CN107642040A - Construction method of super large diameter hollow pile group anchorage - Google Patents
Construction method of super large diameter hollow pile group anchorage Download PDFInfo
- Publication number
- CN107642040A CN107642040A CN201710705945.7A CN201710705945A CN107642040A CN 107642040 A CN107642040 A CN 107642040A CN 201710705945 A CN201710705945 A CN 201710705945A CN 107642040 A CN107642040 A CN 107642040A
- Authority
- CN
- China
- Prior art keywords
- pile
- construction method
- anchorage
- cap
- diameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 97
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 65
- 239000010959 steel Substances 0.000 claims abstract description 65
- 239000004567 concrete Substances 0.000 claims abstract description 48
- 230000007423 decrease Effects 0.000 claims abstract description 7
- 239000002689 soil Substances 0.000 claims description 55
- 238000000034 method Methods 0.000 claims description 38
- 230000008569 process Effects 0.000 claims description 27
- 238000009412 basement excavation Methods 0.000 claims description 23
- 239000011435 rock Substances 0.000 claims description 20
- 230000002787 reinforcement Effects 0.000 claims description 18
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 6
- 210000002435 tendon Anatomy 0.000 claims description 3
- 241000209202 Bromus secalinus Species 0.000 claims 1
- 238000005266 casting Methods 0.000 claims 1
- 238000009434 installation Methods 0.000 claims 1
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 238000007789 sealing Methods 0.000 claims 1
- 238000007569 slipcasting Methods 0.000 claims 1
- 238000009415 formwork Methods 0.000 abstract description 4
- 238000005452 bending Methods 0.000 description 35
- 230000008901 benefit Effects 0.000 description 13
- 239000000725 suspension Substances 0.000 description 12
- 230000005484 gravity Effects 0.000 description 10
- 239000004576 sand Substances 0.000 description 10
- 238000005553 drilling Methods 0.000 description 9
- 239000007787 solid Substances 0.000 description 9
- 238000010586 diagram Methods 0.000 description 7
- 230000000694 effects Effects 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 7
- 238000005219 brazing Methods 0.000 description 6
- 230000007547 defect Effects 0.000 description 6
- 239000000463 material Substances 0.000 description 6
- 238000004873 anchoring Methods 0.000 description 5
- 238000013461 design Methods 0.000 description 5
- 238000009826 distribution Methods 0.000 description 5
- 230000002829 reductive effect Effects 0.000 description 5
- 239000003673 groundwater Substances 0.000 description 4
- 239000002002 slurry Substances 0.000 description 4
- 238000012360 testing method Methods 0.000 description 4
- 239000002699 waste material Substances 0.000 description 4
- 230000003247 decreasing effect Effects 0.000 description 3
- 239000011440 grout Substances 0.000 description 3
- 230000002411 adverse Effects 0.000 description 2
- 238000005422 blasting Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000005457 optimization Methods 0.000 description 2
- 238000003908 quality control method Methods 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 230000002441 reversible effect Effects 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 239000013589 supplement Substances 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000000670 limiting effect Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000003801 milling Methods 0.000 description 1
- 238000012946 outsourcing Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000000246 remedial effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种超大直径空心群桩锚碇的施工方法,包括:1)由上而下开挖多个桩孔直至桩底:在开挖各个桩孔的同时在桩孔的内部设置外模,并且在孔壁与内部之间填充填石注浆;2)在外模的内部设置内模,接着将钢筋笼、注浆管设置于内模、外模之间,然后浇筑混凝土;3)通过注浆管对桩底进行二次注浆直至达到承载要求;4)在桩顶预埋承台连接钢筋,并安装封顶内模,对桩体进行封顶;待桩体及桩顶封顶混凝土达到强度后,安装承台模,最后浇筑承台以及锚固系统;其中,桩孔、内模、外模的口径自上而下均呈阶梯型递减。通过该施工方法建造而成的超大直径空心群桩锚碇具有优异的承载能力。
The invention discloses a construction method for super large-diameter hollow pile group anchorage, which includes: 1) Excavating a plurality of pile holes from top to bottom to the bottom of the pile; mold, and fill rockfill grouting between the hole wall and the inside; 2) set the inner mold inside the outer mold, then set the steel cage and the grouting pipe between the inner mold and the outer mold, and then pour concrete; 3) Carry out secondary grouting to the bottom of the pile through the grouting pipe until the load-bearing requirements are met; 4) Pre-embed the cap to connect the steel bars at the top of the pile, and install the capping inner mold to cap the pile; wait until the pile body and the capping concrete on the pile top reach After the strength, the cap formwork is installed, and finally the cap and the anchorage system are poured; among them, the calibers of the pile holes, the inner mold, and the outer mold all decrease in steps from top to bottom. The ultra-large-diameter hollow pile group anchorage constructed by this construction method has excellent bearing capacity.
Description
技术领域technical field
本发明涉及悬索桥锚碇,具体地,涉及一种超大直径空心群桩锚碇的施工方法。The invention relates to a suspension bridge anchorage, in particular to a construction method for an ultra-large-diameter hollow pile group anchorage.
背景技术Background technique
悬索桥的承重构件主要由主缆、桥塔和锚碇三部分组成。其中桥体结构的自重和主要荷载通过主缆传导至桥塔,而主缆两端仅由锚碇结构锚固,其内力通过锚碇传递到地基中,因此锚碇结构的承载能力是决定悬索桥的整体稳定性的关键构件。The load-bearing components of the suspension bridge are mainly composed of three parts: the main cable, the bridge tower and the anchorage. The self-weight and main load of the bridge structure are transmitted to the bridge tower through the main cable, while the two ends of the main cable are only anchored by the anchorage structure, and its internal force is transmitted to the foundation through the anchorage. Therefore, the bearing capacity of the anchorage structure is the decisive factor for the suspension bridge. A key building block for overall stability.
中国公路悬索桥重力式锚碇基础现状:国内最常用的锚碇承载方案是重力式锚碇,其承载原理是通过锚碇结构的自重来平衡锚索的竖向拉向,通过锚碇底部与地基之间摩擦力来平衡锚索的水平拉力。悬索桥锚碇的施工方案包括地下连续墙、沉井等方案,其特点包括:Current status of gravity anchorage foundations of highway suspension bridges in China: The most commonly used anchorage bearing scheme in China is gravity anchorage. The friction between them is used to balance the horizontal tension of the anchor cable. The construction scheme of suspension bridge anchorage includes underground diaphragm wall, caisson and other schemes, and its characteristics include:
(1)地下连续墙锚碇施工方案(1) Construction scheme of underground diaphragm wall anchorage
这种方案最为常用,适用于多种地质条件。该方案首先进行地下连续墙围堰施工,在围堰施工完毕后在基坑中下放钢筋网,分层浇注混凝土,最后形成钢筋混凝土锚碇结构。其中地下连续墙的外包范围远大于锚碇结构的受力范围,与其他支护体系一样,其功能仅仅是挡土止水,并不参与分担主缆的荷载,造成了材料的极大浪费。同时地下连续墙施工需要采用铣槽机等专用机械,在地下水较丰富的地层施工时,还需要注意墙幅之间的咬合止水,对施工要求较高,因此造价比较昂贵。This scheme is the most commonly used and is suitable for a variety of geological conditions. In this scheme, the cofferdam of the underground diaphragm wall is firstly constructed. After the construction of the cofferdam is completed, the reinforcement mesh is lowered in the foundation pit, the concrete is poured in layers, and finally the reinforced concrete anchorage structure is formed. Among them, the outsourcing range of the underground diaphragm wall is much larger than the stress range of the anchorage structure. Like other support systems, its function is only to retain soil and water, and does not participate in sharing the load of the main cable, resulting in a great waste of materials. At the same time, the construction of the underground diaphragm wall requires the use of special machines such as slot milling machines. When constructing in strata with rich groundwater, it is also necessary to pay attention to the occlusal water stop between the wall widths, which requires high construction requirements, so the cost is relatively expensive.
(2)沉井锚碇施工方案(2) Construction scheme of caisson anchorage
该方案是通过在大体积井筒内取土,井筒结构在自重作用下同步下沉形成基础结构。这种井筒结构体积巨大,整体性好,其承载能力可达数万吨级。然而受施工方法制约,井筒下沉过程中不可避免地切削了筒周土体,造成过大的相对位移,破坏了筒周土摩阻力,导致沉井基础竖向承载能力损失严重。且在施工过程,沉井下沉所需自重常超出结构强度限值,在地质不均匀土层中施工容易倾斜,极难纠正。因此近来年沉井方案在悬索桥锚碇施工中的应用不多。The scheme is to take soil in a large-volume shaft, and the shaft structure sinks synchronously under the action of its own weight to form a basic structure. This kind of wellbore structure has huge volume and good integrity, and its bearing capacity can reach tens of thousands of tons. However, restricted by the construction method, the soil around the caisson is inevitably cut during the sinking process, resulting in excessive relative displacement, which destroys the frictional resistance of the soil around the caisson, and results in a serious loss of the vertical bearing capacity of the caisson foundation. Moreover, during the construction process, the self-weight required for caisson sinking often exceeds the structural strength limit, and construction in uneven geological soil layers is prone to inclination, which is extremely difficult to correct. Therefore, the caisson scheme has not been widely used in the anchorage construction of suspension bridges in recent years.
从上述两种方案可以看到,重力式锚碇的普遍体积巨大,决定了其开挖量大,混凝土用量多,工期长,造价高的特点。以湖南在建某大型悬索桥为例(图10),其主缆拉力高达8.75×105kN,一侧锚碇地处于粘性土风化岩地层,采用传统的地下连续墙重力式锚碇基础。该重力式锚碇混凝土用量高达 16万方,占全桥混凝土总用量的90%,造价1.37亿,两岸锚碇总造价为全桥总造价的15%,可见其重要性。It can be seen from the above two schemes that the general volume of the gravity anchorage is huge, which determines its characteristics of large excavation volume, large amount of concrete, long construction period and high cost. Taking a large-scale suspension bridge under construction in Hunan as an example (Fig. 10), the tension of the main cable is as high as 8.75×10 5 kN, and the anchorage on one side is in the cohesive soil weathered rock stratum, and the traditional underground diaphragm wall gravity anchorage foundation is adopted. The concrete consumption of the gravity anchor is as high as 160,000 cubic meters, accounting for 90% of the total concrete consumption of the whole bridge, and the cost is 137 million. The total cost of the anchorage on both sides is 15% of the total cost of the whole bridge, which shows its importance.
尽管重力式锚碇结构承载方案应用最广,然而其根本缺陷在于全面抛弃的土抗力和过大的自重。重力式锚碇承载原理是依靠其自身的巨大配重来平衡主缆的竖向分力,通过锚碇基础与基底面产生的摩阻力(f=0.2G)或嵌固力来平衡主缆的水平分力,其中水平分力是主缆荷载的主要部分。在重力式锚碇方案设计中另一个非常重要的水平承载因素——锚碇受拉面土体的被动抗力被完全忽略了,因此为达到增大基底摩擦力的目的,锚碇体积必须要设计得非常大,不仅材料上造成过大浪费,而且过大的自重对基底持力层土体的承载能力要求非常高,这一缺陷是导致重力式锚碇结构造价居高不下的最主要原因,阻碍了悬索桥的大范围推广。Although the gravity-type anchorage structure load-bearing scheme is the most widely used, its fundamental defects lie in the completely abandoned soil resistance and excessive self-weight. The bearing principle of the gravity anchor is to balance the vertical component force of the main cable by its own huge counterweight, and to balance the force of the main cable through the frictional resistance (f=0.2G) or embedded force generated between the anchorage foundation and the base surface. Horizontal component force, where the horizontal component force is the main part of the main cable load. Another very important horizontal load-bearing factor in the design of the gravity anchorage scheme—the passive resistance of the anchorage tension surface soil is completely ignored, so in order to achieve the purpose of increasing the base friction force, the anchorage volume must be designed It is very large, which not only causes excessive waste of materials, but also requires a very high load-bearing capacity of the base bearing layer soil due to excessive self-weight. This defect is the main reason for the high cost of the gravity anchorage structure. Widespread promotion of suspension bridges.
(3)群桩锚碇方案(3) Group pile anchorage scheme
群桩基础由桩和承台两部分组成,适用于抗剪强度较高的地质条件,可充分发挥桩侧土抗力来抵抗水平荷载,是常用的水平承载方案。其荷载传递路线是上部荷载通过承台分配给各桩,基桩再把荷载传递到深层地基中,这一过程中桩身强度和桩周土抗力是决定水平承载能力的关键因素,桩身直径越大,则桩身强度越强。目前国内大直径桩钻机成孔直径极限为3~5m,不足以抵抗锚碇所受的数万吨主缆水平拉力,因此锚碇采用群桩基础承载方案需要桩径达10米以上的超大直径桩。The pile group foundation is composed of piles and caps. It is suitable for geological conditions with high shear strength and can fully exert the resistance of the pile side soil to resist horizontal loads. It is a commonly used horizontal bearing scheme. The load transfer route is that the upper load is distributed to each pile through the cap, and the foundation pile transfers the load to the deep foundation. In this process, the strength of the pile body and the resistance of the soil around the pile are the key factors determining the horizontal bearing capacity. The diameter of the pile body The larger the value, the stronger the strength of the pile body. At present, the hole diameter limit of domestic large-diameter pile drilling rigs is 3-5m, which is not enough to resist the tens of thousands of tons of main cable horizontal tension on the anchorage. Therefore, the pile group foundation bearing scheme for the anchorage requires a pile diameter of more than 10 meters. pile.
根据结构力学原理,当承受均布荷载的基桩结构两端采用一端固支一端铰支方案时,桩身最大弯矩约为两端采用固支方案的1.5倍,因此水平承载的群桩基础必须尽量达到两端固支,以减小桩身内力。一般桩底通过嵌入基岩中可达到固支条件,而桩顶只有增大承台刚度才能满足固支条件,然而对于直径达10米以上的超大直径桩而言,满足桩顶固支连接要求的承台高度将达到数十米,这将大大增大承台体积,不利于结构优化。如采用空心桩构造,则满足固支条件的承台厚度可大大减小,空心桩方案不但减小了基础自重,节约了造价,而且相比实心桩而言其抗弯性能并未有较大降低。由此可见,基桩空心构造是锚碇基础超大直径群桩方案的必由之路。According to the principle of structural mechanics, when the two ends of the foundation pile structure bearing uniform load are fixed at one end and hinged at one end, the maximum bending moment of the pile body is about 1.5 times that of the fixed support at both ends. Both ends must be fixed as much as possible to reduce the internal force of the pile body. Generally, the bottom of the pile can be fixed by embedding it into the bedrock, while the top of the pile can only meet the condition of fixed support by increasing the stiffness of the cap. The height of the cap will reach tens of meters, which will greatly increase the volume of the cap, which is not conducive to structural optimization. If the hollow pile structure is used, the thickness of the cap that meets the fixed support conditions can be greatly reduced. The hollow pile scheme not only reduces the self-weight of the foundation, saves the cost, but also has no greater bending resistance compared with the solid pile. reduce. It can be seen that the hollow structure of the foundation pile is the only way for the super large diameter pile group scheme of the anchorage foundation.
超大直径波纹钢围堰挖孔空心基桩方案的提升:锚碇群桩基础超大直径桩的施工方案需要满足两个原则:一是保证成孔过程不漏水不塌孔,二是不能对桩周土产生过大扰动,破坏土抗力。目前我国钻机技术已经发展到可以完成直径4~5m的大直径钻孔桩,但10m以上的超大直径桩目前还无法钻孔完成,施工技术尚不成熟且钻孔桩自重过大(自重达承载力的一半)是限制其发展的主要原因。这种施工方案对超大直径桩成孔过程中很难保证止水不塌孔,不能满足上述原则,不宜采用。Improvement of super-large-diameter corrugated steel cofferdam excavated hollow foundation pile scheme: The construction scheme of super-large-diameter piles for anchor pile group foundations needs to meet two principles: one is to ensure that the hole does not leak or collapse during the hole forming process, and the other is not to damage the surrounding piles. Excessive soil disturbance will destroy soil resistance. At present, my country's drilling rig technology has developed to the point where large-diameter bored piles with a diameter of 4 to 5 m can be completed, but ultra-large-diameter piles with a diameter of more than 10 m cannot be drilled at present. half of the force) is the main reason for limiting its development. This kind of construction plan is difficult to ensure water stop and no collapse of the hole during the hole forming process of super-large diameter piles, and cannot meet the above principles, so it should not be adopted.
安徽省高速公路总公司曾经提出在传统的沉井基础侧壁植入根键形成根式基础的承载方法(如图11所示,参见专利文献:根式基础及施工方法,专利号200610038147.5),这种方法和传统的沉井基础、桩基础不同,结构形式较复杂,与土体相互作用时受力机理尚不明确,沉降变形也难以预测。由于该方法还是基于沉井结构,施工过程中将切削土体,破坏土的侧摩阻力,且在筒壁打入的混凝土钎将对筒周土体产生明显扰动,破坏了土的抗力,因此本方案也不适用于超大直径桩成桩的施工。Anhui Provincial Expressway Corporation once proposed a method of implanting root keys on the side wall of traditional caisson foundations to form a root foundation bearing method (as shown in Figure 11, see patent literature: root foundation and construction method, patent number 200610038147.5), this The method is different from the traditional caisson foundation and pile foundation, the structure form is more complicated, the force mechanism when it interacts with the soil is not clear, and the settlement deformation is also difficult to predict. Because this method is still based on the caisson structure, the soil will be cut during the construction process, destroying the side friction of the soil, and the concrete drill inserted into the wall of the cylinder will obviously disturb the soil around the cylinder, destroying the resistance of the soil, so This scheme is also not suitable for the construction of piles with super large diameter piles.
发明内容Contents of the invention
本发明的目的是提供一种超大直径空心群桩锚碇的施工方法,该施工方法建造的超大直径空心群桩锚碇具有优异的承载能力,同时还具有节约钻孔桩体积、缩短工期的特点进而使其具有显著经济效益。The purpose of the present invention is to provide a construction method for super large-diameter hollow pile group anchorage. The super-large-diameter hollow pile group anchorage constructed by this construction method has excellent bearing capacity, and also has the characteristics of saving the volume of bored piles and shortening the construction period. Thereby making it have significant economic benefits.
为了实现上述目的,本发明提供了一种超大直径空心群桩锚碇,包括超大直径空心群桩、承台以及锚固系统;超大直径空心群桩由多根竖直设置的桩体有机组成,桩体的底端嵌固与岩土体中且上端嵌固于承台的底端的内部;锚固系统设置于承台的顶部以连接主缆;其中,桩体为空心桩体,并且桩体的内径与外径自上而下均呈阶梯型递减。In order to achieve the above object, the present invention provides a super-large-diameter hollow pile group anchorage, which includes a super-large-diameter hollow pile group, a cap and an anchoring system; the super-large-diameter hollow pile group is composed of a plurality of vertical piles, The bottom end of the body is embedded in the rock-soil body and the upper end is embedded in the bottom end of the cap; the anchor system is set on the top of the cap to connect the main cable; the pile body is a hollow pile body, and the inner diameter of the pile body Both the outer diameter and the outer diameter decrease stepwise from top to bottom.
本发明提供了一种超大直径空心群桩锚碇的施工方法,包括:The invention provides a construction method for super large-diameter hollow pile group anchorage, comprising:
1)由上而下开挖多个桩孔直至桩底:在开挖各个桩孔的同时在桩孔的内部设置外模,并且在孔壁与内部之间填充填石注浆;1) Excavating multiple pile holes from top to bottom to the bottom of the pile: while excavating each pile hole, set an outer mold inside the pile hole, and fill the hole wall and the inside with rock-fill grouting;
2)在外模的内部设置内模,接着将钢筋笼、注浆管设置于内模、外模之间,然后浇筑混凝土;2) An inner mold is set inside the outer mold, and then a reinforcement cage and a grouting pipe are arranged between the inner mold and the outer mold, and then concrete is poured;
3)通过注浆管对桩底进行二次注浆直至达到承载要求;3) Carry out secondary grouting to the bottom of the pile through the grouting pipe until the bearing requirements are met;
)在桩顶预埋承台连接钢筋,并安装封顶内模,对桩体进行封顶;待桩体及桩顶封顶混凝土达到强度后,安装承台模,最后浇筑承台以及锚固系统;) Pre-embed the cap to connect the steel bars at the top of the pile, and install the capping inner mold to cap the pile body; after the pile body and the capping concrete on the pile top reach the strength, install the cap form, and finally pour the cap and the anchoring system;
其中,桩孔、内模、外模的口径自上而下均呈阶梯型递减。Among them, the calibers of pile holes, inner molds, and outer molds all decrease stepwise from top to bottom.
在上述技术方案中,本发明采用内模人工挖孔方案成功解决了超大直径桩成桩问题;锚碇基础超大直径空心群桩体系包括超大直径桩、承台以及连接主缆的锚固系统(包括上锚块、散索鞍和前支撑等部件)三部分。超大直径空心群桩作为系统的主要抗弯构件,底端嵌固在基岩中,顶端嵌固入承台一定深度。桩外径从上至下呈阶梯型递减,进入微风化岩达到不塌孔条件,桩径便不再变化,桩体内部为空心构造(施工图见图12);其核心技术是在钻孔桩内使用内、外模,外模与孔壁之间填石注浆形成钻埋空心桩;施工过程中可保证侧壁不垮,内、外模与桩结构可整体浇筑。从结构优化角度看,当桩底支于基岩中,可适当缩小底部桩径,形成上大下小的竖向变截面桩型。该型式无论是在钢材还是混凝土的用量上都更为节约,而且受力特征与人工挖孔施工方案完美统一,施工工艺更为成熟。In the above technical scheme, the present invention successfully solves the pile-forming problem of super-large-diameter piles by adopting the scheme of internal mold manual digging; upper anchor block, loose cable saddle and front support) three parts. The ultra-large-diameter hollow pile group is the main flexural member of the system. The bottom end is embedded in the bedrock, and the top end is embedded in the cap to a certain depth. The outer diameter of the pile decreases stepwise from top to bottom, and the diameter of the pile does not change when it enters the micro-weathered rock to achieve the condition of not collapsing the hole, and the inside of the pile body is a hollow structure (see Figure 12 for the construction drawing); The inner and outer molds are used inside the pile, and grouting is filled between the outer mold and the hole wall to form a drilled and buried hollow pile; during the construction process, the side wall can be guaranteed not to collapse, and the inner, outer mold and pile structure can be integrally poured. From the perspective of structural optimization, when the bottom of the pile is supported in the bedrock, the pile diameter at the bottom can be appropriately reduced to form a vertically variable cross-section pile with a large top and a small bottom. This type is more economical in terms of the amount of steel and concrete, and the force characteristics are perfectly unified with the manual excavation construction scheme, and the construction technology is more mature.
相对于实心群桩,本发明具有以下优点:Compared with solid pile groups, the present invention has the following advantages:
1)更满足受力特征的空心构造1) Hollow structure that better meets the force characteristics
对于群桩基础而言,为了有效分配上部荷载,充分发挥群桩承载能力,需要保证承台的尺寸必须与基桩的直径相对应,基桩越大则承台尺寸越大。同时为减小桩身最大弯矩,也要求桩端形成固支连接,承台刚度要远大于桩身刚度。超大直径桩外径可达到10米以上,基于以上考虑相对应的承台厚度将达到数十米,如此大体积的承台不但额外增加了锚碇基础的自重,对下部持力层的承载能力提出极大考验,而且浪费混凝土体积,增加了工程造价。为了解决承台过大的问题,基桩必须设置为空心结构,从而大幅减小了基桩尺寸和承台体积,有效解决了超大体积承台带来的不利影响。For the pile group foundation, in order to effectively distribute the upper load and give full play to the bearing capacity of the pile group, it is necessary to ensure that the size of the cap must correspond to the diameter of the foundation pile. The larger the foundation pile, the larger the cap size. At the same time, in order to reduce the maximum bending moment of the pile body, it is also required to form a fixed support connection at the pile end, and the stiffness of the cap is much greater than that of the pile body. The outer diameter of super-large-diameter piles can reach more than 10 meters. Based on the above considerations, the corresponding cap thickness will reach tens of meters. Such a large-volume cap not only increases the self-weight of the anchorage foundation, but also increases the bearing capacity of the lower bearing layer. It puts forward a great test, and wastes the volume of concrete, which increases the cost of the project. In order to solve the problem of excessively large caps, the foundation piles must be set in a hollow structure, thereby greatly reducing the size of the foundation piles and the volume of the caps, and effectively solving the adverse effects of super-large caps.
此外基桩作为抗弯的主要部件,其抗弯性能与抗弯截面惯性矩I直接相关。基桩空心构造的优势在于,虽然环形截面的净面积相比实心桩的圆形截面而言小了得多,但是截面惯性矩I的损失值非常微弱(例如桩内径取外径的一半,惯性矩仅损失了7%)。此外桩截面在受弯条件下,最大弯矩位于桩截面的外侧,为了充分发挥钢筋的抗拉性能,将受力主筋布置于截面上弯矩最大处,因此空心环形截面更有利用受力主筋的布置。In addition, the foundation pile is the main part of the bending resistance, and its bending performance is directly related to the moment of inertia I of the bending section. The advantage of the hollow structure of the foundation pile is that although the net area of the circular section is much smaller than that of the solid pile, the loss value of the section moment of inertia I is very weak (for example, the inner diameter of the pile is half of the outer diameter, and the inertia The moment is only lost by 7%). In addition, under the bending condition of the pile section, the maximum bending moment is located on the outside of the pile section. In order to give full play to the tensile performance of the steel bar, the stressed main reinforcement is arranged at the maximum bending moment on the section, so the hollow annular section makes more use of the stressed main reinforcement. layout.
2)桩底二次压浆的实现2) Realization of secondary grouting at pile bottom
过预埋的注浆孔对桩底高压压入混凝土浆,使得桩体产生微量上抬,相当于桩底施加了预应力。这一工艺不但对桩底土层进行了加固处理,大幅降低了桩身的工后沉降量。而且当持力层为硬实土层时,二次注浆反抬桩体相当于进行了一次空心桩的承载力试验,根据注浆压力σ和空心桩的上抬量Δ的对应关系可以反算得到桩体的容许承载力,用以验算单桩的设计承载力。而传统实心桩构造受过大自重和混凝土实体的巨大压力限制,混凝土浆液无法通过注浆管注入。二次压浆的实现是空心桩构造独有的一大优势。The pre-buried grouting hole is used to press the concrete slurry into the bottom of the pile under high pressure, which makes the pile body slightly lifted, which is equivalent to applying prestress to the bottom of the pile. This process not only strengthens the soil layer at the bottom of the pile, but also greatly reduces the post-construction settlement of the pile body. Moreover, when the bearing layer is a hard soil layer, the reverse lifting of the pile body after the second grouting is equivalent to a test of the bearing capacity of the hollow pile. According to the corresponding relationship between the grouting pressure σ and the lifting amount Δ of the hollow pile, it can be back-calculated The allowable bearing capacity of the pile is obtained to check the design bearing capacity of the single pile. However, the traditional solid pile structure is limited by the excessive self-weight and the huge pressure of the concrete entity, and the concrete grout cannot be injected through the grouting pipe. The realization of secondary grouting is a unique advantage of the hollow pile structure.
3)受力特点与施工工艺相统一的阶梯形变截面构造3) Staircase deformation cross-section structure with uniform force characteristics and construction technology
当超大直径空心桩下端嵌固在基岩中,上端嵌固入承台底部一定深度后,桩身弯矩分布呈现上下两端大,中间小的特征。由于下端嵌入基岩,抗弯刚度较大,因此可对桩底截面进行优化,桩底直径可适当减小,以达到节约材料的目的。而桩顶直径较大,通过嵌入承台也能达成较大抗弯刚度。综上考虑,将基桩直径由上至下设置为阶梯型递减方案,可充分发挥桩身的抗弯能力。从施工角度考虑,阶梯型变截面桩径不但有利于施工设备的吊装,而且更大程度保证上下相邻两环之间浇筑的紧密性,施工工艺更为简便。When the lower end of the ultra-large-diameter hollow pile is embedded in the bedrock, and the upper end is embedded in the bottom of the cap to a certain depth, the bending moment distribution of the pile body presents the characteristics that the upper and lower ends are large and the middle is small. Since the lower end is embedded in the bedrock, the bending rigidity is relatively large, so the section of the pile bottom can be optimized, and the diameter of the pile bottom can be appropriately reduced to achieve the purpose of saving materials. However, the diameter of the pile top is relatively large, and a large bending stiffness can also be achieved by embedding the cap. In summary, setting the pile diameter from top to bottom as a step-wise decreasing scheme can give full play to the bending resistance of the pile body. From the construction point of view, the stepped variable section pile diameter is not only conducive to the hoisting of construction equipment, but also ensures the tightness of pouring between the upper and lower adjacent rings to a greater extent, and the construction process is simpler.
4)波纹钢护壁人工挖孔施工4) Manual digging construction of corrugated steel retaining wall
超大直径桩的开挖施工,采用波纹钢围堰护壁加人工挖孔成孔方案。相比传统沉井基础而言,人工成孔方式对桩周土体的扰动最小,能最大限度地保留了桩周土的摩擦力,而且波纹钢围堰与周围土壁之间空隙浇筑混凝土后,桩周摩阻力可增大数倍。而传统钻机开挖成孔法不但受桩径的限制,在开挖过程中还需辅以泥浆护壁,泥浆将会削弱孔周土壁的摩阻力。相同地质条件下,沉井施工的侧摩阻力约为钻孔施工方案的0.3~0.5倍,而波纹钢护壁人工挖孔施工的侧摩阻力约为钻孔施工方案的1.3倍。因此,采用本方案成孔,桩周摩阻力发挥最充分,施工工艺也最为简便。For the excavation construction of super-large diameter piles, the scheme of corrugated steel cofferdam retaining wall and manual digging is adopted. Compared with the traditional caisson foundation, the artificial hole-forming method has the least disturbance to the soil around the pile, and can retain the friction of the soil around the pile to the greatest extent, and the gap between the corrugated steel cofferdam and the surrounding soil wall is poured with concrete. , the frictional resistance around the pile can be increased several times. However, the traditional drilling method is not only limited by the diameter of the pile, but also needs to be supplemented by mud wall protection during the excavation process. The mud will weaken the frictional resistance of the soil wall around the hole. Under the same geological conditions, the side friction resistance of caisson construction is about 0.3 to 0.5 times that of the drilling construction plan, while the side friction resistance of corrugated steel retaining wall manual excavation construction is about 1.3 times that of the drilling construction plan. Therefore, using this scheme to form holes, the frictional resistance around the pile can be fully exerted, and the construction technology is the most convenient.
具体应用过程中,在吉安市超大直径波纹钢围堰挖孔空心桩成功应用的基础上,把单桩施工技术引入到锚碇群桩基础中,根据锚碇结构的承载特性提出一种悬索桥超大直径空心群桩锚碇结构方案及施工方法。这一结构形式不但能充分调动桩周土体的被动抗力、桩底土摩擦力和刚性承台受拉侧的土抗力,而且空心构造在不损失承载能力的前提下减轻了30%左右的自重,形成了一套安全合理,经济有效的新型悬索桥锚碇基础设计方案。In the specific application process, on the basis of the successful application of super large-diameter corrugated steel cofferdam hollow piles in Ji'an City, the single pile construction technology is introduced into the anchor pile group foundation, and a suspension bridge oversized structure is proposed according to the bearing characteristics of the anchor structure Diameter hollow pile group anchorage structure scheme and construction method. This structural form can not only fully mobilize the passive resistance of the soil around the pile, the friction of the soil at the bottom of the pile, and the soil resistance of the tension side of the rigid cap, but also reduce the weight of the hollow structure by about 30% without losing the bearing capacity. A safe, reasonable, economical and effective design scheme for the anchorage foundation of a new type of suspension bridge has been formed.
本发明的其他特征和优点将在随后的具体实施方式部分予以详细说明。Other features and advantages of the present invention will be described in detail in the following detailed description.
附图说明Description of drawings
附图是用来提供对本发明的进一步理解,并且构成说明书的一部分,与下面的具体实施方式一起用于解释本发明,但并不构成对本发明的限制。在附图中:The accompanying drawings are used to provide a further understanding of the present invention, and constitute a part of the description, together with the following specific embodiments, are used to explain the present invention, but do not constitute a limitation to the present invention. In the attached picture:
图1是本发明提供的超大直径空心群桩锚碇的优选实施方式的结构示意图;Fig. 1 is the structural representation of the preferred embodiment of super-large-diameter hollow pile group anchorage provided by the present invention;
图2是本发明提供的超大直径空心群桩锚碇的水平承载示意图;Fig. 2 is a schematic diagram of the horizontal bearing of the ultra-large-diameter hollow pile group anchorage provided by the present invention;
图3是本发明提供的超大直径空心群桩锚碇的平面示意图;Fig. 3 is a schematic plan view of the super large-diameter hollow pile group anchorage provided by the present invention;
图4是图3中A部分的剖视放大图;Fig. 4 is a sectional enlarged view of part A in Fig. 3;
图5是图1中超大直径空心群桩的平面示意图;Fig. 5 is a schematic plan view of super large-diameter hollow pile group in Fig. 1;
图6是本发明提供的波纹钢以及螺栓的组装结构示意图;Fig. 6 is a schematic diagram of the assembled structure of corrugated steel and bolts provided by the present invention;
图7是本发明提供的波纹钢围堰的平面示意图;Fig. 7 is the schematic plan view of the corrugated steel cofferdam provided by the present invention;
图8是本发明提供的波纹钢围堰的立体结构图;Fig. 8 is the three-dimensional structural diagram of the corrugated steel cofferdam provided by the present invention;
图9是本发明提供的超大直径空心群桩锚碇的施工流程示意图;Fig. 9 is a schematic diagram of the construction process of the ultra-large-diameter hollow pile group anchorage provided by the present invention;
图10是现有技术中悬索桥重力式锚碇构的结构示意图;Fig. 10 is a structural schematic diagram of a gravity anchorage structure of a suspension bridge in the prior art;
图11是现有技术中根式基础的结构示意图;Fig. 11 is a structural schematic diagram of a root foundation in the prior art;
图12是本发明提供的的超大直径空心群桩锚碇的施工现场图。Fig. 12 is a construction site diagram of the super large-diameter hollow pile group anchorage provided by the present invention.
附图标记说明Explanation of reference signs
1、桩体 2、承台1. Pile body 2. Cap
3、上锚块 4、散索鞍3. Upper anchor block 4. Scatter saddle
5、前支撑块 6、主缆5. Front support block 6. Main cable
7、岩土体 8、螺栓7. Rock and soil mass 8. Bolts
10、首层波纹钢围堰 11、中层波纹钢围堰10. The first corrugated steel cofferdam 11. The middle corrugated steel cofferdam
12、底层波纹钢围堰 13、填石注浆12. Bottom corrugated steel cofferdam 13. Rock filling and grouting
14、卵石砂石垫层 15、底段波纹钢内模14. Pebble sand cushion layer 15. Corrugated steel inner mold in the bottom section
16、中间段波纹钢内模 17、混凝土16. Corrugated steel inner mold in the middle section 17. Concrete
18、封顶混凝土 19、注浆管18. Capping concrete 19. Grouting pipe
20、岩石锚杆20. Rock bolt
具体实施方式detailed description
以下结合附图对本发明的具体实施方式进行详细说明。应当理解的是,此处所描述的具体实施方式仅用于说明和解释本发明,并不用于限制本发明。Specific embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described here are only used to illustrate and explain the present invention, and are not intended to limit the present invention.
在本发明中,在未作相反说明的情况下,“内、外、上、下包含在术语中的方位词仅代表该术语在常规使用状态下的方位,或为本领域技术人员理解的俗称,而不应视为对该术语的限制。In the present invention, in the absence of a contrary description, the orientation words included in the term "inner, outer, upper, and lower" only represent the orientation of the term in the normal use state, or are commonly known as understood by those skilled in the art. , and should not be construed as a limitation of this term.
本发明提供了一种超大直径空心群桩锚碇,如图1-5以及图9所示包括超大直径空心群桩、承台2以及锚固系统;超大直径空心群桩由多根竖直设置的桩体1有机组成,桩体1的底端嵌固与岩土体7中且上端嵌固于承台2 的底端的内部;锚固系统设置于承台2的顶部以连接主缆6;其中,桩体1 为空心桩体,并且桩体1的内径与外径自上而下均呈阶梯型递减。The present invention provides a super-large-diameter hollow pile group anchorage, which includes a super-large-diameter hollow group pile, cap 2 and an anchoring system as shown in Figures 1-5 and Figure 9; the super-large-diameter hollow group pile consists of multiple vertically arranged The pile body 1 is organically composed, the bottom end of the pile body 1 is embedded in the rock soil body 7 and the upper end is embedded inside the bottom end of the cap 2; the anchoring system is arranged on the top of the cap 2 to connect the main cable 6; wherein, The pile body 1 is a hollow pile body, and the inner diameter and the outer diameter of the pile body 1 decrease stepwise from top to bottom.
在上述超大直径空心群桩锚碇,通过将桩体1上而下均呈阶梯型递减的设置,对于群桩基础而言,为了有效分配上部荷载,充分发挥群桩承载能力,需要保证承台的尺寸必须与基桩的直径相对应,基桩越大则承台尺寸越大。同时为减小桩身最大弯矩,也要求桩端形成固支连接,承台刚度要远大于桩身刚度。超大直径桩外径可达到10米以上,基于以上考虑相对应的承台厚度将达到数十米,如此大体积的承台不但额外增加了锚碇基础的自重,对下部持力层的承载能力提出极大考验,而且浪费混凝土体积,增加了工程造价。为了解决承台过大的问题,基桩必须设置为空心结构,从而大幅减小了基桩尺寸和承台体积,有效解决了超大体积承台带来的不利影响。In the super-large-diameter hollow pile group anchorage mentioned above, by setting the pile body 1 in a stepwise decreasing manner from top to bottom, for the pile group foundation, in order to effectively distribute the upper load and fully exert the bearing capacity of the pile group, it is necessary to ensure that the cap The size of the pile must correspond to the diameter of the foundation pile. The larger the foundation pile, the larger the size of the cap. At the same time, in order to reduce the maximum bending moment of the pile body, it is also required to form a fixed support connection at the pile end, and the stiffness of the cap is much greater than that of the pile body. The outer diameter of super-large-diameter piles can reach more than 10 meters. Based on the above considerations, the corresponding cap thickness will reach tens of meters. Such a large-volume cap not only increases the self-weight of the anchorage foundation, but also increases the bearing capacity of the lower bearing layer. It puts forward a great test, and wastes the volume of concrete, which increases the cost of the project. In order to solve the problem of excessively large caps, the foundation piles must be set in a hollow structure, thereby greatly reducing the size of the foundation piles and the volume of the caps, and effectively solving the adverse effects of super-large caps.
此外基桩作为抗弯的主要部件,其抗弯性能与抗弯截面惯性矩I直接相关。基桩空心构造的优势在于,虽然环形截面的净面积相比实心桩的圆形截面而言小了得多,但是截面惯性矩I的损失值非常微弱(例如桩内径取外径的一半,惯性矩仅损失了7%)。此外桩截面在受弯条件下,最大弯矩位于桩截面的外侧,为了充分发挥钢筋的抗拉性能,将受力主筋布置于截面上弯矩最大处,因此空心环形截面更有利用受力主筋的布置。In addition, the foundation pile is the main part of the bending resistance, and its bending performance is directly related to the moment of inertia I of the bending section. The advantage of the hollow structure of the foundation pile is that although the net area of the circular section is much smaller than that of the solid pile, the loss value of the section moment of inertia I is very weak (for example, the inner diameter of the pile is half of the outer diameter, and the inertia The moment is only lost by 7%). In addition, under the bending condition of the pile section, the maximum bending moment is located on the outside of the pile section. In order to give full play to the tensile performance of the steel bar, the stressed main reinforcement is arranged at the maximum bending moment on the section, so the hollow annular section makes more use of the stressed main reinforcement. layout.
在本发明中,桩体1的内部结构可以在宽的范围内选择,但是为了使得超大直径空心群桩锚碇具有更优异的力学性能,优选地,桩体1包括外模、内模;外模设置于桩周土以及内模之间;外模、桩周土之间设置有填石注浆 13,外模、内模之间设置有钢筋笼并浇筑有混凝土17;更优选地,如6-8所示,外模、内模均是由波纹钢围堰组成,波纹钢围堰是由多块波纹钢通过螺栓8错位拼接而成。In the present invention, the internal structure of the pile body 1 can be selected in a wide range, but in order to make the super-large-diameter hollow pile group anchorage have more excellent mechanical properties, preferably, the pile body 1 includes an outer mold and an inner mold; The mold is arranged between the soil around the pile and the inner mold; the rockfill grouting 13 is arranged between the outer mold and the soil around the pile, and a reinforcement cage is arranged between the outer mold and the inner mold and concrete 17 is poured; more preferably, as As shown in 6-8, both the outer mold and the inner mold are composed of corrugated steel cofferdams, and the corrugated steel cofferdams are formed by splicing multiple pieces of corrugated steel through 8 dislocation bolts.
波纹钢围堰与周围土壁之间空隙浇筑混凝土后,桩周摩阻力可增大数倍。而传统钻机开挖成孔法不但受桩径的限制,相同地质条件下,沉井施工的侧摩阻力约为钻孔施工方案的0.3~0.5倍,而波纹钢护壁人工挖孔施工的侧摩阻力约为钻孔施工方案的1.3倍。因此,采用本方案成孔,桩周摩阻力发挥最充分,施工工艺也最简便。After pouring concrete in the gap between the corrugated steel cofferdam and the surrounding soil wall, the frictional resistance around the pile can increase several times. However, the traditional drilling rig excavation method is not only limited by the pile diameter. Under the same geological conditions, the side friction resistance of caisson construction is about 0.3 to 0.5 times that of the drilling construction plan, while the side friction resistance of manual excavation of corrugated steel retaining walls The resistance is about 1.3 times that of the drilling construction scheme. Therefore, using this scheme to form holes, the frictional resistance around the pile can be fully exerted, and the construction technology is also the most convenient.
在上述实施方式中,为了进一步提高超大直径空心群桩锚碇的性能,优选地,外模、内模之间内预设有注浆管19;注浆管19的一端能够延伸至桩体1的外部,另一端延伸至设置于桩壁的底部以使得混凝土浆能够通过注浆管19对桩体1进行二次注浆。In the above-mentioned embodiment, in order to further improve the performance of the super-large-diameter hollow pile group anchorage, preferably, a grouting pipe 19 is preset between the outer mold and the inner mold; one end of the grouting pipe 19 can extend to the pile body 1 The other end extends to the bottom of the pile wall so that the concrete slurry can pass through the grouting pipe 19 to perform secondary grouting on the pile body 1 .
过预埋的注浆孔对桩底高压压入混凝土浆,使得桩体产生微量上抬,相当于桩底施加了预应力。这一工艺不但对桩底土层进行了加固处理,大幅降低了桩身的工后沉降量。而且当持力层为硬实土层时,二次注浆反抬桩体相当于进行了一次空心桩的承载力试验,根据注浆压力σ和空心桩的上抬量Δ的对应关系可以反算得到桩体的容许承载力,用以验算单桩的设计承载力。而传统实心桩构造受过大自重和混凝土实体的巨大压力限制,混凝土浆液无法通过注浆管注入。二次压浆的实现是空心桩构造独有的一大优势。The pre-buried grouting hole is used to press the concrete slurry into the bottom of the pile under high pressure, which makes the pile body slightly lifted, which is equivalent to applying prestress to the bottom of the pile. This process not only strengthens the soil layer at the bottom of the pile, but also greatly reduces the post-construction settlement of the pile body. Moreover, when the bearing layer is a hard soil layer, the reverse lifting of the pile body after the second grouting is equivalent to a test of the bearing capacity of the hollow pile. According to the corresponding relationship between the grouting pressure σ and the lifting amount Δ of the hollow pile, it can be back-calculated The allowable bearing capacity of the pile is obtained to check the design bearing capacity of the single pile. However, the traditional solid pile structure is limited by the excessive self-weight and the huge pressure of the concrete entity, and the concrete grout cannot be injected through the grouting pipe. The realization of secondary grouting is a unique advantage of the hollow pile structure.
在上述实施方式中,为了进一步提高超大直径空心群桩锚碇的性能,优选地,注浆管19延伸至承台2内部。当超大直径空心桩下端嵌固在基岩中,上端嵌固入承台底部一定深度后,桩身弯矩分布呈现上下两端大,中间小的特征。由于下端嵌入基岩,抗弯刚度较大,因此可对桩底截面进行优化,桩底直径可适当减小,以达到节约材料的目的。而桩顶直径较大,通过嵌入承台也能达成较大抗弯刚度。由此可见,将基桩直径由上至下设置为阶梯型递减方案,可充分发挥桩身的抗弯能力。从施工角度考虑,阶梯型变截面桩径不但有利于施工设备的吊装,而且更大程度保证上下相邻两环之间浇筑的紧密性,施工工艺更为简便。In the above embodiment, in order to further improve the anchorage performance of the ultra-large-diameter hollow pile group, preferably, the grouting pipe 19 extends to the inside of the cap 2 . When the lower end of the ultra-large-diameter hollow pile is embedded in the bedrock, and the upper end is embedded in the bottom of the cap to a certain depth, the bending moment distribution of the pile body presents the characteristics that the upper and lower ends are large and the middle is small. Since the lower end is embedded in the bedrock, the bending rigidity is relatively large, so the section of the pile bottom can be optimized, and the diameter of the pile bottom can be appropriately reduced to achieve the purpose of saving materials. However, the diameter of the pile top is relatively large, and a large bending stiffness can also be achieved by embedding the cap. It can be seen that setting the pile diameter from top to bottom as a stepwise decreasing scheme can give full play to the bending resistance of the pile body. From the construction point of view, the stepped variable section pile diameter is not only conducive to the hoisting of construction equipment, but also ensures the tightness of pouring between the upper and lower adjacent rings to a greater extent, and the construction process is simpler.
在本发明中,为了进一步提高超大直径空心群桩锚碇的性能,优选地,桩体1的底部的混凝土的底部回填有卵石砂石垫层14。卵石砂石垫层14的设置能够更加便于桩体1的底部的混凝土的浇筑;在桩底遇到岩层无法继续开挖时,可采用爆破开挖。In the present invention, in order to further improve the performance of the super-large-diameter hollow pile group anchorage, preferably, the bottom of the concrete at the bottom of the pile body 1 is backfilled with a pebble sandstone cushion 14 . The setting of pebble sandstone cushion layer 14 can be more convenient for the pouring of the concrete at the bottom of pile body 1; When pile bottom encounters rock stratum and can't continue to excavate, can adopt blasting excavation.
同时,在本发明中,为了进一步提高超大直径空心群桩锚碇的抗拔效果,优选地,桩体1的底部的混凝土内设置有岩石锚杆20,并且岩石锚杆20延伸至下部基岩中。当基础位于深埋基岩上,桩底无法嵌入基岩中形成固结端。为了使桩底受力稳定,可在承受上拔力的基桩桩底开孔,打设岩石锚杆20 贯入下部基岩中,再分层浇筑成桩,锚杆提供拉力抵抗主缆拉力引起的过大弯矩。空心桩构造便于锚杆施工,在一定程度上可以形成有效的抗拔体系。At the same time, in the present invention, in order to further improve the pull-out effect of the super-large-diameter hollow pile group anchorage, preferably, a rock bolt 20 is arranged in the concrete at the bottom of the pile body 1, and the rock bolt 20 extends to the lower bedrock middle. When the foundation is on deeply buried bedrock, the bottom of the pile cannot be embedded in the bedrock to form a consolidated end. In order to stabilize the stress on the bottom of the pile, a hole can be opened at the bottom of the foundation pile that bears the uplifting force, and rock anchors 20 are drilled to penetrate into the lower bedrock, and then piles are poured in layers, and the anchors provide tension to resist the tension of the main cable. caused by excessive bending moments. The hollow pile structure is convenient for bolt construction, and can form an effective pullout system to a certain extent.
此外,为了进一步提高基桩承载力,优选地,桩体1的侧壁上钻设有钻孔,钻孔内设置有根腱式钢管钎且根腱式钢管钎延伸出桩体1的外部以形成根腱式基础。当基桩承载力不足时,可在空心桩内壁钻孔,用千斤顶向孔外顶出根腱式钢管钎,形成根键式群桩基础,用以补救基桩承载力不足的缺陷。In addition, in order to further improve the bearing capacity of the foundation pile, preferably, a borehole is drilled on the side wall of the pile body 1, and a tendon type steel pipe brazing is arranged in the borehole, and the root tendon type steel pipe brazing extends out of the pile body 1 to Form a tendon-like foundation. When the bearing capacity of the foundation pile is insufficient, holes can be drilled in the inner wall of the hollow pile, and the tendon-type steel pipe brazing can be pushed out of the hole with a jack to form a root-key type pile group foundation to remedy the defect of insufficient bearing capacity of the foundation pile.
进一步地,为了进一步提高超大直径空心群桩锚碇的弯矩抵抗力,优选地,在远离主缆6的桩体1的内腔中填充有砂石。当主缆的拉力过大,且锚碇群桩基础依靠自重产生的抵抗弯矩无法抗衡主缆施加的弯矩时,可在受拉侧(远离主缆端)空心基桩中填充砂石,通过增大这一部分基桩的自重来提高锚碇基础的弯矩抵抗力。这一方案中砂石填充物的作用仅仅是增加桩体的配重,不参与基桩的抗弯作用,因此不会影响承台的荷载分配,同样也不会导致过大的承台尺寸。Further, in order to further improve the bending moment resistance of the ultra-large-diameter hollow pile group anchorage, preferably, the inner cavity of the pile body 1 away from the main cable 6 is filled with sand and gravel. When the tensile force of the main cable is too large, and the anchorage pile group foundation relies on its own weight to produce resisting bending moment and cannot resist the bending moment imposed by the main cable, sand and gravel can be filled in the hollow foundation pile on the tension side (away from the main cable end), through Increase the self-weight of this part of the foundation pile to improve the moment resistance of the anchorage foundation. In this scheme, the role of sand and gravel filling is only to increase the counterweight of the pile body, and does not participate in the bending resistance of the foundation pile, so it will not affect the load distribution of the cap, nor will it cause excessive cap size.
在上述超大直径空心群桩锚碇中,锚固系统的具体结构可以在宽的范围内选择,但是为了进一步提高超大直径空心群桩锚碇锚固效果,优选地,锚固系统包括上锚块3、散索鞍4和前支撑块5,上锚块3、前支撑块5间隔设置于承台2的顶部,散索鞍4位于上锚块3、前支撑块5的顶部且位于上锚块3、前支撑块5之间,散索鞍4的顶部与主缆6相连接。这样,上锚块3、散索鞍4和前支撑块5三者之间的配合形成的导力体系便可有效将上部主缆 6的拉力传导至承台2,进而提高锚碇的承载能力。In the super-large-diameter hollow pile group anchorage described above, the specific structure of the anchorage system can be selected within a wide range, but in order to further improve the anchorage effect of the super-large-diameter hollow pile group anchorage, preferably, the anchorage system includes an upper anchor block 3, a discrete The cable saddle 4 and the front support block 5, the upper anchor block 3 and the front support block 5 are arranged at intervals on the top of the bearing platform 2, and the loose cable saddle 4 is located on the top of the upper anchor block 3 and the front support block 5 and is located at the upper anchor block 3, Between the front support blocks 5, the top of the scatter saddle 4 is connected with the main cable 6. In this way, the force guiding system formed by the cooperation between the upper anchor block 3, the loose cable saddle 4 and the front support block 5 can effectively transmit the tension of the upper main cable 6 to the cap 2, thereby improving the bearing capacity of the anchorage .
同时,在本发明中,空心群桩中各桩体1的组合形式多变,但是为了便于施工,优选地,如图5所示,多根桩体1的分布形式为:横向与纵向垂直交错分布。超大直径空心群桩成规则矩形阵列布置,不仅能够使得桩间距的设置满足群桩效应的要求,同时也达到了不影响相邻桩体的开挖施工的目的。At the same time, in the present invention, the combination form of each pile body 1 in the hollow pile group is changeable, but for the convenience of construction, preferably, as shown in Figure 5, the distribution form of multiple pile bodies 1 is: horizontal and vertical vertically staggered distributed. The ultra-large-diameter hollow piles are arranged in a regular rectangular array, which not only enables the setting of the pile spacing to meet the requirements of the pile group effect, but also achieves the purpose of not affecting the excavation construction of adjacent piles.
在本发明为了进一步提高超大直径空心群桩锚碇的效果,优选地,桩周土的内壁上敷设有泥浆。在开挖过程中还需辅以泥浆护壁,泥浆将会削弱孔周土壁的摩阻力,进而使得桩周摩阻力发挥最充分,施工工艺也最为简便。In order to further improve the anchorage effect of the ultra-large-diameter hollow pile group in the present invention, preferably, mud is laid on the inner wall of the soil around the pile. In the process of excavation, it is necessary to supplement the mud protection wall, and the mud will weaken the frictional resistance of the soil wall around the hole, so that the frictional resistance around the pile can be fully exerted, and the construction process is also the most convenient.
本发明还提供了一种超大直径空心群桩锚碇的施工方法,如图9所示,包括:The present invention also provides a construction method for super large-diameter hollow pile group anchorage, as shown in Figure 9, comprising:
1)由上而下开挖多个桩孔直至桩底:在开挖各个桩孔的同时在桩孔的内部设置外模,并且在孔壁与内部之间填充填石注浆13;机械成孔的速度取决于取土速度,为高效取土,可在桩顶两侧设置龙门吊抓斗代替挖掘机取土。开挖首段桩孔并拼首层波纹钢围堰10作为内衬围堰,首段开挖深度一般不超过4m无支护安全深度。及时往首层波纹钢围堰10与孔壁之间填石注浆 13,同时开挖第二节段缩颈基坑。完成第二节段波纹钢拼装成中层波纹钢围堰后,在其周边填石压浆13,再开挖第三段缩颈基坑,重复第一、二节段桩孔开挖步骤,直至孔底拼装底层波纹钢围堰12并填石压浆13。土方开挖与波纹钢的拼装需保持同步进行,两部分的施工工序和速度要合理安排。在地下水充沛的地区还需做好围堰止水防护,施工过程中坑底及时排水干燥。1) Excavating multiple pile holes from top to bottom to the bottom of the pile: while excavating each pile hole, an external mold is set inside the pile hole, and rock filling grouting 13 is filled between the hole wall and the inside; The speed of the hole depends on the soil fetching speed. For efficient soil fetching, a gantry crane grab bucket can be installed on both sides of the pile top instead of an excavator to fetch soil. Excavate the first section of pile holes and assemble the first layer of corrugated steel cofferdam 10 as the lining cofferdam. The excavation depth of the first section is generally not more than 4m without support safety depth. Fill stone grouting 13 between first floor corrugated steel cofferdam 10 and hole wall in time, and excavate the second section necking foundation pit simultaneously. After the corrugated steel of the second section is assembled into the corrugated steel cofferdam of the middle layer, rock filling and grouting 13 are carried out around it, and then the necking foundation pit of the third section is excavated, and the pile hole excavation steps of the first and second sections are repeated until Assemble the bottom corrugated steel cofferdam 12 at the bottom of the hole and fill it with stone grouting 13 . The excavation of earth and the assembly of corrugated steel must be carried out simultaneously, and the construction procedures and speed of the two parts must be reasonably arranged. In areas with abundant groundwater, it is necessary to do a good job of cofferdam water-stop protection, and the bottom of the pit should be drained and dried in time during the construction process.
多桩可同步进行开挖,开挖工序宜平面错位开挖,以免开挖间距过小影响相邻桩侧土稳定性,导致塌孔。开挖首段桩孔并拼装第一节段围堰(图9 中a部分),无地下水影响的区域可直接采用波纹钢作为首段的围堰10。在第一节段围堰完工后,应立即在围堰与桩周土之间区域填石注浆13,同时开挖第二节段缩颈基坑,第二节段桩孔缩颈直径为1m,无支护开挖深度宜为 4m左右。完成第二节段波纹钢围堰拼装后,在其周边填石压浆,再开挖其余节段缩颈基坑,拼装中间段围堰11(图9中b部分)。重复第一、二节段围堰施工,缩颈到10m后不再继续缩颈,直至完成最底段波纹钢围堰12(图 9中c部分)。Multiple piles can be excavated at the same time, and the excavation process should be excavated in a plane dislocation, so as to avoid the small excavation spacing from affecting the stability of the side soil of adjacent piles and causing hole collapse. Excavate the pile holes of the first section and assemble the cofferdam of the first section (part a in Fig. 9). Corrugated steel can be directly used as the cofferdam 10 of the first section in areas without groundwater influence. After the completion of the cofferdam of the first section, the area between the cofferdam and the soil around the pile should be filled with rock and grouted 13 at the same time, and the necking foundation pit of the second section should be excavated at the same time. The diameter of the pile hole necking of the second section is 1m, and the unsupported excavation depth should be about 4m. After completing the assembly of the corrugated steel cofferdam of the second section, rock filling and grouting around it, excavation of the necking foundation pit of the remaining sections, and assembly of the cofferdam 11 of the middle section (part b in Fig. 9 ). Repeat the cofferdam construction of the first and second sections, and stop necking after the necking reaches 10m, until the corrugated steel cofferdam 12 at the bottom section is completed (part c in Figure 9).
2)在外模的内部设置内模,接着将钢筋笼、注浆管19设置于内模、外模之间,然后浇筑混凝土17;待孔底混凝土强度达标后,吊放相应管节的波纹钢内模,注浆管19和内模(由上而下包括底段波纹钢内模15、中间段波纹钢内模16)共同捆扎,同步沉放。注浆管在平面上放置于桩壁中心,即内外纵向钢筋之间,埋入不取出,可作为主筋使用。在内模与孔壁之间下放钢筋笼并通过注浆管浇筑混凝土17,形成空心桩实体部分。重复安装空心内模、下放钢筋笼并浇筑混凝土的步骤,直至完成整个空心桩体的浇筑。2) Set the inner mold inside the outer mold, then set the reinforcement cage and grouting pipe 19 between the inner mold and the outer mold, and then pour concrete 17; after the strength of the concrete at the bottom of the hole reaches the standard, hang the corrugated steel of the corresponding pipe joint Inner mold, grouting pipe 19 and inner mold (comprising bottom section corrugated steel inner mold 15, middle section corrugated steel inner mold 16 from top to bottom) are bundled together, sinking synchronously. The grouting pipe is placed in the center of the pile wall on the plane, that is, between the inner and outer longitudinal steel bars. It can be used as the main bar if it is buried without taking it out. A reinforcement cage is lowered between the inner mold and the hole wall and the concrete 17 is poured through the grouting pipe to form the solid part of the hollow pile. Repeat the steps of installing the hollow inner formwork, lowering the reinforcement cage and pouring concrete until the pouring of the entire hollow pile body is completed.
开挖到空心桩底端后,浇筑素封底混凝土垫层,并绑扎钢筋,钢筋上绑扎注浆管,浇筑底部混凝土。待混凝土有一定强度以后,安装底端空心桩内模15,下放钢筋笼并浇筑混凝土17(图9中d部分)。重复安装中间段波纹钢空心内模16,下放钢筋笼并浇筑混凝土的步骤,直至完成整个桩体壁的浇筑(图9中e部分)。After excavating to the bottom of the hollow pile, pour plain bottom concrete cushion, and bind steel bars, tie grouting pipes on the steel bars, and pour concrete at the bottom. After the concrete has a certain strength, install the hollow pile inner mold 15 at the bottom, lower the reinforcement cage and pour concrete 17 (part d in Fig. 9). Repeat the steps of installing the corrugated steel hollow inner mold 16 in the middle section, lowering the reinforcement cage and pouring concrete until the pouring of the entire pile body wall is completed (part e in Figure 9).
3)通过注浆管19对桩底进行二次注浆直至达到承载要求;在桩侧压浆 60天后,可以通过桩底压浆孔对桩底填石层进行二次压浆,压浆过程中检测并记录水泥浆的压力数据以及空心桩的上抬量,用以核算空心桩的承载能力。通过控制浆液压力和注浆量,能使桩端一定范围的强度和刚度得到充分提高,不但增大端承载力,还同时提高桩侧摩阻力。3) Carry out secondary grouting to the bottom of the pile through the grouting pipe 19 until the load-bearing requirements are met; after 60 days of grouting on the pile side, the rockfill layer at the bottom of the pile can be grouted again through the grouting holes at the bottom of the pile. The grouting process Detect and record the pressure data of the cement slurry and the lifting amount of the hollow pile in order to calculate the bearing capacity of the hollow pile. By controlling the grout pressure and grouting volume, the strength and rigidity of a certain range of pile ends can be fully improved, which not only increases the end bearing capacity, but also increases the pile side friction resistance at the same time.
4)在桩顶预埋承台连接钢筋,并安装封顶内模,对桩体进行封顶;待桩体及桩顶封顶混凝土达到强度后,安装承台模,最后浇筑承台2以及锚固系统;其中,桩孔、内模、外模的口径自上而下均呈阶梯型递减。在桩顶预埋承台的连接钢筋,然后安装封顶内模,对桩体进行封顶得到封顶混凝土18。群桩施工完毕后,待桩体及桩顶封顶混凝土达到一定强度后,安装承台模,浇筑承台。在桩顶预埋承台的连接钢筋,然后安装封顶内模,对桩体进行封顶(图9中f部分)。待桩体及桩基封顶混凝土达到一定强度后,安装承台模,浇筑承台2、上锚块3、散索鞍4及前支撑5。4) Pre-embed the cap to connect the steel bars at the top of the pile, and install the capping inner mold to cap the pile body; after the pile body and the capping concrete on the pile top reach the strength, install the cap form, and finally pour the cap 2 and the anchoring system; Among them, the calibers of pile holes, inner molds, and outer molds all decrease stepwise from top to bottom. Pre-embed the connecting reinforcement of the cap at the top of the pile, then install the capping inner mold, and cap the pile body to obtain the capping concrete 18. After the construction of the pile group is completed, after the pile body and pile top capping concrete reach a certain strength, the cap formwork is installed and the cap is poured. Pre-embed the connecting reinforcement of the cap at the top of the pile, and then install the capping inner mold to cap the pile body (part f in Figure 9). After the pile body and pile foundation capping concrete reach a certain strength, the cap formwork is installed, and the cap 2, the upper anchor block 3, the loose cable saddle 4 and the front support 5 are poured.
在本施工方法中,为了进一步减小对桩周土体的扰动,优选地,在步骤 1)中,桩孔的开挖是通过人工完成的。相比传统沉井基础而言,人工成孔方式对桩周土体的扰动最小,能最大限度地保留了桩周土的摩擦力。In this construction method, in order to further reduce the disturbance to the soil around the pile, preferably, in step 1), the excavation of the pile hole is done manually. Compared with the traditional caisson foundation, the artificial hole forming method has the least disturbance to the soil around the pile, and can retain the friction of the soil around the pile to the greatest extent.
在本发明中,桩体1的内部结构可以在宽的范围内选择,但是为了使得超大直径空心群桩锚碇具有更优异的力学性能,优选地,外模、内模均是由波纹钢围堰组成,波纹钢围堰是由多块波纹钢通过螺栓8错位拼接而成。In the present invention, the internal structure of the pile body 1 can be selected in a wide range, but in order to make the super-large-diameter hollow pile group anchorage have more excellent mechanical properties, preferably, the outer mold and the inner mold are both made of corrugated steel. The corrugated steel cofferdam is composed of multiple pieces of corrugated steel spliced by 8 dislocation bolts.
在上述施工方法中,为了进一步便于桩体1的底部的混凝土的浇筑,优选地,在步骤2)中,在设置钢筋笼、注浆管19之前,施工方法还包括在桩孔的底部回填卵石砂石垫层14。在开挖至坑底后,回填卵石砂石垫层至孔底标高,绑扎桩底钢筋网,浇筑底层混凝土。在桩底遇到岩层无法继续开挖时,可采用爆破开挖。In the above-mentioned construction method, in order to further facilitate the pouring of concrete at the bottom of the pile body 1, preferably, in step 2), before the reinforcement cage and the grouting pipe 19 are set, the construction method also includes backfilling pebbles at the bottom of the pile hole Sand and gravel cushion 14. After excavating to the bottom of the pit, backfill the pebble sand and gravel cushion to the elevation of the bottom of the hole, bind the steel mesh at the bottom of the pile, and pour the bottom concrete. When the bottom of the pile encounters a rock formation and cannot continue to excavate, blasting can be used for excavation.
同时,在本发明中,为了进一步提高超大直径空心群桩锚碇的抗拔效果,优选地,在步骤2)中,在浇筑混凝土17之前,桩底的底部打设有岩石锚杆 20至下部基岩中。当基础位于深埋基岩上,桩底无法嵌入基岩中形成固结端。为了使桩底受力稳定,可在承受上拔力的基桩桩底开孔,打设岩石锚杆20 贯入下部基岩中,再分层浇筑成桩,锚杆提供拉力抵抗主缆拉力引起的过大弯矩。空心桩构造便于锚杆施工,在一定程度上可以形成有效的抗拔体系。At the same time, in the present invention, in order to further improve the pullout effect of the ultra-large-diameter hollow pile group anchorage, preferably, in step 2), before pouring the concrete 17, the bottom of the pile bottom is driven with a rock anchor 20 to the lower part in bedrock. When the foundation is on deeply buried bedrock, the bottom of the pile cannot be embedded in the bedrock to form a consolidated end. In order to stabilize the stress on the bottom of the pile, a hole can be opened at the bottom of the foundation pile that bears the uplifting force, and rock anchors 20 are drilled to penetrate into the lower bedrock, and then piles are poured in layers, and the anchors provide tension to resist the tension of the main cable. caused by excessive bending moments. The hollow pile structure is convenient for bolt construction, and can form an effective pullout system to a certain extent.
此外,为了进一步提高基桩承载力,优选地,该施工方法还包括:在桩体1的侧壁上钻孔,然后将根腱式钢管钎通过孔延伸至岩土体7中。当基桩承载力不足时,可在空心桩内壁钻孔,用千斤顶向孔外顶出根腱式钢管钎,形成根键式群桩基础,用以补救基桩承载力不足的缺陷。In addition, in order to further improve the bearing capacity of the foundation pile, preferably, the construction method further includes: drilling a hole on the side wall of the pile body 1 , and then extending the tendon-type steel pipe brazing into the rock-soil body 7 through the hole. When the bearing capacity of the foundation pile is insufficient, holes can be drilled in the inner wall of the hollow pile, and the tendon-type steel pipe brazing can be pushed out of the hole with a jack to form a root-key type pile group foundation to remedy the defect of insufficient bearing capacity of the foundation pile.
进一步地,为了进一步提高超大直径空心群桩锚碇的弯矩抵抗力,优选地,该施工方法还包括:将砂石设置于桩体1的内腔中,并且砂石位于远离主缆6一侧。当主缆的拉力过大,且锚碇群桩基础依靠自重产生的抵抗弯矩无法抗衡主缆施加的弯矩时,可在受拉侧(远离主缆端)空心基桩中填充砂石,通过增大这一部分基桩的自重来提高锚碇基础的弯矩抵抗力。这一方案中砂石填充物的作用仅仅是增加桩体的配重,不参与基桩的抗弯作用,因此不会影响承台的荷载分配,同样也不会导致过大的承台尺寸。Further, in order to further improve the bending moment resistance of the super-large-diameter hollow pile group anchorage, preferably, the construction method further includes: placing sand and gravel in the inner cavity of the pile body 1, and the sand and gravel are located far away from the main cable 6- side. When the tensile force of the main cable is too large, and the anchorage pile group foundation relies on its own weight to produce resisting bending moment and cannot resist the bending moment imposed by the main cable, sand and gravel can be filled in the hollow foundation pile on the tension side (away from the main cable end), through Increase the self-weight of this part of the foundation pile to improve the moment resistance of the anchorage foundation. In this scheme, the role of sand and gravel filling is only to increase the counterweight of the pile body, and does not participate in the bending resistance of the foundation pile, so it will not affect the load distribution of the cap, nor will it cause excessive cap size.
在上述施工方法中,为了进一步保证周土壁的摩阻力,优选地,在步骤 1)中,桩孔的开挖过程中,桩孔的内壁上还辅以泥浆护壁。在开挖过程中还需辅以泥浆护壁,泥浆将会削弱孔周土壁的摩阻力。In the above construction method, in order to further ensure the frictional resistance of the surrounding soil wall, preferably, in step 1), during the excavation of the pile hole, the inner wall of the pile hole is supplemented with a mud wall. In the excavation process, it is necessary to supplement the mud wall, and the mud will weaken the frictional resistance of the soil wall around the hole.
同时,为了在施工过程中的挖孔安全,优选地,在步骤1)中,在所有桩孔中,最顶部的桩孔深度不超过4m,其他的桩孔深度为3.9-4.1m;最底端的桩孔的直径为10m。At the same time, for the safety of digging holes in the construction process, preferably, in step 1), among all pile holes, the depth of the top pile hole is no more than 4m, and the depth of other pile holes is 3.9-4.1m; The diameter of the pile hole at the end is 10m.
最后,在上述施工方法中,为了进一步地保证桩孔的安全,优选地,在步骤1中,在地下水充沛的区域,施工方法还包括进行围堰止水保护,同时在施工过程中坑底进行排水干燥。Finally, in the above-mentioned construction method, in order to further ensure the safety of the pile hole, preferably, in step 1, in the area with abundant groundwater, the construction method also includes the protection of the cofferdam water stop, and at the same time, the bottom of the pit is protected during the construction process. Drain and dry.
以下通过实施例进一步对本发明进行阐述,具体如下:The present invention is further set forth below by embodiment, specifically as follows:
以湖南省某在建主跨1480m悬索桥工程为例,具有以下特点:Taking a suspension bridge project with a main span of 1480m under construction in Hunan Province as an example, it has the following characteristics:
1)创新技术含量高,经济效益好。六大特点,七大工艺,属世界首创1) High innovative technology content and good economic benefits. Six features, seven crafts, the world's first
与原方案重力式锚碇(地下连续墙围堰)相比,超大直径空心桩锚碇砼体积节省近4万立方米,锚碇岩石土体挖方量减少2/3,工期可缩短一半。总概算费用约低20%,其经济效益十分显著。超大直径空心桩锚碇基础有更大的水平承载能力,承载过程中充分利用了桩周土抗力,通过大直径桩体和承台两部分与土体的相互作用来抵抗锚索水平拉力。此外,采用空心构造不但有效利用了桩身抗弯强度,减轻了自重,而且大量节约了混凝土材料和工程造价,具体见表1。Compared with the gravity anchor (underground diaphragm wall cofferdam) of the original scheme, the concrete volume of the super-large-diameter hollow pile anchorage can be saved by nearly 40,000 cubic meters, the excavation of rock and soil for the anchorage can be reduced by 2/3, and the construction period can be shortened by half. The total estimated cost is about 20% lower, and its economic benefits are very significant. The super-large-diameter hollow pile anchorage foundation has a greater horizontal bearing capacity. During the bearing process, the resistance of the soil around the pile is fully utilized, and the horizontal tension of the anchor cable is resisted through the interaction between the large-diameter pile body and the cap and the soil. In addition, the use of hollow structure not only effectively utilizes the flexural strength of the pile body, reduces the self-weight, but also saves a lot of concrete materials and engineering costs, see Table 1 for details.
表1Table 1
本发明选用刚度大、薄壁的波纹钢作为超大直径桩基的内模,同比平钢板用量减少一半,同时波纹钢围堰与土壁通过混凝土粘结,产生的巨大摩擦力比一般卵石土层摩阻力还要大1.5倍以上。The present invention selects corrugated steel with high rigidity and thin wall as the inner mold of super large-diameter pile foundation, which reduces the amount of flat steel plate by half compared with that of flat steel plate. At the same time, corrugated steel cofferdam and soil wall are bonded by concrete, and the huge friction force generated is higher than that of ordinary pebble soil layer. The frictional resistance is more than 1.5 times larger.
2)施工工艺简便2) The construction process is simple
相对于沉井和地下连续墙等大体积围堰施工方案,超大直径群桩基础的桩基数量少,可多桩同时开工,施工速度更快。基坑可直接采用挖机施工,成孔简单,施工速度快,工艺简便。波纹钢围堰施工无需专用施工设备,费用低。在施工进度、节能环保、质量控制、工程造价等方面,本发明具有独特的优势。Compared with large-volume cofferdam construction schemes such as caissons and underground diaphragm walls, the number of pile foundations for ultra-large-diameter pile group foundations is small, and multiple piles can be started at the same time, and the construction speed is faster. The foundation pit can be directly constructed by an excavator, with simple hole forming, fast construction speed and simple process. Corrugated steel cofferdam construction does not require special construction equipment, and the cost is low. The invention has unique advantages in construction progress, energy saving and environmental protection, quality control, project cost and the like.
3)灵活的工后补救方案3) Flexible post-work remedial solutions
空心桩的另一大优势在于工后补救。成桩承载力如未能达到设计要求,可以在空心桩内壁钻孔,用千斤顶向孔外顶出根腱式钢管钎,形成根键式基础,用以补救桩体承载力不足的缺陷,这与实体桩成桩后缺陷无药可救形成鲜明对比。此外,为平衡弯矩,群桩可部分相对于实心构造而言,空心构造的补强方案灵活多变,适应于多种工况。Another great advantage of hollow piles is post-work recovery. If the bearing capacity of the pile fails to meet the design requirements, a hole can be drilled in the inner wall of the hollow pile, and a tendon-type steel pipe brazing can be pushed out of the hole with a jack to form a root-key foundation to remedy the defect of insufficient bearing capacity of the pile body. It is in stark contrast to the fact that there is no cure for the defects of the solid pile after the pile is formed. In addition, in order to balance the bending moment, the pile group can be partially compared with the solid structure, and the reinforcement scheme of the hollow structure is flexible and adaptable to various working conditions.
综上所述,超大直径空心桩锚碇基础成孔设备简单、针对不同地质具有较强的适用性,工艺简便,经济效益好。波纹钢围堰相比传统钢筋砼沉井和双壁钢围堰质量轻、耗材少、所需吊装设备简易。在施工进度、节能环保、质量控制、造价等方面兼具优势。To sum up, the super-large-diameter hollow pile anchorage foundation has simple hole-forming equipment, strong applicability to different geology, simple process, and good economic benefits. Compared with traditional reinforced concrete caissons and double-wall steel cofferdams, corrugated steel cofferdams are lighter in weight, less in consumable materials, and require simpler hoisting equipment. It has advantages in construction progress, energy saving and environmental protection, quality control, and cost.
以上结合附图详细描述了本发明的优选实施方式,但是,本发明并不限于上述实施方式中的具体细节,在本发明的技术构思范围内,可以对本发明的技术方案进行多种简单变型,这些简单变型均属于本发明的保护范围。The preferred embodiment of the present invention has been described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the specific details of the above embodiment, within the scope of the technical concept of the present invention, various simple modifications can be made to the technical solution of the present invention, These simple modifications all belong to the protection scope of the present invention.
另外需要说明的是,在上述具体实施方式中所描述的各个具体技术特征,在不矛盾的情况下,可以通过任何合适的方式进行组合,为了避免不必要的重复,本发明对各种可能的组合方式不再另行说明。In addition, it should be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable way if there is no contradiction. The combination method will not be described separately.
此外,本发明的各种不同的实施方式之间也可以进行任意组合,只要其不违背本发明的思想,其同样应当视为本发明所公开的内容。In addition, various combinations of different embodiments of the present invention can also be combined arbitrarily, as long as they do not violate the idea of the present invention, they should also be regarded as the disclosed content of the present invention.
Claims (10)
- A kind of 1. construction method of the hollow clump of piles anchorage of super-large diameter, it is characterised in that including:1) multiple stake holes are from top to bottom excavated until stake bottom:In the inside of the stake holes, setting is outer while each stake holes is excavated Mould, and slip casting (13) of being rockfilled between hole wall and inside;2) the external mold inside set internal model, then by steel reinforcement cage, Grouting Pipe (19) be arranged at the internal model, external mold it Between, then casting concrete (17);3) secondary grouting is carried out until reaching bearing requirements to stake bottom by Grouting Pipe (19);4) in the pre-buried cushion cap connection reinforcing bar of stake top, and the internal model that binds is installed, pile body is bound;Treat pile body and stake top bind it is mixed After solidifying soil reaches intensity, installation platform mould, cushion cap (2) and anchor system are finally poured;Wherein, the stake holes, internal model, the bore of external mold successively decrease in step type from top to bottom.
- 2. construction method according to claim 1, it is characterised in that in step 1), the excavation of the stake holes is to pass through It is accomplished manually.
- 3. construction method according to claim 1, it is characterised in that the external mold, internal model are by ripple steel cofferdam group Into the ripple steel cofferdam is to be spliced by polylith corrugated steel by bolt (8) dislocation.
- 4. construction method according to claim 1, it is characterised in that in step 2), steel reinforcement cage, Grouting Pipe are being set (19) before, the construction method is additionally included in the bottom backfill cobble sand-gravel cushion (14) of the stake holes.
- 5. according to the construction method described in any one in claim 1-4, it is characterised in that in step 2), pouring Before stating concrete (17), the bottom at the stake bottom has set rock-bolt (20) into bottom basement rock.
- 6. according to the construction method described in any one in claim 1-4, it is characterised in that the construction method also includes: Drill in the side wall of the pile body (1), then extend to root tendon formula steel pipe pricker in Rock And Soil (7) by hole.
- 7. according to the construction method described in any one in claim 1-4, it is characterised in that the construction method also includes: Sandstone is arranged in the inner chamber of the pile body (1), and the sandstone is located remotely from the main push-towing rope (6) side.
- 8. according to the construction method described in any one in claim 1-4, it is characterised in that in step 1), the stake holes Digging process in, be also aided with mud off on the inwall of the stake holes.
- 9. according to the construction method described in any one in claim 1-4, it is characterised in that in step 1), in all piles Kong Zhong, the stake holes depth of top are no more than 4m, and other stake holes depth are 3.9-4.1m;The stake holes of lowermost end it is a diameter of 10m。
- 10. according to the construction method described in any one in claim 1-4, it is characterised in that in the step 1), on ground The abundant region of lower water, the construction method also includes carrying out cofferdam sealing protection, while cheats bottom in work progress and arranged Water is dried.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710705945.7A CN107642040A (en) | 2017-08-17 | 2017-08-17 | Construction method of super large diameter hollow pile group anchorage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710705945.7A CN107642040A (en) | 2017-08-17 | 2017-08-17 | Construction method of super large diameter hollow pile group anchorage |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107642040A true CN107642040A (en) | 2018-01-30 |
Family
ID=61111053
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710705945.7A Pending CN107642040A (en) | 2017-08-17 | 2017-08-17 | Construction method of super large diameter hollow pile group anchorage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107642040A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629556A (en) * | 2019-01-24 | 2019-04-16 | 华东交通大学 | A kind of bridge pier variable cross-section vibration isolation pile foundation and its construction method |
CN110185390A (en) * | 2019-06-10 | 2019-08-30 | 中铁五局集团建筑工程有限责任公司 | A kind of mini pile clump of piles boring positioning guiding device and application method |
CN113006113A (en) * | 2021-03-04 | 2021-06-22 | 浙江大学 | Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation |
CN117988357A (en) * | 2024-04-07 | 2024-05-07 | 中国铁建大桥工程局集团有限公司 | Ultra-large diameter column pile foundation supporting structure and construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2734986B2 (en) * | 1994-06-09 | 1998-04-02 | 鹿島建設株式会社 | Existing bridge repair method |
CN1254393A (en) * | 1997-05-12 | 2000-05-24 | 东京电力株式会社 | Method of arranging reinforcement in forming foundation of ground reinforcing type and foundation body |
CN101761088A (en) * | 2010-01-13 | 2010-06-30 | 河海大学 | Filling method of anchor open caisson compartment for controlling subsection cable saddle displacement of a suspension bridge |
CN102359110A (en) * | 2011-08-03 | 2012-02-22 | 安徽省高速公路控股集团有限公司 | Modular cast-in-place construction method for large-diameter root foundation |
CN103510531A (en) * | 2013-09-18 | 2014-01-15 | 中交公路长大桥建设国家工程研究中心有限公司 | Split type open caisson pile-added combined anchorage foundation and construction method thereof |
CN203639929U (en) * | 2013-09-18 | 2014-06-11 | 中交公路长大桥建设国家工程研究中心有限公司 | Split open caisson and pile composite anchor foundation |
CN105256794A (en) * | 2015-09-21 | 2016-01-20 | 周兆弟 | Cement soil mixing pile with strong variable-diameter core piles |
CN206173990U (en) * | 2016-11-18 | 2017-05-17 | 江苏交科交通设计研究院有限公司 | Asymmetric clump of piles cushion cap formula anchorage structure suitable for suspension bridge |
-
2017
- 2017-08-17 CN CN201710705945.7A patent/CN107642040A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2734986B2 (en) * | 1994-06-09 | 1998-04-02 | 鹿島建設株式会社 | Existing bridge repair method |
CN1254393A (en) * | 1997-05-12 | 2000-05-24 | 东京电力株式会社 | Method of arranging reinforcement in forming foundation of ground reinforcing type and foundation body |
CN101761088A (en) * | 2010-01-13 | 2010-06-30 | 河海大学 | Filling method of anchor open caisson compartment for controlling subsection cable saddle displacement of a suspension bridge |
CN102359110A (en) * | 2011-08-03 | 2012-02-22 | 安徽省高速公路控股集团有限公司 | Modular cast-in-place construction method for large-diameter root foundation |
CN103510531A (en) * | 2013-09-18 | 2014-01-15 | 中交公路长大桥建设国家工程研究中心有限公司 | Split type open caisson pile-added combined anchorage foundation and construction method thereof |
CN203639929U (en) * | 2013-09-18 | 2014-06-11 | 中交公路长大桥建设国家工程研究中心有限公司 | Split open caisson and pile composite anchor foundation |
CN105256794A (en) * | 2015-09-21 | 2016-01-20 | 周兆弟 | Cement soil mixing pile with strong variable-diameter core piles |
CN206173990U (en) * | 2016-11-18 | 2017-05-17 | 江苏交科交通设计研究院有限公司 | Asymmetric clump of piles cushion cap formula anchorage structure suitable for suspension bridge |
Non-Patent Citations (2)
Title |
---|
李东: "悬索桥大直径空心桩锚碇基础变位分析", 《中国学位论文全文数据库》 * |
程永峰等: "《微型桩基础在输电线路工程中的应用》", 31 October 2012, 中国电力出版社 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629556A (en) * | 2019-01-24 | 2019-04-16 | 华东交通大学 | A kind of bridge pier variable cross-section vibration isolation pile foundation and its construction method |
CN109629556B (en) * | 2019-01-24 | 2023-10-27 | 华东交通大学 | Pier variable cross-section vibration isolation pile foundation and construction method thereof |
CN110185390A (en) * | 2019-06-10 | 2019-08-30 | 中铁五局集团建筑工程有限责任公司 | A kind of mini pile clump of piles boring positioning guiding device and application method |
CN113006113A (en) * | 2021-03-04 | 2021-06-22 | 浙江大学 | Composite anchorage foundation of enlarged-diameter steel pipe pile of underground diaphragm wall and construction method of composite anchorage foundation |
CN113006113B (en) * | 2021-03-04 | 2022-05-06 | 浙江大学 | A composite anchorage foundation of an underground diaphragm wall with enlarged diameter steel pipe piles and a construction method thereof |
CN117988357A (en) * | 2024-04-07 | 2024-05-07 | 中国铁建大桥工程局集团有限公司 | Ultra-large diameter column pile foundation supporting structure and construction method |
CN117988357B (en) * | 2024-04-07 | 2024-06-04 | 中国铁建大桥工程局集团有限公司 | Ultra-large diameter column pile foundation supporting structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107642041A (en) | Super large diameter hollow pile group anchorage | |
CN108914931B (en) | An assembled vertical shield ring foundation pile and construction method | |
CN102352632B (en) | Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope | |
US20140026518A1 (en) | Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts | |
CN103510510B (en) | A kind of enhancement mode long auger cast-with-pressure concrete pile and construction method | |
CN103898916B (en) | Mini stake Composite Braced Retaining Structure and construction method | |
CN206070508U (en) | Device for reinforcing foundation | |
CN105525627A (en) | Two-way anchorage plate retaining wall and construction method thereof | |
CN111705795A (en) | A prefabricated anchor pier reinforced by a side slope and an integral construction method for the assembly of a post-cast lattice beam | |
CN104196014A (en) | Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof | |
CN103321234B (en) | Constructing method of load-bearing structure built on high slope or geological complex area | |
CN110777836A (en) | Reinforced concrete plate-anchor rod composite foundation and using method thereof | |
CN107642040A (en) | Construction method of super large diameter hollow pile group anchorage | |
CN110055973B (en) | Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method | |
CN207484290U (en) | The hollow clump of piles anchorage of super-large diameter | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN101691760A (en) | Composite foundation combining anchor rods with excavation and construction method thereof | |
CN203594023U (en) | Enhanced type long auger drilling pressure-grouting concrete pile | |
CN108330963A (en) | A kind of constructing device for inside soil body existing pile foundation pile extension | |
CN105484270B (en) | Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit | |
CN201406687Y (en) | Deep foundation pit supporting structure | |
CN106337421B (en) | A kind of lattice concrete is compound to go along with sb. to guard him piling wall and the construction method based on BIM | |
CN212052850U (en) | Bridge abutment and pier-column infrastructure in mountainous areas | |
CN210712916U (en) | Combined anchoring road shoulder retaining wall | |
CN201495554U (en) | An Anchor Combined Excavation and Excavation Composite Foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180130 |
|
RJ01 | Rejection of invention patent application after publication |