CN107724384A - A kind of stake and stake attachment structure and its construction method - Google Patents

A kind of stake and stake attachment structure and its construction method Download PDF

Info

Publication number
CN107724384A
CN107724384A CN201711193799.0A CN201711193799A CN107724384A CN 107724384 A CN107724384 A CN 107724384A CN 201711193799 A CN201711193799 A CN 201711193799A CN 107724384 A CN107724384 A CN 107724384A
Authority
CN
China
Prior art keywords
stake
bolt
pile body
built
bottom plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711193799.0A
Other languages
Chinese (zh)
Other versions
CN107724384B (en
Inventor
郑俊杰
付海平
曹文昭
杨文钰
崔博
桂志鹏
饶钰琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong University of Science and Technology
Original Assignee
Huazhong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong University of Science and Technology filed Critical Huazhong University of Science and Technology
Priority to CN201711193799.0A priority Critical patent/CN107724384B/en
Publication of CN107724384A publication Critical patent/CN107724384A/en
Application granted granted Critical
Publication of CN107724384B publication Critical patent/CN107724384B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments

Abstract

The invention discloses a kind of stake and stake attachment structure and its construction method, including lower stake and upper stake, lower stake is connected with upper stake by connector, lower stake top portion is provided with several built-in bolt sleeves, upper stake bottom is fixedly connected with connector, connector includes upper head plate, bottom plate and ribbed stiffener, is connected between upper head plate and bottom plate by several ribbed stiffeners, and several bolts hole corresponding with built-in bolt sleeve position are provided with bottom plate;Connecting bolt is set to be threadedly connected to through the bolt hole on bottom plate in the built-in bolt sleeve corresponding to lower stake top portion, connecting bolt is used to realize that bottom plate is fixedly connected to realize that lower stake is interconnected and fixed with upper stake with the detachable of lower stake top portion.The present invention is connected by connecting bolt through the bolt hole on bottom plate and the built-in bolt sleeve in lower stake top portion, can realize the fixation that is vertically connected with of more piles successively, attachment structure is firm, attended operation is convenient.

Description

A kind of stake and stake attachment structure and its construction method
Technical field
The present invention relates to building pile foundation engineering construction technical field, more particularly to a kind of stake and stake attachment structure and its construction Method.
Background technology
Pile foundation can bear larger uplift load due to high capacity, and field, embankment work are built so as to be widely used in room Journey, retaining wall structure and transmission line foundation etc..Precast reinforced concrete pile can in factory's mass production, pile quality Lean on, be the larger pile foundation material of current usage amount.
In prefabricated pile basis work progress, the connection of stake and stake is an important construction technology, and it resists to foundation pile It is larger to pull out performance impact.Connection between stake and stake at present uses and is welded to connect or enters along pile body transverse direction built-in bolt sleeve mostly Row connection.When being welded to connect, because staff's level difference causes pile body quality of connection to differ greatly, construction technology quality is not Easy to control, pile crown welding quality is difficult to carry out mechanics detection.In addition, during Site Welding, uncertain factor is more, difficulty of construction Larger, welding interval is grown, and labor strength is big, and welding quality is difficult to control.Connected along pile body transverse direction built-in bolt sleeve When connecing, the bolt shearing resistance under uplift load effect, required Number of Bolts is more.Bolt collar is typically welded on pile crown end plate, its The more difficult accurate control in position, therefore stake side connecting plate upper bolt hole is usually slotted hole, so that bolt is connected with bolt collar.Should Under less uplift load, two may disengage for connection method, produce the amount of pulling out on certain, until on screw rod and connecting plate Uplift effect is just played when bolt hole is in close contact.
The content of the invention
For the shortcomings of the prior art, it is an object of the invention to provide a kind of stake and stake attachment structure and Its construction method, connector is provided with upper stake bottom, and lower stake top portion is provided with built-in bolt sleeve, passes through company between upper pile and lower pile Fitting is connected, and specific connected mode is:Connecting bolt passes through the bolt hole on bottom plate and the pre-embedded bolt in lower stake top portion Sleeve connection is fixed;According to above-mentioned connected mode, the fixation that is vertically connected with of more piles can be realized successively, attachment structure firmly, Attended operation is convenient;Built-in bolt sleeve of the present invention is positioned by locating end plate, and position is accurate, locating end plate flat shape And size is consistent with bottom plate, and bolt hole site on locating end plate and size are consistent with the bolt hole on bottom plate, Therefore it is difficult situation about being aligned when being connected in the absence of connecting bolt through the bolt hole on bottom plate with built-in bolt sleeve;Positioning end When plate mating connection bolt positions built-in bolt sleeve, not only make built-in bolt sleeve position accurate, it is thus also avoided that to take extra Measure prevents that built-in bolt sleeve blocks when pile concrete from pouring;The reliable in quality of connector, by connector when pile body is prefabricated Muscle is indulged with pile body to be connected.
The purpose of the present invention is achieved through the following technical solutions:
A kind of stake and stake attachment structure, including lower stake and upper stake, lower pile is connected with upper stake by connector, under described Stake top portion is provided with several built-in bolt sleeves, the built-in bolt sleeve nozzle plane and lower stake either flush;Upper pile Bottom is fixedly connected with connector, and the connector includes upper head plate, bottom plate and ribbed stiffener, the upper head plate and bottom plate phase Mutual parallel alignment, it is connected between the upper head plate and bottom plate by several ribbed stiffeners, if being provided with the bottom plate The dry bolt hole corresponding with built-in bolt sleeve position;Connecting bolt is set to be threadedly connected to through the bolt hole on bottom plate In built-in bolt sleeve corresponding to lower stake top portion, the connecting bolt is used to realize the detachable of bottom plate and lower stake top portion It is fixedly connected to realize that lower stake is interconnected and fixed with upper stake.
In order to which the present invention is better achieved, lower pile top surface is provided with locating end plate, be provided with the locating end plate with advance The corresponding positioning bolt hole in bolt collar position is buried, the positioning bolt hole is used for the pre-buried position for positioning built-in bolt sleeve Put.
Preferably, it is connected between the upper head plate and bottom plate of the connector by three ribbed stiffeners;Three add Cross section after strength rib is vertically fixed is in " ten " font.
Preferably, it is connected between the upper head plate and bottom plate of the connector by eight ribbed stiffeners;Eight add Strength rib cross section overall after vertically fixing is in " well " font.
Preferably, lower pile is fabricated with upper stake by armored concrete, the cross section of the locating end plate, under The cross section of stake and cross section three's shape, the size all same of upper stake.
Currently preferred lower pilework scheme is:Lower pile indulges muscle by pile body and forms pile body framework simultaneously with pile body stirrup It is fabricated to pile body framework casting concrete, the built-in bolt sleeve is anchored by welding anchor bar thereon, Or the built-in bolt sleeve is anchored by direct be welded to connect with the vertical muscle of lower stake.
Currently preferred upper pilework scheme is:Upper pile indulges muscle by pile body and forms pile body framework simultaneously with pile body stirrup It is fabricated to pile body framework casting concrete, the vertical muscle lower end bending of upper stake pile body is L-shaped so as to form L-shaped linkage section, described Connector upper head plate is welded to connect with L-shaped linkage section.
Preferably, the height of the ribbed stiffener is not less than 80mm, the thickness of the ribbed stiffener is not less than 6mm;On described The thickness of end plate and bottom plate is not less than 10mm.
Preferably, being provided with four built-in bolt sleeves at the top of lower pile, four built-in bolt sleeves are evenly distributed to be set It is placed in lower stake top portion;Four bolts hole are provided with the bottom plate, four positioning bolt holes are provided with the locating end plate, it is described Built-in bolt sleeve, bolt hole and positioning bolt hole, which correspond, to be set.
A kind of stake and stake connection construction method, its method are as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, it is fixed in the pile body framework top surface arrangement of lower stake Position end plate, connecting bolt is connected through the positioning bolt hole on locating end plate with built-in bolt sleeve, makes built-in bolt sleeve The pile body lower portion of lower stake is placed in, built-in bolt sleeve is anchored by welding anchor bar thereon;
B, disengaging oily substance, the disengaging oily substance are scribbled between locating end plate and the pile body framework top surface of lower stake Including used oil, casting concrete obtains the lower stake containing built-in bolt sleeve in the pile body framework of downward stake;By connecting bolt Depart from locating end plate from the pile body framework top surface of lower stake and take down;
C, muscle and pile body stirrup are indulged by pile body and form the pile body framework of upper stake, by upper stake indulge the bending of muscle lower end it is L-shaped from And L-shaped linkage section is formed, connector upper head plate is welded to connect with L-shaped linkage section, coagulation is poured in the pile body framework of upward stake Soil obtains the upper stake containing connector;The connector includes upper head plate, bottom plate and ribbed stiffener, the upper head plate and bottom plate It is aligned parallel to each other, is connected by several ribbed stiffeners between the upper head plate and bottom plate, is provided with the bottom plate Several bolts hole corresponding with built-in bolt sleeve position;Make connecting bolt through the bolt hole threaded connection on bottom plate In the built-in bolt sleeve corresponding to lower stake top portion, the connecting bolt is used to realize the detachable of bottom plate and lower stake top portion Formula is fixedly connected to realize that lower stake is interconnected and fixed with upper stake.
A kind of stake and stake connection construction method, its method are as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, it is fixed in the pile body framework top surface arrangement of lower stake Position end plate, connecting bolt is connected through the positioning bolt hole on locating end plate with built-in bolt sleeve, makes built-in bolt sleeve The pile body lower portion of lower stake is placed in, built-in bolt sleeve is directly indulged muscle with the pile body of lower stake and is welded and fixed;
B, disengaging oily substance, the disengaging oily substance are scribbled between locating end plate and the pile body framework top surface of lower stake Including used oil, it is L-shaped and form L-shaped linkage section that the pile body of lower stake lower end is indulged into muscle bending;Poured in the pile body framework of downward stake Build concrete and obtain the lower stake containing built-in bolt sleeve, connecting bolt and locating end plate are taken off from the pile body framework top surface of lower stake From taking down;
C, muscle and pile body stirrup are indulged by pile body and form the pile body framework of upper stake, by upper stake indulge the bending of muscle lower end it is L-shaped from And L-shaped linkage section is formed, connector upper head plate is welded to connect with L-shaped linkage section, coagulation is poured in the pile body framework of upward stake Soil obtains the upper stake containing connector;The connector includes upper head plate, bottom plate and ribbed stiffener, the upper head plate and bottom plate It is aligned parallel to each other, is connected by several ribbed stiffeners between the upper head plate and bottom plate, is provided with the bottom plate Several bolts hole corresponding with built-in bolt sleeve position;For hollow pile, upper head plate, bottom plate and locating end plate center Corresponding perforate, the center bore size of the center bore of upper head plate, the center bore of bottom plate and locating end plate is and hollow pile Hole it is in the same size;Connecting bolt is set to be threadedly connected to the pre-embedded bolt corresponding to lower stake top portion through the bolt hole on bottom plate In sleeve, the connecting bolt is used to realize that bottom plate is fixedly connected to realize lower stake and upper stake with the detachable of lower stake top portion It is interconnected and fixed.
The present invention compared with prior art, has advantages below and beneficial effect:
(1) present invention is provided with connector in upper stake bottom, and lower stake top portion is provided with built-in bolt sleeve, between upper pile and lower pile It is connected by connector, specific connected mode is:Connecting bolt is pre- through the bolt hole on bottom plate and lower stake top portion Bolt collar is buried to be connected.According to above-mentioned connected mode, the fixation that is vertically connected with of more piles, attachment structure can be realized successively Firmly, attended operation is convenient.
(2) built-in bolt sleeve of the present invention is positioned by locating end plate, and position is accurate.Locating end plate flat shape and Size is consistent with bottom plate, and bolt hole site on locating end plate and size are consistent with the bolt hole on bottom plate, therefore It is difficult situation about being aligned when being connected in the absence of connecting bolt through the bolt hole on bottom plate with built-in bolt sleeve.Locating end plate When mating connection bolt positions built-in bolt sleeve, not only make built-in bolt sleeve position accurate, it is thus also avoided that to take and additionally arrange Applying prevents that built-in bolt sleeve blocks when pile concrete from pouring.The reliable in quality of connector, when pile body is prefabricated by connector with Pile body is indulged muscle and is connected.
(3) connecting bolt resistance to plucking of the invention, not shearing resistance, the high capacity that connecting bolt plays, required connecting bolt And built-in bolt sleeve quantity is small.During live pile extension, only need to by connecting bolt through the bolt hole on connector bottom plate with it is pre- Bolt collar is buried to be connected, simple and quick, quality of connection is reliable, is not influenceed by extraneous factor, and construction quality is easy to control, And reduce labor strength, after pile extension can direct pile sinking, without waiting for greatly improving efficiency of construction.Two after pile extension It is in close contact, uplift load acts on lower bolt tension immediately, and two cannot come off, and greatly improve foundation pile extraction-resistant behavior.Pile sinking After the completion of, stake top has built-in bolt sleeve, and built-in bolt sleeve is connected with being machined with externally threaded reinforcing bar, the reinforcing bar and pile cap steel Muscle connect, after-pouring cushion cap concrete, so as to realize the connection of stake and cushion cap.
(4) present invention in pile crown welded reinforcement or need not cut pile crown at the scene, reduce and cut shadow of the stake to pile strength Ring, and reduce pile crown welded reinforcement or cut the engineering time that stake occupies;The invention provides a kind of excellent stake to be connected with stake Structure and connection method.
Brief description of the drawings
Fig. 1 is the structural representation that stake of the present invention is connected with stake;
Fig. 2 is connecting-piece structure schematic diagram of the present invention;
Fig. 3 is connector A-A diagrammatic cross-sections in Fig. 2;
Fig. 4 is the structural representation of locating end plate of the present invention.
Wherein, it is entitled corresponding to the reference in accompanying drawing:
1- built-in bolt sleeves, 2- connecting bolts, 3- connectors, 4- upper head plates, 5- bottom plates, 6- ribbed stiffeners, 7- bolts hole, 8- locating end plates, 9- positioning bolt holes.
Embodiment
The present invention is described in further detail with reference to embodiment:
Embodiment
As shown in Figure 1 to 4, a kind of stake and stake attachment structure, including lower stake and upper stake, the lower stake of the present embodiment is positioned at upper Stake lower section, lower stake and upper stake are fabricated by Reinforced Concrete Materials.Currently preferred lower stake, the shape of cross section of upper stake Unanimously, it is circular or square.Lower stake is connected with upper stake by connector 3, and lower stake top portion is provided with several built-in bolt sleeves 1, the nozzle plane of built-in bolt sleeve 1 and lower stake either flush.Upper stake bottom is fixedly connected with connector 3, and connector 3 includes upper End plate 4, bottom plate 5 and ribbed stiffener 6, upper head plate 4 are aligned parallel to each other with bottom plate 5, are passed through between upper head plate 4 and bottom plate 5 Several ribbed stiffeners 6 are connected, and several bolts hole 7 corresponding with the position of built-in bolt sleeve 1 are provided with bottom plate 5. Connecting bolt 2 is set to be threadedly connected to through the bolt hole 7 on bottom plate 5 in the built-in bolt sleeve 1 corresponding to lower stake top portion, even Connecting bolt 2 is used to realize that bottom plate 5 is fixedly connected to realize that lower stake and upper stake interconnection are solid with the detachable of lower stake top portion It is fixed.As shown in Figure 1 to 4, lower stake top portion is provided with four built-in bolt sleeves 1, four 1 evenly distributed settings of built-in bolt sleeve In lower stake top portion, the distance between the pile concrete surface of the outside of built-in bolt sleeve 1 away from lower stake is not less than 30mm.Lower stake top Face is provided with locating end plate 8, and the positioning bolt hole 9 corresponding with the position of built-in bolt sleeve 1 is provided with locating end plate 8, positions spiral shell Keyhole 9 is used for the pre-buried position for positioning built-in bolt sleeve 1.Four bolts hole 7 are provided with currently preferred bottom plate 5, it is fixed Four positioning bolt holes 9 are provided with the end plate 8 of position, built-in bolt sleeve 1, bolt hole 7 and positioning bolt hole 9, which correspond, to be set.
As shown in Figure 2 and Figure 3, it is connected between the upper head plate 4 and bottom plate 5 of connector 3 by three ribbed stiffeners 6.This Invention is welded at the position contacted between upper head plate 4, bottom plate 5 and three ribbed stiffeners 6, so as to form connector 3.Three Individual ribbed stiffener 6 be respectively longitudinal stiffener, the first transverse stiffener and the second transverse stiffener, first transverse stiffener with Second transverse stiffener linearly sets and is fixedly connected at left and right sides of longitudinal stiffener, the first transverse stiffener, the second horizontal stroke It is in " ten " font after being fixed to ribbed stiffener and longitudinal stiffener.May be used also between the upper head plate 4 and bottom plate 5 of connector 3 of the present invention To be connected by eight ribbed stiffeners 6.The position that the present invention will contact between upper head plate 4, bottom plate 5 and eight ribbed stiffeners 6 Welded, so as to form connector 3.Eight ribbed stiffeners 6 are respectively first longitudinal direction ribbed stiffener, second longitudinal direction ribbed stiffener, the One transverse stiffener A, the first transverse stiffener B, the first transverse stiffener C, the second transverse stiffener A, the second transverse stiffener B, the second transverse stiffener C, the first longitudinal direction ribbed stiffener and second longitudinal direction ribbed stiffener are mutually parallel longitudinal, the first lateral stiffening Rib A, the first transverse stiffener B, the first transverse stiffener C are linearly set, and it is vertical that the first transverse stiffener A is fixedly connected on first On the left of to ribbed stiffener, the first transverse stiffener B is fixedly connected between first longitudinal direction ribbed stiffener and second longitudinal direction ribbed stiffener, and first Transverse stiffener C is fixedly connected on the right side of second longitudinal direction ribbed stiffener;Second transverse stiffener A, the second transverse stiffener B, second Transverse stiffener C is linearly set, and the second transverse stiffener A is fixedly connected on the left of first longitudinal direction ribbed stiffener, and second laterally adds Strength rib B is fixedly connected between first longitudinal direction ribbed stiffener and second longitudinal direction ribbed stiffener, and the second transverse stiffener C is fixedly connected on It is in " well " font after the vertical fixation of eight ribbed stiffeners on the right side of two longitudinal stiffeners.
Currently preferred lower stake is fabricated with upper stake by armored concrete, the cross section of locating end plate 8, lower stake Cross section and cross section three's shape, the size all same of upper stake.
Currently preferred lower stake indulges muscle and pile body stirrup from pile body and forms pile body framework and pour coagulation to pile body framework Soil is fabricated;Built-in bolt sleeve 1 is anchored by welding anchor bar thereon, or built-in bolt sleeve 1 passes through Directly it is welded to connect and is anchored with the vertical muscle of lower stake.Currently preferred upper stake indulges muscle by pile body and forms pile body frame with pile body stirrup Frame is simultaneously fabricated to pile body framework casting concrete, and the vertical muscle lower end bending of upper stake is L-shaped so as to form L-shaped linkage section, will be even The upper head plate 4 of fitting 3 is welded to connect with L-shaped linkage section.
The height of the preferred ribbed stiffener 6 of the present embodiment is not less than 80mm, and the thickness of ribbed stiffener 6 is not less than 6mm;Upper head plate 4 with The thickness of bottom plate 5 is not less than 10mm.
For first section stake, the lower end of lower stake is pile crown, the upper end built-in bolt sleeve 1 of lower stake;For standard paragraphs stake, lower stake Lower end be connected with connector, the upper end built-in bolt sleeve 1 of lower stake.
The present invention can also include the prism of third order, and in order to realize being vertically connected between three piles, upper stake top portion is provided with some Individual built-in bolt sleeve 1, the nozzle plane of built-in bolt sleeve 1 and upper stake either flush.Prism of third order bottom is fixedly connected with connection Part 3, upper stake are connected with the prism of third order by connector 3;Simultaneously several built-in bolt sleeves 1, pre-buried spiral shell are provided with the top of the prism of third order The nozzle plane of bolt sleeve 1 and the 3rd either flush, prism of third order top built-in bolt sleeve 1 is with being machined with externally threaded reinforcing bar phase Even, the reinforcing bar and cushion cap bar connecting, after-pouring cushion cap concrete, so as to realize the connection of stake and cushion cap.It is similar successively, this Invention can also include the 4th, the 5th ..., N stakes, lower stake, upper stake, the prism of third order, the 4th, the 5th ..., N stakes according to Secondary to realize the connection between stake and stake according to above-mentioned connected mode from bottom to up, N stake tops portion is provided with several pre-embedded bolts Sleeve 1, N stake tops portion built-in bolt sleeve 1 are connected with being machined with externally threaded reinforcing bar, the reinforcing bar and cushion cap bar connecting, it After-pouring cushion cap concrete, so as to realize the connection of stake and cushion cap.
A kind of stake and stake connection construction method, its method are as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, it is fixed in the pile body framework top surface arrangement of lower stake Position end plate 8, connecting bolt 2 is connected through the positioning bolt hole 9 on locating end plate 8 with built-in bolt sleeve 1, makes pre-embedded bolt Sleeve 1 is placed in the pile body lower portion of lower stake, and built-in bolt sleeve 1 is anchored by welding anchor bar thereon;
B, disengaging oily substance is scribbled between locating end plate 8 and the pile body framework top surface of lower stake, departs from oily substance bag Used oil is included, casting concrete obtains the lower stake containing built-in bolt sleeve 1 in the pile body framework of downward stake;By connecting bolt 2 Depart from locating end plate 8 from the pile body framework top surface of lower stake and take down;So as to complete the positioning of built-in bolt sleeve 1.
C, muscle and pile body stirrup are indulged by pile body and form the pile body framework of upper stake, by upper stake indulge the bending of muscle lower end it is L-shaped from And L-shaped linkage section is formed, the upper head plate 4 of connector 3 is welded to connect with L-shaped linkage section, poured in the pile body framework of upward stake Concrete obtains the upper stake containing connector 3;Connector 3 includes upper head plate 4, bottom plate 5 and ribbed stiffener 6, upper head plate 4 and lower end Plate 5 is aligned parallel to each other, and is connected between upper head plate 4 and bottom plate 5 by several ribbed stiffeners 6, if being provided with bottom plate 5 The dry bolt hole 7 corresponding with the position of built-in bolt sleeve 1;Make connecting bolt 2 through the screw thread of bolt hole 7 on bottom plate 5 It is connected in the built-in bolt sleeve 1 corresponding to lower stake top portion, what connecting bolt 2 was used to realizing bottom plate 5 and lower stake top portion can Detachable is fixedly connected to realize that lower stake is interconnected and fixed with upper stake.
A kind of stake and stake connection construction method, its method are as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, it is fixed in the pile body framework top surface arrangement of lower stake Position end plate 8, connecting bolt 2 is connected through the positioning bolt hole 9 on locating end plate 8 with built-in bolt sleeve 1, makes pre-embedded bolt Sleeve 1 is placed in the pile body lower portion of lower stake, and built-in bolt sleeve 1 is directly indulged muscle with the pile body of lower stake and is welded and fixed;
B, disengaging oily substance is scribbled between locating end plate 8 and the pile body framework top surface of lower stake, departs from oily substance bag Used oil is included, it is L-shaped and form L-shaped linkage section that the pile body of lower stake lower end is indulged into muscle bending;Poured in the pile body framework of downward stake Concrete obtains the lower stake containing built-in bolt sleeve 1, the pile body framework top surface by connecting bolt 2 and locating end plate 8 from lower stake Disengaging takes down, so as to complete the positioning of built-in bolt sleeve 1.
When prefabricated pile produces, the upper end of lower stake carries out the positioning of built-in bolt sleeve 1, and the lower end of lower stake is indulged muscle and is bent into L-shaped is simultaneously welded to connect (for first section stake, the lower end of lower stake is pile crown) with connector 3, after-pouring pile concrete, treat lower stake Pile concrete when reaching design load, connecting bolt 2 and locating end plate 8 are removed, so as to complete determining for built-in bolt sleeve 1 Position.
C, muscle and pile body stirrup are indulged by pile body and form the pile body framework of upper stake, by upper stake indulge the bending of muscle lower end it is L-shaped from And L-shaped linkage section is formed, the upper head plate 4 of connector 3 is welded to connect with L-shaped linkage section, poured in the pile body framework of upward stake Concrete obtains the upper stake containing connector 3;Connector 3 includes upper head plate 4, bottom plate 5 and ribbed stiffener 6, upper head plate 4 and lower end Plate 5 is aligned parallel to each other, and is connected between upper head plate 4 and bottom plate 5 by several ribbed stiffeners 6, if being provided with bottom plate 5 The dry bolt hole 7 corresponding with the position of built-in bolt sleeve 1;For hollow pile, upper head plate 4, bottom plate 5 and locating end plate 8 Center corresponds to perforate, the center bore size of the center bore of upper head plate 4, the center bore of bottom plate 5 and locating end plate 8 with The hole of hollow pile is in the same size;Connecting bolt 2 is set to be threadedly connected to through the bolt hole 7 on bottom plate 5 corresponding to lower stake top portion Built-in bolt sleeve 1 in, connecting bolt 2 is used to realize that the detachable of bottom plate 5 and lower stake top portion is fixedly connected with realization Lower stake is interconnected and fixed with upper stake.
During pile extension at the scene of the invention, connecting bolt 2 need to only be passed through to bolt hole 7 and pre-embedded bolt set on bottom plate 5 Cylinder 1 is connected, you can realizes the connection of upper pile and lower pile.After the completion of pile sinking, stake top is provided with built-in bolt sleeve 1, pre-embedded bolt set Cylinder 1 is connected with being machined with externally threaded reinforcing bar, the reinforcing bar and cushion cap bar connecting, after-pouring cushion cap concrete, so as to realize Stake and the connection of cushion cap.
Above-mentioned embodiment is a preferred embodiment of the present invention, is not the implementation for limiting the present invention and power Sharp scope, the equivalence changes and approximate replacement that all contents according to described in the present patent application scope of patent protection are made all should It is within the scope of the present invention.

Claims (10)

1. a kind of stake and stake attachment structure, it is characterised in that:Including lower stake and upper stake, lower pile passes through connector with upper stake (3)Connection, lower pile top are provided with several built-in bolt sleeves(1), the built-in bolt sleeve(1)Nozzle plane is with Stake either flush;Upper pile bottom and connector(3)It is fixedly connected, the connector(3)Including upper head plate(4), bottom plate (5)And ribbed stiffener(6), the upper head plate(4)With bottom plate(5)It is aligned parallel to each other, the upper head plate(4)With bottom plate(5) Between pass through several ribbed stiffeners(6)It is connected, the bottom plate(5)On be provided with several and built-in bolt sleeve(1)Position Put corresponding bolt hole(7);Make connecting bolt(2)Through bottom plate(5)On bolt hole(7)It is threadedly connected to lower stake top portion Corresponding built-in bolt sleeve(1)In, the connecting bolt(2)For realizing bottom plate(5)It is detachable with lower stake top portion Formula is fixedly connected.
2. according to a kind of stake described in claim 1 and stake attachment structure, it is characterised in that:Lower pile top surface is provided with positioning end Plate(8), the locating end plate(8)On be provided with and built-in bolt sleeve(1)The corresponding positioning bolt hole in position(9), it is described fixed Position bolt hole(9)For positioning built-in bolt sleeve(1)Pre-buried position.
3. according to a kind of stake described in claim 1 and stake attachment structure, it is characterised in that:The connector(3)Upper head plate (4)With bottom plate(5)Between pass through three ribbed stiffeners(6)It is connected;Three ribbed stiffeners(6)Cross section after vertically fixing is in " ten " font.
4. according to a kind of stake described in claim 1 and stake attachment structure, it is characterised in that:The connector(3)Upper head plate (4)With bottom plate(5)Between pass through eight ribbed stiffeners(6)It is connected;Eight ribbed stiffeners(6)It is overall transversal after vertical fixed Face is in " well " font.
5. according to a kind of stake described in claim 2 and stake attachment structure, it is characterised in that:Lower pile is with upper stake by reinforcing bar Concrete is fabricated, the locating end plate(8)Cross section, the cross section of lower stake and cross section three's shape, big of upper stake Small all same.
6. according to a kind of stake described in claim 1 and stake attachment structure, it is characterised in that:Lower pile indulges muscle and stake by pile body Body stirrup forms pile body framework and is fabricated to pile body framework casting concrete;The built-in bolt sleeve(1)By at it Upper welding anchor bar is anchored, or the built-in bolt sleeve(1)By direct progress is welded to connect with the vertical muscle of lower stake Anchoring;Upper pile indulges muscle from pile body and forms pile body framework with pile body stirrup and be fabricated to pile body framework casting concrete; The connector(3)The L-shaped linkage section that muscle lower end is indulged with upper stake pile body is welded to connect.
7. according to a kind of stake described in claim 1 or 3 and stake attachment structure, it is characterised in that:The ribbed stiffener(6)Height Not less than 80mm, the ribbed stiffener(6)Thickness be not less than 6mm;The upper head plate(4)With bottom plate(5)Thickness it is not small In 10mm.
8. according to a kind of stake described in claim 2 and stake attachment structure, it is characterised in that:Four are provided with the top of lower pile in advance Bury bolt collar(1), four built-in bolt sleeves(1)It is evenly distributed to be arranged at lower stake top portion;The bottom plate(5)On be provided with four Individual bolt hole(7), the locating end plate(8)On be provided with four positioning bolt holes(9), the built-in bolt sleeve(1), bolt hole (7)And positioning bolt hole(9)Correspond and set.
9. a kind of stake and stake connection construction method, it is characterised in that:Its method is as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, positioning end is arranged in the pile body framework top surface of lower stake Plate(8), by connecting bolt(2)Through locating end plate(8)On positioning bolt hole(9)With built-in bolt sleeve(1)Connection, makes pre- Bury bolt collar(1)It is placed in the pile body lower portion of lower stake, built-in bolt sleeve(1)By welding anchor bar progress thereon Anchoring;
B, in locating end plate(8)Disengaging oily substance, the disengaging oily substance are scribbled between the pile body framework top surface of lower stake Including used oil, casting concrete is obtained containing built-in bolt sleeve in the pile body framework of downward stake(1)Lower stake;Spiral shell will be connected Bolt(2)And locating end plate(8)Depart from from the pile body framework top surface of lower stake and take down;
C, muscle is indulged by pile body and forms the pile body framework of upper stake with pile body stirrup, it is L-shaped so as to shape that upper stake is indulged into the bending of muscle lower end L-shaped linkage section, by connector(3)Upper head plate(4)It is welded to connect with L-shaped linkage section, is poured in the pile body framework of upward stake Concrete is obtained containing connector(3)Upper stake;The connector(3)Including upper head plate(4), bottom plate(5)And ribbed stiffener (6), the upper head plate(4)With bottom plate(5)It is aligned parallel to each other, the upper head plate(4)With bottom plate(5)Between by some Individual ribbed stiffener(6)It is connected, the bottom plate(5)On be provided with several and built-in bolt sleeve(1)The corresponding spiral shell in position Keyhole(7);Make connecting bolt(2)Through bottom plate(5)On bolt hole(7)It is threadedly connected to pre-buried corresponding to lower stake top portion Bolt collar(1)In, the connecting bolt(2)For realizing bottom plate(5)With lower stake top portion it is detachable be fixedly connected with Realize that lower stake is interconnected and fixed with upper stake.
10. a kind of stake and stake connection construction method, it is characterised in that:Its method is as follows:
A, muscle is indulged by pile body and forms the pile body framework of lower stake with pile body stirrup, positioning end is arranged in the pile body framework top surface of lower stake Plate(8), by connecting bolt(2)Through locating end plate(8)On positioning bolt hole(9)With built-in bolt sleeve(1)Connection, makes pre- Bury bolt collar(1)It is placed in the pile body lower portion of lower stake, built-in bolt sleeve(1)Directly muscle is indulged with the pile body of lower stake to be welded Connect fixation;
B, in locating end plate(8)Disengaging oily substance, the disengaging oily substance are scribbled between the pile body framework top surface of lower stake Including used oil, it is L-shaped and form L-shaped linkage section that the pile body of lower stake lower end is indulged into muscle bending;Poured in the pile body framework of downward stake Concrete is built to obtain containing built-in bolt sleeve(1)Lower stake, by connecting bolt(2)And locating end plate(8)From the pile body of lower stake Framework top surface, which departs from, to be taken down;
C, muscle is indulged by pile body and forms the pile body framework of upper stake with pile body stirrup, it is L-shaped so as to shape that upper stake is indulged into the bending of muscle lower end L-shaped linkage section, by connector(3)Upper head plate(4)It is welded to connect with L-shaped linkage section, is poured in the pile body framework of upward stake Concrete is obtained containing connector(3)Upper stake;The connector(3)Including upper head plate(4), bottom plate(5)And ribbed stiffener (6), the upper head plate(4)With bottom plate(5)It is aligned parallel to each other, the upper head plate(4)With bottom plate(5)Between by some Individual ribbed stiffener(6)It is connected, the bottom plate(5)On be provided with several and built-in bolt sleeve(1)The corresponding spiral shell in position Keyhole(7);For hollow pile, upper head plate(4), bottom plate(5)And locating end plate(8)Center corresponds to perforate, upper head plate(4)In Heart aperture, bottom plate(5)Center bore and locating end plate(8)Center bore size it is in the same size with the hole of hollow pile; Make connecting bolt(2)Through bottom plate(5)On bolt hole(7)It is threadedly connected to the built-in bolt sleeve corresponding to lower stake top portion (1)In, the connecting bolt(2)For realizing bottom plate(5)Detachable with lower stake top portion is fixedly connected to realize lower stake It is interconnected and fixed with upper stake.
CN201711193799.0A 2017-11-24 2017-11-24 Pile-to-pile connection construction method Active CN107724384B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711193799.0A CN107724384B (en) 2017-11-24 2017-11-24 Pile-to-pile connection construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711193799.0A CN107724384B (en) 2017-11-24 2017-11-24 Pile-to-pile connection construction method

Publications (2)

Publication Number Publication Date
CN107724384A true CN107724384A (en) 2018-02-23
CN107724384B CN107724384B (en) 2023-09-15

Family

ID=61218337

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711193799.0A Active CN107724384B (en) 2017-11-24 2017-11-24 Pile-to-pile connection construction method

Country Status (1)

Country Link
CN (1) CN107724384B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661045A (en) * 2018-07-20 2018-10-16 东北大学 A kind of prefabricated GFRP pipe concretes spliced pile
CN111622210A (en) * 2020-04-17 2020-09-04 鸿厦建设有限公司 High-strength pile body connecting structure and method for connecting pile bodies by using same

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT8125492A0 (en) * 1981-12-09 1981-12-09 Scac Spa JOINT FOR CONNECTION BETWEEN SEGMENTS OR TRUNKS OF REINFORCED CONCRETE POLES.
CN202954356U (en) * 2012-10-30 2013-05-29 中国石油化工股份有限公司 Concrete pile with connecting mechanism
CN103590414A (en) * 2013-11-19 2014-02-19 中铁第四勘察设计院集团有限公司 Structure for connecting concrete tubular pile with bearing platform
CN103866761A (en) * 2014-03-21 2014-06-18 李全民 Mechanical connection pile head using repetitively used precast concrete pile as end plate and manufacturing method of mechanical connection pile head
CN104099926A (en) * 2013-04-10 2014-10-15 斯马泰克工程技术株式会社 Connecting Device Of High Strength Hollow Concrete Piles And Connecting Construction Utilizing Same
CN105544530A (en) * 2016-02-03 2016-05-04 福建建华建材有限公司 Connecting structure and production method of tubular pile prefabricated part
CN207512732U (en) * 2017-11-24 2018-06-19 华中科技大学 A kind of stake and stake connection structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT8125492A0 (en) * 1981-12-09 1981-12-09 Scac Spa JOINT FOR CONNECTION BETWEEN SEGMENTS OR TRUNKS OF REINFORCED CONCRETE POLES.
CN202954356U (en) * 2012-10-30 2013-05-29 中国石油化工股份有限公司 Concrete pile with connecting mechanism
CN104099926A (en) * 2013-04-10 2014-10-15 斯马泰克工程技术株式会社 Connecting Device Of High Strength Hollow Concrete Piles And Connecting Construction Utilizing Same
CN103590414A (en) * 2013-11-19 2014-02-19 中铁第四勘察设计院集团有限公司 Structure for connecting concrete tubular pile with bearing platform
CN103866761A (en) * 2014-03-21 2014-06-18 李全民 Mechanical connection pile head using repetitively used precast concrete pile as end plate and manufacturing method of mechanical connection pile head
CN105544530A (en) * 2016-02-03 2016-05-04 福建建华建材有限公司 Connecting structure and production method of tubular pile prefabricated part
CN207512732U (en) * 2017-11-24 2018-06-19 华中科技大学 A kind of stake and stake connection structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661045A (en) * 2018-07-20 2018-10-16 东北大学 A kind of prefabricated GFRP pipe concretes spliced pile
CN108661045B (en) * 2018-07-20 2023-11-24 东北大学 Precast GFRP pipe concrete spliced pile
CN111622210A (en) * 2020-04-17 2020-09-04 鸿厦建设有限公司 High-strength pile body connecting structure and method for connecting pile bodies by using same

Also Published As

Publication number Publication date
CN107724384B (en) 2023-09-15

Similar Documents

Publication Publication Date Title
CN107989029A (en) A kind of stake is connected system and its construction method with stake
CN104947603B (en) A kind of rc beam bridge girder reinforcing construction and reinforcement means
CN106284840B (en) A kind of second pouring steel reinforced concrete frame beam and its construction method
CN103088915A (en) Cast-in-site column with column cap and construction method
CN109779012A (en) A kind of reinforced beam and concrete filled steel tube column connected node
CN108797791B (en) A kind of assembly method of upper and lower self-heat conserving external wall and floor
CN109779282A (en) The construction method and structure that reinforced column transformation is reinforced
CN109440634A (en) The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN104929278A (en) Assembly type dense column hollow shear wall structure
CN109371963A (en) Back taper steel jacket box and its construction method in water in the prefabricated constructing tie beam of pier foundation
CN109537929A (en) Demolishing columns bracing means and reinforcement means
CN107724384A (en) A kind of stake and stake attachment structure and its construction method
CN207512732U (en) A kind of stake and stake connection structure
CN106759858B (en) A kind of connecting node and preparation method of H profile steel beam and rectangular steel-tube concrete column
CN205531016U (en) Precast concrete post component and connected node
CN209260897U (en) Assembly concrete beam column sleeve combination connecting node
CN109322319A (en) The bindiny mechanism of concrete precast pile and pile foundation support table
CN205677070U (en) A kind of building frame construction
CN105625573B (en) The bean column node of intensity presstressed reinforcing steel and regular reinforcement sleeve connection in beam bottom
CN209669688U (en) A kind of half assembled thin-wall piers
CN209243750U (en) The bindiny mechanism of concrete precast pile and pile foundation support table
CN110528734A (en) A kind of steel-concrete combination shear wall with short piers
CN208251077U (en) A kind of positioning constructing device of networking measurement control stake
CN205999730U (en) A kind of non-fragment orbit base pours uses template
CN207484261U (en) A kind of T-shaped bridge structure of pipe stiffener

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant