CN107724444A - 一种改进的大型发电机基础预埋钢管偏位校正方法 - Google Patents

一种改进的大型发电机基础预埋钢管偏位校正方法 Download PDF

Info

Publication number
CN107724444A
CN107724444A CN201711028493.XA CN201711028493A CN107724444A CN 107724444 A CN107724444 A CN 107724444A CN 201711028493 A CN201711028493 A CN 201711028493A CN 107724444 A CN107724444 A CN 107724444A
Authority
CN
China
Prior art keywords
steel tube
embedded steel
hole
sampling machine
core boring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711028493.XA
Other languages
English (en)
Inventor
彭宝安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Zexin Energy Technology Co Ltd
Original Assignee
Jingmen Chuangjia Machinery Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jingmen Chuangjia Machinery Technology Co Ltd filed Critical Jingmen Chuangjia Machinery Technology Co Ltd
Priority to CN201711028493.XA priority Critical patent/CN107724444A/zh
Publication of CN107724444A publication Critical patent/CN107724444A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明一种改进的大型发电机基础预埋钢管偏位校正方法主要用于大型发电机基础预埋钢管偏位校正使用,它大大缩短了工期,而且费用低;其方法是:先在发电机基础顶面测量放线,标识出预埋钢管的正确位置,再选用钻芯取样机进行钻进施工,钻芯取样机钻头外径比预埋钢管B的外径大40毫米左右,用钻芯取样机钻出一个比预埋钢管B的外径大40毫米左右的孔,再用专用钻头在孔的内壁上切削出多个圆环槽,然后在孔内重新安装新的预埋钢管B,并对重新安装的预埋钢管B进行位置与垂直度校正并将预埋钢管B进行临时固定,最后用工程结构胶回灌预埋钢管B与孔之间的空隙,待工程结构胶达到100%强度后拆除临时固定,可以进行正常的发电机工装了。

Description

一种改进的大型发电机基础预埋钢管偏位校正方法
技术领域
本发明主要用于大型发电机基础预埋钢管偏位校正使用。
背景技术
我单位大型发电机基础预埋钢管由于在土建施工过程中偏位,水平方向及垂直度均有偏差,导致发电机定子及转子轴承座无法安装,如果采用修改定子底板及转子轴承座底板螺栓孔位置的方法不但要延迟工期一个多月,而且上述构件体积大,运输、加工困难。
发明内容
本发明解决了上述问题,它大大缩短了工期,而且费用低,仅仅是修改底板螺栓孔位置方案的十分之一;发电机基础预埋钢管偏位校正的方法是:先在发电机基础顶面测量放线,标识出需重新安装新的预埋钢管B(4)的正确位置,然后选用钻芯取样机进行钻进施工,钻芯取样机需满足能钻进2000毫米以上孔深的要求,钻芯取样机钻头外径比预埋钢管B(4)的外径大40毫米左右,用钻芯取样机钻出一个比预埋钢管B(4)的外径大40毫米左右的孔(2),孔深2000毫米,此时孔(2)处的混凝土、基础钢筋及原预埋的预埋钢管A(3)一并取出,预埋钢管A(3)作废,在钻进过程中需严格控制钻杆的垂直度,再用专用钻头在孔(2)的内壁上切削出多个圆环槽(8),然后在孔(2)内重新安装新的预埋钢管B(4),并对新安装的预埋钢管B(4)进行位置与垂直度校正并将预埋钢管B(4)进行临时固定,预埋钢管B(4)的外壁焊接有多个箍筋(6)及纵向锚固筋(7),再用工程结构胶(5)回灌预埋钢管B(4)与孔(2)之间的空隙,待工程结构胶(5)达到100%强度后拆除临时固定,可以进行正常的发电机工装了。
附图说明
附图标记说明:1-发电机基础,2-孔,3-预埋钢管A,4-预埋钢管B,5-工程结构胶,6-箍筋,7-纵向锚固筋,8-圆环槽。
图1是在发电机基础上新钻的孔及原预埋钢管A偏位的立面示意图。
图2是重新安装的预埋钢管B的立面示意图。
图3是工程结构胶灌注完成后预埋钢管B的立面示意图。
图4是重新安装的预埋钢管B与箍筋、纵向锚固筋的立面示意图。
具体实施方式
发明内容已详细说明了本发明的具体实施方式,这里不再重复;需说明:本发明所述的工程结构胶5是建筑工程领域常用的结构加固胶,它与钢筋和混凝土有着良好的粘接性能且工程结构胶5本身的强度也非常高;孔2的直径比预埋钢管B4的外径大40毫米左右,是为了保证预埋钢管B4在孔2内有位置及垂直度调整的余地;在孔2的内壁上切削出多个圆环槽8,这一方案是为了增加工程结构胶5与孔2内壁的结合强度。

Claims (1)

1.一种改进的大型发电机基础预埋钢管偏位校正方法,其施工方法是:先在发电机基础顶面测量放线,标识出需重新安装新的预埋钢管B(4)的正确位置,然后选用钻芯取样机进行钻进施工,钻芯取样机需满足能钻进2000毫米以上孔深的要求,钻芯取样机钻头外径比预埋钢管B(4)的外径大40毫米左右,用钻芯取样机钻出一个比预埋钢管B(4)的外径大40毫米左右的孔(2),孔深2000毫米,此时孔(2)处的混凝土、基础钢筋及原预埋的预埋钢管A(3)一并取出,预埋钢管A(3)作废,在钻进过程中需严格控制钻杆的垂直度,再用专用钻头在孔(2)的内壁上切削出多个圆环槽(8),然后在孔(2)内重新安装新的预埋钢管B(4),并对新安装的预埋钢管B(4)进行位置与垂直度校正并将预埋钢管B(4)进行临时固定,预埋钢管B(4)的外壁焊接有多个箍筋(6)及纵向锚固筋(7),再用工程结构胶(5)回灌预埋钢管B(4)与孔(2)之间的空隙,待工程结构胶(5)达到100%强度后拆除临时固定,可以进行正常的发电机工装了。
CN201711028493.XA 2017-10-29 2017-10-29 一种改进的大型发电机基础预埋钢管偏位校正方法 Pending CN107724444A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711028493.XA CN107724444A (zh) 2017-10-29 2017-10-29 一种改进的大型发电机基础预埋钢管偏位校正方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711028493.XA CN107724444A (zh) 2017-10-29 2017-10-29 一种改进的大型发电机基础预埋钢管偏位校正方法

Publications (1)

Publication Number Publication Date
CN107724444A true CN107724444A (zh) 2018-02-23

Family

ID=61203135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711028493.XA Pending CN107724444A (zh) 2017-10-29 2017-10-29 一种改进的大型发电机基础预埋钢管偏位校正方法

Country Status (1)

Country Link
CN (1) CN107724444A (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11336457A (ja) * 1998-05-22 1999-12-07 Takenaka Komuten Co Ltd リブ付き場所打ちコンクリート杭の拡径掘削方法及び拡径掘削機
JP2000001849A (ja) * 1998-06-12 2000-01-07 Geotop Corp 現場打ち節杭
JP2003278152A (ja) * 2002-03-25 2003-10-02 Nippon Steel Corp 異径断面杭基礎工法及びその築造工法
KR101024259B1 (ko) * 2010-06-07 2011-03-29 주식회사 하이드로코리아 파일두부 브라켓을 이용한 가설교량 시공방법
CN203176644U (zh) * 2013-04-02 2013-09-04 中国十七冶集团有限公司 地脚螺栓标高超差的增高装置
CN104047230A (zh) * 2014-06-26 2014-09-17 葛洲坝集团项目管理有限公司 下承式钢管拱混凝土简支梁系杆拱桥吊杆预埋管偏位的处理方法
CN105220892A (zh) * 2015-10-19 2016-01-06 长春轨道客车股份有限公司 预埋工字梁位置偏差的补救方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11336457A (ja) * 1998-05-22 1999-12-07 Takenaka Komuten Co Ltd リブ付き場所打ちコンクリート杭の拡径掘削方法及び拡径掘削機
JP2000001849A (ja) * 1998-06-12 2000-01-07 Geotop Corp 現場打ち節杭
JP2003278152A (ja) * 2002-03-25 2003-10-02 Nippon Steel Corp 異径断面杭基礎工法及びその築造工法
KR101024259B1 (ko) * 2010-06-07 2011-03-29 주식회사 하이드로코리아 파일두부 브라켓을 이용한 가설교량 시공방법
CN203176644U (zh) * 2013-04-02 2013-09-04 中国十七冶集团有限公司 地脚螺栓标高超差的增高装置
CN104047230A (zh) * 2014-06-26 2014-09-17 葛洲坝集团项目管理有限公司 下承式钢管拱混凝土简支梁系杆拱桥吊杆预埋管偏位的处理方法
CN105220892A (zh) * 2015-10-19 2016-01-06 长春轨道客车股份有限公司 预埋工字梁位置偏差的补救方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
席浩等: "《水利水电工程施工技术全书-第3卷-混凝土工程-第7册-混凝土施工》", 31 July 2016, 中国水利水电出版社 *
胡波等: "非能动核电厂一回路核辅助设备安装方式探讨", 《机械工程师》 *

Similar Documents

Publication Publication Date Title
CN103821520B (zh) 固定矿山立井井筒装备的方法
JP4375733B2 (ja) 鋼管打設工法
JP6296867B2 (ja) 層別沈下計の設置方法および層別沈下計測システム
CN104141318A (zh) 一种大直径钢管柱柱脚安装施工方法
CN105927254A (zh) 一种暗挖隧道拱顶坍塌应急装置及使用方法
US10106976B2 (en) Method for producing a reinforced structure in the ground
CN203546728U (zh) 一种改进后逆作钢管柱的安装固定装置
JP6163374B2 (ja) 基礎杭及び基礎杭施工方法
CN108005392A (zh) 一种装配式混凝土剪力墙精确定位装置及其安装方法
CN107724444A (zh) 一种改进的大型发电机基础预埋钢管偏位校正方法
KR20120130589A (ko) 기존 건축물의 기둥 상부를 보강하여 설치한 반력틀을 이용한 말뚝기초 시공방법
CN106087991A (zh) 桩顶标高在自然地面以下的挖孔桩施工方法
CN107724417A (zh) 一种大型发电机基础预埋钢管偏位校正方法
JP5814816B2 (ja) アンカーボルト施工方法
JP2019027037A (ja) 基礎構造、鋼管杭の杭頭構造、及び基礎構造の施工方法
CN109441352A (zh) 一种用于钻孔角度控制的装置
JP2015074881A (ja) 基礎杭施工方法及び基礎杭
CN108104488A (zh) 预埋地脚螺栓的安装方法
JP2017166203A (ja) 建物の水平修復工法および建物の水平修復構造
KR101138499B1 (ko) 마이크로 파일의 두부 정착방법 및 그 장치
CN108130896A (zh) 超深孔深部位移监测装置及其安装施工方法
CN107642207A (zh) 一种装配式楼梯连接装置
CN211850031U (zh) 一种混凝土墙体预埋支架槽道的安装装置
JP6362867B2 (ja) 建築物の補強方法
CN113529814A (zh) 百米级超深地下连续墙墙身质量钻孔取芯的检测方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
TA01 Transfer of patent application right

Effective date of registration: 20180223

Address after: 448000 Hubei province Jingmen city Jingmen high tech Zone and Duodao District Road No. 69

Applicant after: Hubei Zexin Energy Technology Co Ltd

Address before: 448000 Hubei Province, Jingmen city Dongbao District Road No. 1 Building 6 401 aquamarine

Applicant before: Jingmen Chuangjia Machinery Technology Co., Ltd.

TA01 Transfer of patent application right
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223

RJ01 Rejection of invention patent application after publication