CN107724689A CN201610661855.8A CN201610661855A CN107724689A CN 107724689 A CN107724689 A CN 107724689A CN 201610661855 A CN201610661855 A CN 201610661855A CN 107724689 A CN107724689 A CN 107724689A
Authority
CN
China
Prior art keywords
construction
coordinate system
coordinate
steel
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610661855.8A
Other languages
Chinese (zh)
Other versions
CN107724689B (en
Inventor
张翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201610661855.8A priority Critical patent/CN107724689B/en
Publication of CN107724689A publication Critical patent/CN107724689A/en
Application granted granted Critical
Publication of CN107724689B publication Critical patent/CN107724689B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of steel structures in construction works to measure construction method, including the foundation of coordinate system and in-site measurement construction;The foundation of coordinate system provides general layout according to designing institute, coordinate establishes measuring coordinate system to individual works with CAD, respectively by surveying to steel construction bottom plate localization method, coordinate system examination and steel structure column bottom plate off normal line coordinates establishing to complete the foundation of column foundation coordinate system;In-site measurement construction measures unwrapping wire at the scene with total powerstation, each point position in CAD coordinate systems is marked at the construction field (site), mark point should be clear, it is not easy to be destroyed, this kind of steel structures in construction works measures construction method, accurately steel construction can be installed, after steel structure base installs, the situation that top node does not dock is avoided to occur, avoid the situation generation that return-to-factory re-works part, while improving the installation speed of steel structure base, the progress of integrated engineering is also improved.

Description

A kind of steel structures in construction works measures construction method
Technical field
The present invention relates to one kind to measure construction method, specially a kind of steel structures in construction works measurement construction method.
Background technology
In recent years, variation is built in urban construction, polymorphic structure is seen everywhere.This irregular building uses steel construction To build, steel structure node is controlled and is provided with this very high technological requirement.Therefore how steel construction is accurately installed, to a lot Enterprise brings huge challenge, and many enterprises, because method is not right, cause steel structure base to install when doing this respect work After, the problem that top node does not dock is of common occurrence, if according to the good steel structure base of site operation, returns again to factory Family re-works part, not anxious time-consuming, but also delays the mistake of integrated engineering progress.
The content of the invention
The present invention provides a kind of steel structures in construction works measurement construction method, can effectively solve Cheng Gangjie in practical application After structure basis installs, the problem of problem that top node does not dock is of common occurrence.
In order to solve the above-mentioned technical problem, the invention provides following technical scheme:
A kind of steel structures in construction works measurement construction method of the present invention, methods described comprise the following steps:
The foundation of coordinate system and in-site measurement construction;
The foundation of the coordinate system provides general layout according to designing institute, coordinate establishes measuring coordinate system to individual works with CAD, Respectively by surveying to steel construction bottom plate localization method, coordinate system examination and steel structure column bottom plate off normal line coordinates establishing to complete base for post The foundation of plinth coordinate system;
The in-site measurement construction measures unwrapping wire at the scene with total powerstation, and each point position in CAD coordinate systems is being constructed Scene is marked, and mark point should be clear, is not easy to be destroyed.
It is described to steel construction bottom plate localization method as a preferred technical solution of the present invention:Select any one angle point The elements of a fix, straight line order is inputted, sequentially input X, Y-coordinate, coordinate value provides data with reference to designing institute's drawing;Carry out second jiao Point coordinates positions, and inputs straight line order, sequentially inputs X, Y-coordinate, coordinate value provides data with reference to designing institute's drawing, according to 2 points Coordinate points establish global coordinate system;Designing institute's steel structure base floor plan is copied in coordinate system figure, uses alignment command One basis of steel construction for establishing coordinate points is snapped into coordinate points, successively by remaining coordinate system central point in coordinate system drawing Coordinate is established out;Global coordinate system, which is established, to be completed.
As a preferred technical solution of the present invention, the steel structure column bottom plate off normal line coordinates is established:In coordinate system In figure, draw and column base plate parallel lines two, it is desirable to which two straight lines, apart from being suitable, should not exceed base with post centre coordinate system Plinth margin of foundation pit;Facilitate site operation;Post center point coordinate and off normal line position of intersecting point are established into coordinate system again;So far can establish Column foundation integral position.
As a preferred technical solution of the present invention, the coordinate system examination is surveyed:Entered using total powerstation to establishing coordinate system Row examination is surveyed, and examination measuring point is preceding viewpoint and backsight point, multi-point retest, it is ensured that coordinate system accuracy.
As a preferred technical solution of the present invention, the method for the in-site measurement construction is:Measure in steel structure column Heart point coordinates and two axis and off normal line intersecting point coordinate, cross hairs is located by connecting into line;Make template, template size and shape Shape is identical with steel construction bottom plate, carries out perforate in foundation bolt position, marks opposite side midpoint snap the line in template;Foundation bolt It is put into pattern hole, is placed in below cross hairs, it is to align that cross hairs overlaps with top cross in template(Template can not be with lead Contact);Foundation bolt is welded on the reinforcing bar in pile foundation and carries out the lowest point, takes out template, descending reinforcing cage is watered concrete and entered Row is reinforced;Steel structure hoisting, steel construction bed bolt hole is alignd with foundation bolt and is put into, nut is screwed on and fixes, checked vertical Degree is until reach requirement;Around foundation bolt and steel reinforcement cage, pouring concrete are put in structural column lower end, and concrete is highly steel mechanism 1.5 times of column diameter;So far steel structure column installation.
The beneficial effect that is reached of the present invention is:This kind of steel structures in construction works measures construction method, can be accurately right Steel construction is installed, and after steel structure base installs, is avoided the situation that top node does not dock and is occurred, avoid The situation that return-to-factory re-works part occurs, and while improving the installation speed of steel structure base, also improves whole The progress of body engineering.
Brief description of the drawings
Accompanying drawing is used for providing a further understanding of the present invention, and a part for constitution instruction, the reality with the present invention Apply example to be used to explain the present invention together, be not construed as limiting the invention.In the accompanying drawings:
Fig. 1 is a kind of one of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 2 is the two of a kind of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 3 is the three of a kind of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 4 is the four of a kind of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 5 is the five of a kind of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 6 is the six of a kind of flow chart of steel structures in construction works measurement construction method of the present invention;
Fig. 7 is the seven of a kind of flow chart of steel structures in construction works measurement construction method of the present invention.
Embodiment
The preferred embodiments of the present invention are illustrated below in conjunction with accompanying drawing, it will be appreciated that described herein preferred real Apply example to be merely to illustrate and explain the present invention, be not intended to limit the present invention.
Embodiment:As shown in figs. 1-7, a kind of steel structures in construction works measurement construction method of the present invention, method includes as follows Step:
The foundation of coordinate system and in-site measurement construction;
The foundation of coordinate system provides general layout according to designing institute, coordinate establishes measuring coordinate system to individual works with CAD, respectively By being surveyed to steel construction bottom plate localization method, coordinate system examination and steel structure column bottom plate off normal line coordinates establishing to complete column foundation seat Mark the foundation of system;
In-site measurement construction measures unwrapping wire at the scene with total powerstation, by each point position in CAD coordinate systems at the construction field (site) It is marked, mark point should be clear, is not easy to be destroyed.
To steel construction bottom plate localization method:Any one Corner character coordinate is selected, straight line order is inputted, sequentially inputs X, Y Coordinate, coordinate value provide data with reference to designing institute's drawing;The second angular coordinate positioning is carried out, straight line order is inputted, sequentially inputs X, Y-coordinate, coordinate value provide data with reference to designing institute's drawing, and global coordinate system is established according to 2 point coordinates points;Such as Fig. 1.It will set Meter institute steel structure base floor plan is copied in coordinate system figure, and one base of steel construction of coordinate points will be established with alignment command Plinth snaps to coordinate points, establishes out by remaining coordinate system center point coordinate successively in coordinate system drawing;Global coordinate system is built It is vertical to complete;Such as Fig. 2.
Coordinate system examination is surveyed:Examination survey is carried out to establishing coordinate system, examination measuring point is preceding viewpoint and backsight point, multiple spot using total powerstation Position retest, it is ensured that coordinate system accuracy.
Steel structure column bottom plate off normal line coordinates is established:In coordinate system figure, draw and column base plate parallel lines two, it is desirable to Two straight lines, apart from being suitable, should not exceed foundation pit edge with post centre coordinate system;Facilitate site operation;Again by post center Point coordinates establishes coordinate system with off normal line position of intersecting point;So far column foundation integral position can be established;Such as Fig. 3.
In-site measurement construction method be:Steel structure column center point coordinate and two axis are measured to sit with inclined bit line crossings Mark, cross hairs is located by connecting into line;Template is made, template size is identical with steel construction bottom plate with shape, in foundation bolt position Carry out perforate is put, marks opposite side midpoint snap the line in template;Such as Fig. 5.Foundation bolt is put into pattern hole, is placed under cross hairs Square, it is to align that cross hairs overlaps with top cross in template(Template can not be with wire contacts);Such as Fig. 6.Foundation bolt is welded It is connected on the reinforcing bar in pile foundation and carries out the lowest point, take out template, descending reinforcing cage is watered concrete and reinforced;Steel structure hoisting, Steel construction bed bolt hole is alignd with foundation bolt and is put into, nut is screwed on and fixes, checks perpendicularity until reaching requirement;On ground Steel reinforcement cage, pouring concrete are put in around foot bolt and structural column lower end, and concrete is highly 1.5 times of steel mechanism column diameter;So far Steel structure column installation;Such as Fig. 7.
This kind of steel structures in construction works measures construction method, accurately steel construction can be installed, in steel construction base After plinth installs, avoid the situation that top node does not dock and occur, avoid return-to-factory and re-work part Situation occurs, and while improving the installation speed of steel structure base, also improves the progress of integrated engineering.
Finally it should be noted that:The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, Although the present invention is described in detail with reference to the foregoing embodiments, for those skilled in the art, it still may be used To be modified to the technical scheme described in foregoing embodiments, or equivalent substitution is carried out to which part technical characteristic. Within the spirit and principles of the invention, any modification, equivalent substitution and improvements made etc., it should be included in the present invention's Within protection domain.

Claims (5)

1. a kind of steel structures in construction works measures construction method, methods described comprises the following steps:
The foundation of coordinate system and in-site measurement construction;
The foundation of the coordinate system provides general layout according to designing institute, coordinate establishes measuring coordinate system to individual works with CAD, Respectively by surveying to steel construction bottom plate localization method, coordinate system examination and steel structure column bottom plate off normal line coordinates establishing to complete base for post The foundation of plinth coordinate system;
The in-site measurement construction measures unwrapping wire at the scene with total powerstation, and each point position in CAD coordinate systems is being constructed Scene is marked, and mark point should be clear, is not easy to be destroyed.
2. a kind of steel structures in construction works measurement construction method according to claim 1, it is characterised in that described to steel knot Structure bottom plate localization method:Any one Corner character coordinate is selected, straight line order is inputted, sequentially inputs X, Y-coordinate, coordinate value reference Designing institute's drawing provides data;The second angular coordinate positioning is carried out, inputs straight line order, sequentially inputs X, Y-coordinate, coordinate value ginseng Data are provided according to designing institute's drawing, global coordinate system is established according to 2 point coordinates points;By designing institute's steel structure base horizontal layout Figure is copied in coordinate system figure, one basis of steel construction for establishing coordinate points is snapped into coordinate points with alignment command, in coordinate It is to establish out by remaining coordinate system center point coordinate successively in drawing;Global coordinate system, which is established, to be completed.
A kind of 3. steel structures in construction works measurement construction method according to claim 1, it is characterised in that the coordinate system Examination is surveyed:Examination survey is carried out to establishing coordinate system, examination measuring point is preceding viewpoint and backsight point, multi-point retest, really using total powerstation Protect coordinate system accuracy.
A kind of 4. steel structures in construction works measurement construction method according to claim 1, it is characterised in that the steel construction Column base plate off normal line coordinates is established:In coordinate system figure, draw and column base plate parallel lines two, it is desirable in two straight lines and post Heart coordinate system distance is suitable, should not exceed foundation pit edge;Facilitate site operation;Again by post center point coordinate and off normal line Position of intersecting point establishes coordinate system;So far column foundation integral position can be established.
5. a kind of steel structures in construction works measurement construction method according to claim 1, it is characterised in that the scene is surveyed Measuring the method constructed is:Steel structure column center point coordinate and two axis and off normal line intersecting point coordinate are measured, is located by connecting with line Into cross hairs;Template is made, template size is identical with steel construction bottom plate with shape, perforate is carried out in foundation bolt position, in mould Opposite side midpoint snap the line is marked on plate;Foundation bolt is put into pattern hole, is placed in below cross hairs, cross hairs and top in template It is to align that cross, which overlaps,(Template can not be with wire contacts);Foundation bolt is welded on the reinforcing bar in pile foundation and carries out paddy Bottom, takes out template, and descending reinforcing cage is watered concrete and reinforced;Steel structure hoisting, by steel construction bed bolt hole and lower margin spiral shell Bolt alignment is put into, and is screwed on nut and is fixed, and checks perpendicularity until reaching requirement;Around foundation bolt and steel is put in structural column lower end Muscle cage, pouring concrete, concrete are highly 1.5 times of steel mechanism column diameter;So far steel structure column installation.
CN201610661855.8A 2016-08-12 2016-08-12 Construction engineering steel structure measurement construction method Active CN107724689B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610661855.8A CN107724689B (en) 2016-08-12 2016-08-12 Construction engineering steel structure measurement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610661855.8A CN107724689B (en) 2016-08-12 2016-08-12 Construction engineering steel structure measurement construction method

Publications (2)

Publication Number Publication Date
CN107724689A true CN107724689A (en) 2018-02-23
CN107724689B CN107724689B (en) 2021-09-10

Family

ID=61199911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610661855.8A Active CN107724689B (en) 2016-08-12 2016-08-12 Construction engineering steel structure measurement construction method

Country Status (1)

Country Link
CN (1) CN107724689B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457722A (en) * 2018-10-30 2019-03-12 安徽信息工程学院 A kind of localization method of foundation bolt
CN114645550A (en) * 2022-03-31 2022-06-21 中国核工业华兴建设有限公司 Mounting and positioning method for embedded part of main pump evaporator

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201770992U (en) * 2010-07-22 2011-03-23 武汉一冶钢结构有限责任公司 Foundation bolt positioning device
CN201826437U (en) * 2010-09-29 2011-05-11 上海市机械施工有限公司 Structure for accurately embedding column pin bolts for steel structures
CN102306226A (en) * 2011-10-14 2012-01-04 中国十九冶集团有限公司 Method and usage for locating installation component by utilizing cartographic software matched with total station
CN102425187A (en) * 2011-08-30 2012-04-25 中国三冶集团有限公司第一建筑工程公司 Large steel structure heel embedded part positioning device and method
CN102759351A (en) * 2011-04-25 2012-10-31 五冶集团上海有限公司 Measuring and positioning method of installation of large-scale annular equipment foundation bolt sleeves

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201770992U (en) * 2010-07-22 2011-03-23 武汉一冶钢结构有限责任公司 Foundation bolt positioning device
CN201826437U (en) * 2010-09-29 2011-05-11 上海市机械施工有限公司 Structure for accurately embedding column pin bolts for steel structures
CN102759351A (en) * 2011-04-25 2012-10-31 五冶集团上海有限公司 Measuring and positioning method of installation of large-scale annular equipment foundation bolt sleeves
CN102425187A (en) * 2011-08-30 2012-04-25 中国三冶集团有限公司第一建筑工程公司 Large steel structure heel embedded part positioning device and method
CN102306226A (en) * 2011-10-14 2012-01-04 中国十九冶集团有限公司 Method and usage for locating installation component by utilizing cartographic software matched with total station

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王雷等: "某大型工业厂房地脚螺栓高精度安装施工技术", 《青岛理工大学学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457722A (en) * 2018-10-30 2019-03-12 安徽信息工程学院 A kind of localization method of foundation bolt
CN114645550A (en) * 2022-03-31 2022-06-21 中国核工业华兴建设有限公司 Mounting and positioning method for embedded part of main pump evaporator

Also Published As

Publication number Publication date
CN107724689B (en) 2021-09-10

Similar Documents

Publication Publication Date Title
CN101413348B (en) Steel structure three-dimensional scanning observe and control method
CN103591944B (en) A kind of arcuate building measures construction method
CN107869249B (en) Arcuate structure high-formwork construction method
CN109443324A (en) A kind of construction site construction survey method
CN102966041A (en) Spatial stay-cable positioning method of multispan continuous S-shaped landscape bridge
CN107724689A (en) A kind of steel structures in construction works measures construction method
CN105887915A (en) Foundation bolt locating method based on BIM
CN106193330B (en) A kind of steel building construction land tenure foot bolt pre-embedded construction method
CN114541264A (en) Cable-stayed bridge cable guide pipe integrated measuring and positioning method
CN106193094A (en) A kind of embedding anchor bolts construction mould and foundation bolt regulation construction method
CN108612075A (en) A method of monitoring deep basal pit horizontal displacement
CN211948529U (en) Positioning support of big post rag bolt crowd of multi-chamber
CN111549815A (en) Steel structure foundation bolt pre-embedding construction method
CN107905108A (en) Tubular arch bolted web member hole group's accuracy control method
CN218059932U (en) Steel anchor box installation mechanism
CN106368330B (en) Steel building construction land tenure foot bolt pre-embedded construction method
CN104964674A (en) Control net used for large structure building size
CN212375857U (en) Deepwater pile foundation steel protects a position appearance positioner
CN105926663B (en) The locating mounting method of annular foundation bolt group
CN113670259A (en) Method for measuring inclination of large and small-head cylinder of historic building timber structure
CN206396782U (en) A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing
CN107268666B (en) A kind of localization method of auxiliary locator and foundation bolt
CN203878604U (en) Pre-buried screw rod support
JP6870478B2 (en) Ruler for tower site
CN215450649U (en) Modular splicing type modeling device for manufacturing complex terrain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant