CN107620831A - A kind of construction method for passing through existing roadbed pipeline - Google Patents

A kind of construction method for passing through existing roadbed pipeline Download PDF

Info

Publication number
CN107620831A
CN107620831A CN201710853269.8A CN201710853269A CN107620831A CN 107620831 A CN107620831 A CN 107620831A CN 201710853269 A CN201710853269 A CN 201710853269A CN 107620831 A CN107620831 A CN 107620831A
Authority
CN
China
Prior art keywords
roadbed
pipe
pipeline
passing
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710853269.8A
Other languages
Chinese (zh)
Inventor
董肖宇
孟金平
夏云
赵春洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd filed Critical Electricity Affair Engineering Co of China Railway No 8 Engineering Group Co Ltd
Priority to CN201710853269.8A priority Critical patent/CN107620831A/en
Publication of CN107620831A publication Critical patent/CN107620831A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of construction method for passing through existing roadbed pipeline, comprise the following steps:A, in roadbed side, ground excavates downwards operating pit;B, drilled in the operating pit to the opposite side of the roadbed;C, pipe, the end-enclosed of the pipe are penetrated into the hole;D, after the pipe is set in place, backfilled into the operating pit, complete construction.With a kind of construction method for passing through existing roadbed pipeline of the present invention, drilling construction application mini-plant, roadbed will not be affected greatly, existing line normal operation is not influenceed, it is not necessary to is cashed the skylight phase and is constructed again, the more existing artificial ditching of efficiency of construction is passed through roadbed and greatly improved, effectively reduce construction cost, this method step is simple, easy to operate, is easy to promotion and implementation.

Description

A kind of construction method for passing through existing roadbed pipeline
Technical field
The present invention relates to pipeline construction field, more particularly to a kind of construction method for passing through existing roadbed pipeline.
Background technology
The existing pipeline for passing through existing roadbed, due to can not be affected greatly to existing roadbed, it is impossible to using large scale computer Tool equipment is excavated, and typically uses hand excavation's roadbed, is influenceed by the commuting skylight of vehicle phase big, it is necessary to several manually time-consuming 1-2 Roadbed is passed through in the ditching of skylight phase, and the method cost is high, time-consuming more, and is had a great influence by skylight encashment ratio and Window time, not really It is more to determine factor, often occur because skylight cancel and caused by workmen's work holdup phenomenon.
The content of the invention
It is time-consuming more it is an object of the invention to overcome hand excavation's roadbed cost in the presence of prior art high, and by Skylight encashment ratio and Window time have a great influence, and uncertain factor is more, often occur because skylight cancel and caused by workmen's nest A kind of above-mentioned deficiency of work phenomenon, there is provided construction method for passing through existing roadbed pipeline.
In order to realize foregoing invention purpose, the invention provides following technical scheme:
A kind of construction method for passing through existing roadbed pipeline, comprises the following steps:
A, in roadbed side, ground excavates downwards operating pit;
B, at least one hole is bored to the opposite side of the roadbed in the operating pit;
C, pipe, the end-enclosed of the pipe are penetrated into each hole;
D, after the pipe is set in place, backfilled into the operating pit, complete construction.
Wherein, the operating pit is excavated in step A downwards and exposes the ground under the roadbed, and punching is worn in this place The roadbed;By the end-enclosed of the pipe in the step C, soil enters inside the pipe during avoiding poling, shadow Ring the follow-up threading in pipe.It should be noted that the sky required for the size adaptation puncher work of operating pit described herein Between.
Using a kind of construction method for passing through existing roadbed pipeline of the present invention, drilling construction application mini-plant, Roadbed will not be affected greatly, not influence existing line normal operation, it is not necessary to cash the skylight phase and construct again, efficiency of construction More existing artificial ditching is passed through roadbed and greatly improved, and effectively reduces construction cost, this method step is simple, easy to operate, is easy to Promotion and implementation.
Preferably, in the step B, be first molded the hole with puncher, then with reamer by the aperture in the hole expand to The caliber of the pipe needed for adaptation.
Preferably, when need through the caliber of the pipe be more than 80mm when, first with diameter 50-60mm reamers counterboring institute State hole, then the hole described in the reamer counterboring of the adaptation caliber.
In this way, avoid using relatively high power motor during disposable enlarged diameter hole, bring larger vibration to influence The roadbed.
Preferably, 1-2m often is crept into the puncher, sets extension bar to be further continued for drilling on the puncher.
Preferably, appropriate water is injected by injector with the puncher boring procedure.
In this way, the soil tunneled the puncher or reamer front end needs in drilling process Softening, beneficial to the vibration reduced in equipment attrition and reduction work progress.
Preferably, in the step D, the operating pit is backfilled using the woven bag for being filled with sandstone, is easy to subsequently wear electricity Cable takes out the end that sandstone bag finds the pipe in time when constructing.
Preferably, in the step C, the end of the pipe is blocked with gauze or polybag cladding.
Preferably, after performing the step D, dug at the tube end of the operating pit offside and connect hole, expose institute Tube end is stated, is easy to subsequently thread in the tube, and hole is connected with being filled with described in the woven bag backfill of sandstone, is easy to follow-up The end that sandstone bag finds the pipe is taken out when wearing cable construction in time.
In summary, by adopting the above-described technical solution, the beneficial effects of the invention are as follows:
1st, set with a kind of construction method for passing through existing roadbed pipeline of the present invention, drilling construction using small-sized It is standby, roadbed will not be affected greatly, not influence existing line normal operation, it is not necessary to cashed the skylight phase and construct again, construct The more existing artificial ditching of efficiency is passed through roadbed and greatly improved, and effectively reduces construction cost, and this method step is simple, easy to operate, It is easy to promotion and implementation;
2nd, with a kind of construction method for passing through existing roadbed pipeline of the present invention, when the caliber is more than 80mm, Hole described in 50-60mm reamer counterborings is first used, then with hole described in the reamer counterboring of the caliber is adapted to, in this way, Avoid using relatively high power motor during disposable enlarged diameter hole, bring larger vibration to influence the roadbed;
3rd, with a kind of construction method for passing through existing roadbed pipeline of the present invention, with the puncher boring procedure In appropriate water is injected by injector, in this way, by the puncher or the reamer in drilling process Front end needs the soil softening tunneled, beneficial to the vibration reduced in equipment attrition and reduction work progress.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram for the construction method for passing through existing roadbed pipeline of the present invention;
Fig. 2 is a kind of flow chart for the construction method for passing through existing roadbed pipeline of the present invention.
Marked in figure:1- roadbeds, 2- grounds, 3- operating pits, 4- pipes, 5- connect hole.
Embodiment
With reference to test example and embodiment, the present invention is described in further detail.But this should not be understood Following embodiment is only limitted to for the scope of the above-mentioned theme of the present invention, it is all that this is belonged to based on the technology that present invention is realized The scope of invention.
Embodiment
As shown in Figure 1-2, a kind of construction method for passing through existing roadbed pipeline of the present invention, comprises the following steps:
A, operating pit 3 is excavated downwards in the side ground 2 of roadbed 1;
B, at least one hole is bored to the opposite side of the roadbed 1 in the operating pit 3;
C, pipe 4, the end-enclosed of the pipe 4 are penetrated into each hole;
D, after the pipe 4 is set in place, backfilled into the operating pit 3, complete construction.
Wherein, the operating pit 3 is excavated in step A downwards and exposes the ground 2 under the roadbed 1, and is beaten in this place The roadbed 1 is passed through in hole;By the end-enclosed of the pipe 4 in the step C, soil enters the pipe 4 during avoiding poling Inside, influence to thread in the follow-up pipe 4;In the step D, the operating pit 3 is backfilled using the woven bag for being filled with sandstone, The end that sandstone bag finds the pipe 4 is taken out when being easy to subsequently wear cable construction in time.It should be noted that operation described herein Space required for the size adaptation puncher work in hole 3.
As a preferred scheme of the present embodiment, in the step B, the hole first is molded with puncher, then use reaming Device expands in the aperture in the hole to the caliber of the pipe 4 needed for adaptation.When need through the caliber of the pipe 4 be more than 80mm When, the first hole described in diameter 50-60mm reamer counterborings, then with hole described in the reamer counterboring of the caliber is adapted to, using this Kind mode, avoids using relatively high power motor during disposable enlarged diameter hole, brings larger vibration to influence the roadbed 1.Often use The puncher creeps into 1-2m, sets extension bar to be further continued for drilling on the puncher.With in the puncher boring procedure Appropriate water is injected by injector, in this way, by before the puncher or the reamer in drilling process End needs the soil softening tunneled, and beneficial to reduction equipment attrition and reduces the vibration in work progress.In the step C, yarn is used Cloth or polybag cladding block the end of the pipe 4.After performing the step D, in the pipe 4 of the offside of operating pit 3 End is dug and connects hole 5, exposes the end of pipe 4, and connects hole 5 with being filled with described in the woven bag backfill of sandstone, after being easy to Continue and take out the end that sandstone bag finds the pipe 4 in time when wearing cable construction.
With a kind of construction method for passing through existing roadbed pipeline of the present invention, drilling construction application mini-plant, Roadbed will not be affected greatly, not influence existing line normal operation, it is not necessary to cash the skylight phase and construct again, efficiency of construction More existing artificial ditching is passed through roadbed and greatly improved, and effectively reduces construction cost, this method step is simple, easy to operate, is easy to Promotion and implementation.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should be included in the scope of the protection.

Claims (8)

1. a kind of construction method for passing through existing roadbed pipeline, it is characterised in that comprise the following steps:
A, operating pit (3) is excavated downwards in roadbed (1) side ground (2);
B, at least one hole is bored to the opposite side of the roadbed (1) in the operating pit (3);
C, pipe (4), the end-enclosed of the pipe (4) are penetrated into each hole;
D, after the pipe (4) is set in place, backfilled into the operating pit (3), complete construction.
2. the construction method according to claim 1 for passing through existing roadbed pipeline, it is characterised in that in the step B, first The hole is molded with puncher, then is expanded in the aperture in the hole to the caliber of the pipe (4) needed for adaptation with reamer.
3. the construction method according to claim 2 for passing through existing roadbed pipeline, it is characterised in that when need through institute When stating the caliber of pipe (4) and being more than 80mm, the first hole described in diameter 50-60mm reamer counterborings, then with the expansion for being adapted to the caliber Hole described in the device counterboring of hole.
4. the construction method according to claim 2 for passing through existing roadbed pipeline, it is characterised in that often with the puncher 1-2m is crept into, sets extension bar to be further continued for drilling on the puncher.
5. the construction method according to claim 2 for passing through existing roadbed pipeline, it is characterised in that with the punching machine drill Appropriate water is injected during hole by injector.
6. the construction method for passing through existing roadbed pipeline according to claim any one of 1-5, it is characterised in that the step In rapid D, the operating pit (3) is backfilled using the woven bag for being filled with sandstone.
7. the construction method for passing through existing roadbed pipeline according to claim any one of 1-5, it is characterised in that the step In rapid C, the end of the pipe (4) is blocked with gauze or polybag cladding.
8. the construction method according to claim 7 for passing through existing roadbed pipeline, it is characterised in that perform the step D Afterwards, dug in the pipe (4) end of the operating pit (3) offside and connect hole (5), expose the pipe (4) end, and with filling The woven bag for having sandstone connects hole (5) described in backfilling.
CN201710853269.8A 2017-09-20 2017-09-20 A kind of construction method for passing through existing roadbed pipeline Pending CN107620831A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710853269.8A CN107620831A (en) 2017-09-20 2017-09-20 A kind of construction method for passing through existing roadbed pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710853269.8A CN107620831A (en) 2017-09-20 2017-09-20 A kind of construction method for passing through existing roadbed pipeline

Publications (1)

Publication Number Publication Date
CN107620831A true CN107620831A (en) 2018-01-23

Family

ID=61090107

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710853269.8A Pending CN107620831A (en) 2017-09-20 2017-09-20 A kind of construction method for passing through existing roadbed pipeline

Country Status (1)

Country Link
CN (1) CN107620831A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109869154A (en) * 2019-02-26 2019-06-11 朔黄铁路发展有限责任公司 Under wear existing railway technique and lower penetrating device
CN112747173A (en) * 2020-12-29 2021-05-04 河北华友文化遗产保护股份有限公司 Ancient building pipe penetrating construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1095807A (en) * 1994-01-31 1994-11-30 戴君 Under-road pipeline construction method without breaking road surface
CN1280263A (en) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 Construction method of drawing casing through drilled hole
CN102147033A (en) * 2010-02-09 2011-08-10 中国机械工业建设总公司 Non-excavation directional traversing construction method for thermal power pipeline
CN102661441A (en) * 2012-04-23 2012-09-12 于占国 Trenchless pipeline construction method
CN102953683A (en) * 2012-11-27 2013-03-06 福建省泷澄建设集团有限公司 Pipe pulling construction method through horizontal directional drilling
CN103398215A (en) * 2013-08-20 2013-11-20 江苏沃迪建设工程有限公司 Minimally-invasive non-excavation pipe jacking and pull technology
CN103791159A (en) * 2012-11-02 2014-05-14 成张佳宁 Pipe-jacking construction method for small-diameter pipes
CN105673934A (en) * 2015-12-24 2016-06-15 上海神洁环保科技股份有限公司 Non-excavation cable laying and pipe arranging method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1095807A (en) * 1994-01-31 1994-11-30 戴君 Under-road pipeline construction method without breaking road surface
CN1280263A (en) * 1999-07-12 2001-01-17 四川石油管理局川东钻探公司 Construction method of drawing casing through drilled hole
CN102147033A (en) * 2010-02-09 2011-08-10 中国机械工业建设总公司 Non-excavation directional traversing construction method for thermal power pipeline
CN102661441A (en) * 2012-04-23 2012-09-12 于占国 Trenchless pipeline construction method
CN103791159A (en) * 2012-11-02 2014-05-14 成张佳宁 Pipe-jacking construction method for small-diameter pipes
CN102953683A (en) * 2012-11-27 2013-03-06 福建省泷澄建设集团有限公司 Pipe pulling construction method through horizontal directional drilling
CN103398215A (en) * 2013-08-20 2013-11-20 江苏沃迪建设工程有限公司 Minimally-invasive non-excavation pipe jacking and pull technology
CN105673934A (en) * 2015-12-24 2016-06-15 上海神洁环保科技股份有限公司 Non-excavation cable laying and pipe arranging method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109869154A (en) * 2019-02-26 2019-06-11 朔黄铁路发展有限责任公司 Under wear existing railway technique and lower penetrating device
CN109869154B (en) * 2019-02-26 2020-08-11 朔黄铁路发展有限责任公司 Underpass device for existing railway
CN112747173A (en) * 2020-12-29 2021-05-04 河北华友文化遗产保护股份有限公司 Ancient building pipe penetrating construction method

Similar Documents

Publication Publication Date Title
CN103410182B (en) Unilateral pile foundation unloading horizontal top-level pull deviation rectifying and broken pile reinforcement construction method
CN102071683A (en) Water drill dug pile construction method
CN110195580A (en) A kind of gas-liquid two-phase synergy coal seam anti-reflection method
CN104198676B (en) A kind of fender graded method being applicable to milling and holing
CN104775433A (en) Pile extracting construction method
CN107620831A (en) A kind of construction method for passing through existing roadbed pipeline
CN103277037A (en) Pipe pile leading-hole construction method under boulder cluster geological condition
KR20080027481A (en) Ground boring method using multi-point rock boring
CN101251020A (en) Subsection hole-drilling repeatedly slip-casting method
CN111944997B (en) Horizontal hole electroosmosis pipeline liquid collecting method
CN103835647A (en) Method for drilling floating pebble bed
CN102828692A (en) Pneumatic drilling method for casing pipe type spiral drilling machine
CN110645033A (en) Device and method for deep grouting in sandy cobble stratum shield construction tunnel
CN212716448U (en) Drill bit with reamer
KR102186261B1 (en) Order wall installation device and order wall installation method for constructing ground drilling
JPH11256970A (en) Excavating method for hard rock bed and its device
CN209654048U (en) A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN209293677U (en) A kind of sidetracked hole may be selected to exempt to bore mill completion system
CN206034466U (en) Foundation ditch or basic groove precipitation system for construction
CN206785383U (en) A kind of duct fracturing device
CN102003191B (en) Mine curtain grouting effect determining method
CN104533444B (en) Time-factor considered dynamic allocation method of shield tunnel structure
CN116971733B (en) Probing and injecting integrated machine tool and process suitable for tunneling under complex geological conditions
CN109184743A (en) Existing tunnel construction method is worn under circle boulder clay rock compound stratum slurry shield short distance
CN108266198A (en) A kind of expanding shield machine

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180123