CN206396782U - A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing - Google Patents
A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing Download PDFInfo
- Publication number
- CN206396782U CN206396782U CN201720033398.8U CN201720033398U CN206396782U CN 206396782 U CN206396782 U CN 206396782U CN 201720033398 U CN201720033398 U CN 201720033398U CN 206396782 U CN206396782 U CN 206396782U
- Authority
- CN
- China
- Prior art keywords
- cotton rope
- construction
- timber
- positioning
- positioning timber
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Abstract
The utility model provides a kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing, including:The predetermined altitude laid by theodolite and the first positioning timber, the second positioning timber, the 3rd positioning timber and the 4th positioning timber spaced a predetermined distance, the construction cotton rope of connection first between the first positioning timber and the 3rd positioning timber, the construction cotton rope of connection second between the second positioning timber and the 4th positioning timber, the first construction cotton rope and the described second construction cotton rope intersecting vertical;The foundation bolt includes multiple, and multiple foundation bolts are centrally located at the top of the first construction cotton rope and the described second construction cotton rope crosspoint, the foundation bolt and flushed with the described first construction cotton rope with the described second height for constructing cotton rope crosspoint.Positioned by the positioner, pre-buried foundation bolt construction precision is high, and axial dimension and absolute altitude can control to arrive zero error.The steel member of subsequent construction, is easily installed, and speed of application is faster.
Description
Technical field
The utility model is related to a kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing.
Background technology
Pre-embedded anchoring bolts on isolated footing, are structure type common in architectural engineering, steel-structure factory building, high-tension line
Basis and assembled architecture basis just use this structure type.This basis, the accuracy of embedding anchor bolts is critically important,
Foundation construction it is good again, if position (axial location and height) incorrect or bigger error of embedding anchor bolts, also only
It can again be constructed after demolition blasting, both influence the duration, very big economic loss is caused again, so must have one during construction correctly
Localization method.
Utility model content
The purpose of this utility model is to provide a kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing, to solve
Easily there is the technical problem of deviation in current embedding anchor bolts position.
In order to solve the above technical problems, the utility model provides a kind of determining for pre-embedded anchoring bolts of being constructed on isolated footing
Position device, it is characterised in that including:
The predetermined altitude laid by theodolite and the first positioning timber spaced a predetermined distance, the second positioning timber, the
Three position timbers and the 4th positioning timber, the construction line of connection first between the first positioning timber and the 3rd positioning timber
Rope, it is described second positioning timber and it is described 4th positioning timber between connection second construct cotton rope, it is described first construction cotton rope with
The second construction cotton rope intersecting vertical;
The foundation bolt includes multiple, and multiple foundation bolts are centrally located at the first construction cotton rope with described second
Construct cotton rope crosspoint, with the described first construction cotton rope and the height in the described second construction cotton rope crosspoint at the top of the foundation bolt
Degree is flushed.
Further, the foundation bolt is arranged in template, and is fixed by stirrup.
Further, the foundation bolt includes four, and the point midway of adjacent foundation bolt line is applied described first
On work cotton rope or the second construction cotton rope.
Further, the concrete of the fixed foundation bolt is poured in the template.
Compared with prior art, the beneficial effects of the utility model are:
The positioner for pre-embedded anchoring bolts of being constructed on a kind of isolated footing that the utility model is provided, including:Pass through warp
Predetermined altitude that latitude instrument is laid and the first positioning timber, the second positioning timber, the 3rd positioning timber and the spaced a predetermined distance
Four positioning timbers, the construction cotton rope of connection first between the first positioning timber and the 3rd positioning timber, described second determines
The construction cotton rope of connection second between position timber and the 4th positioning timber, the first construction cotton rope and the described second construction line
Rope intersecting vertical;The foundation bolt include it is multiple, multiple foundation bolts be centrally located at it is described first construction cotton rope with it is described
With the described first construction cotton rope and the described second construction cotton rope crosspoint at the top of second construction cotton rope crosspoint, the foundation bolt
Height flush.Positioned by the positioner, pre-buried foundation bolt construction precision is high, and axial dimension and absolute altitude can be controlled
To zero error.The steel member of subsequent construction, is easily installed, and speed of application is faster.
Brief description of the drawings
Fig. 1 diagrammatically illustrates the structural representation of the utility model embodiment concrete application;
Fig. 2 diagrammatically illustrates the structural representation at another visual angle of the utility model embodiment concrete application.
Reference in figure:
1st, the first positioning timber;2nd, the second positioning timber;3rd, the 3rd positioning timber;4th, the 4th positioning timber;5th, first apply
Work cotton rope;6th, the second construction cotton rope;7th, foundation bolt;8th, template.
Embodiment
Embodiment of the present utility model is described in detail below, but the utility model can be defined by the claims
Implement with the multitude of different ways of covering.
It refer to shown in Fig. 1 and Fig. 2, the utility model embodiment provides pre-embedded anchoring bolts of being constructed on a kind of isolated footing
Positioner, including:The predetermined altitude laid by theodolite and the first positioning timber 1, second spaced a predetermined distance is determined
The position positioning positioning timber 4 of timber 3 and the 4th of timber the 2, the 3rd, between the first positioning timber 1 and the 3rd positioning timber 3
The first construction cotton rope 5 is connected, the construction cotton rope 6 of connection second between the second positioning timber 2 and the 4th positioning timber 4,
The first construction cotton rope 5 and the described second construction intersecting vertical of cotton rope 6;The foundation bolt 7 includes multiple, multiple lower margin spiral shells
Bolt 7 is centrally located at the first construction cotton rope 5 and the described second construction cotton rope 6 crosspoint, the top of foundation bolt 7 and institute
The height that the first construction cotton rope 5 is stated with the described second construction cotton rope 6 crosspoint is flushed.
Positioned by the positioner, pre-buried foundation bolt construction precision is high, and axial dimension and absolute altitude can control to arrive
Zero error.The steel member of subsequent construction, is easily installed, and speed of application is faster.
The foundation bolt 7 is arranged in template 8, and is fixed by stirrup.The foundation bolt 7 is adjacent including four
The point midway of the line of foundation bolt 7 is on the described first construction construction cotton rope 6 of cotton rope 5 or second.Poured in the template 8
The concrete of the fixed foundation bolt 7.
The operation principle of the utility model embodiment is that as Figure 1-Figure 2, the utility model embodiment provides one kind
The positioner for pre-embedded anchoring bolts of being constructed on isolated footing, first, lays four in basic surrounding theodolite and is mutually perpendicular to
Positioning timber (first positioning timber 1, second positioning timber the 2, the 3rd positioning timber 3 and the 4th positioning timber 4), pull on construction
Cotton rope (the first construction construction of cotton rope 5 and second cotton rope 6).First construction cotton rope 5 and second construction cotton rope 6 and pre-embedded anchoring bolts
Orientation axis it is consistent.Fig. 2 is the altitude location figure of this location technology, is applied the first construction cotton rope 5 with second with spirit level
It is high consistent with the top mark of foundation bolt 7 that the height of work cotton rope 6 is set.
Before casting concrete, foundation bolt 7 is fixed on location-plate with stirrup, is placed in template 8, mould is fixed on flitch
On plate 7, highly concordant with the second construction cotton rope 6 with the first construction cotton rope 5, the line midpoint per adjacent two foundation bolts 7 is just
Fall well on the first construction construction cotton rope 6 of cotton rope 5 or second, the early stage positioning of pre-embedded anchoring bolts 7 is just completed.
During casting concrete, the foundation bolt 7 fixed may be shifted, so, after concreting, it is necessary to enter immediately
Row is repositioned, it is ensured that finished product after concreting basis, the height of foundation bolt 7 still with the first construction cotton rope 5 and the
Two construction cotton ropes 6 are concordant, and the line midpoint of every two foundation bolts 7 still just falls constructs in the first construction cotton rope 5 or second
On cotton rope 6.Occur to handle before concrete setting during error, the method for processing is:If height and construction cotton rope are uneven
Together, just when concrete does not solidify, raise or reduce the heights of roofs of foundation bolt 7;It is also when mixed if axial location has error
Solidifying soil is not solidified, and the line midpoint of every two bolts is adjusted to overlap with the second construction cotton rope 6 with the first construction cotton rope 5, so,
Pre-buried foundation bolt 7 is with regard to precise positioning, and after concrete formation, pre-buried foundation bolt 7 has not a particle of error.
Preferred embodiment of the present utility model is these are only, the utility model is not limited to, for this area
Technical staff for, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle within,
Any modification, equivalent substitution and improvements made etc., should be included within protection domain of the present utility model.
Claims (4)
1. a kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing, it is characterised in that including:
The predetermined altitude laid by theodolite and the first positioning timber (1) spaced a predetermined distance, the second positioning timber (2),
3rd positioning timber (3) and the 4th positioning timber (4), between the first positioning timber (1) and the 3rd positioning timber (3)
The construction cotton rope of connection first (5), the second construction is connected between the second positioning timber (2) and the described 4th positioning timber (4)
Cotton rope (6), the first construction cotton rope (5) and described second construction cotton rope (6) intersecting vertical;
The foundation bolt (7) includes multiple, and multiple foundation bolts (7) are centrally located at the first construction cotton rope (5) and institute
Second construction cotton rope (6) crosspoint is stated, foundation bolt (7) top is applied with the described first construction cotton rope (5) with described second
The height in work cotton rope (6) crosspoint is flushed.
2. the positioner for pre-embedded anchoring bolts of being constructed on isolated footing according to claim 1, it is characterised in that described
Foundation bolt (7) is arranged in template (8), and is fixed by stirrup.
3. the positioner for pre-embedded anchoring bolts of being constructed on isolated footing according to claim 2, it is characterised in that described
Foundation bolt (7) includes four, and the point midway of adjacent foundation bolt (7) line is in the described first construction cotton rope (5) or second
Construct on cotton rope (6).
4. the positioner for pre-embedded anchoring bolts of being constructed on isolated footing according to claim 3, it is characterised in that described
The concrete of the fixed foundation bolt (7) is poured in template (8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720033398.8U CN206396782U (en) | 2017-01-11 | 2017-01-11 | A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720033398.8U CN206396782U (en) | 2017-01-11 | 2017-01-11 | A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206396782U true CN206396782U (en) | 2017-08-11 |
Family
ID=59513069
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720033398.8U Expired - Fee Related CN206396782U (en) | 2017-01-11 | 2017-01-11 | A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206396782U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677201A (en) * | 2017-01-14 | 2017-05-17 | 山东飞越钢结构工程有限公司 | Positioning method of built-in foundation bolts constructed on independent foundation |
-
2017
- 2017-01-11 CN CN201720033398.8U patent/CN206396782U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677201A (en) * | 2017-01-14 | 2017-05-17 | 山东飞越钢结构工程有限公司 | Positioning method of built-in foundation bolts constructed on independent foundation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104895092B (en) | The method that a kind of interim lattice column of inner support is used as permanent structure post | |
CN209636847U (en) | A kind of adjustable tower crane built-in fitting accurate positioning tool | |
CN102162305B (en) | Construction process for installing elastic slippage shock isolation support | |
CN102943565B (en) | Construction method of large-sized arc-shaped wall | |
CN100476142C (en) | Construction method for combined V-shape steel pipe concrete pile | |
CN103993597B (en) | A kind of high accuracy vertical pillars stake construction method | |
CN103590603B (en) | Large span multi-curvature shell structure of reinforced concrete method | |
CN103469806A (en) | Construction method for replacing brick forming die with prefabricated concrete foundation bearing platform side die | |
CN103526930A (en) | Multi-directional intersection reinforced bare concrete inclined column construction method | |
CN105421476B (en) | The construction method and mounting structure of tower crane built-in fitting are installed on raft foundation | |
CN106592990A (en) | Prefabricated building foundation column bar precise positioning tool and positioning method | |
CN206127746U (en) | Isolation bearing handles accurate location structure of pre -buried steel sheet in back | |
CN105696800A (en) | Temporary fixed sleeve frame for preventing relative displacement generated during construction of steel-structured anchor bolts | |
CN104897143B (en) | A kind of cylinder forced centering observation pier and its method for embedding | |
CN103469732B (en) | Construction method of preformed holes for foundation bolts of bridge support | |
CN113202222A (en) | Construction method for assembled type superposed beam slab | |
CN207047881U (en) | The prefabricated cushion cap of core is filled with joint bar | |
CN206396782U (en) | A kind of positioner for pre-embedded anchoring bolts of being constructed on isolated footing | |
CN114809029A (en) | High cutting slope anchor rod frame beam coupling construction method | |
CN107299764A (en) | A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar | |
CN106759943A (en) | A kind of pre-assembled Anchor Bolts in Steel Column Bases structure | |
CN104264682A (en) | Anchor traction wall protection pile base layer concrete beam support pouring technology | |
CN108756243A (en) | Girder steel and concrete ring beam, the structure-integrated construction of concrete floor | |
CN205713091U (en) | A kind of diagonal column mold plate system | |
CN104947853B (en) | A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170811 Termination date: 20190111 |