CN107299764A CN201710606227.4A CN201710606227A CN107299764A CN 107299764 A CN107299764 A CN 107299764A CN 201710606227 A CN201710606227 A CN 201710606227A CN 107299764 A CN107299764 A CN 107299764A
Authority
CN
China
Prior art keywords
positioning
upright post
horizontal
vertical
post main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710606227.4A
Other languages
Chinese (zh)
Inventor
赫英男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201710606227.4A priority Critical patent/CN107299764A/en
Publication of CN107299764A publication Critical patent/CN107299764A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, including Horizontal concrete layer and plant in Horizontal concrete layer horizontal reinforcement, the concrete apparatus for being conveniently constructed the positioning of post cage bar is vertical column structure, it includes upright post main and the hole in upright post main, the upright post main is fixed with horizontal reinforcement, its underpart is located in Horizontal concrete layer, and described hole is implanted into vertical reinforcing bar, and the upright post main top has poured secondary constructional column.Construction method is simple to operate in technical scheme, vertical columns main body and reserving hole only need to be increased before Horizontal concrete layer is poured, extensive work is reduced during the secondary constructional column of construction in later period, construction period is reduced while improving construction quality.

Description

A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar
Technical field
The invention belongs to construction improved device, and in particular to a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar And construction method.
Background technology
At present, in traditional constructional column cage bar position fixing process, operating personnel is on Horizontal concrete layer during boring positioning Random drilling, not only can not accurately steel planting, and it is difficult to ensure that quality, while gluing is not added manually and not Environmental protection, the waste of artificial and material for causing constructional column rebar-planting quality to decline and brought.
In addition, with duration and the demand more and more higher of construction quality, rapid construction simultaneously ensures that construction quality is gone for building Industry common problem, the construction of secondary constructional column is difficult to complete to coordinate construction, it is necessary to one with Horizontal concrete layer in reality construction Kind of device to reserve the construction location of secondary constructional column with solve to need during traditional secondary Constructional Col-umn Construction drilling, gluing, The complicated process for being difficult to ensure construction quality again such as bar planting.
The problem to be solved in the present invention is the coagulation that matching hole is made according to the specification of secondary constructional column cage bar Soil protection block is a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, and the fast thickness of protection is determined further according to on-site actual situations Degree, then by concrete protective block before concreting floor, is embedded into the position of the secondary constructional column of design drawing requirement, Beam main tendon and concrete protective block are used into overlap welding, it is ensured that concrete protective exceeds plate face after casting concrete soon, so Drilled in secondary structure and when being put into reinforcing bar, can fast and accurately insertion configuration post cage bar, reduce people while improving quality Power and material resources.
The content of the invention
The technical problems to be solved by the invention are:For provide it is a kind of be conveniently constructed post cage bar positioning concrete apparatus and Construction method.
In order to solve the above-mentioned technical problem, the invention discloses a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, Including Horizontal concrete layer and plant in Horizontal concrete layer horizontal reinforcement, it is described be conveniently constructed post cage bar positioning concrete dress Vertical column structure is set to, it includes upright post main and the hole in upright post main, the upright post main is consolidated with horizontal reinforcement Fixed, its underpart is located in Horizontal concrete layer, and described hole is implanted into vertical reinforcing bar, and the upright post main top has poured secondary Constructional column.
It is preferred that, the upright post main side is provided with positioning bar.
It is preferred that, the positioning bar at least one.
It is preferred that, the positioning bar is located at the vertical side of upright post main two.
It is preferred that, the upright post main section is square or hexagon or circle.
The invention also discloses a kind of construction method for the concrete apparatus for being conveniently constructed the positioning of post cage bar, including following step Suddenly:
Step one:Make the concrete apparatus for being conveniently constructed the positioning of post cage bar
Upright post main and hole are made according to construction demand;
Step 2:Vertical columns main body and horizontal reinforcement
Upright post main and horizontal reinforcement are fixed before Horizontal concrete layer is poured, wherein upright post main bottom is located at level In concrete layer, the upright post main top remains for pouring secondary constructional column in advance;
Step 3:Pour Horizontal concrete layer
Filler, after-pouring Horizontal concrete layer are placed in described hole;
Step 4:It is implanted into vertical reinforcing bar
With filler in vertical reinforcing bar replacement step three, and set up vertical structure template;
Step 5:Pour secondary constructional column
Secondary constructional column is poured in template, vertical structure template is dismantled after secondary constructional column solidifies.
It is preferred that, filler is vertical reinforcing bar in the step 3.
It is preferred that, fixed in the step 2 by positioning bar with horizontal reinforcement.
Compared with prior art, the present invention can obtain following technique effect:
1. technical scheme efficiency high, positioning are accurate, plasticity is good, without gluing, easy construction and cost is low It is honest and clean.
2. the concrete that technical scheme makes matching hole according to the specification of secondary constructional column cage bar is protected Protecting block is a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, and the fast thickness of protection is determined further according to on-site actual situations, Then by concrete protective block before concreting floor, the position of the secondary constructional column of design drawing requirement is embedded into, will Beam main tendon and concrete protective block use overlap welding, it is ensured that concrete protective exceeds plate face after casting concrete soon, so exists Secondary structure drills and when being put into reinforcing bar, can fast and accurately insertion configuration post cage bar, reduce manpower while improving quality And material resources.
3. positioning bar plays a part of fixed position in technical scheme.
4. upright post main section described in technical scheme is square or hexagon or circle, that is, difference is adapted to The need for vertical secondary constructional column.
5. construction method is simple to operate in technical scheme, only it need to increase solid before Horizontal concrete layer is poured Determine upright post main and reserving hole, reduce extensive work during the secondary constructional column of construction in later period, improve construction matter Construction period is reduced while amount.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, come for those of ordinary skill in the art Say, on the premise of not paying creative work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is upright post main schematic perspective view.
Fig. 2 is that upright post main fixes schematic diagram with horizontal reinforcement.
Fig. 3 is that Horizontal concrete layer pours schematic diagram.
Fig. 4 is to be implanted into vertical reinforcing bar schematic diagram in hole
Wherein:1. upright post main, 2. holes, 3. horizontal reinforcements, 4. vertical reinforcing bars, 5. positioning bars, 6. Horizontal concretes layer.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
Below in conjunction with the accompanying drawings and specific embodiment to the present invention application principle be further described.
Embodiment 1
As shown in Figures 1 to 4, a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, including Horizontal concrete 6 He of layer Plant in the horizontal reinforcement 3 of Horizontal concrete layer 6, the concrete apparatus for being conveniently constructed the positioning of post cage bar is vertical column structure, It includes upright post main 1 and the hole 2 in upright post main 1, and the upright post main 1 is fixed with horizontal reinforcement 3, its underpart position In in Horizontal concrete layer 6, described hole 2 is implanted into vertical reinforcing bar 4, and the top of upright post main 1 has poured secondary constructional column.
Wherein:The side of upright post main 1 is provided with positioning bar 5;, the positioning bar 5 at least one;The positioning bar 5 are located at 1 liang of vertical side of upright post main;The section of upright post main 1 is square.
Embodiment 2
As shown in Figures 1 to 4, a kind of construction method for the concrete apparatus for being conveniently constructed the positioning of post cage bar, including following Step:
Step one:Make the concrete apparatus for being conveniently constructed the positioning of post cage bar
Upright post main 1 and hole 2 are made according to construction demand;
Step 2:Vertical columns main body 1 and horizontal reinforcement 3
Upright post main 1 and horizontal reinforcement 3 are fixed before Horizontal concrete layer 6 is poured, the wherein bottom of upright post main 1 is located at In Horizontal concrete layer 6, the top of upright post main 1 remains for pouring secondary constructional column in advance;
Step 3:Pour Horizontal concrete layer 6
Filler, after-pouring Horizontal concrete layer 6 are placed in described hole 2;
Step 4:It is implanted into vertical reinforcing bar 4
With filler in the vertical replacement step three of reinforcing bar 4, and set up vertical structure template;
Step 5:Pour secondary constructional column
Secondary constructional column is poured in template, vertical structure template is dismantled after secondary constructional column solidifies.
Wherein:Filler is vertical reinforcing bar 4 in the step 3, passes through positioning bar 5 and horizontal reinforcement 3 in the step 2 It is fixed.
As the deformation of embodiment 1 and embodiment 2, the section of upright post main 1 is hexagon or circle.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit is required rather than described above is limited, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.Any reference in claim should not be considered as to the claim involved by limitation.
Moreover, it will be appreciated that although the present specification is described in terms of embodiments, not each embodiment is only wrapped Containing an independent technical scheme, this narrating mode of specification is only that for clarity, those skilled in the art should Using specification as an entirety, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art It may be appreciated other embodiment.

Claims (8)

1. a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar, including Horizontal concrete layer and are planted in Horizontal concrete at (6) The horizontal reinforcement (3) of layer (6), it is characterised in that:The concrete apparatus for being conveniently constructed the positioning of post cage bar is vertical column structure, It includes upright post main (1) and the hole (2) in upright post main (1), and the upright post main (1) is solid with horizontal reinforcement (3) Fixed, its underpart is located in Horizontal concrete layer (6), and described hole (2) is implanted on vertical reinforcing bar (4), the upright post main (1) Portion has poured secondary constructional column.
2. a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar according to claim 1, it is characterised in that:It is described vertical Post main body (1) is provided with positioning bar (5) sideways.
3. a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar according to claim 2, it is characterised in that:It is described fixed Position muscle (5) at least one.
4. a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar according to claim 2, it is characterised in that:It is described fixed Position muscle (5) is located at the vertical side of upright post main (1) two.
5. a kind of concrete apparatus for being conveniently constructed the positioning of post cage bar according to claim 1, it is characterised in that:It is described vertical Post main body (1) section is square or hexagon or circle.
6. a kind of construction of concrete apparatus for being conveniently constructed the positioning of post cage bar according to any one of claim 1 to 5 Method, it is characterised in that comprise the following steps:
Step one:Make the concrete apparatus for being conveniently constructed the positioning of post cage bar
Upright post main (1) and hole (2) are made according to construction demand;
Step 2:Vertical columns main body (1) and horizontal reinforcement (3)
Upright post main (1) and horizontal reinforcement (3) are fixed before Horizontal concrete layer (6) is poured, wherein upright post main (1) bottom In Horizontal concrete layer (6), upright post main (1) top remains for pouring secondary constructional column in advance;
Step 3:Pour Horizontal concrete layer (6)
Filler, after-pouring Horizontal concrete layer (6) are placed in described hole (2);
Step 4:It is implanted into vertical reinforcing bar (4)
With filler in vertical reinforcing bar (4) replacement step three, and set up vertical structure template;
Step 5:Pour secondary constructional column
Secondary constructional column is poured in template, vertical structure template is dismantled after secondary constructional column solidifies.
7. construction method according to claim 6, it is characterised in that:Filler is vertical reinforcing bar (4) in the step 3.
8. according to construction method according to claim 6, it is characterised in that:In the step 2 by positioning bar (5) with Horizontal reinforcement (3) is fixed.
CN201710606227.4A 2017-07-24 2017-07-24 A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar Pending CN107299764A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710606227.4A CN107299764A (en) 2017-07-24 2017-07-24 A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710606227.4A CN107299764A (en) 2017-07-24 2017-07-24 A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar

Publications (1)

Publication Number Publication Date
CN107299764A true CN107299764A (en) 2017-10-27

Family

ID=60134479

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710606227.4A Pending CN107299764A (en) 2017-07-24 2017-07-24 A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar

Country Status (1)

Country Link
CN (1) CN107299764A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
CN109024912A (en) * 2018-08-02 2018-12-18 中国十七冶集团有限公司 It is a kind of to prevent constructional column embedded ribs from falling off and accurate pre-buried device and construction method
CN110485634A (en) * 2019-08-16 2019-11-22 广西建工集团第五建筑工程有限责任公司 Constructional column top rebars pre-buried structure component and its method for constructional column top rebars installation
CN115467551A (en) * 2022-09-19 2022-12-13 中国一冶集团有限公司 Reinforced concrete deep hole structure integral type bar planting equipment and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200323939Y1 (en) * 2003-06-03 2003-08-21 (주)한도엔지니어링 Steel reinforcing Fixture
KR200323938Y1 (en) * 2003-06-03 2003-08-21 (주)한도엔지니어링 Arranging Structure of steel for reinforced concrete
KR100832848B1 (en) * 2007-06-01 2008-05-28 원용석 Method for constructing pier and concrete permanent form applied to it
CN201567584U (en) * 2009-12-02 2010-09-01 张吉华 Prefabricated construction reinforced concrete cushion cap foundation
CN103161313A (en) * 2013-03-14 2013-06-19 中国华冶科工集团有限公司 Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN203741997U (en) * 2014-03-04 2014-07-30 北京天恒建设工程有限公司 Steel bar pre-burying and connecting structure of beam and construction column
CN205476075U (en) * 2016-04-02 2016-08-17 内蒙古建筑职业技术学院 Multi -functional building structure post
CN106284846A (en) * 2016-09-28 2017-01-04 西安建筑科技大学 A kind of assembled steel reinforced concrete-constituted pile and utilize the system of this post, construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200323939Y1 (en) * 2003-06-03 2003-08-21 (주)한도엔지니어링 Steel reinforcing Fixture
KR200323938Y1 (en) * 2003-06-03 2003-08-21 (주)한도엔지니어링 Arranging Structure of steel for reinforced concrete
KR100832848B1 (en) * 2007-06-01 2008-05-28 원용석 Method for constructing pier and concrete permanent form applied to it
CN201567584U (en) * 2009-12-02 2010-09-01 张吉华 Prefabricated construction reinforced concrete cushion cap foundation
CN103161313A (en) * 2013-03-14 2013-06-19 中国华冶科工集团有限公司 Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN203741997U (en) * 2014-03-04 2014-07-30 北京天恒建设工程有限公司 Steel bar pre-burying and connecting structure of beam and construction column
CN205476075U (en) * 2016-04-02 2016-08-17 内蒙古建筑职业技术学院 Multi -functional building structure post
CN106284846A (en) * 2016-09-28 2017-01-04 西安建筑科技大学 A kind of assembled steel reinforced concrete-constituted pile and utilize the system of this post, construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
CN109024912A (en) * 2018-08-02 2018-12-18 中国十七冶集团有限公司 It is a kind of to prevent constructional column embedded ribs from falling off and accurate pre-buried device and construction method
CN110485634A (en) * 2019-08-16 2019-11-22 广西建工集团第五建筑工程有限责任公司 Constructional column top rebars pre-buried structure component and its method for constructional column top rebars installation
CN115467551A (en) * 2022-09-19 2022-12-13 中国一冶集团有限公司 Reinforced concrete deep hole structure integral type bar planting equipment and method
CN115467551B (en) * 2022-09-19 2023-08-29 中国一冶集团有限公司 Reinforced concrete deep hole structure integral type bar planting device and method

Similar Documents

Publication Publication Date Title
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN107299764A (en) A kind of concrete apparatus and construction method for being conveniently constructed the positioning of post cage bar
CN104695557B (en) Steel structure building construction method for one-step pre-burying of foundation bolts
CN103132537A (en) Steel latticed column homocentric-square-shaped concrete bearing platform combination type tower crane base structure and construction method
CN105155853B (en) A kind of high-rise residential building reinforced concrete positioning construction process
CN106401207A (en) Superimposed connection structure for additionally arranging column foundation on existing building and construction method of superimposed connection structure
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN105421476B (en) The construction method and mounting structure of tower crane built-in fitting are installed on raft foundation
CN103526930A (en) Multi-directional intersection reinforced bare concrete inclined column construction method
CN208068549U (en) A kind of prefabricated piping lane segment framework of steel reinforcement installation molding bed rack
CN107083804A (en) A kind of wall structure post joint bar construction method
CN207277691U (en) A kind of concrete column position apparatus for form
CN206408515U (en) Precast pier section assembling structure
CN102733307A (en) Method for constructing cast-in-place beam falsework
CN106480827A (en) A kind of construction technology of segmented casting concrete box beam
CN107489284A (en) Basement locally increases the construction method in deeper subsurface garage newly
CN206189607U (en) Rag bolt location structure
CN203034476U (en) Tower crane base structure in type of combination of steel latticework columns and concrete bearing platform shaped like Chinese character 'hui'
CN204825945U (en) A fixture for fixing buried bolt in advance
CN103352568A (en) Method for building constructional column on foundation pad
CN207314523U (en) A kind of Novel steel-mixed bean column node constructing structure
CN106401276A (en) Construction method for wall column binding bars of frame type building block enclosing wall
CN205975995U (en) Cast -in -place concrete floor indent steel tube frame
CN203603525U (en) Reinforcing structure with clamp plate girder and clamp plate column externally arranged for stone structure
CN103498572B (en) The construction method of the additional clamping plate beam of stone structure and clamping plate post ruggedized construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171027

RJ01 Rejection of invention patent application after publication