessaries that gas chamber comprehensively utilizes as iron and steel enterprise's coal-gas recovering, plays in low-carbon economy and focuses on The effect wanted.
Current domestic rubber diaphragm sealing type gas chamber is divided into unistage type sealing and two-part sealing;Unistage type sealing only one Individual pressure, the pressure balance with piston deadweight, counterweight and process equipment heavy phase;Two-part sealing gas storage has two pressure, i.e., living Plug is a pressure when rising, and piston driving T-shaped baffle plate is a pressure when rising.No matter unistage type and two-part have largely Piston prop, the effect of prop is when overhauling bottom plate or piston plate, makes prop through piston, props up work Plug, about 1m space for maintenance is formed under piston plate.Piston prop divides two parts:First, piston week quarter line pillaring;It is second, living Fill in center pole.Piston week quarter line pillaring borrow piston baffle at the top of annular walk on stage lower support circular orbit on two slide fasteners Cucurbit slings all quarter line pillarings in symmetric points respectively, through concrete guard wall rear support on gas chamber bottom plate, makees for semi-mechanization Industry, its centre pillar cover closure using manually installed, prevent blow-by of piston again.
Its centre pillar number is quite a lot of, with 50,000 m3Exemplified by rubber film sealing gas chamber, center pole is about 150 Left and right, with the increase of gas holder capacity, pillar number is also more and more, 150,000 m3Rubber film sealing gas chamber is up to more than 300 Root.The work that the peace installation and dismantling of piston pillar are pulled out, on the one hand, artificial consumption is more;On the other hand, because bottom plate is ball collar shape, The lower end of prop just needs to cut arc, to be directed at arc during installation, these pillars, to accomplish each alignment, be very in distress Degree, if misalignment, gas holder bottom plate and piston local pressure will be made uneven, damaged, therefore give gas holder safe operation Bring certain hidden danger.Even, some enterprises allow piston to be run with these pillars to reduce workload, but so to work The impact for filling in concrete bridge wall and the injury for overhauling pillar are all no small, and potential safety hazard more highlights.
In a word, peace installation and dismantling, which pull out piston maintenance pillar and are one, takes a lot of work and time-consuming operation.The mode of operation of this backwardness, Obviously require inconsistent with the efficient, laborsaving of current generation, it is imperative to improve it.
The content of the invention
The purpose of the present invention is to propose to permanent support and the rubber film sealing gas chamber for being provided with permanent support, using permanent Support replaces original substantial amounts of piston pillar, not only reduces the labor workload needed for installation and removal piston pillar, also carries The high security of piston maintenance.
To reach above-mentioned purpose, the present invention proposes a kind of permanent support, wherein, the permanent support include center bearing bracket, Multiple radial girders and multiple ring beams, the center bearing bracket are vertically arranged and are fixed in the bottom of cabinet plate of rubber film sealing gas chamber At center, multiple radial girders are installed radially in the periphery of the center bearing bracket, and each radial girders are along described Rubber film sealing gas chamber is radially arranged, and is mounted on multiple spaced columns below each radial girders, often The individual column is vertically arranged, and the top of the column and the radial girders are affixed, the bottom of the column and the bottom of cabinet Plate is affixed, and each ring beam in annular and is horizontally disposed with, and multiple ring beams are using the center bearing bracket as the center of circle Order is arranged and is fixedly connected with the radial girders from inside to outside, has interval between adjacent two ring beams.
Permanent support as described above, wherein, the permanent support also includes being arranged on the rubber film sealing gas chamber Bridge wall on multiple side seat supports, the bridge wall is in annular, and multiple side seat supports are distributed on the top of the bridge wall, There is interval between two adjacent side seat supports.
Permanent support as described above, wherein, what the center bearing bracket included is vertically arranged multiple support posts, Duo Gesuo State that support post is uniform along annular, the bottom of each support post is fixedly connected with the bottom of cabinet plate, and adjacent two Spaced multiple depression bars are also equipped between the individual support post, the depression bar is horizontally disposed with, the both ends of the depression bar It is respectively and fixedly connected on two adjacent support posts.
Permanent support as described above, wherein, it is also equipped with bearing diagonal on the center bearing bracket.
Permanent support as described above, wherein, each column is fixedly connected on the bottom of cabinet by mounting assembly On plate, the mounting assembly includes built-in fitting and two otic placodes, and the built-in fitting is installed in below the bottom of cabinet plate, the column It is fixedly connected through the bottom of cabinet plate and with the built-in fitting, two otic placodes are separately mounted to the both sides of the column, institute It is affixed to state top and the radial girders of otic placode, the bottom of the otic placode and the bottom of cabinet plate are affixed.
Permanent support as described above, wherein, it is also equipped with bracing members between adjacent two radial girders.
The present invention also proposes a kind of rubber film sealing gas chamber for being provided with permanent support, wherein, it is described rubber diaphragm sealed Permanent support of the gas chamber described in including at least any one in cabinet, piston and claim 1 to 8, during the cabinet has Empty accommodating cavity, the top of the accommodating cavity are provided with cabinet top structure, and the bottom of the accommodating cavity is provided with bottom of cabinet plate, the piston peace In the accommodating cavity, the permanent support is arranged between the bottom of cabinet plate and the piston.
The rubber film sealing gas chamber as described above for being provided with permanent support, wherein, the core of the bottom of cabinet plate Higher than the marginal portion of the bottom of cabinet plate.
The rubber film sealing gas chamber as described above for being provided with permanent support, wherein, the top of the center bearing bracket is also Provided with the piston mounting bracket for setting up piston, the piston mounting bracket is vertically arranged and can dismantled with the center bearing bracket Ground connects.
Compared with prior art, the invention has the characteristics that and advantage:
Permanent support proposed by the present invention forms one by center bearing bracket, multiple radial girders, multiple ring beams and multiple columns Individual stable space operation architecture, power transmission are direct, safe and stable, economical, reasonable.
Permanent support proposed by the present invention can be either permanently mounted the bottom of cabinet plate of piston and rubber film sealing gas chamber Between, so as to replace original substantial amounts of piston pillar, not only substantially reduce the artificial work needed for installation and removal piston pillar Measure, also substantially increase the security of piston maintenance.
Do not have to open up maintenance again because the piston of rubber film sealing gas chamber is positioned on permanent support, therefore on piston Pillar hole, adds the air-tightness and durability of piston, while also improves gasmeter property safe and reliable to operation.
Further, since piston is positioned on permanent support so that piston can be separated with bottom of cabinet plate, such piston Just separated with the ponding on bottom of cabinet plate, avoid the influence that the ponding on bottom of cabinet plate is run for piston so that piston rises flat Steady profit, it ensure that rubber film sealing gas chamber air inlet is smooth.
Permanent support proposed by the present invention is easy to process, accelerating construction progress, time saving and energy saving.
Brief description of the drawings
Accompanying drawing described here is only used for task of explanation, and is not intended in any way to limit model disclosed by the invention Enclose.In addition, shape and proportional sizes of each part in figure etc. are only schematical, the understanding of the present invention is used to help, and It is not the specific shape and proportional sizes for limiting each part of the present invention.Those skilled in the art under the teachings of the present invention, can To select various possible shapes and proportional sizes to implement the present invention as the case may be.
Fig. 1 is the structural representation of rubber film sealing gas chamber proposed by the present invention;
Fig. 2 is the top view of permanent support proposed by the present invention;
Fig. 3 is the structural representation of piston holder and bridge wall in the present invention;
Fig. 4 is the top view of piston holder and bridge wall in the present invention;
Fig. 5 is the structural representation of the embodiment of center bearing bracket one of the present invention;
Fig. 6 be Fig. 5 in A-A to sectional view;
Fig. 7 is the structural representation of another embodiment of center bearing bracket of the present invention;
Fig. 8 is the sectional view of B-B direction in Fig. 7;
Fig. 9 is the top view of radial girders in the present invention;
Figure 10 is the structural representation of radial girders, column and mounting assembly in the present invention;
Figure 11 is permanent support and the scheme of installation of cabinet top structure (one) in the present invention;
Figure 12 is permanent support and the scheme of installation of cabinet top structure (two) in the present invention;
Figure 13 is permanent support and the scheme of installation of cabinet top structure (three) in the present invention;
Figure 14 is permanent support and the scheme of installation of cabinet top structure (four) in the present invention.
Description of reference numerals:
100th, permanent support;110th, center bearing bracket;
111st, support post;112nd, depression bar;
113rd, bearing diagonal;120th, radial girders;
121st, first radial girders;122nd, second radial girders;
130th, ring beam;131st, first ring beam;
140th, column;150th, mounting assembly;
151st, built-in fitting;152nd, otic placode;
160th, cabinet top center tooling bracket;170th, bracing members;
180th, side seat support;190th, cabinet top end tooling bracket;
200th, rubber film sealing gas chamber;210th, cabinet;
220th, bottom of cabinet plate;230th, cabinet top structure;
240th, accommodating cavity;250th, piston plate;
260th, asphaltic sands;270th, piston holder;
280th, bridge wall;300th, truck crane;
F, erection sequence;161st, piston mounting bracket;
162nd, extending bracket.
Embodiment
With reference to the description of accompanying drawing and the specific embodiment of the invention, details of the invention can be clearly understood.But It is the embodiment of invention described herein, is only used for explaining the purpose of the present invention, and can not understands in any way Into being limitation of the present invention.Under the teachings of the present invention, technical staff is contemplated that any possible change based on the present invention Shape, these are regarded as belonging to the scope of the present invention.
Fig. 1 to Figure 14 is refer to, the present invention proposes a kind of permanent support 100, as shown in Figure 1 and Figure 2, the permanent support 100 Including center bearing bracket 110, multiple radial girders 120 and multiple ring beams 130, center bearing bracket 110 is vertically arranged and is fixed in rubber At the center of the bottom of cabinet plate 220 of film sealed gas chamber 200, multiple radial girders 120 are installed radially in the outer of center bearing bracket 110 In week, each radial girders 120 being radially arranged along rubber film sealing gas chamber 200, the lower section of each radial girders 120 is mounted on Multiple spaced columns 140, each column 140 are vertically arranged, and the top of column 140 and radial girders 120 are affixed, column 140 bottom and bottom of cabinet plate 220 are affixed, and each ring beam 130 in annular and is horizontally disposed with, and multiple ring beams 130 are in Cardiac skeleton 110 is that the center of circle sequentially arranges and is fixedly connected with radial girders 120 from inside to outside, between adjacent two ring beams 130 With interval.
The invention also provides a kind of rubber film sealing gas chamber 200 for being provided with permanent support, as shown in figure 1, the rubber Glued membrane sealed gas chamber 200 includes cabinet 210, piston and permanent support 100, and cabinet 210 has hollow accommodating cavity 240, holds The top for putting chamber 240 is provided with cabinet top structure 230, and the bottom of accommodating cavity 240 is provided with bottom of cabinet plate 220, and piston is arranged on accommodating cavity 240 Interior, permanent support 100 is arranged between bottom of cabinet plate 220 and piston.
Permanent support 100 proposed by the present invention is by center bearing bracket 110, multiple radial girders 120, multiple ring beams 130 and more Individual column 140 forms a stable space operation architecture, and power transmission is direct, safe and stable, economical, reasonable.
Permanent support 100 proposed by the present invention can be either permanently mounted piston and rubber film sealing gas chamber 200 Between bottom of cabinet plate 220, so as to replace original substantial amounts of piston pillar, not only substantially reduce needed for installation and removal piston pillar Labor workload, also substantially increase piston maintenance security.
Also, because the piston of rubber film sealing gas chamber 200 is positioned on permanent support 100, therefore on piston not With maintenance pillar hole is opened up again, the air-tightness and durability of piston are added, while it is safe for operation to also improve gasmeter Reliability.
Further, since piston is positioned on permanent support 100 so that piston can be separated with bottom of cabinet plate 220, so Piston also just separates with the ponding on bottom of cabinet plate 220, avoids the influence that the ponding on bottom of cabinet plate 220 is run for piston, makes It is steady smooth to obtain piston rise, ensure that the air inlet of rubber film sealing gas chamber 200 is smooth.
Permanent support 100 proposed by the present invention is easy to process, accelerating construction progress, time saving and energy saving.
In the present invention, tactic multiple its radius of ring beam 130 from inside to outside increase successively, each ring beam 130 are fixedly connected with multiple radial girders 120, and so, multiple radial girders 120 and multiple ring beams 130 form latticed branch Support body system, stable support is provided for piston.
In an optional example of the invention, as shown in Figure 2, Figure 3 and Figure 4, permanent support 100 also includes being arranged on rubber Multiple side seat supports 180 on the bridge wall 280 of glued membrane sealed gas chamber 200, bridge wall 280 are in annular, multiple side seat supports 180 The top of bridge wall 280 is distributed on, there is interval between adjacent two side seat supports 180.So, the piston plate of piston base 250 edge can to ride upon on side seat support 180, meanwhile, ridden upon in the middle part of piston plate by ring beam 130 and radial girders In the supporting construction of 120 compositions, it ensure that permanent support 100 can provide uniform support force for piston plate, be further ensured that The normal operation of piston.
In an optional example of the invention, as shown in Figure 1 to Figure 3, a pair of radial girders 120 and side seat support 180 1 It should set, the outer end of each radial girders 120 is correspondingly arranged on a side seat support 180, and radial girders 120 and corresponding side There is interval between seat support 180.
Further, each radial girders 120 are obliquely installed, one end (radial direction of the radial girders 120 towards center bearing bracket 110 The inner of beam 120) it is higher than the other end (outer ends of radial girders 120) of radial girders 120.
In an optional example of the invention, as shown in Fig. 2 being also equipped with steel between two adjacent radial girders 120 Support 170, it is further ensured that the linking intensity for the support system being made up of radial girders 120 and ring beam 130.
In an optional example of the invention, the bottom of column 140 is welded on bottom of cabinet plate 220.
In another optional example of the invention, as shown in Figure 9, Figure 10, column 140 is solid by mounting assembly 150 Surely it is arranged on bottom of cabinet plate 220, mounting assembly 150 includes built-in fitting 151 and two otic placodes 152, built-in fitting 151 are arranged on bottom of cabinet In the asphaltic sands 260 of the lower section of plate 220, column 140 is through bottom of cabinet plate 220 and is fixedly connected with built-in fitting 151, two otic placodes 152 are separately mounted to the both sides of support post 111, and the top of otic placode 152 and radial girders 120 are affixed, the bottom of otic placode 152 and cabinet Bottom plate 220 is affixed.
Further, the top of otic placode 152 is welded in radial girders 120, and the bottom of otic placode 152 is welded on bottom of cabinet plate 220 On.
In an optional example of the invention, as shown in Fig. 5 to Fig. 8, what center bearing bracket 110 included is vertically arranged multiple Support post 111, multiple support posts 111 are uniform along annular, and the bottom of each support post 111 is fixedly installed on bottom of cabinet On plate 220, spaced multiple depression bars 112 are also equipped between adjacent two support posts 111, depression bar 112 is horizontally disposed, The both ends of depression bar 112 are respectively and fixedly connected on two adjacent support posts 111.Two adjacent supports are connected by depression bar 112 Column 111, to ensure that center bearing bracket 110 has enough intensity, vertical load can be undertaken, and can is radial girders 120 and ring Stable support is provided to the support system for being used to support piston that beam 130 forms.
In an optional example, three depression bars 112 are mounted between the adjacent support post 111 of each two, three Individual depression bar 112 is from top to bottom uniformly distributed.
In an optional example, as shown in Figure 5, Figure 6, center bearing bracket 110 includes 4 support posts, 111,4 branch It is uniform along annular to support column 111, just (4 support posts 111 are set such 4 support posts 111 respectively for square arrangement On four summits of square).
In another optional example, as shown in Figure 7, Figure 8, center bearing bracket 110 includes 8 support posts 111,8 Support post 111 is uniform along annular, and in octagon arrangement, (8 support posts 111 are set such 8 support posts 111 respectively Put on four summits of octagon).
In an optional example of the invention, as shown in Fig. 5 to Fig. 8, bearing diagonal is also equipped with center bearing bracket 110 113, it is further ensured that the support strength of center bearing bracket 110.
In an optional example of the invention, first ring beam 131 is set in outside center bearing bracket 110 and is fixedly connected On the outer wall on the top of support post 111.Pass through being fixedly connected for ring beam 130 and support post 111, radial girders 120 and ring To being fixedly connected for beam 130, what center bearing bracket 110 can think that radial girders 120 and ring beam 130 form is used to support piston Support system provides stable support.
In an optional example, bearing diagonal 113 includes two steel columns being obliquely installed, and the both ends of steel column are fixed respectively It is connected on two support posts 111.
In an optional example of the invention, support post 111 can also be fixedly connected on cabinet by mounting assembly 150 On bottom plate 220, mounting assembly 150 includes built-in fitting 151 and two otic placodes 152, built-in fitting 151 are arranged under bottom of cabinet plate 220 Side, support post 111 are fixedly connected through bottom of cabinet plate 220 and with built-in fitting 151, and it is vertical that two otic placodes 152 are separately mounted to support The both sides of post 111, the top of otic placode 152 and support post 111 are affixed, and the bottom of otic placode 152 and bottom of cabinet plate 220 are affixed.
In an optional example, column 140 and support post 111 are steel column of the cross section for H-shaped.
In an optional example of the invention, the piston that the top of center bearing bracket 110 is additionally provided with for setting up piston is pacified Support 161 is filled, piston mounting bracket 161 is vertically arranged and is releasably connected with center bearing bracket 110.
In an optional example, the steel column as support post 111 is higher than the design height of center bearing bracket 110, takes If after complete permanent support 100, the piston of cylindrical shape is set up higher than the part of first ring beam 131 in multiple steel columns;In steel column Top installation cabinet top center tooling bracket 160, cabinet top end tooling bracket 190 is set up at the top of piston holder, so as to complete Into setting up for top of gas cabinet structure;After the completion of the cabinet top structure 230 of gas chamber is set up, the top surface along piston and bottom surface respectively Cut steel column, the piston mounting bracket 161 for make steel column be separated into center bearing bracket 110, being fixedly connected with the piston and higher than piston Extending bracket 162, extending bracket 162 is removed, (especially prevent coal gas from branch being installed from piston using the bottom of piston plate closed piston The bottom of frame 160 enters internal piston), piston mounting bracket 161 can be run up and down with piston, and center bearing bracket 110 is as permanent The center of support 100 is retained.
In an optional example of the invention, as shown in figure 1, the center section of bottom of cabinet plate 220 is higher than bottom of cabinet plate 220 Marginal portion, makes the center of bottom of cabinet plate 220 have certain gradient to edge, is easy to draining.According to proposed by the present invention permanent Support 100 and the rubber film sealing gas chamber 200 for being provided with permanent support, it is also proposed that a kind of permanent support and cabinet top structure Installation method, as shown in FIG. 10 to 14, it is specially:
Step 1, multiple steel columns are fixedly installed at the center of bottom of cabinet plate 220 as support post, and adjacent two Depression bar 112 is installed between individual steel column;
Step 2, first ring beam 131 is installed, first ring beam 131 is set in outside center bearing bracket 110, makes first Individual ring beam 131 is fixedly connected with multiple steel columns and ensures the top of support 110 centered on the height residing for first ring beam 131 Height;
Step 3, first radial girders 121 is installed using truck crane 300, first radial girders 121 is along rubber diaphragm sealed coal Gas holder 200 is radially arranged, and one end of first radial girders 121 is fixedly connected on first ring beam 131, first footpath To beam 121 the other end backwards to center bearing bracket, and multiple columns 140 of first lower section of radial girders 121 are installed;
Step 4, two second radial girders 122 are symmetrically mounted on the two of first radial girders 120 using truck crane 300 Side, and part of multiple ring beams 130 between first radial girders 120 and second radial girders 120 is installed;
Step 5, repeat step 4, remaining radial girders 120 is installed along smooth F orders are installed;
Step 6, piston is set up higher than the part of first ring beam 131 in multiple steel columns;
Step 7, in the top of steel column installation cabinet top center tooling bracket 160, cabinet top end is set up at the top of piston holder Portion's tooling bracket 190;
Step 8, rubber diaphragm sealed coal gas is set up using cabinet top center tooling bracket 160 and cabinet top end tooling bracket 190 The cabinet top structure of cabinet 200;
Step 9, cabinet top center tooling bracket 160 and cabinet top end tooling bracket 190 are removed, respectively along piston top surface and Steel column is cut in bottom surface, steel column is separated into center bearing bracket 110, piston mounting bracket 161 and extending bracket 162, removes extension branch Frame 162, using the bottom of piston plate closed piston, piston mounting bracket 161 can be run up and down with piston, and center bearing bracket 110 is made Center for permanent support 100 is retained.
For explaining in detail for the respective embodiments described above, its purpose is only that to explain to the present invention, in order to be able to The present invention is more fully understood, still, these descriptions can not be particularly with any explanation into being limitation of the present invention, Each feature described in different embodiments can also be mutually combined, so as to form other embodiment, except having Opposite description is specified, these features should be understood to be applied in any one embodiment, and be not limited merely to Described embodiment.

Claims (9)

1. a kind of permanent support, it is characterised in that the permanent support includes center bearing bracket, multiple radial girders and multiple rings Beam, the center bearing bracket are vertically arranged and are fixed at the center of bottom of cabinet plate of rubber film sealing gas chamber, multiple radial directions Beam is installed radially in the periphery of the center bearing bracket, and each radial girders are along the footpath of the rubber film sealing gas chamber To setting, multiple spaced columns are mounted on below each radial girders, each column is vertically arranged, The top of the column and the radial girders are affixed, and the bottom of the column and the bottom of cabinet plate are affixed, each ring beam In annular and being horizontally disposed with, multiple ring beams using the center bearing bracket be the center of circle sequentially arrange from inside to outside and with institute State radial girders to be fixedly connected, there is interval between adjacent two ring beams.
2. permanent support as claimed in claim 1, it is characterised in that the permanent support also includes being arranged on the rubber membrane Multiple side seat supports on the bridge wall of sealed gas chamber, the bridge wall are in annular, and multiple side seat supports are distributed on described The top of bridge wall, there is interval between adjacent two side seat supports.
3. permanent support as claimed in claim 1, it is characterised in that what the center bearing bracket included is vertically arranged multiple supports Column, multiple support posts are uniform along annular, and the bottom of each support post is fixed with the bottom of cabinet plate to be connected Connect, be also equipped with spaced multiple depression bars between adjacent two support posts, the depression bar is horizontally disposed with, described The both ends of depression bar are respectively and fixedly connected on two adjacent support posts.
4. permanent support as claimed in claim 3, it is characterised in that be also equipped with bearing diagonal on the center bearing bracket.
5. permanent support as claimed in claim 1, it is characterised in that each column is fixedly connected by mounting assembly On the bottom of cabinet plate, the mounting assembly includes built-in fitting and two otic placodes, and the built-in fitting is installed under the bottom of cabinet plate Side, the column are fixedly connected through the bottom of cabinet plate and with the built-in fitting, and two otic placodes are separately mounted to described vertical The both sides of post, the top of the otic placode and the radial girders are affixed, and the bottom of the otic placode and the bottom of cabinet plate are affixed.
6. permanent support as claimed in claim 1, it is characterised in that be also equipped with steel between two adjacent radial girders Support.
7. a kind of rubber film sealing gas chamber for being provided with permanent support, it is characterised in that the rubber film sealing gas chamber is extremely Include the permanent support in cabinet, piston and claim 1 to 6 described in any one less, the cabinet has hollow accommodating Chamber, the top of the accommodating cavity are provided with cabinet top structure, and the bottom of the accommodating cavity is provided with bottom of cabinet plate, and the piston is arranged on described In accommodating cavity, the permanent support is arranged between the bottom of cabinet plate and the piston.
8. the rubber film sealing gas chamber as claimed in claim 7 for being provided with permanent support, it is characterised in that the bottom of cabinet plate Core be higher than the bottom of cabinet plate marginal portion.
9. the rubber film sealing gas chamber as claimed in claim 8 for being provided with permanent support, it is characterised in that the center branch The top of frame is additionally provided with the piston mounting bracket for setting up piston, the piston mounting bracket be vertically arranged and with the center Support releasably connects.
CN201711046897.1A 2017-10-31 2017-10-31 Permanent support and rubber membrane sealing gas tank provided with same Active CN107816629B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711046897.1A CN107816629B (en) 2017-10-31 2017-10-31 Permanent support and rubber membrane sealing gas tank provided with same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711046897.1A CN107816629B (en) 2017-10-31 2017-10-31 Permanent support and rubber membrane sealing gas tank provided with same

Publications (2)

Publication Number Publication Date
CN107816629A true CN107816629A (en) 2018-03-20
CN107816629B CN107816629B (en) 2023-08-04

Family

ID=61603096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711046897.1A Active CN107816629B (en) 2017-10-31 2017-10-31 Permanent support and rubber membrane sealing gas tank provided with same

Country Status (1)

Country Link
CN (1) CN107816629B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2814685A1 (en) * 1978-04-05 1979-10-18 Dietmar Rudolph Dry gas holder membrane plate - has stabilisation equipment contg. three suspension ropes with counter-weights and connected together
CN2608816Y (en) * 2003-03-25 2004-03-31 李伟 8-10 KPA rubber film sealing gas storage cabinet
CN201057354Y (en) * 2007-07-03 2008-05-07 中冶南方工程技术有限公司 Cabinet top structure of revolving furnace gas chamber
CN201382255Y (en) * 2009-02-24 2010-01-13 孔庆哲 6-8kpa rubber membrane sealed dry gas storage cabinet
CN202598114U (en) * 2012-06-18 2012-12-12 安徽工业大学 Cylindrical dry type gas storage cabinet piston
CN203395568U (en) * 2013-05-31 2014-01-15 中冶华天工程技术有限公司 High-pressure rubber membrane sealed-type gas holder piston
CN203641866U (en) * 2013-12-27 2014-06-11 北京京诚泽宇能源环保工程技术有限公司 Gas chamber piston
CN203641865U (en) * 2013-12-27 2014-06-11 北京京诚泽宇能源环保工程技术有限公司 Gas chamber piston
CN104344206A (en) * 2013-07-26 2015-02-11 中冶华天南京工程技术有限公司 High-pressure and constant-pressure two-section rubber membrane sealing air cabinet
CN104633437A (en) * 2015-02-12 2015-05-20 中冶华天工程技术有限公司 Piston of cylindrical gas chamber
CN207500800U (en) * 2017-10-31 2018-06-15 北京京诚泽宇能源环保工程技术有限公司 Permanent support and rubber film sealed gas cabinet provided with same

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2814685A1 (en) * 1978-04-05 1979-10-18 Dietmar Rudolph Dry gas holder membrane plate - has stabilisation equipment contg. three suspension ropes with counter-weights and connected together
CN2608816Y (en) * 2003-03-25 2004-03-31 李伟 8-10 KPA rubber film sealing gas storage cabinet
CN201057354Y (en) * 2007-07-03 2008-05-07 中冶南方工程技术有限公司 Cabinet top structure of revolving furnace gas chamber
CN201382255Y (en) * 2009-02-24 2010-01-13 孔庆哲 6-8kpa rubber membrane sealed dry gas storage cabinet
CN202598114U (en) * 2012-06-18 2012-12-12 安徽工业大学 Cylindrical dry type gas storage cabinet piston
CN203395568U (en) * 2013-05-31 2014-01-15 中冶华天工程技术有限公司 High-pressure rubber membrane sealed-type gas holder piston
CN104344206A (en) * 2013-07-26 2015-02-11 中冶华天南京工程技术有限公司 High-pressure and constant-pressure two-section rubber membrane sealing air cabinet
CN203641866U (en) * 2013-12-27 2014-06-11 北京京诚泽宇能源环保工程技术有限公司 Gas chamber piston
CN203641865U (en) * 2013-12-27 2014-06-11 北京京诚泽宇能源环保工程技术有限公司 Gas chamber piston
CN104633437A (en) * 2015-02-12 2015-05-20 中冶华天工程技术有限公司 Piston of cylindrical gas chamber
CN207500800U (en) * 2017-10-31 2018-06-15 北京京诚泽宇能源环保工程技术有限公司 Permanent support and rubber film sealed gas cabinet provided with same

Also Published As

Publication number Publication date
CN107816629B (en) 2023-08-04

Similar Documents

Publication Publication Date Title
US8713892B2 (en) Method for assembling shell segments for forming tower sections of a hybrid wind turbine tower
CN104674854B (en) Ballasting system for detecting engineering pile foundation
CN103883132B (en) Low head assemble method and jig structure on a kind of Nuclear Safety shell
CN105586833B (en) Stiff skeleton steel reinforcement cage global formation large-scale cast-in-place tall pier and thin wall construction method
CN102967480B (en) The water tank type test mass block of bridge type crane slow test
CN210316779U (en) Template supporting structure of water tower inverted cone shell
CN101899540B (en) Construction method for overhauling blast furnace and keeping furnace shell and cooling wall
CN207500800U (en) Permanent support and rubber film sealed gas cabinet provided with same
CN107816629A (en) Permanent support and rubber film sealed gas cabinet provided with same
CN107654063A (en) A kind of monoblock type may move sliding form apparatus
CN110346159A (en) Hydraulic jacking equipment load test crossbeam and rolling-mill housing lift analogy method
CN106049523B (en) Land blower foundation, foundation construction method and blower
CN106223377A (en) A kind of folded spelling formula reinforced vertical adjustment mechanism adjusted for contrary sequence method verticality of stand column
CN104141390B (en) AP1000 nuclear power dome assembly moulding bed
CN110259150B (en) Assembling support and assembling method for steel containment vessel top head of nuclear power station
CN210457291U (en) Movable lifting device for assembling vault tank top plate
CN206267562U (en) Detachable platform frame
CN114961286A (en) Hoisting construction method for ultrahigh camber large-section K-shaped stiffened steel rib column
CN210013467U (en) Umbrella-shaped high formwork supporting device
RU2390600C1 (en) Prefabricated bridge pillar
CN107060835B (en) A kind of underground chamber branch-that changes the outfit hangs combination unit and its construction method
CN108252309B (en) Easily-assembled foundation pit supporting mechanism
CN217710813U (en) A back cover concrete reinforcing structure for pouring jacket
CN108914993B (en) A kind of works is by uneven settlement of foundation and the pilot system of horizontal loads
CN107975148B (en) Primary system component pre-introduced method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant