CN107816359A - A kind of construction method of the artificial pillar of underground engineering - Google Patents

A kind of construction method of the artificial pillar of underground engineering Download PDF

Info

Publication number
CN107816359A
CN107816359A CN201711085572.4A CN201711085572A CN107816359A CN 107816359 A CN107816359 A CN 107816359A CN 201711085572 A CN201711085572 A CN 201711085572A CN 107816359 A CN107816359 A CN 107816359A
Authority
CN
China
Prior art keywords
bearing structure
self
courtyard
pillar
artificial
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711085572.4A
Other languages
Chinese (zh)
Other versions
CN107816359B (en
Inventor
李元辉
吴大伟
安龙
冯夏庭
戴星航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeastern University China
Original Assignee
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeastern University China filed Critical Northeastern University China
Priority to CN201711085572.4A priority Critical patent/CN107816359B/en
Publication of CN107816359A publication Critical patent/CN107816359A/en
Application granted granted Critical
Publication of CN107816359B publication Critical patent/CN107816359B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Abstract

The present invention relates to underground engineering support technical field, and in particular to a kind of artificial pillar construction method of underground engineering.The construction method of the artificial pillar of underground engineering of the present invention, include the bearing structure formed by integrally casting forming method of artificial pillar, by the courtyard of specification needed for driving, be built into the armored concrete bearing structure that formed by integrally casting is molded;Floor rocks, bearing structure, self-expanding device and roof rock are connected in turn respectively by anchor pole, enhance the globality of artificial pillar and country rock.So as to improve the pressure-bearing of artificial pillar and shear resistance, while self-expanding connects roof construction realizes that artificial pillar is overall effectively, the purpose of active roof supporting country rock.

Description

A kind of construction method of the artificial pillar of underground engineering
Technical field
The present invention relates to artificial support technology field, more particularly to the artificial support technology field of underground engineering.
Background technology
At present, the conventional mining methods of mining level and gently inclined medium thick orebody are room-and-pillar methods.During room and pillar caving, In order to keep the stability of stope, it usually needs stay and set primary ore pillar Stope roof is supported, stay the primary ore pillar set to lead to Unified recovery is often either carried out in mining production latter stage without recovery, but the rate of recovery is low, and loss and dilution rate is high, result in ore deposit A large amount of losses of stone, are unfavorable for mineral resources conservation;And generally existing stratification, joint, crack etc. are natural weak in primary ore pillar Face, under the effect and exploitation blast disturbance of crustal stress, phenomena such as primary ore pillar produces rapidly slabbing, size reduction, support energy Power weakens so that primary ore pillar weakens to the support action of Stope roof even to fail;With the increase of mining depth, deep is adopted Field effect on crustalstress is more obvious, such as continues to be exploited using traditional room-and-pillar method, certainly will stay and set more larger-sized originals Rawore post supports stope, further deteriorates the recovery index of ore.
For produced problem during room and pillar caving, primary ore can be substituted by way of constructing artificial ore pillar Post, so as to reduce ore losses, the method for pillar strength is improved to solve.By consulting data of literatures, Wei Lijian It is proposed《A kind of method for forming artificial ore pillar and corresponding mining methods》In, artificial ore pillar does not have any top that connects to arrange after being formed Apply, certain space be present between Stope roof at the top of artificial ore pillar, after needing to wait for roof deformation sedimentation, ore pillar could driven bearing Carry, have impact on the support effect of artificial ore pillar;Meanwhile constructing for artificial ore pillar mainly uses masonry of cement mortar in this method The method of deads, is limited by construction technology, the artificial ore pillar limited height that this kind of method is constructed, is usually no more than 3m, right More than the room-and-pillar method stope of the height, the problems such as high-altitude working safety hidden danger, complicated construction technique be present, it is difficult to meet it is horizontal and Gently inclined medium thick orebody stope and underground heavy construction artificial ore pillar construct needs.
Notification number is that CN103161467B Chinese invention patent discloses a kind of horizontal middle thickness orebody van-type mining with stowing Method, by laying steel wire along bottom plate both sides in the mining methods, barren rock is then filled in steel wire, to steel wire on the inside of Delivering concrete forms artificial pillar, and the height of the artificial pillar of individual layer is 3m, by constructing the artificial pillar of multilayer close to ore bed top Plate, is finally blocked in passage both sides formwork supporting plate, and casting concrete connects top, is built into final artificial pillar.Though the artificial pillar So realize artificial pillar and bed top connects top completely, but simply with concrete by artificial pillar and bed top it is cementing Together, itself does not have the support force for producing active to bed top.
Notification number be CN105422146B Chinese invention patent disclose a kind of underground mining stope manually put post expansion connect top Device and building method, realize artificial point post and bed top effectively actively connects top.The expansion of the patent, which connects ejection device, not to be had Have and effectively fixed with manually putting post, the artificial ore pillar being combined into has the problem of anti-shear ability difference.
It is existing to construct existing for the method for artificial ore pillar that distinct issues are the most it was found from such scheme:The big height of size The active that high artificial ore pillar formed by integrally casting molding construction is difficult, overall artificial ore pillar is not carried out with bed top is spent effectively to connect Top.In addition, the shortcomings of artificial ore pillar intensity is difficult to ensure that, globality is poor also be present.
The content of the invention
(1) technical problems to be solved
In order to solve the large-sized artificial ore pillar of prior art be integrally formed it is difficult, can not realize high ore pillar space support, with And pillar strength it is low the problem of, the present invention provides the method for a kind of artificial pillar bearing structure formed by integrally casting shaping and corresponding The structure and construction method of artificial pillar, to reach, construction technology is simple, cost is cheap, stability is strong, reliability is high and can fit In the construction method for the underground engineering large-sized artificial pillar for actively effectively supporting Stope roof.
(2) technical scheme
In order to achieve the above object, the main technical schemes that the present invention uses include:
A kind of method of the artificial pillar bearing structure formed by integrally casting shaping of underground engineering, excavates and is formed and bearing structure specification The courtyard to match;Bar-mat reinforcement is laid along the borehole wall, and some anchor poles are installed in the bottom plate of the courtyard;Coagulation is poured into courtyard Soil, construct the armored concrete bearing structure of artificial pillar.
Described excavation forms the courtyard with bearing structure match specifications, is according to the dimensions of artificial pillar, opens It is empty to adopt the ore in the range of artificial pillar, the courtyard of specification needed for formation between bottom plate cutting tunnel and top plate cutting tunnel Between.
Described bar-mat reinforcement includes vertical muscle and circle muscle, and axially welds some hoops of putting more energy into along courtyard.
The described anchor pole for being installed on bottom plate, partial insertion bottom plate, and by remaining exposure part and courtyard inner bearing structure Bar connecting to together.
In the casting process of described concrete bearing structure, mechanical pudding is carried out after often pouring certain altitude.
A kind of artificial pillar of underground engineering, including formed by integrally casting shaping bearing structure and with the bearing structure fix connect The self-expanding connect connects roof construction,
The self-expanding, which connects roof construction, includes self-expanding device, bar assembly of casting anchor and upper bolt component;
The bar assembly of casting anchor is used for the top that self-expanding device is fixedly mounted on to the bearing structure;
The upper bolt component is used to self-expanding device being fixedly connected with courtyard top plate;
The self-expanding device supports the bearing structure and the courtyard top by means of itself along the expansion of short transverse Plate.
Described self-expanding, which connects roof construction, includes multiple expansion gears, and matrix form or annular spread are in the formed by integrally casting The top of the bearing structure of shaping.
The height for being highly suitable for any underground engineering space of the bearing structure of described formed by integrally casting shaping.
The construction method of the artificial pillar of underground engineering, comprises the following steps:
Step 1:Formed by integrally casting is molded the bearing structure, makes the top of the bearing structure and courtyard top plate interval certain Distance, the distance are more than the elemental height of the self-expanding device and less than the height after self-expanding device expansion;
Step 2:In bar assembly of being casted anchor described in the setting of the top of the bearing structure, and will by means of the bar assembly of casting anchor The self-expanding device that self-expanding connects roof construction is fixedly connected with the top of the bearing structure;
Step 3:The self-expanding connect roof construction self-expanding device expansion connect top after, make to be set in advance in courtyard top plate In upper bolt component be fixedly connected with the self-expanding device.
The described upper bolt component for being pre-set at courtyard top plate, only exposure can be used for connecing the self-expanding device after pushing up The length being fixedly connected, remainder insertion top plate.
(3) beneficial effect
The beneficial effects of the invention are as follows:
1st, the method that the present invention uses courtyard Cheng Zhu using open column shape courtyard is excavated in ore body before stope exploitation, Solve the difficulty in process for constructing the integrally formed large-sized artificial pillar of underground engineering, realize underground engineering large-sized artificial pillar Construct, the height of artificial pillar can reach more than 8 meters, or even 10 meters -20 meters;
2nd, the present invention replaces primary ore pillar using armored concrete ore pillar, ensure that the intensity of artificial pillar, this intensity Ensure that can be linked together self-expanding device, bearing structure and the top of artificial pillar, floor rocks using anchor pole, enhancing The globality of artificial pillar and country rock, improves the pressure-bearing and shear resistance of artificial pillar, is finally reached to more than 8 meters even The secure support of 10 meters of -20 meters of underground spaces;
3rd, the present invention realizes that artificial pillar is effective, fast quick access top using self-expanding device, simplifies and connects top technique, reaches The purpose of active roof supporting country rock;
4th, construction technology of the present invention is simple, and wherein bearing structure constructs usable existing concrete casting craft, expansion dress Put simple in construction, it is cheap that artificial pillar constructs cost.
Brief description of the drawings
Fig. 1 is:A kind of schematic diagram of the artificial pillar of underground engineering of the present invention;
Fig. 2 is:A kind of artificial pillar construction method of underground engineering of the present invention connects enlarged drawing between head space.【Reference is said It is bright】
1:Roof rock;2:Top plate cuts tunnel;3:Bar-mat reinforcement;4:Ore body;5:Reinforcement hoop;6:Bearing structure;7:Bottom plate Cut tunnel;8:Bottom anchor pole;9:Floor rocks;10:Upper bolt component;11:Self-expanding device;12:Cast anchor bar assembly.
Embodiment
In order to preferably explain the present invention, in order to understand, below in conjunction with the accompanying drawings, by embodiment, to this hair It is bright to be described in detail.
The construction method of artificial pillar and itself and bearing structure will be retouched in detail by taking underground mining stope as an example below State.It is to be appreciated that artificial pillar of the invention not merely can be used for underground mining stope, therefore the description as described in underground mining stope Limitation of the invention is not formed, the related technical characteristic of underground mining stope can be interpreted as other ground by those skilled in the art The individual features of lower engineering.
As shown in figure 1, the artificial pillar of underground engineering of the present invention includes bearing structure 6 and the self-expanding of formed by integrally casting shaping Connect roof construction 10,11,12.The construction method of this artificial pillar mainly includes bearing structure formed by integrally casting and is molded and installs expansion Connect two steps of roof construction:
1st, the artificial pillar bearing structure of integrated pouring molding
Form courtyard space:
Using the method for driving courtyard, back production is upwardly into the top plate cutting artificial pillar scope in tunnel 2 by bottom plate cutting tunnel 7 Interior ore, form the courtyard space with the artificial match specifications of pillar bearing structure 6.Though it is understood that the present embodiment So using the preferred mining method that top plate cutting tunnel 2 is upwardly into from bottom plate cutting tunnel 7, tunnel 2 is cut to bottom plate from top plate The digging for cutting tunnel 7 is also feasible, therefore the present invention does not limit the direction of digging, and is by being cut in bottom plate emphatically Cut digging between tunnel 7 and top plate cutting tunnel 2 and form courtyard space.So as to which roof rock 1 and floor rocks 9 correspond to courtyard Position respectively constituted courtyard top plate 1 and courtyard bottom plate 9.
Pour bearing structure:
Bottom anchor pole 8 (in the present embodiment using long anchor pole) is squeezed into drilling in floor rocks 9 corresponding to day bottom, The partial-length of bottom anchor pole 8 insertion courtyard bottom plate 9 (floor rocks), partial-length is exposed;Inside courtyard steel is laid along the borehole wall Muscle net 3, and the bottom anchor pole 8 of exposure is welded and fixed with bar-mat reinforcement 3, then along courtyard axially in bar-mat reinforcement 3 every a spacing Put more energy into hoop 5 from welding;The concrete being stirred is delivered to courtyard by pipe special, often pours 1~2m mechanical puddings, and in advance Reserve between connecing head space, connect after height between head space is more than the elemental height of self-expanding device 11 and expanded less than self-expanding device 11 Height, be finally completed the bearing structure 6 that formed by integrally casting is molded artificial pillar, then carried out to bearing structure 6 a period of time Maintenance, reaches certain intensity.
2nd, self-expanding connects the installation of roof construction:
After the completion of the maintenance of bearing structure 6, using casting anchor, bar assembly 12 (in the present embodiment using Short bolt) will be from swollen Swollen device 11 is fixed on the top of bearing structure 6, after self-expanding device 11 connects top, then with anchor rod component 10 (in this implementation Short bolt is used in example) ore body roof country rock 1 is fixed in, as shown in Figure 2.Bar assembly of casting anchor 12, the and of upper bolt component 10 Self-expanding device 11 respectively can be multiple in the setting of the top of bearing structure, and preferably uniformly such as matrix form or arrangement annular in shape On the top of bearing structure, top support is uniformly connect on whole top end face to provide.Bar assembly of casting anchor 12 and upper bolt group The length direction almost all of the Short bolt of part 10 is inserted respectively into the top and roof rock 1 of bearing structure 6, and only reserving must The end wanted with self-expanding device 11 to be fixedly connected.Such as with the metal shell of self-expanding device 11, chassis or take over a business welding.
Wherein, the principle that self-expanding device 11 connects top is:Self-expanding device 11 includes being set in upper outer above inner sleeve Set bucket and the lower overcoat bucket that is set in below inner sleeve, inner sleeve be sequentially provided with from the bottom to top blotter, expansion medicament volume and Sandstone;Reacted volumetric expansion with water when expanding medicament volume in self-expanding device 11, due to the constraint of inner sleeve, expand medicament Volume can only axially expand, and so as to promote upper overcoat bucket edge axially to move up, promote lower overcoat bucket edge axially to move down, final to realize Self-expanding device 11 connects top with roof rock 1.It for details, reference can be made to the first patent CN105422146B of the present inventor.
Artificial pillar construction method, forms the artificial pillar of underground engineering of the present invention more than, including integrally pours Build up the bearing structure 6 of type and self-expanding connect roof construction 10,11,12, the self-expanding connect roof construction include self-expanding device 11, Bar assembly of casting anchor 12 and upper bolt component 10;The bar assembly 12 of casting anchor is used to self-expanding device 11 being fixedly mounted on described hold Carry the top of structure 6;The upper bolt component 10 is used to self-expanding device 11 being fixedly connected with roof rock 1;It is described from swollen Swollen device 11 supports the bearing structure 6 and the roof rock 1 by means of itself along the expansion of short transverse.
The dimensions of artificial pillar in the present embodiment, these sizes are only that this specifically descends stope design, are not formed Limitation of the invention, those skilled in the art can be carried out according to the scale of underground engineering, geological environment and/or operation property Adjustment.Wherein top plate cutting tunnel 2 and bottom plate cutting tunnel 7 are respectively highly 2m, and the height in courtyard space is 8.55m, that is, is pushed up The distance between plate country rock 1 and floor rocks 9.The circle that the artificial section of pillar bearing structure 6 is a diameter of 3.5m, highly it is 8m, bottom plate anchor pole 8 are 18 × 2250mm of Φ, and bar assembly of casting anchor 12 and upper bolt component 10 are 18 × 1000mm of Φ, reinforcing bar host Muscle is Φ 18mm and circle muscle is Φ 16mm, and hoop of putting more energy into is Φ 18mm reinforcing bars, is axially welded into triangle every 1m along courtyard, pours Concrete strength be C20, often pour 2m carry out mechanical pudding, reserve 530-550mm connect head space between, self-expanding device 11 Elemental height before inflation is 500mm.
For horizontal or gently inclined medium thick orebody underground mining stope and underground engineering, its artificial pillar is designed and constructed Generally comprise following steps:
Step 1: determine quantity, specification and the position of artificial pillar needed for underground engineering;
It is Step 2: upward by the bottom plate of ore body 4 cutting tunnel 7 using the method for driving courtyard, back production at defined location Ore to the top plate of ore body 4 cutting 2 artificial pillar of tunnel, the cylindrical courtyard for forming a height of 8m of a diameter of 3.5m are empty Between;
Step 3: squeezing into some bottom anchor poles 8 into floor rocks 9 corresponding to day bottom, bottom anchor pole 8 inserts country rock Length 1125mm, exposed 1125mm;Roof rock 1 corresponding at the top of to courtyard squeezes into some upper bolt components 10, upper bolt group Part 10 inserts country rock length 900mm, exposure 100mm;
Step 4: the borehole wall in cylindrical courtyard space lays bar-mat reinforcement 3, and hoop 5 of putting more energy into is welded every 1m vertically, and The exposed parts of bottom anchor pole 8 are welded and fixed with bar-mat reinforcement;
Step 5: into cylindrical courtyard space, casting concrete, the height for often pouring 2m are shaken by pipe special Dynamic tamping operation, and reserved 530-550mm connect head space between, ultimately form the armored concrete bearing structure 6 that height is 8m;
Step 6: the progress of armored concrete bearing structure 6 more than the 28d to the artificial pillar of underground mining stope is conserved, make its strong Degree reaches C20;
Step 7: squeezing into some bar assemblies 12 of casting anchor on the top surface of the armored concrete bearing structure 6 conserved, cast anchor The depth that bar assembly 12 inserts the top surface of bearing structure 6 is 900mm, and the 100mm of remaining exposure and self-expanding device 11 are welded Fixed, the top of self-expanding device 11 is with roof rock 1 at a distance of 30-50mm;
Step 8: after the expansion of self-expanding device 11 connects top, the exposure part of itself and upper bolt component 10 is welded and fixed, It is finally completed constructing for the artificial pillar of underground mining stope.
Presently preferred embodiments of the present invention is these are only, is not construed as limiting the scope of the present invention, any to be familiar with sheet special The technical staff of industry is changed or is modified as other equivalent embodiments possibly also with the technology contents of the disclosure above.As long as do not take off From technical solution of the present invention content, any simply modification, equivalent variations that the design according to the present invention is made to above example With remodeling, the protection domain of technical solution of the present invention is still fallen within.

Claims (10)

  1. A kind of 1. method of the artificial pillar bearing structure formed by integrally casting shaping of underground engineering, it is characterised in that
    Excavate the courtyard formed with bearing structure match specifications;
    Bar-mat reinforcement is laid along the borehole wall, and some anchor poles are installed in the bottom plate of the courtyard;
    The casting concrete into courtyard, construct the armored concrete bearing structure of artificial pillar.
  2. 2. a kind of method of the artificial pillar bearing structure formed by integrally casting shaping of underground engineering as claimed in claim 1, its feature It is, described excavation forms the courtyard with bearing structure match specifications, is situated between according to the dimensions of artificial pillar, exploitation The rock between tunnel and top plate cutting tunnel in the range of artificial pillar, the courtyard space of specification needed for formation are cut in bottom plate.
  3. 3. a kind of method of the artificial pillar bearing structure formed by integrally casting shaping of underground engineering as claimed in claim 1, its feature It is, described bar-mat reinforcement includes vertical muscle and circle muscle, and axially welds some hoops of putting more energy into along courtyard.
  4. 4. a kind of method of the bearing structure formed by integrally casting shaping of artificial pillar of underground engineering as claimed in claim 1, it is special Sign is, the described anchor pole for being installed on bottom plate, partial insertion bottom plate, and by remaining exposure part and courtyard inner bearing structure Bar connecting is to together.
  5. 5. a kind of method of the bearing structure formed by integrally casting shaping of artificial pillar of underground engineering as claimed in claim 1, it is special Sign is, in the casting process of described concrete bearing structure, mechanical pudding is carried out after often pouring certain altitude.
  6. A kind of 6. artificial pillar of underground engineering, it is characterised in that including formed by integrally casting shaping bearing structure and with the carrying The self-expanding that structure is fixedly connected connects roof construction,
    The self-expanding, which connects roof construction, includes self-expanding device, bar assembly of casting anchor and upper bolt component;
    The bar assembly of casting anchor is used for the top that self-expanding device is fixedly mounted on to the bearing structure;
    The upper bolt component is used to self-expanding device being fixedly connected with courtyard top plate;
    The self-expanding device supports the bearing structure and the courtyard top plate by means of itself along the expansion of short transverse.
  7. 7. the artificial pillar of underground engineering as claimed in claim 6, it is characterised in that described self-expanding connects roof construction including more Individual expansion gear, and the top of bearing structure that matrix form or annular spread are molded in the formed by integrally casting.
  8. 8. the artificial pillar of underground engineering as claimed in claim 6, it is characterised in that the carrying knot of described formed by integrally casting shaping The height for being highly suitable for any underground engineering space of structure.
  9. 9. a kind of construction method of the artificial pillar of underground engineering as claimed in claim 6, comprises the following steps:
    Step 1:Formed by integrally casting is molded the bearing structure, makes top and the spacing of courtyard top plate interval one of the bearing structure From the distance is more than the elemental height of the self-expanding device and less than the height after self-expanding device expansion;
    Step 2:Casted anchor bar assembly described in being set on the top of the bearing structure, and will be from swollen by means of the bar assembly of casting anchor The self-expanding device of expanded joint roof construction is fixedly connected with the top of the bearing structure;
    Step 3:The self-expanding connect roof construction self-expanding device expansion connect top after, make to be set in advance in courtyard top plate Upper bolt component is fixedly connected with the self-expanding device.
  10. 10. a kind of construction method of the artificial pillar of underground engineering as claimed in claim 9, it is characterised in that described is advance The upper bolt component of courtyard top plate is arranged at, only exposure can be used for the length being fixedly connected with connecing the self-expanding device after pushing up, its Remaining partial insertion top plate.
CN201711085572.4A 2017-11-07 2017-11-07 Construction method of underground engineering manual support Active CN107816359B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711085572.4A CN107816359B (en) 2017-11-07 2017-11-07 Construction method of underground engineering manual support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711085572.4A CN107816359B (en) 2017-11-07 2017-11-07 Construction method of underground engineering manual support

Publications (2)

Publication Number Publication Date
CN107816359A true CN107816359A (en) 2018-03-20
CN107816359B CN107816359B (en) 2020-02-21

Family

ID=61604876

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711085572.4A Active CN107816359B (en) 2017-11-07 2017-11-07 Construction method of underground engineering manual support

Country Status (1)

Country Link
CN (1) CN107816359B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825233A (en) * 2018-06-06 2018-11-16 徐庆余 A kind of pillar recovery method
CN112065472A (en) * 2020-08-06 2020-12-11 黑龙江工业学院 Construction method of mine hole support column

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088986A (en) * 1996-09-12 1998-04-07 Ohbayashi Corp Funnel lining formwork and tunnel lining method
CN1904313A (en) * 2006-08-01 2007-01-31 贵州开磷(集团)有限责任公司 Concrete pole top protection mining method
CN103161467A (en) * 2013-02-25 2013-06-19 湖北杉树垭矿业科技开发有限公司 Horizontal moderately thick mine body compartment type filling mining method
CN105422146A (en) * 2015-12-15 2016-03-23 东北大学 Underground stope artificial pillar expansion jacking device and construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1088986A (en) * 1996-09-12 1998-04-07 Ohbayashi Corp Funnel lining formwork and tunnel lining method
CN1904313A (en) * 2006-08-01 2007-01-31 贵州开磷(集团)有限责任公司 Concrete pole top protection mining method
CN103161467A (en) * 2013-02-25 2013-06-19 湖北杉树垭矿业科技开发有限公司 Horizontal moderately thick mine body compartment type filling mining method
CN105422146A (en) * 2015-12-15 2016-03-23 东北大学 Underground stope artificial pillar expansion jacking device and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825233A (en) * 2018-06-06 2018-11-16 徐庆余 A kind of pillar recovery method
CN112065472A (en) * 2020-08-06 2020-12-11 黑龙江工业学院 Construction method of mine hole support column

Also Published As

Publication number Publication date
CN107816359B (en) 2020-02-21

Similar Documents

Publication Publication Date Title
CN108678769A (en) Deep Gateway anchor note cuts top master control and stays lane method
CN103291305B (en) Quick and low-cost artificial fake roof construction method for ground mine
CN104074529B (en) A kind of cave continuous bivalve, lane, deep reinforcement means
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN106400820A (en) Cofferdam formed by latched steel tube and concrete combined piles and construction method
CN107642041A (en) The hollow clump of piles anchorage of super-large diameter
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN108532586A (en) A kind of construction method of garage parking diaphram wall
CN109595029A (en) Goaf partial stowage supporting structure and its construction method under the conditions of tight roof
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN104564091A (en) Method and device for removing anchor rods from shield crossing area
CN210948688U (en) Artificial false lane
CN109853399A (en) Big section for arch bridge tilts tunnel type skewback structure and its construction method
CN109577989A (en) A kind of novel deeps mines shaft wall structure and construction method
CN107816359A (en) A kind of construction method of the artificial pillar of underground engineering
CN207484290U (en) The hollow clump of piles anchorage of super-large diameter
CN208702421U (en) The tunnel support structure of existing pile foundation building is worn under a kind of
CN104863613B (en) Rocky stratum tunneling underground structure flash joist anchor draws just branch structure and construction method
CN107060778B (en) Pass through super high-rise building group back filled region method for tunnel construction
CN111236949B (en) Small-angle cross tunnel construction method
CN111594168B (en) Pseudo-goaf-layer supporting and sinking-limiting stoping method formed by matching rock waste with rock waste
CN107642040A (en) The construction method heavy stone used as an anchor of the hollow clump of piles anchorage of super-large diameter
CN108590710B (en) Underground goaf inner prefabricated roadway to be filled and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant