CN107806150A - A kind of complete separate flow system and its control method for controlling sewage and early-stage rainwater pollution - Google Patents
A kind of complete separate flow system and its control method for controlling sewage and early-stage rainwater pollution Download PDFInfo
- Publication number
- CN107806150A CN107806150A CN201710796368.7A CN201710796368A CN107806150A CN 107806150 A CN107806150 A CN 107806150A CN 201710796368 A CN201710796368 A CN 201710796368A CN 107806150 A CN107806150 A CN 107806150A
- Authority
- CN
- China
- Prior art keywords
- sewer
- rainwater
- storm
- water
- online
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000010865 sewage Substances 0.000 title claims abstract description 117
- 238000000034 method Methods 0.000 title claims abstract description 26
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 222
- 238000012545 processing Methods 0.000 claims abstract description 106
- 239000008239 natural water Substances 0.000 claims abstract description 42
- 230000008676 import Effects 0.000 claims description 11
- 239000002245 particle Substances 0.000 claims description 9
- 238000005065 mining Methods 0.000 claims description 5
- 239000002689 soil Substances 0.000 claims description 5
- IJGRMHOSHXDMSA-UHFFFAOYSA-N Atomic nitrogen Chemical compound N#N IJGRMHOSHXDMSA-UHFFFAOYSA-N 0.000 claims 2
- 229910052757 nitrogen Inorganic materials 0.000 claims 1
- 238000000926 separation method Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 3
- 101100366940 Mus musculus Stom gene Proteins 0.000 description 6
- 239000003344 environmental pollutant Substances 0.000 description 5
- 231100000719 pollutant Toxicity 0.000 description 5
- 230000001413 cellular effect Effects 0.000 description 4
- 230000001276 controlling effect Effects 0.000 description 4
- 230000002452 interceptive effect Effects 0.000 description 4
- 230000033228 biological regulation Effects 0.000 description 2
- 230000008021 deposition Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000001105 regulatory effect Effects 0.000 description 2
- 230000017105 transposition Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000010842 industrial wastewater Substances 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
- 238000005406 washing Methods 0.000 description 1
- 239000002351 wastewater Substances 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
- 238000003911 water pollution Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
- E03F1/001—Methods, systems, or installations for draining-off sewage or storm water into a body of water
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/02—Arrangement of sewer pipe-lines or pipe-line systems
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F2201/00—Details, devices or methods not otherwise provided for
- E03F2201/10—Dividing the first rain flush out of the stormwater flow
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
Abstract
The complete separate flow system of sewage and early-stage rainwater pollution and its control method, the system is controlled to include trunk sewer and Storm-water sewer the invention discloses a kind of;The outlet of the trunk sewer is provided with sewage treatment plant;The outlet of the Storm-water sewer connects with natural water, and the system also includes at least one unit area;Branch sewer and rainwater branch pipe are provided with unit area;The outlet of the branch sewer connects with trunk sewer;The outlet of the rainwater branch pipe is provided with the first online rainwater treatment facility;The outlet of the first online rainwater treatment facility is provided with the first sewage vent line connected with trunk sewer, and the first storm drain lines connected with Storm-water sewer.The present invention is simple in construction, and mounting arrangements are convenient, effectively city non point source of pollution can be control effectively, first rain can be collected accurately, improves the Efficiency and accuracy of water body processing.
Description
Technical field
The present invention relates to municipal drainage system field, and in particular to what a kind of control sewage and early-stage rainwater polluted divides completely
Stream system and its control method.
Background technology
Municipal drainage system is broadly divided into combined drainage system and separate sewage system.The interflow occurred earliest
Drainage system processed, it is that sewage, industrial wastewater and rainwater are blended in same pipe duct, is just directly arranged nearby without any processing
Enter water body, be stained significantly receiving water body, lot of domestic and international mature city is nearly all in this way.Now frequently with
It is interceptive combined system drainage system.
Interceptive combined system drainage system and traditional combined drainage system are essentially identical in structure, and distinctive points are
Interceptive combined system drainage system is provided with Vatch basin between municipal administration interflow main and sewage treatment plant.Interceptive combined system is arranged
When water system works, the rainwater that the sewage and inlet for stom water of resident's discharge are collected all enters municipal administration interflow main by combined pipeline,
The rainwater that inlet for stom water along town road is collected also all enters municipal administration interflow main, and Vatch basin is set in main end.Fine day
When, all sewage are all delivered to sewage plant, and natural water is discharged into after processing.During rainfall, the rainwater at sewage and rainfall initial stage
Also sewage plant can be transported to, natural water is discharged into after processing.But with the increase of rainfall, rainfall runoff also increases,
After the flow of combined sewage exceedes the conveyance power of water for the main that dams, just have part combined sewage overflow and be directly entered nature
Water body.
For this combined drainage system, its problem is mainly:1. during rainfall, it can be produced on residential area and town road
Pollution of area source, although existing combined drainage system is dammed in end provided with Vatch basin, the interception ratio of design
Not enough so that Vatch basin could not intercept to area source pollutants, and area source pollutants are directly entered natural water, to natural water
Pollute.2. to be controlled to pollution of area source, it is necessary to increase the size of Vatch basin, increase the size for the main that dams,
Increase the capacity of sewage plant.3. Vatch basin dams for the control of extensive style, it is impossible to accurately early-stage rainwater is dammed.
Separate sewage system is divided into complete separate system and incomplete separate system two again according to the difference for excluding rainwater mode
Kind drainage system.Complete separate sewage system is completely to separate rainwater and sewage, trade effluent, is carried out by different pipelines
Conveying.The sewage of resident's discharge enters trunk sewer by sewage conduct, is discharged after being then sent to sewage plant processing, inlet for stom water
The rainwater of collection enters Storm-water sewer by storm sewer, is directly discharged to natural water.Inlet for stom water along town road is received
The rainwater of collection also all enters Storm-water sewer, is directly discharged to natural water.In this separate sewage system, there is a lot
Problem:1. the part of contaminated water in residential area mistakenly enters the sewage that washing machine is discharged on storm sewer, such as balcony can be straight
Run in and be put into natural water.2. the part of contaminated water on town road mistakenly enters storm sewer, for example is produced during road cleaning
Raw sewage can be directly discharged to natural water.3. during rainfall, pollution of area source can be produced on residential area and town road, face source is dirty
Dye thing can be directly entered natural water.
Incomplete separate system is primarily directed on the rainwater and town road that in the collection processing of rainwater, residential block is collected
The rainwater being collected into is separated.The rainwater that the sewage and inlet for stom water of resident's discharge are collected all is discharged by combined pipeline, is being entered
Vatch basin is set to be dammed before entering municipal drainage pipeline.The rainwater that inlet for stom water along town road is collected is done into rainwater
Pipe, is directly discharged to natural water.During fine day, the sewage of residential area discharge is trapped to trunk sewer, is then sent to sewage
Factory, natural water is discharged into after processing, but part of contaminated water is had on town road and is directly discharged to certainly into Storm-water sewer
Right water body.During rainfall, the sewage and the rainwater at rainfall initial stage of residential area discharge can be also trapped to trunk sewer, be then sent to
Sewage plant, natural water is discharged into after processing, but as the increase of rainfall, rainfall runoff also increase, when combined sewage
After flow exceedes the conveyance power of water for the pipeline that dams, just have part combined sewage overflow and be directly entered Storm-water sewer, while city
The early-stage rainwater of a large amount of pollutants is carried on political affairs road can also be directly entered Storm-water sewer, be then discharged to natural water.This
The problem of kind of drainage system is mainly:1. whole system can not effectively be intercepted to area source pollutants, intercepting efficiency is low.②
The sewage for entering storm sewer can not be controlled.3. during rainfall, sewage is easily carried along into natural water by rainwater.4. dam
The control of well is extensive, on the one hand more early-stage rainwaters may not be sent into sewage plant processing so that area source pollutants discharge
Natural water has been arrived, on the other hand substantial amounts of later stage rainwater sewage plant may be sent into, add the load of sewage plant, reduce
The treatment effeciency of sewage plant.
All things considered, there is problems with for current run-off system:First, it is impossible to which pollution of area source is controlled;The
Two, control is extensive, it is impossible to which sewage and early-stage rainwater are accurately controlled;3rd, pipeline hybrid junction, sewage has been directly discharged to certainly
Right water body;4th, for the area that land used is nervous, end treatment can not effectively be implemented.
Publication No. CN105625545A, a kind of entitled " region burst rainwater treatment based on separate system pipe network
The Chinese invention patent of system ", there is provided a kind of new pipe network division methods solve the above problems.This application is by whole pipe network
Latticed multiple sections are divided into by area, individually online rainwater treatment facility is set in each section, by section
Online rainwater treatment facility in the section rainwater carry out integrated treatment.But the present inventor sends out after substantial amounts of experiment
It is existing, this end treatment thinking, although rainwater treatment efficiency and the degree in corresponding section are improved to a certain extent, and to this
Pollution of area source in section is controlled;But overland flow still be present and collect the problem of being difficult to accurately control, moreover, for
Poor, the collection nothing of first rain and pollution of area source apart from the first rain of online rainwater treatment facility distalmost end and most proximal end collection existence time
Method realizes accurate control, so as to accomplish accurately to administer.Further, since the problem of urban planning, urban pipe network is divided into
There are many interference in latticed section, realize that difficulty is very big, can be caused to the urban pipe network arrangement of this pattern very big
Puzzlement.
The content of the invention
Present invention aim to the existing urban pipe network system for solving to mention in above-mentioned background technology to be difficult to accurately control
The problem of early-stage rainwater processed is collected, processing, there is provided a kind of complete separate flow system for controlling sewage and early-stage rainwater pollution and its
Control method.
The technical scheme is that:
A kind of complete separate flow system for controlling sewage and early-stage rainwater pollution, including trunk sewer and Storm-water sewer;Institute
The outlet for stating trunk sewer is provided with sewage treatment plant;The outlet of the Storm-water sewer connects with natural water, it is characterised in that:
The system also includes at least one unit area;Branch sewer and rainwater branch are provided with the unit area
Pipe;The outlet of the branch sewer connects with trunk sewer;The outlet of the rainwater branch pipe is provided with the first online rainwater treatment
Facility;The outlet of the first online rainwater treatment facility is provided with the first sewage vent line connected with trunk sewer, with
And the first storm drain lines connected with Storm-water sewer.
According to the present invention, the system, which is additionally included between trunk sewer and Storm-water sewer, to be provided with the second online rainwater
Facility is managed, the import of the second online rainwater treatment facility connects with Storm-water sewer, and the second online rainwater treatment facility goes out
Mouth connects with the trunk sewer and Storm-water sewer respectively.
According to the present invention, it is dirty that the outlet of the second online rainwater treatment facility is provided with second connected with trunk sewer
Water discharge spout road, and the second storm drain lines connected with Storm-water sewer.
According to the present invention, the entrance of the second online rainwater treatment facility and the Storm-water sewer connectivity part is not less than the
Two online rainwater treatment facilities and the outlet of Storm-water sewer connectivity part, and positioned at the downstream of the entrance on the Storm-water sewer
Place sets the first water conservancy to switch;Or
The second online rainwater treatment facility and the entrance of the Storm-water sewer connectivity part are less than at the second online rainwater
Manage facility and the outlet of Storm-water sewer connectivity part.
According to the present invention, the system also includes rainwater pretreatment system, and the rainwater pretreatment system is arranged on rainwater
On main, or with Storm-water sewer and connecing setting;When the rainwater pretreatment system and Storm-water sewer and when connecing setting, the rainwater
The water inlet end of pretreatment system connects with Storm-water sewer, and its discharge ends connects with Storm-water sewer or natural water.
According to the present invention, the rainwater pretreatment system and the entrance of the Storm-water sewer connectivity part are located in advance not less than rainwater
The outlet of reason system and Storm-water sewer connectivity part, and set the second water conservancy to switch at the downstream of the entrance;Or
The rainwater pretreatment system and the entrance of the Storm-water sewer connectivity part are less than rainwater pretreatment system and rainwater
The outlet of main connectivity part.
According to the present invention, the unit area be urban area in function and usage attribute or rain dirt pollution level it is identical or
The soil region for including building or structures of close division division.
According to the present invention, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 squares of public affairs
In.
According to the present invention, drainpipe of branch sewer and the rainwater branch pipe respectively with building or structures connects.
According to the present invention, the building or structures are residential area, industrial and mining enterprises, office, school, hospital, market
Or other combinations there may be one or both of unit area of large amount of sewage above.
According to the present invention, the system also includes municipal storm sewer, and the municipal storm sewer connects with Storm-water sewer.
According to the present invention, the system can also set one or more in trunk sewer close to the position of sewage treatment plant
End storage pond in parallel or series.
According to the present invention, the first water conservancy switch and the second water conservancy switch are respectively selected from valve, gate, flap valve or weir
Door;Preferably ball valve, the flap valve that dams, upper open type gate or bottom-open type weir gate.
According to the present invention, the quantity of the first online rain processing system is one or more;When described first online
, can be by the described first online rain processing system in a manner of in series or in parallel when the quantity of rain processing system is multiple
On pipeline.
According to the present invention, the quantity of the second online rain processing system is one or more;When described second online
, can be by the described second online rain processing system in a manner of in series or in parallel when the quantity of rain processing system is multiple
On pipeline.
According to the present invention, the quantity of the rainwater pretreatment system is one or more;When the rainwater pretreatment system
Quantity for it is multiple when, can by the rainwater pretreatment system in parallel be arranged on pipeline on.
According to the present invention, the quantity of the first online rain processing system is according to the area or cellular zone in unit area
Overseas size is divided.
According to the present invention, the quantity of the second online rainwater treatment facility is according to the area or cellular zone in unit area
Overseas size is divided.
According to the present invention, the quantity of the rainwater pretreatment system is according to outside the area in unit area or unit area
Size is divided.
According to the present invention, the import serial or parallel connection of the multiple second online rainwater treatment facility is located at the first online rain
Downstream of the outlet of first storm drain lines of water processing establishment on Storm-water sewer.
According to the present invention, the first online rainwater treatment facility includes functional rain water treatment facilities;It is described multi-functional
Rainwater treatment device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
According to the present invention, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;It is described
Online processing storage pond serial or parallel connection is multiple.
According to the present invention, in the first online rainwater treatment facility, the port of export of the buffer pool, which is provided with, promptly to be let out
Big vast gallery;Control valve is installed on the urgent flood discharge gallery, the port of export of urgent flood discharge gallery connects with Storm-water sewer;Institute
State just rain storage pond entrance point to connect with buffer pool, the port of export connects with online processing storage pond entrance point;The online processing
The port of export of storage pond connects with Storm-water sewer.
According to the present invention, the second online rainwater treatment facility includes functional rain water treatment facilities;It is described multi-functional
Rainwater treatment device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
According to the present invention, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;It is described
Online processing storage pond serial or parallel connection is multiple.
According to the present invention, in the second online rainwater treatment facility, the just rain storage pond entrance point connects with buffer pool
Logical, the port of export connects with online processing storage pond entrance point;The port of export of the online processing storage pond connects with Storm-water sewer.
According to the present invention, the first online rainwater treatment facility is arranged in unit area or outside unit area.
According to the present invention, the rainwater pretreatment system is selected from particle separator, filter, rainwater treatment module or biology
Denitrogenate any of dephosphorization equipment or two or more combinations, it is preferable that the rainwater pretreatment system separates selected from particle
Device, filter or rainwater treatment module and combinations thereof, it is highly preferred that the rainwater pretreatment system includes being sequentially connected in series connection
Particle separator, filter and rainwater treatment module.
The present invention also provides a kind of method for controlling sewage and the complete separate system of early-stage rainwater pollution, methods described bag
Include:
Trunk sewer is set, is emitted into after the sewage in urban area is delivered into sewage treatment plant's processing by trunk sewer
Natural water;
Storm-water sewer is set, the rainwater in urban area is emitted into natural water by Storm-water sewer;
At least one unit area is set;Branch sewer and rainwater branch pipe are provided with the unit area;The sewage
The outlet of branch pipe connects with trunk sewer;The outlet of the rainwater branch pipe is provided with the first online rainwater treatment facility;Described
The outlet of one online rainwater treatment facility is provided with the first sewage vent line connected with trunk sewer, and, done with rainwater
First storm drain lines of pipe connection.
According to the present invention, methods described, which is additionally included between trunk sewer and Storm-water sewer, to be provided with the second online rainwater
Facility is managed, the import of the second online rainwater treatment facility connects with Storm-water sewer, and the second online rainwater treatment facility goes out
Mouth connects with the trunk sewer and Storm-water sewer respectively.
According to the present invention, it is dirty that the outlet of the second online rainwater treatment facility is provided with second connected with trunk sewer
Water discharge spout road, and the second storm drain lines connected with Storm-water sewer.
According to the present invention, the entrance of the second online rainwater treatment facility and the Storm-water sewer connectivity part is not less than the
Two online rainwater treatment facilities and the outlet of Storm-water sewer connectivity part, and positioned at the downstream of the entrance on the Storm-water sewer
Place sets the first water conservancy to switch;Or
The second online rainwater treatment facility and the entrance of the Storm-water sewer connectivity part are less than at the second online rainwater
Manage facility and the outlet of Storm-water sewer connectivity part.
According to the present invention, the system also includes rainwater pretreatment system, and the rainwater pretreatment system is arranged on rainwater
On main, or with Storm-water sewer and connecing setting;When the rainwater pretreatment system and Storm-water sewer and when connecing setting, the rainwater
The water inlet end of pretreatment system connects with Storm-water sewer, and its discharge ends connects with Storm-water sewer or natural water.
According to the present invention, the rainwater pretreatment system and the entrance of the Storm-water sewer connectivity part are located in advance not less than rainwater
The outlet of reason system and Storm-water sewer connectivity part, and set the second water conservancy to switch at the downstream of the entrance;Or
The rainwater pretreatment system and the entrance of the Storm-water sewer connectivity part are less than rainwater pretreatment system and rainwater
The outlet of main connectivity part.
According to the present invention, methods described also includes:
When fine day and early-stage rainwater, the early-stage rainwater in the rainwater branch pipe is discharged into the first online rainwater treatment facility
It is emitted into trunk sewer through the first sewage vent line after processing afterwards or is emitted into rainwater through the first storm drain lines and does
Pipe;The sewage of the branch sewer is directly discharged into trunk sewer;
When middle and later periods rainwater, the middle and later periods rainwater in the rainwater branch pipe passes through after being discharged into the first online rainwater treatment facility
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after crossing processing;Institute
The sewage stated in branch sewer is directly discharged into trunk sewer;
When rainfall increases to the disposal ability upper limit of the first online rain processing system, the first online rainwater treatment system is opened
The urgent flood discharge gallery of system, carry out flood discharge.
According to the present invention, methods described also includes:
When fine day and early-stage rainwater, the early-stage rainwater in the rainwater branch pipe is discharged into the first online rainwater treatment facility
It is emitted into trunk sewer through the first sewage vent line after processing afterwards or is emitted into rainwater through the first storm drain lines and does
Pipe;Sewage in the branch sewer is directly discharged into trunk sewer;Water body in the Storm-water sewer is online by described second
Storm-water sewer is emitted into through the second storm drain lines or discharged through the second sewage vent line after rain processing system processing
To trunk sewer;
When middle and later periods rainwater, the middle and later periods rainwater in the rainwater branch pipe passes through after being discharged into the first online rainwater treatment facility
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after crossing processing;Institute
The sewage stated in branch sewer is directly discharged into trunk sewer;Water body in the Storm-water sewer is by the described second online rainwater
Storm-water sewer is emitted into through the second storm drain lines or be emitted into sewage through the second sewage vent line after the processing of reason system
Main;
When rainfall increases to the disposal ability upper limit of the first online rain processing system, the first online rainwater treatment system is opened
The urgent flood discharge gallery of system, carry out flood discharge.
Preferably, the water body in the Storm-water sewer is discharged into rainwater pretreatment system, and system is pre-processed by the rainwater
Storm-water sewer or the pipeline being connected with natural water are emitted into after system processing.
According to the present invention, the unit area is identical with function and usage or sewage and rainwater pollution degree in urban area
Or the soil region for including building and structures of close Attribute transposition.
According to the present invention, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 squares of public affairs
In.
According to the present invention, drainpipe of branch sewer and the rainwater branch pipe respectively with building or structures connects.
According to the present invention, the building or structures are residential area, industrial and mining enterprises, office, school, hospital, market
Or other combinations there may be one or both of unit area of large amount of sewage above.
According to the present invention, methods described also includes setting municipal storm sewer, the municipal storm sewer and Storm-water sewer
Connection.
According to the present invention, methods described is additionally included in trunk sewer and sets one or more close to the position of sewage treatment plant
End storage pond in parallel or series.
According to the present invention, the first water conservancy switch and the second water conservancy switch are respectively selected from valve, gate, flap valve or weir
Door;Preferably ball valve, the flap valve that dams, upper open type gate or bottom-open type weir gate.
According to the present invention, the quantity of the first online rain processing system is one or more;When described first online
, can be by the described first online rain processing system in a manner of in series or in parallel when the quantity of rain processing system is multiple
On pipeline.
According to the present invention, the quantity of the second online rain processing system is one or more;When described second online
, can be by the described second online rain processing system in a manner of in series or in parallel when the quantity of rain processing system is multiple
On pipeline.
According to the present invention, the quantity of the rainwater pretreatment system is one or more;When the rainwater pretreatment system
Quantity for it is multiple when, can by the rainwater pretreatment system in parallel be arranged on pipeline on.
According to the present invention, the quantity of the first online rain processing system is according to the area or cellular zone in unit area
Overseas size is divided.
According to the present invention, the quantity of the second online rainwater treatment facility is according to the area or cellular zone in unit area
Overseas size is divided.
According to the present invention, the quantity of the rainwater pretreatment system is according to outside the area in unit area or unit area
Size is divided.
According to the present invention, the import serial or parallel connection of the multiple second online rainwater treatment facility is located at the first online rain
Downstream of the outlet of first storm drain lines of water processing establishment on Storm-water sewer.
According to the present invention, the first online rainwater treatment facility includes functional rain water treatment facilities;It is described multi-functional
Rainwater treatment device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
According to the present invention, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;It is described
Online processing storage pond serial or parallel connection is multiple.
According to the present invention, in the first online rainwater treatment facility, the port of export of the buffer pool, which is provided with, promptly to be let out
Big vast gallery;Control valve is installed on the urgent flood discharge gallery, the port of export of urgent flood discharge gallery connects with Storm-water sewer;Institute
State just rain storage pond entrance point to connect with buffer pool, the port of export connects with online processing storage pond entrance point;The online processing
The port of export of storage pond connects with Storm-water sewer.
According to the present invention, the second online rainwater treatment facility includes functional rain water treatment facilities;It is described multi-functional
Rainwater treatment device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
According to the present invention, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;It is described
Online processing storage pond serial or parallel connection is multiple.
According to the present invention, in the second online rainwater treatment facility, the just rain storage pond entrance point connects with buffer pool
Logical, the port of export connects with online processing storage pond entrance point;The port of export of the online processing storage pond connects with Storm-water sewer.
According to the present invention, the first online rainwater treatment facility is arranged in unit area or outside unit area.
According to the present invention, the rainwater pretreatment system is selected from particle separator, filter, rainwater treatment module or biology
Denitrogenate any of dephosphorization equipment or two or more combinations, it is preferable that the rainwater pretreatment system separates selected from particle
Device, filter or rainwater treatment module and combinations thereof, it is highly preferred that the rainwater pretreatment system includes being sequentially connected in series connection
Particle separator, filter and rainwater treatment module.
According to the present invention, do not have to the quantity and mounting means of the online rainwater treatment facility and rainwater pretreatment system
Especially limitation, can be adjusted according to the rain dirt pollution condition and land used situation in each region.
According to the present invention, to Inner Constitution and its installation side of the online rainwater treatment facility and rainwater pretreatment system
Formula is not particularly limited, and can be adjusted according to the rain dirt pollution condition and land used situation in each region.
Beneficial effects of the present invention:
1st, the building in pipe network is divided by function as unit area, then in unit area or the peripheral hardware of unit area
Put online rainwater treatment facility and Precise collection control carried out to the pollution of area source in unit area, administered in pollution source,
It is more nearly with pollution sources, the comprehensive regulation and processing more accurately can be carried out to early-stage rainwater and sewage, can accurately, efficiently
Pollution of area source is controlled;
2nd, by online rainwater treatment facility corresponding to being set to each unit area, reduce distalmost end just rain with recently
The end time difference that just rain is entered in online rainwater treatment facility, make the collection of first rain and polluted-water more accurate, improve
The Efficiency and accuracy of sewage disposal;
3rd, by setting the online rainwater treatment facility of multiple serial or parallel connections, energy in unit area or outside unit area
Enough concentrate effectively is handled the rainwater in unit area, reduces the water body being discharged into unit area in trunk sewer
Flow, reduces the processing load of sewage treatment plant, while improves the water body cleannes being discharged into Storm-water sewer, avoids
The water pollution natural water being discharged into unit area in natural water;
The 4th, the online rainwater treatment facility of multiple serial or parallel connections, Neng Goujin are set between trunk sewer and Storm-water sewer
One step is handled the water body in Storm-water sewer, is avoided because the pollution of area source source on town road enters natural water
In, the pollution level of natural water is reduced, improves the clean level of water body;
5th, online rainwater treatment facility is that synthesis that multiple components combine is regulated and stored processing unit, can be according to unit area
Function make corresponding adjustment, floor space is small, occupies that space is small, and sewage treatment capacity is big, and arrangement is convenient, cost-effective,
Difficulty of construction is small, is advantageous to promote on a large scale;
6th, online rainwater treatment facility may be provided at unit area or the lower section of town road, not occupy urban ground sky
Between, urban ground has been saved, has reduced whole device pipe net arrangement cost;
7th, by setting online rainwater treatment facility can be in the unit area according to division in each unit area
Sewage situation makes corresponding adjustment, can select suitable treatment measures, countless places according to the sewage situation in unit area
Reason is more efficient;
8th, the present invention is simple in construction, and mounting arrangements are convenient, effectively source processing can be carried out to city non point source of pollution, to first
Rain can carry out Precise collection, improve the Efficiency and accuracy of water body processing, reduce the load of sewage treatment plant and to certainly
The pollution of right water body, has great promotional value.
9th, the present invention is the shunting processing in source, and first rain contracts significantly from ground to the excessively stream time of regulate and store facility or shunting well
It is short, so as to reduce this source region probability that for example cell later stage rainwater mixes with early-stage rainwater, retention or the early-stage rainwater collected
Concentration will be higher, and it is very high to cut dirty efficiency.
10th, it is 0.4-4 square kilometres that existing end burst, which receives water area value, and scattered section of the source of present invention sewage
Receive water area and there was only 0.01-0.6 square kilometres.
11st, when end cuts dirty, the deposition of duct bottom can influence the characteristic of first rain, the unobvious for allowing the characteristic of first rain to become,
But source wastewater interception pipe is shorter, the influence of deposition can be ignored substantially, and first rain feature becomes apparent from.
12nd, when end cuts dirty, pipeline distance is longer, and the breakage of pipeline can cause pipeline Groundwater infiltration on the way, can dilute
The concentration of first rain, just rain a certain amount of to the interception of first rain will contain a certain proportion of secondary water;But dirt is cut in source, due to pipe
Road is shorter, can be ignored substantially the problem of pipe network, the first rain concentration of interception will also greatly improve.
Brief description of the drawings
Fig. 1:The pipe network structure schematic diagram of the present invention;
Fig. 2:The structural representation of the online rainwater treatment facility of the present invention;
1- natural waters;2- buffer pools;The first rain storage ponds of 3-;4- handles storage pond online;The urgent flood discharge passages of 5-;6- is controlled
Valve processed;7- sewage treatment plants;8- unit areas;9- trunk sewers;10- Storm-water sewers;11- branch sewers;12-rainwater branch
Pipe;13-catch-basin;14-the first sewage vent line;15-the first storm drain lines;16-the second sewage vent line;
17-the second storm drain lines;18-bottom-open type weir gate;I-the first online rainwater treatment facility;II-the second online rainwater
Treatment facility.
Embodiment
With reference to specific embodiment, the present invention is expanded on further.It should be understood that these embodiments are merely to illustrate the present invention
Rather than limitation the scope of the present invention.Furthermore, it is to be understood that after described content of the invention has been read, this area skill
Art personnel can make various changes or modifications to the present invention, and these equivalent form of values equally fall within limited range of the present invention.
Such as Fig. 1~2, pipe network region division is multiple unit areas 8 by the pipe network structure of the present embodiment, and unit area 8 is
It is flat for 0.3 with the soil region including structures of function and usage Attribute transposition, the area of the unit area in urban area
Fang Gongli;The structures of the present embodiment are one kind in the places such as industrial and mining enterprises, office, school, hospital, market.By by this
A little regions are independent, come accurate Control the Plan Pollution Sources, the collection and processing of the accurate first rain of control with this.
The pipe network of the present embodiment includes trunk sewer 9 and Storm-water sewer 10, and the outlet of trunk sewer 9 is provided with sewage disposal
Factory 7, the outlet of Storm-water sewer 10 connects with natural water 1 (is communicated with more branch pipes, branch pipe is collected with being used on Storm-water sewer 10
Rainwater connects with the catch-basin of pollution of area source water body), in the light of actual conditions, sewage enters sewage disposal by trunk sewer 9
Integrated treatment is carried out in factory 7, rainwater is entered in natural water 1 by Storm-water sewer 10.
The multiple second online rainwater treatment facilities II, the second online rain are provided between trunk sewer 9 and Storm-water sewer 10
Water processing establishment II can correspond with unit area 8, can also not have to correspond with unit area 8.Second online rain
The import of water processing establishment II connects with Storm-water sewer 10, is provided with the outlet of the second online rainwater treatment facility II and sewage
Second sewage vent line 16 of the connection of main 9 and the second storm drain lines 17 connected with Storm-water sewer 10, positioned at second
It is provided with down on Storm-water sewer 10 between the import of online rainwater treatment facility II and the outlet of the second storm drain lines 17
Open type weir gate 18, each second online rainwater treatment facility II are provided with a corresponding bottom-open type weir gate 18, pass through bottom-open type
The closing of weir gate 18, the first rain in the length of tubing can be dammed and entered in the second online rainwater treatment facility II.Second
Line rainwater treatment facility can be collected processing to the early-stage rainwater being discharged into Storm-water sewer 10, avoid early-stage rainwater from entering
Natural water 1 is polluted into natural water 1.It is provided between trunk sewer 9 and Storm-water sewer 10 at multiple second online rainwater
Facility II is managed, division adjustment can be carried out according to region area.
The branch sewer 11 connected with structures drainpipe and (the rainwater branch pipe of rainwater branch pipe 12 are provided with unit area 8
12 collect rainwater and pollution of area source water body in the region by the catch-basin 13 being arranged in unit area 8), branch sewer
11 outlet connects with trunk sewer 9, and the pipe network structure in unit area 8 is separate system structure, sewage in unit area 8 and
Rainwater is completely separable without mixing.The outlet of rainwater branch pipe 12 is provided with the first online rainwater treatment facility I, the first online rain
Water processing establishment I can be located in town road region and can also be located in unit area 8.First online rainwater treatment facility I
Outlet is provided with the first sewage vent line 14 connected with trunk sewer 9 and the first rainwater connected with Storm-water sewer 10 discharge
Pipeline 15.First online rainwater treatment facility I can be handled the early-stage rainwater being discharged into rainwater branch pipe 12 in time, energy
Sewage is enough avoided to be directly discharged to pollute natural water 1 in natural water 1.
The first online rainwater treatment facility I of the present embodiment is identical with the second online structure of rainwater treatment facility II, including
Functional rain water treatment facilities, as shown in Fig. 2 functional rain water treatment facilities is buffer pool, first rain storage pond or online place
Manage one kind in storage pond or several combinations.The import of at least one the second online rainwater treatment facility II of the present embodiment
Positioned at downstream of the outlet on Storm-water sewer 10 of the first storm drain lines 15 of the first online rainwater treatment facility I.So
Setting structure allow for the first online rainwater treatment facility for the early-stage rainwater in processing unit region, the second online rain
Water processing establishment is the early-stage rainwater entered for solving road area along the line.Although the two structure is identical, the division of labor is different,
There is synergy between each other.
As shown in Fig. 1~2, the first online I and second online rainwater treatment facility II of rainwater treatment facility of the present embodiment
Structure includes functional rain water treatment facilities, and functional rain water treatment facilities includes buffer pool 2, first rain storage pond 3 and online place
Storage pond 4 is managed, wherein the import of buffer pool 2 of the first online rainwater treatment facility I and going out for the rainwater branch pipe 12 of unit area 8
Mouth connection, the buffer pool 2 of the second online rainwater treatment facility connect with Storm-water sewer 10.
Caused early-stage rainwater is handled through rainwater branch pipe 12 into the first online rainwater treatment facility in cell;Cell
Sewage caused by interior is directly entered in trunk sewer 9 through branch sewer 11.
The port of export of buffer pool 2 in first online rainwater treatment facility is provided with urgent flood discharge passage 5, and urgent flood discharge is led to
Control valve 6 is installed on road 5.Buffer pool 2 connects with first rain storage pond 3, and the polluted-water overflow in buffer pool 2 enters just
Carry out processing of regulating and storing in rain storage pond 3, the sewage in first rain storage pond 3 can be pumped into online processing storage pond 4 by water pump
Middle to be handled online, the online water body handled in storage pond 4 can be directly discharged in natural water 1 after treatment, when
When rainfall increases, the water body of buffer pool 2 can enter natural water 1 by urgent flood discharge passage 5,.
The water body that urgent flood discharge passage 5 is used to have little time the first online rainwater treatment facility processing is directly discharged to nature
In water body 1, the first online rainwater treatment facility overload operation is avoided.The present embodiment is by setting the first online rainwater treatment to set
Apply concentration and control process is collected to first rain, avoid the load of increase sewage treatment plant 7, it also avoid directly discharge can make
Into the pollution of natural water 1.
In use, during fine day, the sewage that unit area 8 is discharged in branch sewer 11 by entering trunk sewer 9, then
It is delivered to sewage treatment plant 7 to handle, natural water 1 is discharged into after processing.
During rainfall, the sewage that unit area 8 is discharged is then sent to by entering trunk sewer 9 in branch sewer 11
Sewage treatment plant 7 is handled, and natural water 1 is discharged into after processing;The early-stage rainwater part that unit area 8 is discharged can be by slow
Rush pond 2 and enter trunk sewer 9, and be delivered to sewage treatment plant 7 and handle, a part can enter first rain storage pond 3, be adjusted into first rain
The early-stage rainwater of reservoir 3 is pumped into by pump and handled in line after storage pond 4 is handled by the row of the first rainwater discharge pipe 14
Put into Storm-water sewer 10.With continuing for rainfall, when rainfall intensity is small, middle and later periods rainwater enters just rain by buffer pool 2
Storage pond 3, into first rain storage pond 3 middle and later periods rainwater by pump be pumped into line handle storage pond 4 handled after pass through
First rainwater discharge pipe 14 is emitted into Storm-water sewer 10;When rainfall intensity is big, flow exceedes online processing storage pond 4
Disposal ability, on the premise of the online processing maximum processing capability of storage pond 4 is kept, start urgent flood discharge passage 5 directly by flood
Water is discharged into Storm-water sewer 10.
During actual use, in the place that some regions are more narrow, online processing storage pond 4 can be removed to save region
Area, reduce the volume and floor space of whole functional rain water treatment facilities.
Use for the second online rainwater treatment facility II, when being collected into early-stage rainwater in Storm-water sewer 10, you can
Start the second online rainwater treatment facility II and processing control is carried out to it, first rain can be emitted into (the sewage disposal of trunk sewer 9
When factory 7 has the ability to handle), (when sewage treatment plant 7 has no ability to processing) can be voluntarily handled, directly passes through urgent flood discharge passage
It is discharged into Storm-water sewer 10 (rainfall is too big, beyond disposal ability).Second online rainwater treatment facility II is mainly used in city
Caused pollution of area source is controlled on political affairs road, and the sewage that can also be discharged into unit area 8 in Storm-water sewer 10 is carried out
Further regulation and control processing.
More than, embodiments of the present invention are illustrated.But the present invention is not limited to above-mentioned embodiment.It is all
Within the spirit and principles in the present invention, any modification, equivalent substitution and improvements done etc., it should be included in the guarantor of the present invention
Within the scope of shield.
Claims (10)
1. a kind of complete separate flow system for controlling sewage and early-stage rainwater pollution, including trunk sewer and Storm-water sewer;It is described
The outlet of trunk sewer is provided with sewage treatment plant;The outlet of the Storm-water sewer connects with natural water, it is characterised in that:
The system also includes at least one unit area;Branch sewer and rainwater branch pipe are provided with the unit area;Institute
The outlet for stating branch sewer connects with trunk sewer;The outlet of the rainwater branch pipe is provided with the first online rainwater treatment facility;
The outlet of the first online rainwater treatment facility is provided with the first sewage vent line connected with trunk sewer, and and rain
First storm drain lines of water conduit tube connection.
2. system according to claim 1, it is characterised in that the system be additionally included in trunk sewer and Storm-water sewer it
Between be provided with the second online rainwater treatment facility, the import of the second online rainwater treatment facility connects with Storm-water sewer,
The outlet of two online rainwater treatment facilities connects with the trunk sewer and Storm-water sewer respectively.
Preferably, the outlet of the described second online rainwater treatment facility is provided with the second effluent outfall connected with trunk sewer
Road, and the second storm drain lines connected with Storm-water sewer.
Preferably, the described second online rainwater treatment facility and the entrance of the Storm-water sewer connectivity part are not less than the second online rain
The outlet of water processing establishment and Storm-water sewer connectivity part, and set at the downstream of the entrance on the Storm-water sewer the
One water conservancy switchs;Or
The second online rainwater treatment facility and the entrance of the Storm-water sewer connectivity part are set less than the second online rainwater treatment
Grant the outlet of Storm-water sewer connectivity part.
3. system according to claim 1 or claim 2, it is characterised in that the system also includes rainwater pretreatment system, the rain
Water pretreatment system is arranged on Storm-water sewer, or with Storm-water sewer and connecing setting;When the rainwater pretreatment system and rainwater
Main and when connecing setting, the water inlet end of the rainwater pretreatment system connects with Storm-water sewer, its discharge ends and Storm-water sewer or
Natural water connects.
Preferably, the entrance of the rainwater pretreatment system and the Storm-water sewer connectivity part not less than rainwater pretreatment system with
The outlet of Storm-water sewer connectivity part, and set the second water conservancy to switch at the downstream of the entrance;Or
The rainwater pretreatment system and the entrance of the Storm-water sewer connectivity part are less than rainwater pretreatment system and Storm-water sewer
The outlet of connectivity part.
4. according to the system any one of claim 1-3, it is characterised in that the unit area be urban area in
Function and usage attribute or the soil region for including building or structures of the same or like division division of rain dirt pollution level.
Preferably, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 square kilometres.
Preferably, drainpipe of branch sewer and the rainwater branch pipe respectively with building or structures connects.
Preferably, the building or structures be residential area, industrial and mining enterprises, office, school, hospital, market or other can
Combination more than one or both of unit area of large amount of sewage can be produced.
Preferably, the system also includes municipal storm sewer, and the municipal storm sewer connects with Storm-water sewer.
Preferably, the system can also set one or more in parallel or string in trunk sewer close to the position of sewage treatment plant
The end storage pond of connection.
Preferably, the first water conservancy switch and the second water conservancy switch are respectively selected from valve, gate, flap valve or weir gate;It is preferred that
For ball valve, the flap valve that dams, upper open type gate or bottom-open type weir gate.
5. according to the system any one of claim 1-4, it is characterised in that the first online rain processing system
Quantity is one or more;, can be online by described first when the quantity of the described first online rain processing system is multiple
Rain processing system is arranged on pipeline in a manner of in series or in parallel.
Preferably, the described first online rainwater treatment facility includes functional rain water treatment facilities;The functional rain water process
Device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
Preferably, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;The online processing
Storage pond serial or parallel connection is multiple.
Preferably, in the described first online rainwater treatment facility, the port of export of the buffer pool is provided with urgent flood discharge gallery;Institute
State and control valve is installed on urgent flood discharge gallery, the port of export of urgent flood discharge gallery connects with Storm-water sewer;The just rain is adjusted
Reservoir entrance point connects with buffer pool, and the port of export connects with online processing storage pond entrance point;The online processing storage pond
The port of export connects with Storm-water sewer.
Preferably, the described first online rainwater treatment facility is arranged in unit area or outside unit area.
6. according to the system any one of claim 1-5, it is characterised in that the second online rain processing system
Quantity is one or more;, can be online by described second when the quantity of the described second online rain processing system is multiple
Rain processing system is arranged on pipeline in a manner of in series or in parallel.
Preferably, the import serial or parallel connection of the multiple second online rainwater treatment facility is located at the first online rainwater treatment and set
Downstream of the outlet for the first storm drain lines applied on Storm-water sewer.
Preferably, the described second online rainwater treatment facility includes functional rain water treatment facilities;The functional rain water process
Device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
Preferably, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;The online processing
Storage pond serial or parallel connection is multiple.
Preferably, in the described second online rainwater treatment facility, the just rain storage pond entrance point connects with buffer pool, the port of export
Connected with online processing storage pond entrance point;The port of export of the online processing storage pond connects with Storm-water sewer.
Preferably, the quantity of the rainwater pretreatment system is one or more;When the quantity of the rainwater pretreatment system is
When multiple, the rainwater pretreatment system can be arranged on pipeline in parallel.
Preferably, the quantity of the rainwater pretreatment system is according to the area in unit area or the size outside unit area
Divided.
Preferably, the rainwater pretreatment system is selected from particle separator, filter, rainwater treatment module or biological removal of nitrogen dephosphorization
Any of equipment or two or more combinations, it is preferable that the rainwater pretreatment system is selected from particle separator, filter
Or rainwater treatment module and combinations thereof, it is highly preferred that the rainwater pretreatment system includes being sequentially connected in series the particle separation of connection
Device, filter and rainwater treatment module.
7. a kind of method for controlling sewage and the complete separate system of early-stage rainwater pollution, methods described include:
Trunk sewer is set, nature is emitted into after the sewage in urban area is delivered into sewage treatment plant's processing by trunk sewer
Water body;
Storm-water sewer is set, the rainwater in urban area is emitted into natural water by Storm-water sewer;
At least one unit area is set;Branch sewer and rainwater branch pipe are provided with the unit area;The branch sewer
Outlet connected with trunk sewer;The outlet of the rainwater branch pipe is provided with the first online rainwater treatment facility;Described first
The outlet of line rainwater treatment facility is provided with the first sewage vent line connected with trunk sewer, and is connected with Storm-water sewer
The first storm drain lines.
8. according to the method for claim 7, it is characterised in that methods described be additionally included in trunk sewer and Storm-water sewer it
Between be provided with the second online rainwater treatment facility, the import of the second online rainwater treatment facility connects with Storm-water sewer,
The outlet of two online rainwater treatment facilities connects with the trunk sewer and Storm-water sewer respectively.
Preferably, the outlet of the described second online rainwater treatment facility is provided with the second effluent outfall connected with trunk sewer
Road, and the second storm drain lines connected with Storm-water sewer.
Preferably, the system also includes rainwater pretreatment system, and the rainwater pretreatment system is arranged on Storm-water sewer, or
With Storm-water sewer and connecing setting;When the rainwater pretreatment system and Storm-water sewer and when connecing setting, the rainwater pretreatment system
The water inlet end of system connects with Storm-water sewer, and its discharge ends connects with Storm-water sewer or natural water.
Preferably, in the described first online rainwater treatment facility, the port of export of the buffer pool is provided with urgent flood discharge gallery;Institute
State and control valve is installed on urgent flood discharge gallery, the port of export of urgent flood discharge gallery connects with Storm-water sewer;The just rain is adjusted
Reservoir entrance point connects with buffer pool, and the port of export connects with online processing storage pond entrance point;The online processing storage pond
The port of export connects with Storm-water sewer.
Preferably, the described second online rainwater treatment facility includes functional rain water treatment facilities;The functional rain water process
Device is buffer pool, first rain storage pond or one kind in online processing storage pond or several combinations.
Preferably, the buffer pool serial or parallel connection is multiple;The just rain storage pond serial or parallel connection is multiple;The online processing
Storage pond serial or parallel connection is multiple.
Preferably, the quantity of the rainwater pretreatment system is according to the area in unit area or the size outside unit area
Divided.
Preferably, the unit area is with function and usage attribute or the same or like division of rain dirt pollution level in urban area
The soil region for including building or structures of division.
Preferably, the area of the unit area is 0.01-0.6 square kilometres, preferably 0.01-0.3 square kilometres.
Preferably, drainpipe of branch sewer and the rainwater branch pipe respectively with building or structures connects.
Preferably, the building or structures be residential area, industrial and mining enterprises, office, school, hospital, market or other can
Combination more than one or both of unit area of large amount of sewage can be produced.
9. the method according to claim 7 or 8, it is characterised in that methods described also includes:
When fine day and early-stage rainwater, the early-stage rainwater in the rainwater branch pipe passes through after being discharged into the first online rainwater treatment facility
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after crossing processing;Institute
The sewage for stating branch sewer is directly discharged into trunk sewer;
When middle and later periods rainwater, the middle and later periods rainwater in the rainwater branch pipe is discharged into after the first online rainwater treatment facility by place
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after reason;The dirt
Sewage in water branch pipe is directly discharged into trunk sewer;
When rainfall increases to the disposal ability upper limit of the first online rain processing system, the first online rain processing system is opened
Urgent flood discharge gallery, carries out flood discharge.
10. according to the method any one of claim 7-9, it is characterised in that methods described also includes:
When fine day and early-stage rainwater, the early-stage rainwater in the rainwater branch pipe passes through after being discharged into the first online rainwater treatment facility
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after crossing processing;Institute
The sewage stated in branch sewer is directly discharged into trunk sewer;Water body in the Storm-water sewer is by the described second online rainwater
Storm-water sewer is emitted into through the second storm drain lines or be emitted into sewage through the second sewage vent line after the processing of reason system
Main;
When middle and later periods rainwater, the middle and later periods rainwater in the rainwater branch pipe is discharged into after the first online rainwater treatment facility by place
Trunk sewer is emitted into through the first sewage vent line or be emitted into Storm-water sewer through the first storm drain lines after reason;The dirt
Sewage in water branch pipe is directly discharged into trunk sewer;Water body in the Storm-water sewer passes through the described second online rainwater treatment system
Storm-water sewer is emitted into through the second storm drain lines or be emitted into trunk sewer through the second sewage vent line after system processing;
When rainfall increases to the disposal ability upper limit of the first online rain processing system, the first online rain processing system is opened
Urgent flood discharge gallery, carries out flood discharge.
Preferably, the water body in the Storm-water sewer is discharged into rainwater pretreatment system, at the rainwater pretreatment system
Storm-water sewer or the pipeline being connected with natural water are emitted into after reason.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2017205136539 | 2017-05-10 | ||
CN201720513653 | 2017-05-10 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107806150A true CN107806150A (en) | 2018-03-16 |
CN107806150B CN107806150B (en) | 2024-04-02 |
Family
ID=61576504
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710796368.7A Active CN107806150B (en) | 2017-05-10 | 2017-09-06 | Complete diversion system for controlling pollution of sewage and initial rainwater and control method thereof |
CN201721137158.9U Active CN207436170U (en) | 2017-05-10 | 2017-09-06 | A kind of complete separate flow system for controlling sewage and initial rainwater pollution |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721137158.9U Active CN207436170U (en) | 2017-05-10 | 2017-09-06 | A kind of complete separate flow system for controlling sewage and initial rainwater pollution |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN107806150B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113463740A (en) * | 2021-07-02 | 2021-10-01 | 武汉圣禹排水系统有限公司 | System and method for treating rainwater |
CN114592564A (en) * | 2022-03-25 | 2022-06-07 | 西南林业大学 | Intelligent rain and sewage collecting device |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107806150B (en) * | 2017-05-10 | 2024-04-02 | 武汉圣禹智慧生态环保股份有限公司 | Complete diversion system for controlling pollution of sewage and initial rainwater and control method thereof |
CN114775757B (en) * | 2022-05-30 | 2024-03-08 | 中国建筑第五工程局有限公司 | Drainage system based on municipal road confluence pipe network |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002242290A (en) * | 2001-02-15 | 2002-08-28 | Kubota Corp | Rainwater separation basin |
CN203188340U (en) * | 2013-02-05 | 2013-09-11 | 福州市规划设计研究院 | Urban drainage system under closure-type comprehensive drainage system |
CN105544697A (en) * | 2016-02-04 | 2016-05-04 | 武汉圣禹排水系统有限公司 | Area partitioned rainwater flow distribution, storage regulation and processing system based on combined-system pipe network |
CN105625545A (en) * | 2016-02-15 | 2016-06-01 | 武汉圣禹排水系统有限公司 | Region sectioning rainwater treatment system based on separate-system pipe network |
CN205475585U (en) * | 2016-02-05 | 2016-08-17 | 武汉圣禹排水系统有限公司 | Rainwater reposition of redundant personnel, regulation and processing system of reposition of redundant personnel system |
CN106592735A (en) * | 2016-12-30 | 2017-04-26 | 武汉圣禹排水系统有限公司 | Separate-zone rainwater flow, regulation and storage, and on-line treatment system with obvious initial rainwater feature under separate system and mixed flow system |
CN107605003A (en) * | 2017-05-10 | 2018-01-19 | 武汉圣禹排水系统有限公司 | A kind of incomplete separate flow system and its control method for controlling sewage and early-stage rainwater pollution |
CN207436170U (en) * | 2017-05-10 | 2018-06-01 | 武汉圣禹排水系统有限公司 | A kind of complete separate flow system for controlling sewage and initial rainwater pollution |
-
2017
- 2017-09-06 CN CN201710796368.7A patent/CN107806150B/en active Active
- 2017-09-06 CN CN201721137158.9U patent/CN207436170U/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002242290A (en) * | 2001-02-15 | 2002-08-28 | Kubota Corp | Rainwater separation basin |
CN203188340U (en) * | 2013-02-05 | 2013-09-11 | 福州市规划设计研究院 | Urban drainage system under closure-type comprehensive drainage system |
CN105544697A (en) * | 2016-02-04 | 2016-05-04 | 武汉圣禹排水系统有限公司 | Area partitioned rainwater flow distribution, storage regulation and processing system based on combined-system pipe network |
CN205475585U (en) * | 2016-02-05 | 2016-08-17 | 武汉圣禹排水系统有限公司 | Rainwater reposition of redundant personnel, regulation and processing system of reposition of redundant personnel system |
CN105625545A (en) * | 2016-02-15 | 2016-06-01 | 武汉圣禹排水系统有限公司 | Region sectioning rainwater treatment system based on separate-system pipe network |
CN106592735A (en) * | 2016-12-30 | 2017-04-26 | 武汉圣禹排水系统有限公司 | Separate-zone rainwater flow, regulation and storage, and on-line treatment system with obvious initial rainwater feature under separate system and mixed flow system |
CN107605003A (en) * | 2017-05-10 | 2018-01-19 | 武汉圣禹排水系统有限公司 | A kind of incomplete separate flow system and its control method for controlling sewage and early-stage rainwater pollution |
CN207436170U (en) * | 2017-05-10 | 2018-06-01 | 武汉圣禹排水系统有限公司 | A kind of complete separate flow system for controlling sewage and initial rainwater pollution |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113463740A (en) * | 2021-07-02 | 2021-10-01 | 武汉圣禹排水系统有限公司 | System and method for treating rainwater |
CN114592564A (en) * | 2022-03-25 | 2022-06-07 | 西南林业大学 | Intelligent rain and sewage collecting device |
Also Published As
Publication number | Publication date |
---|---|
CN107806150B (en) | 2024-04-02 |
CN207436170U (en) | 2018-06-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106978840A (en) | A kind of face groundwater pollution control for drainage system pipe network system | |
CN107747345B (en) | Surface pollution control system and method for combined drainage pipe network system | |
CN207436170U (en) | A kind of complete separate flow system for controlling sewage and initial rainwater pollution | |
CN106988401A (en) | A kind of face groundwater pollution control for combined flow system pipe network system | |
CN107806159A (en) | A kind of combined drainage system and control method of sewage and rainwater | |
CN207436200U (en) | A kind of shunting well with downflow weir and the drainage system including the shunting well | |
CN107605006A (en) | A kind of drainage system and water discharge control method | |
CN104213599A (en) | Zero-energy-consumption roof recycled rainwater utilizing system | |
CN107806156A (en) | A kind of combined drainage system and control method of sewage and rainwater | |
CN207436169U (en) | A kind of combined flow system pipe network system for controlling sewage and initial rainwater pollution | |
CN107806160A (en) | A kind of combined drainage system and control method of sewage and rainwater | |
CN207959445U (en) | A kind of drainage system with regulate and store facility and online processing facility | |
CN207436171U (en) | A kind of incomplete separate flow system for controlling sewage and initial rainwater pollution | |
CN107842088A (en) | A kind of drainage system and water discharge control method with regulate and store facility and online treatment facility | |
CN107806164A (en) | A kind of road rain water shunting processing system and its control method | |
CN107558568A (en) | A kind of separate sewage system and control method of sewage and rainwater | |
CN208280275U (en) | A kind of road rain water shunting processing system | |
CN103951136A (en) | Balcony wastewater and initial rainwater purifier and purification method used in rainwater pipe network | |
CN208949078U (en) | A kind of rain dirt mixing water treatment system of big interception ratio | |
CN207760988U (en) | A kind of combined drainage system of sewage and rainwater | |
CN208280260U (en) | A kind of combined drainage system of sewage and rainwater | |
CN207436183U (en) | A kind of carry cuts dirty pipe, a drainage system for regulate and store facility and online treatment facility | |
CN207761004U (en) | A kind of shunting well with downflow weir and the drainage system including the shunting well | |
CN207760985U (en) | A kind of band surges the drainage system of bottom-open type weir gate and pump row | |
CN207436185U (en) | A kind of drainage system pipe network control system for no trunk sewer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: No. 509 Weihu Road, Shamao Street, Hannan District, Wuhan City, Hubei Province, 430090 Applicant after: Wuhan Shengyu Smart Ecological Environmental Protection Co.,Ltd. Address before: 430000, No. 189, Minli North Road, Wuhan Economic and Technological Development Zone, Hubei Province Applicant before: WUHAN SHENGYU DRAINAGE SYSTEM Co.,Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant |