CN107687342B - A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method - Google Patents

A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method Download PDF

Info

Publication number
CN107687342B
CN107687342B CN201710719462.2A CN201710719462A CN107687342B CN 107687342 B CN107687342 B CN 107687342B CN 201710719462 A CN201710719462 A CN 201710719462A CN 107687342 B CN107687342 B CN 107687342B
Authority
CN
China
Prior art keywords
exploiting field
dass
active line
width
mode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710719462.2A
Other languages
Chinese (zh)
Other versions
CN107687342A (en
Inventor
刘福明
才庆祥
周伟
陈树召
尚涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201710719462.2A priority Critical patent/CN107687342B/en
Publication of CN107687342A publication Critical patent/CN107687342A/en
Application granted granted Critical
Publication of CN107687342B publication Critical patent/CN107687342B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • E21C41/28Methods of surface mining; Layouts therefor for brown or hard coal

Abstract

The invention discloses a kind of open coal mines, and bucket shovel active line to be drawn to be segmented alternative expression exploiting field forward method, using the continous way steering mode for staying the slow side of ditch, I exploiting field is started to II exploiting field right-angle steering transition period, the mined out ditch of ladder type being arranged in downward direction is reserved within the scope of the coincidence in I exploiting field and II exploiting field, then the drawing bucket in I exploiting field of opencut and II exploiting field shovel active line is divided into two sections from midpoint respectively, equal digging bandwidth is determined according to drawing bucket to shovel job parameter, each segmentation is used as a width dass, pass through being alternately propelled for I exploiting field dass and II exploiting field dass, I exploiting field is discharged in a large amount of after exploiting between emptying, II exploiting field overburden is reversely interior nearby to be arranged, guarantee to draw bucket shovel working condition during exploiting field turns to basicly stable, realize the uninterrupted operation that coal working face smoothly connects, it can be realized and arrange haul distance in shortening , reduce land seizure, and then reduce adopt stripping cost, especially suitable for open coal mine draw bucket shovel active line exploiting field turn to.

Description

A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method
Technical field
The present invention relates to a kind of open coal mine exploiting field forward method, specifically a kind of open coal mine that is suitable for draws bucket shovelman to make The segmentation alternative expression exploiting field forward method of line, belongs to surface mining technical field.
Background technique
The coal resources preservation of China's open coal mine be mainly characterized by mining depth is big, seam inclination is small, coalfield distribution ratio Compared with concentration, it is suitble to the mechanical mining in Large-scale Coal base, the type of opencast mining technique determines its reasonable active line Length, active length are the width in the single exploiting field of opencut, often use block mining for large size strip mining transformation coalfield To realize the maximization of development of resources benefit.
With deepening continuously for outdoor coal exploitation, the large outdoors colliery that the country is built up almost all suffers from exploiting field connecting Problem, in order to guarantee the continuity of Production of Strip Mine and the stability of production capacity, usually when conditions permit, opencut is equal Select the exploiting field continuation method of gradual steering.
Exploiting field is turned to has apparent advantage relative to drawing ditch again in terms of engineering relationships and economic benefit.However it is different Production technology have its own particularity: shovel-truck techmologv is relatively flexible production practice, steering procedure phase Research achievement and knowhow to fairly simple, and in industry is relatively abundanter;And Pull shovel handling technique is turned to Know-how, at home and abroad there is no records at present.
Pull shovel handling technique is the advanced opencut stripping technology that China introduces, and main production equipments are to draw bucket shovel (also known as suspension bucket shovel), drawing bucket shovel is a kind of walking excavator of large size, is mainly used for when removing casting to mined out Area, open pit quarry edge, can by the casting of bulk to larger distance, have be easily installed, be highly reliable, flexibility High, the characteristics of walking ability is good, production cost is low (only monobucket-truck 40%), broad technical operation performance makes it It directly dumps the material of excavation, without the use of transporting equipment, very high efficiency is played in exploitation excacation, but equipment is purchased Set that investment is huge, and single device price convert into nearly 1,000,000,000 yuan of RMB, economically so huge fixed assets are left unused It is huge economic loss.Therefore, the steering of bucket shovelman's skill is drawn not only to guarantee that balanced of relationship is adopted-arranged to opencut itself Match, while to guarantee that bucket shovel equipment is drawn to continue efficiently to produce.
In order to reduce the side of the end between exploiting field pressure coal, open pit mine section is generally delimitated with lowest part coal seam, so that ground Table boundary, which issues, to be overlapped, and will lead to the secondary removing for connecting exploiting field close to the interior row for connecting exploiting field side in previous exploiting field, in order to It reduces secondary removing and generallys use and stay row in ditch, lose in a large amount of between emptying, while the connecting in order to guarantee coal production, connect Continuous exploiting field carries out working face developing and generates a large amount of overburdens, so that serious unbalance, interior row between overburden and interior emptying during turning to Insufficient section needs to be discharged to farther higher place, to increase the freight of equipment, or even needs to increase outer dump, make The economic benefit for obtaining opencut declines to a great extent.
It draws the removing mode of bucket shovel to belong to without transport casting, i.e., overburden is directly dumped into internal dumping, so it is adopted Pick must be a parallel goaf with outside, traditional working method be must previous exploiting field exploitation complete post-tensioning bucket and shovel to stop Only operation waits secondary removing, connects after the completion of exploiting field perforated blasting, working face such as reorganize and outfit at the work and could continue to put into production, Cause equipment to be stagnated and connect interruption with coal working face, it cannot be guaranteed that coal stablizes supply.In addition, the pit of opencut is in leakage By wink at the end of bucket-shaped, before lowest part coal recovery terminates, the huge space in top is not available, and previous exploiting field is exploited Between discharge huge interior emptying between, but nervous node between interior emptying has been had already passed by from the time, so that previous exploiting field is exploited The pit of formation can not restore original landforms.
Summary of the invention
In view of the above-mentioned problems, the present invention provides a kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field steering side Method can be realized between emptying in release in advance, shortens interior row's haul distance, reduce land seizure, and then stripping cost, raising warp are adopted in reduction Ji benefit draws the exploiting field of bucket shovel active line to turn to especially suitable for open coal mine.
To achieve the above object, this open coal mine draws bucket shovel active line segmentation alternative expression exploiting field forward method respectively will be outdoor I exploiting field of mine and the drawing bucket shovel active line in II exploiting field are divided into two sections from midpoint, determine equal adopt according to drawing bucket to shovel job parameter Bandwidth is dug, each segmentation is used as a width dass, passes through being alternately propelled for I exploiting field dass and II exploiting field dass, I exploiting field It is discharged after exploitation in largely between emptying, the nearest reversed interior row of II exploiting field overburden guarantees that drawing bucket shovels during exploiting field turns to Working condition is basicly stable, realizes the uninterrupted operation that coal working face smoothly connects;
Specifically includes the following steps:
A. using the continous way steering mode for staying the slow side of ditch, I exploiting field is boosted to terminal, is started to II exploiting field right angle During transition, the one end of I exploiting field active line towards II exploiting field within the scope of the coincidence in I exploiting field and II exploiting field is using drawing bucket The reserved mined out ditch of ladder type being arranged in downward direction of shovelman's skill;
B. it by I exploiting field active line from medial section, and is boosted and is adopted using drawing bucket shovelman's skill from the left side of medial section A width dass I out;
C. it is boosted from the right side of the medial section of I exploiting field active line using drawing bucket shovelman's skill and produces a width dass II, dass I and dass II penetrate through, and the right end of dass II prolongs the mined out ditch of ladder type upwards with the mined out ditch perforation of ladder type simultaneously It stretches to form II exploiting field active line;
D. I exploiting field active line after penetrating through dass I and dass II is again from medial section, and from medial section Left side is boosted using drawing bucket shovelman's skill and produces a width dass III, while II exploiting field active line extends downwards increase by one The length of dass simultaneously promotes to the right one width dass IV of extraction using shovel-truck techmologv, and the dass III in I exploiting field is exploited After discharge in a large amount of between emptying, II exploiting field overburden nearby in row;
E. II exploiting field active line continues to promote one width digging of extraction to the right on the basis of dass IV using drawing bucket shovelman's skill Band V;
F. I exploiting field active line is boosted using drawing bucket shovelman's skill on the basis of dass II and produces a width and dass III concordant dass VI;
G. II exploiting field active line is boosted on the basis of dass IV produces a width dass VII, dass VII and digging The perforation of band VI is completed right-angle steering block transition and is connected;
H. and so on, repeat the above steps d, e, f, g are constantly promoted using the propulsion mode for being segmented-taking a step, until complete At the propulsion in entire I exploiting field.
As a further improvement of the present invention, in the step b promote extraction one width dass I mode be from The mode that I exploiting field active line medial section promotes to the left;The mode of one width dass II of extraction is promoted in the step c is The mode promoted to the right from I exploiting field active line medial section;The mode of one width dass III of extraction is promoted in the step d It is the mode promoted to the left from active line medial section;The mode of extraction one width and dass VI is promoted in the step f It is the mode promoted to the right from active line medial section.
As a further improvement of the present invention, the mode of one width dass IV of extraction is promoted in the step d is The mode promoted from up to down;It is the side of bottom-up propulsion that the mode for producing a width dass V is promoted in the step e Formula;It is the mode of bottom-up propulsion that the mode for producing a width dass VII is promoted in the step g.
Compared with prior art, this open coal mine draws bucket shovel active line segmentation alternative expression exploiting field forward method using " work The mode that line segmentation alternating " turns to, the dass III in I exploiting field of exploitation is segmented by active line, advances to I exploiting field partial region In boundary's release is a large amount of between emptying, the extensive stripping bench in exactly II exploiting field, is greatly solved between emptying during turning at this time Insufficient problem, it is synchronous with dass III that dass IV is exploited using shovel-truck techmologv, it is connected to draw the shovel that struggles against to create Working face, overcomes equipment halt production caused by dass VI, VII digging of dass coincidence and working face connects the problem of interrupting, and makes It draws bucket shovel to be not required to stagnantly be transitioned into II exploiting field naturally from I exploiting field, ensure that the stabilization of overall throughput and draws bucket shovel equipment Utilization rate, this open coal mine draw bucket shovel active line segmentation alternative expression exploiting field forward method can be realized in advance release in emptying between, Row's haul distance, reduction land seizure in shortening, and then reduce and adopt stripping cost, increase economic efficiency, it is drawn especially suitable for open coal mine The exploiting field of bucket shovel active line turns to.
Detailed description of the invention
Fig. 1 is stope shape top view before opencut turns to;
Fig. 2 is that I exploiting field produces the top view after a width dass I;
Fig. 3 is that I exploiting field produces the top view after a width dass II;
Fig. 4 is that I exploiting field produces a width dass III while the trapezoidal mined out ditch in II exploiting field extends downwardly and increases a dass Length and to the right promote extraction one width dass IV after top view;
Fig. 5 is that II exploiting field produces the top view after a width dass V;
Fig. 6 is that I exploiting field produces the top view after a width dass VI;
Fig. 7 is the top view after II exploiting field produces a width dass VII and penetrates through with the exploiting field I;
Fig. 8 is to turn to front and back stope comparison top view.
In figure: 1, I exploiting field, 2, II exploiting field, 3, the mined out ditch of ladder type, 4, dass I, 5, dass II, 6, dass III, 7, Dass IV, 8, dass V, 9, dass VI, 10, dass VII.
Specific embodiment
The present invention will be further described with reference to the accompanying drawing.
As shown in figure 8, this open coal mine, which draws bucket shovel active line segmentation alternative expression exploiting field forward method to use, stays the slow side of ditch The drawing bucket in I exploiting field 1 of opencut and II exploiting field 2 shovel active line is divided into two sections from midpoint respectively by continous way steering mode, according to Bucket shovel job parameter is drawn to determine equal digging bandwidth, each segmentation is used as a width dass, and I exploiting field is divided into four width dasses (dass I 4, dass II 5, dass III 6, dass VI 9), II exploiting field are divided into three width dass (dasses IV 7, digging Band V 8, dass VII 10), by being alternately propelled for I exploiting field, 1 dass and II exploiting field, 2 dass, after I exploiting field 1 is exploited In release largely between emptying, the nearest reversed interior row of II exploiting field, 2 overburden guarantees that drawing bucket shovels the working condition base during exploiting field turns to This stabilization realizes the uninterrupted operation that coal working face smoothly connects;
Specifically includes the following steps:
A. using the continous way steering mode for staying the slow side of ditch, I exploiting field 1 is advanced into terminal, as shown in Figure 1, starting to II 2 right-angle steering transition period of exploiting field, I exploiting field (1) active line within the scope of the coincidence in I exploiting field 1 and II exploiting field 2 is towards II exploiting field 2 one end is using the reserved mined out ditch 3 of ladder type being arranged in downward direction of drawing bucket shovelman's skill;
B. as shown in Fig. 2, by I exploiting field, 1 active line from medial section, and from the left side of medial section using drawing bucket shovelman's skill It boosts and produces a width dass I 4;
C. as shown in figure 3, from the right side of the medial section of I exploiting field, 1 active line using drawing bucket shovelman's skill to boost extraction One width dass II 5, dass I 4 and dass II 5 penetrate through, and the right end of dass II 5 makes with the mined out perforation of ditch 3 of ladder type simultaneously The mined out ditch 3 of ladder type upwardly extends to form II exploiting field, 2 active line;
D. as shown in figure 4, I exploiting field, 1 active line after dass I 4 and dass II 5 are penetrated through is again from medial section, And from the left side of medial section using draw bucket shovelman's skill push ahead extraction one width dass III 6, while II exploiting field, 2 active line to Extended portion increases the length of a dass and promotes one width dass IV 7 of extraction to the right using shovel-truck techmologv;I adopts The dass III 6 in area 1 discharges a large amount of interior emptyings after exploiting between, II exploiting field, 2 overburden row, guarantee can draw bucket shovel to exist in nearby Working condition is basicly stable during exploiting field turns to;
E. as shown in figure 5, II exploiting field, 2 active line is promoted to the right on the basis of dass IV 7 using drawing bucket shovelman's skill continuation Produce a width dass V 8;
F. as shown in fig. 6, I exploiting field, 1 active line on the basis of dass II 5 using drawing bucket shovelman's skill to boost extraction The one width dass VI 9 concordant with dass III 6;
G. the one width dass VII 10 of extraction as shown in fig. 7, II exploiting field, 2 active line is boosted on the basis of dass IV 7, Dass VII 10 and the perforation of dass VI 9 are completed right-angle steering block transition and are connected;
H. and so on, repeat the above steps d, e, f, g are constantly promoted using the propulsion mode for being segmented-taking a step, until complete At the propulsion in entire I exploiting field 1.
For the ease of drawing the shovel construction that struggles against, reduction to draw the movement of bucket shovel, as a further improvement of the present invention, such as Fig. 8 Shown, the mode of one width dass I 4 of extraction is promoted in the step b to be pushed away to the left from I exploiting field, 1 active line medial section Into mode;In the step c promote extraction one width dass II 5 mode be from I exploiting field, 1 active line medial section to the right The mode just promoted;In the step d promote extraction one width dass III 6 mode be from active line medial section to the left The mode of propulsion;In the step f promote extraction one width and dass VI 9 mode be from active line medial section to the right The mode of propulsion.
In order to further be convenient for the movement for drawing the construction of bucket shovel, reduction to draw bucket shovel, as a further improvement of the present invention, As shown in figure 8, the mode for promoting one width dass IV 7 of extraction in the step d is the mode promoted from up to down;Described It is the mode of bottom-up propulsion that the mode for producing a width dass V 8 is promoted in step e;Extraction is promoted in the step g The mode of one width dass VII 10 is the mode of bottom-up propulsion.
This open coal mine draws bucket shovel active line segmentation alternative expression exploiting field forward method to turn to using " active line segmentation alternating " Mode, the dass III 6 in I exploiting field 1 of exploitation is segmented by active line, make I exploiting field, 1 partial region advance to boundary's release it is a large amount of in Between emptying, the exactly extensive stripping bench in II exploiting field 2 at this time, greatly solve the problems, such as it is insufficient between being emptied during turning to, It is synchronous with dass III 6 that dass IV 7 is exploited using shovel-truck techmologv, to draw the shovel that struggles against to create subsequent duty face, gram It has taken equipment halt production caused by dass VI 9, VII 10 digging of dass coincidence and working face connects the problem of interrupting, shoveled drawing bucket It is not required to stagnantly be transitioned into II exploiting field 2 naturally from I exploiting field 1, ensure that the stabilization of overall throughput and draws bucket shovel equipment utilization Rate, this open coal mine draw bucket shovel active line segmentation alternative expression exploiting field forward method can be realized in advance release in emptying between, shorten Interior row's haul distance reduces land seizure, and then reduces and adopt stripping cost, increases economic efficiency, and draws bucket shovel especially suitable for open coal mine The exploiting field of active line turns to.

Claims (3)

1. a kind of open coal mine draws bucket shovel active line to be segmented alternative expression exploiting field forward method, which is characterized in that respectively by opencut I exploiting field (1) and the drawing bucket shovel active line of II exploiting field (2) from centre be divided into two sections, according to drawing the shovel job parameter that struggles against to determine I exploiting field (1) the equal digging bandwidth of two sections, two sections of equal digging bandwidth for determining II exploiting field (2), each segmentation are used as one Width dass, by being alternately propelled for I exploiting field (1) dass and II exploiting field (2) dass, I exploiting field (1) discharges after exploiting In largely between emptying, it is basic to guarantee that drawing bucket shovels the working condition during exploiting field turns to by the nearest reversed interior row of II exploiting field (2) overburden Stablize, realizes the uninterrupted operation that coal working face smoothly connects;
Specifically includes the following steps:
A. using the continous way steering mode for staying the slow side of ditch, I exploiting field (1) is boosted to terminal, is started straight to II exploiting field (2) During the transition of angle, I exploiting field (1) active line within the scope of the coincidence of I exploiting field (1) and II exploiting field (2) is towards II exploiting field (2) One end using drawing the reserved mined out ditch of ladder type (3) being arranged in downward direction of bucket shovelman's skill;
B. I exploiting field (1) active line is segmented from centre, and is boosted from the left side in middle position using drawing bucket shovelman's skill Produce a width dass I (4);
C. it is boosted from the right side in the middle position of I exploiting field (1) active line using drawing bucket shovelman's skill and produces a width dass II (5), dass I (4) and dass II (5) penetrate through, and the right end of dass II (5) makes ladder with the mined out ditch of ladder type (3) perforation simultaneously The mined out ditch of type (3) upwardly extends to form II exploiting field (2) active line;
D. dass I (4) and I exploiting field (1) active line after dass II (5) perforation are segmented from centre again, and from The left side in middle position using drawing bucket shovelman's skill to boost one width dass III (6) of extraction, while II exploiting field (2) active line to Extended portion, which is increased the length of a dass and promoted to the right using shovel-truck techmologv, produces a width dass IV (7), and I It is discharged after dass III (6) exploitation in exploiting field (1) in largely between emptying, II exploiting field (2) overburden is arranged in nearby;
E. II exploiting field (2) active line using drawing bucket shovelman's skill continues that one width of extraction is promoted to adopt to the right on the basis of dass IV (7) It digs band V (8);
F. I exploiting field (1) active line is boosted using drawing bucket shovelman's skill on the basis of dass II (5) and produces a width and digging The concordant dass VI (9) of band III (6);
G. II exploiting field (2) active line is boosted on the basis of dass IV (7) produces a width dass VII (10), dass VII (10) right-angle steering block transition is completed with dass VI (9) perforation to connect;
H. and so on, repeat the above steps d, e, f, g are constantly promoted using the propulsion mode for being segmented-taking a step, until completing whole The propulsion of a I exploiting field (1).
2. open coal mine according to claim 1 draws bucket shovel active line to be segmented alternative expression exploiting field forward method, feature exists In, in the step b promote extraction one width dass I (4) mode be from I exploiting field (1) active line middle position to the left The mode of propulsion;The mode that one width dass II (5) of extraction is promoted in the step c is from I exploiting field (1) active line interposition Set the mode promoted to the right;The mode that one width dass III (6) of extraction is promoted in the step d is from active line interposition Set the mode promoted to the left;The mode that one width dass VI (9) of extraction is promoted in the step f is from active line interposition Set the mode promoted to the right.
3. open coal mine according to claim 2 draws bucket shovel active line to be segmented alternative expression exploiting field forward method, feature exists In promoting the mode of one width dass IV (7) of extraction in the step d is the mode promoted from up to down;The step e The middle mode for promoting one width dass V (8) of extraction is the mode of bottom-up propulsion;One width of extraction is promoted in the step g The mode of dass VII (10) is the mode of bottom-up propulsion.
CN201710719462.2A 2017-08-21 2017-08-21 A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method Expired - Fee Related CN107687342B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710719462.2A CN107687342B (en) 2017-08-21 2017-08-21 A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710719462.2A CN107687342B (en) 2017-08-21 2017-08-21 A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method

Publications (2)

Publication Number Publication Date
CN107687342A CN107687342A (en) 2018-02-13
CN107687342B true CN107687342B (en) 2019-05-21

Family

ID=61153481

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710719462.2A Expired - Fee Related CN107687342B (en) 2017-08-21 2017-08-21 A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method

Country Status (1)

Country Link
CN (1) CN107687342B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630121B (en) * 2019-01-30 2020-08-28 新疆天池能源有限责任公司 Steering, developing and transporting system for strip mining area
CN109882174B (en) * 2019-04-04 2022-04-01 中国矿业大学(北京) Working face rotary mining mountain coal pillar and through mountain alternately collaborative mining method
CN110348645B (en) * 2019-07-19 2022-01-28 辽宁工程技术大学 Opencut coal mine dumping line arrangement method based on internal dumping space utilization maximization
CN110939446B (en) * 2019-07-29 2020-11-03 中国矿业大学 Steering method for mining area of ultra-thick inclined coal seam
CN111022054B (en) * 2019-12-12 2022-05-20 神华准格尔能源有限责任公司 Adjacent equidirectional asynchronous mining open pit mine and mining method thereof
CN112963150A (en) * 2021-03-22 2021-06-15 辽宁工程技术大学 Steering method for super-huge open coal mine mining area produced in full-mechanized mode
CN112943252B (en) * 2021-04-22 2023-03-31 辽宁工程技术大学 Steering continuous mining method for mining area of strip mine
CN114508353B (en) * 2022-01-29 2022-12-09 中国矿业大学 Initial rapid construction method for strip mine with inclined coal seam

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2361081C2 (en) * 2007-05-07 2009-07-10 Институт проблем комплексного освоения недр Российской академии наук Procedure of open pit development of mineral deposits
CN103470262A (en) * 2013-09-12 2013-12-25 中国矿业大学 Mining method of nearly horizontal mineral deposit of opencast coal field by casting and internally dumping
CN103670419A (en) * 2013-11-20 2014-03-26 中国矿业大学 Run-through inner dumping method between mining areas for opencast coal mine during period of diversion
CN105528495A (en) * 2015-12-30 2016-04-27 中国神华能源股份有限公司 Movement determination method for middle coal transportation ditch in dragline stripping process
CN105545311A (en) * 2015-12-16 2016-05-04 中国神华能源股份有限公司 Dragline standing platform adjustment method
CN105781553A (en) * 2016-03-14 2016-07-20 中国矿业大学 Gentle wall milling method at parallel milling area end under complex geological structure
CN105781554A (en) * 2016-04-11 2016-07-20 中国矿业大学(北京) Mining method for open coal mine through dragline non-transportation casting technology
CN106194189A (en) * 2016-07-30 2016-12-07 肖双双 A kind of mining sequence of the long narrow opencut of inclined seam
CN106368706A (en) * 2016-08-27 2017-02-01 肖双双 Casting blast and pull shovel handling mining procedure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2361081C2 (en) * 2007-05-07 2009-07-10 Институт проблем комплексного освоения недр Российской академии наук Procedure of open pit development of mineral deposits
CN103470262A (en) * 2013-09-12 2013-12-25 中国矿业大学 Mining method of nearly horizontal mineral deposit of opencast coal field by casting and internally dumping
CN103670419A (en) * 2013-11-20 2014-03-26 中国矿业大学 Run-through inner dumping method between mining areas for opencast coal mine during period of diversion
CN105545311A (en) * 2015-12-16 2016-05-04 中国神华能源股份有限公司 Dragline standing platform adjustment method
CN105528495A (en) * 2015-12-30 2016-04-27 中国神华能源股份有限公司 Movement determination method for middle coal transportation ditch in dragline stripping process
CN105781553A (en) * 2016-03-14 2016-07-20 中国矿业大学 Gentle wall milling method at parallel milling area end under complex geological structure
CN105781554A (en) * 2016-04-11 2016-07-20 中国矿业大学(北京) Mining method for open coal mine through dragline non-transportation casting technology
CN106194189A (en) * 2016-07-30 2016-12-07 肖双双 A kind of mining sequence of the long narrow opencut of inclined seam
CN106368706A (en) * 2016-08-27 2017-02-01 肖双双 Casting blast and pull shovel handling mining procedure

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
大型近水平露天煤矿转向期间开拓运输系统优化研究;周伟;《采矿与安全工程学报》;20081231;第25卷(第4期);第404-408页 *
拉斗铲倒堆工艺露天煤矿采区转向关键技术研究;张维世;《中国博士学位论文全文数据库 工程科技Ⅰ辑》;中国学术期刊(光盘版)电子杂志社;20141215(第12期);B021-56 *
露天矿拉斗铲倒堆工艺系统优化理论及应用研究;孙健东;《中国博士学位论文全文数据库 工程科技Ⅰ辑》;20170215(第2期);B21-79 *
黑岱沟露天煤矿转向期间内排均衡性研究;张维世;《煤矿安全》;20131220;第44卷(第12期);第36-39页 *

Also Published As

Publication number Publication date
CN107687342A (en) 2018-02-13

Similar Documents

Publication Publication Date Title
CN107687342B (en) A kind of open coal mine drawing bucket shovel active line segmentation alternative expression exploiting field forward method
CN105781554B (en) A kind of open coal mine draws bucket shovel overcast stripping recovery method
CN108756875B (en) The continuous quarrying apparatus of row's open coal mine medium-thickness seam and method in a kind of
CN111691885B (en) Efficient filling mining method for ultra-thick coal seam
CN103470262A (en) Mining method of nearly horizontal mineral deposit of opencast coal field by casting and internally dumping
US20220243590A1 (en) Dendritic reverse underground mining method for thin coal seam at end slope of strip mine
CN102392642A (en) Method for arranging roadways on coal-pillar-free stope
CN109026006A (en) Exploitation open pit slope covers the new method of mineral products
CN109882239B (en) Open-pit end slope coal-pressing radial filling mining method
CN106368706A (en) Casting blast and pull shovel handling mining procedure
CN110410076A (en) A kind of filling mining method for leaving Pillar Recovery for old pillars of a house goaf
CN104847360A (en) Combined step milling method of strip mine semi-continuous system
CN104088662A (en) Construction method of gob-side entry retaining wall of solid filling coal mining
CN106907177A (en) A kind of girdle gob side entry retaining roadside packing method for protecting support
CN105421198A (en) Method for building slope ramp in open pit coal mine
CN108035714A (en) Spoil zero-emission short face is without coal pillar mining method
CN102287211A (en) Gob roadway end part hydraulic support frame and gob roadway coal mining method thereof
CN109882237B (en) Strip filling mining roof connecting system
CN103061767B (en) Lower to horizontal slice Dry-placed fill mining
CN105626076B (en) It is a kind of to draw bucket shovel zigzag working berm high-efficiency mining method
CN105971607A (en) Method for gob-side entry retaining of medium-thickness coal seam
CN101881179A (en) Coal mine up-dip working face slant range paste-like filling method
CN114183140B (en) Mining and filling method for advanced replacement section coal pillar
CN115163189A (en) Double-lane arrangement auxiliary lane-to-negative coal pillar single-lane continuous and sequential mining method
CN116163730A (en) Method for mining and sealing carbon dioxide by bidirectional forward filling of thin coal layer drilling machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190521

Termination date: 20210821

CF01 Termination of patent right due to non-payment of annual fee