CN209654048U - A kind of water discharge tunnel tunnel shielding portal pre-buried structure - Google Patents

A kind of water discharge tunnel tunnel shielding portal pre-buried structure Download PDF

Info

Publication number
CN209654048U
CN209654048U CN201920390777.1U CN201920390777U CN209654048U CN 209654048 U CN209654048 U CN 209654048U CN 201920390777 U CN201920390777 U CN 201920390777U CN 209654048 U CN209654048 U CN 209654048U
Authority
CN
China
Prior art keywords
portal
hole
antetheca
tunnel
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920390777.1U
Other languages
Chinese (zh)
Inventor
李新
朱先杰
曹鹏飞
李昊雨
陈建
陈晨
王文芬
马涛
袁明国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN201920390777.1U priority Critical patent/CN209654048U/en
Application granted granted Critical
Publication of CN209654048U publication Critical patent/CN209654048U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of water discharge tunnel tunnel shielding portal pre-buried structures, including location hole, route hole, the hanging ring, spy ground hole being embedded on portal, route hole is embedded in portal rear wall, hanging ring is embedded in portal antetheca, portal surrounding has constructed portal periphery wall, and portal periphery wall is connected with bottom plate below, and location hole penetrates portal to hole portal rear wall from portal antetheca, and be connected to route hole one end by elbow, the other end in route hole is connected to another location hole by elbow;Ground hole is visited to be embedded on portal, on portal from top to bottom, layering be staggered pre-buried, and penetrate portal to portal rear wall from portal antetheca, shell manway end is blocked by seeping seepy material after visiting ground hole, and antetheca side outlet end is sealed by dismountable sealing device.The utility model solves and can not conveniently and efficiently find out underground water leakage scenarios before tunnel shielding portal is abolished in advance, and when tunnel shielding portal is abolished, and abolishes that intensity is big, the problem of low efficiency and safety difference.

Description

A kind of water discharge tunnel tunnel shielding portal pre-buried structure
Technical field
The utility model belongs to hydraulic engineering field, is related to a kind of water discharge tunnel tunnel shielding portal pre-buried structure.
Background technique
In tunnel shield driving technique, to ensure operation safety, shield received well (or starting well) and tunnel junction Portal again abolishes portal into hole or before appearing frequently with reinforced concrete wall (portal) temporary plugging, to shield machine.Portal is broken Except mainly being carried out using man-hour manually hand-held pneumatic pick, drilling machine etc., operating efficiency is lower, manually cuts that intensity is higher, and the duration is longer;Operation Face noise, dust etc. are larger, and there are more unfavorable factors for occupational health;When portal size is larger, job platform need to be set up, it is high Also there is certain security risk in place's operation.Currently, abolishing that have the degree of automation such as rope saw higher for large-scale, hard block Mechanical equipment can greatly reduce and reduce the investment of manpower.But it is limited by shield driving technique and received well (or to originate Well) limitation that applies process, fail to introduce relevant automatic equipment into abolishing for tunnel shielding portal, main cause includes two sides Face: first is that portal is underground soil-baffling structure, buried depth number meter, more than ten rice even tens of rice are differed, and portal rear wall is (close before abolishing Tunnel side) full of banketing, higher underground soil pressure (water pressure) is born, personnel not can enter and reach, can not be by sawing of restricting It cuts rope and passes through wall and the back side soil body, form the steric requirements of operation;Second is that shield received well (or starting well) geological conditions is not One, the complicated multiplicity of space enrironment causes foundation pit enclosure structure, support system various informative, and portal structure form is also different, and Portal is generally formed with the completion of foundation pit enclosure, supporting together, based on the factor of reason one, by cutting tool introduce also compared with For difficulty.But when the foundation pit form of shield received well (or starting well), structure function and different conventional method, cutting tool Introducing become as a kind of possibility.Such as in the shield-tunneling construction of Binhai Generator Station water discharge tunnel, siphonic water-collecting well doubles as shield received well, root According to site condition and geological condition, siphonic water-collecting well foundation pit is that classification slope is excavated, the sequence of construction taken are as follows: siphonic water-collecting well (received well) (shield launching synchronous averaging is simultaneously for excavation of foundation pit (starting well synchronous construction) → siphonic water-collecting well external structure and partial internal structure construction Driving) → siphonic water-collecting well (received well) and tunnel junction portal temporary plugging → siphonic water-collecting well foundation pit backfill → shield driving to siphon Well foundation pit nearby → siphonic water-collecting well (received well) portal abolishes → shield machine passes through portal → shield machine and reach received well → shield machine Hang out received well → siphonic water-collecting well residue internal structure construction.Using this sequence of construction, it is two with the main distinction of Normal practice A aspect: it first is that siphonic water-collecting well doubles as shield received well, after the completion of siphonic water-collecting well external structure and partial internal structure are constructed, then carries out Portal temporary plugging;Second is that increasing foundation pit backfill process, portal temporary plugging must be completed before foundation pit backfill.If item can be created The cutting tools such as rope saw are applied to portal and abolished, will play positive effect to the propulsion of engineering by part, have stronger reality meaning Justice and value.In addition, shield machine passes through siphonic water-collecting well (received well) excavation slope and reaches received well after using aforementioned sequence of construction Before, the original sealing system of foundation pit is just destroyed because shield machine passes through, and underground water just carries out seepage flow along shield machine driving path, if Siphonic water-collecting well (received well) portal rear wall (close to tunnel side) backfill effect is not ideal enough, after portal is abolished, just there is underground water The risk poured in, there are very big security risks.Risk is poured in eliminate underground water, Normal practice is when portal is abolished, in hole Men Shangyong drilling machine drills out several level detection holes on portal, judges construction risk, but this method according to infiltration water flow artificial situation It not only needs to call in special equipment, set up job platform, high-rise working, and increase security risk, increase human input, delay Construction period.If, using a kind of simple method, the infiltration situation of underground water can be found out in advance when portal is abolished, have compared with Strong security implications and application value.
Utility model content
In view of the shortcomings of the prior art, the utility model provides a kind of water discharge tunnel tunnel shielding portal pre-buried structure, To solve to carry out in the prior art conveniently and efficiently find out underground water leakage scenarios, Yi Ji in advance before tunnel shielding portal is abolished When tunnel shielding portal is abolished, abolish that intensity is big, the technical problem of low efficiency and safety difference.
In order to solve the above-mentioned technical problem, it realizes the utility model aim, adopts the following technical scheme that: a kind of water discharge tunnel Tunnel shielding portal pre-buried structure, including location hole, route hole, the hanging ring, spy ground hole being embedded on portal, route hole is embedded in portal Rear wall (tunnel side), hanging ring are embedded in portal antetheca (received well side), and portal surrounding has constructed portal periphery wall, portal periphery Wall is connected with bottom plate below, and location hole penetrates portal to portal rear wall (tunnel side) from portal antetheca (received well side), And be connected to route hole one end by elbow, the other end in route hole is connected to another location hole by elbow;It is pre-buried to visit ground hole On portal, on portal from top to bottom, layering be staggered pre-buried, and penetrate portal to portal rear wall from portal antetheca, visit ground Shell manway end is blocked by seeping seepy material behind hole, and antetheca side outlet end is sealed by dismountable sealing device.
Further, the infiltration seepy material is rubble, and shell manway is blocked by string bag package rubble after visiting ground hole, and Rubble filtering layer is backfilled around shell manway end after visiting ground hole.
Further, dismountable sealing device includes flange, bolt and blind plate, before portal is stretched out in spy ground hole Wall is connected with flange, and the blind plate is bolted on flange.
Further, the location hole, route hole are that PVC or PPR pipe are pre-buried.
Further, spy ground hole is that steel pipe is pre-buried, and the antetheca side of portal is stretched out in its outlet end.
Compared with prior art, the utility model has the following beneficial effects:
The structure is formed from portal antetheca to portal rear wall by location hole, route hole and elbow again to the company of portal antetheca Siphunculus road, cutting rope, which pierces into this connecting pipeline and can facilitate, cuts portal, and portal is cut into several pieces, logical using loop wheel machine It crosses the hanging ring being embedded on cutting cube to hang out cutting cube, so that tunnel shielding portal be made to abolish cost, at low cost, easy for construction, work Industry is high-efficient, reduces and manually abolishes intensity, reduces broken block cleaning workload, reduce the occupational hazards such as noise, dust and High-rise working risk;Before abolishing, i.e., before rope saw cuts portal, by opening the blind plate visited on ground hole being arranged on portal, According to from the infiltration streamflow regime for visiting the outflow of ground hole, judge whether portal can be abolished, thus precognition and evaluation of subterranean water penetration Risk reduces security risk, reduces the investment such as human resources, shortens the construction period.In short, the utility model structure is simple, apply Work is convenient and efficient, at low cost, high-efficient and highly-safe.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and embodiments.
Fig. 1 is the utility model structural facades figure;
Fig. 2 is A-A sectional view in the utility model Fig. 1;
Fig. 3 is B-B sectional view in the utility model Fig. 1;
Fig. 4 is Tu1Zhong thin portion area a enlarged drawing;
Fig. 5 is Tu2Zhong thin portion area b enlarged drawing;
Fig. 6 is Tu3Zhong thin portion area c enlarged drawing;
In figure: 1- portal;2- location hole;3- route hole;4- elbow;5- hanging ring;6- cutting line;7- portal periphery wall; 8- bottom plate;9- cutting rope;10- bolt;11- rubble filtering layer;12- visits ground hole;13- flange;14- blind plate;15- wraps up rubble.
Specific embodiment
Further explanation is made to the utility model with reference to the accompanying drawing, the utility model embodiment includes but is not limited to The following example.
As shown in Figures 1 to 6, the utility model provides a kind of water discharge tunnel tunnel shielding portal pre-buried structure, including pre-buried Location hole 2, route hole 3, hanging ring 5, spy ground hole 12 on portal 1, route hole 3 is embedded in 1 rear wall of portal (tunnel side), hanging ring 5 are embedded in 1 antetheca of portal (received well side), and 1 surrounding of portal has constructed portal periphery wall 7, portal periphery wall 7 with below Bottom plate 8 be connected, location hole 2 penetrates portal to portal rear wall (tunnel side) from portal antetheca (received well side), and with route hole 3 One end is connected to by elbow 4, and the other end in route hole 3 is connected to another location hole 2 by elbow 4;It visits ground hole 12 and is embedded in hole On door 1, on portal 1 from top to bottom, layering be staggered pre-buried, and penetrate portal to portal rear wall from portal antetheca, visit ground hole Shell manway end is blocked by seeping seepy material after 12, and preferably infiltration seepy material is rubble, and shell manway passes through after visiting ground hole 12 The string bag wraps up rubble 15 and blocks, and backfills rubble filtering layer around shell manway end after visiting ground hole 12;Ground 12 antetheca side of hole is visited to go out Mouth end is sealed by dismountable sealing device, and preferably dismountable sealing device includes flange 13, bolt 10 and blind plate 14, institute It states the spy ground stretching of hole 12 portal antetheca to be connected with flange 13, the blind plate 14 is fixed on flange 13 by bolt 10.It is wherein fixed Before position hole 2, route hole 3 are that PVC or PPR pipe are pre-buried, and it is pre-buried for steel pipe to visit ground hole 12, and portal 1 is stretched out in its outlet end Wall side.
When the pre-buried structure, weight is lifted according to loop wheel machine maximum, calculates the maximum allowable size of cutting block, knot in advance It closes portal size and cutting subregion is carried out to portal, each block that cuts must not exceed loop wheel machine maximum lifting weight;It is tied up in portal reinforcing bar During bundle, setting-out is measured according to cutting subregion, marks position and the trend of cutting line 6;It is pre-buried fixed on cutting line 6 Position hole 2, route hole 3, and pre-buried 3 or 4 hanging rings 5, location hole 2 are (close from portal antetheca on cutting cube according to lifting requirements Received well side) portal is penetrated to portal rear wall (close to tunnel side), location hole 2 and route hole 3 are connected to by elbow 4, using D50 The pvc pipe of diameter or PPR pipe etc. be used as location hole 2, route hole 3, the pre-buried pipeline of elbow 4, using 14 steel bar meter of ¢ it is good after conduct Pre-buried hanging ring 5.Using diameter D100 and the steel pipe with flange 13 is pre-buried in advance as ground hole 12 is visited, and it is pre- on portal to visit ground hole 12 Bury principle be from top to bottom, layering be staggered, using the string bag package rubble 15 will visit ground hole 12 after shell manway block.In pre-buried mistake Cheng Zhong, pre-buried pipeline and pre-buried hanging ring and reinforcing bar are bound the positioning that pre-buried pipeline is securely checked during template support and Trend.
After portal demoulding, when foundation pit has backfill condition, in the 5m width range of portal two sides, along canal axes 5m length model In enclosing, back-filling in layers cement volume is the soil cement of 15% ratio, when being backfilled to spy ground 12 entrance of hole, starts to backfill Rubble filtering layer is advisable with wrapping to visit ground hole entrance and other backfill material has been prevented to be mixed into, is then further continued for backfill soil cement point After layer is densified to 1 river rising in Ningxia and flowing into central Shaanxi Bei Dong absolute altitude of hole top top, finally using mountain skin earthen backfill to foundation pit top.In backfilling process, it should prevent The miscellaneous hard block of backfill equipment, backfill feed collet touches pre-buried pvc pipe (or PPR pipe), in order to avoid cause tubing damaged.Work as shield Machine passes through siphonic water-collecting well (received well) foundation pit, before soon reaching portal 1, opens blind plate 14, the infiltration flowed out according to from visiting hole 12 Streamflow regime, judges whether portal can be abolished, and if amount of seepage is excessive, need to take corresponding measure (second pulp feeding etc.);Such as nothing Water or amount of seepage very little are permeated, cutting is carried out to portal using rope saw and is abolished, before formal cutting, is guided using thin wire, it will Cutting rope 9 is directed across location hole 2 and route hole 3;After rope saw and ready cutting rope 9 etc., according to the positioning of location hole 2 and The trend of route hole 3 cuts portal, logical using loop wheel machine after the completion of each side of each monolith (three or four edges) is cut The hanging ring 5 being embedded on cutting cube is crossed to hang out its entirety.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art within the technical scope disclosed by the utility model, can readily occur in Change or replacement, should be covered within the scope of the utility model.

Claims (5)

1. a kind of water discharge tunnel tunnel shielding portal pre-buried structure, including be embedded on portal (1) location hole (2), route hole (3), Hanging ring (5) visits ground hole (12), and route hole (3) are embedded in portal (1) rear wall, and hanging ring (5) is embedded in portal (1) antetheca, portal (1) surrounding has constructed portal periphery wall (7), and portal periphery wall (7) is connected with bottom plate (8) below, it is characterised in that: Location hole (2) penetrates portal to hole portal rear wall from portal antetheca, and is connected to route hole (3) one end by elbow (4), route The other end in hole (3) is connected to another location hole (2) by elbow (4);
Ground hole (12) is visited to be embedded on portal (1), on portal (1) from top to bottom, layering be staggered it is pre-buried, and from portal antetheca Portal is penetrated to portal rear wall, visiting ground hole (12), shell manway end is blocked by seeping seepy material afterwards, and antetheca side outlet end is logical Cross dismountable sealing device sealing.
2. a kind of water discharge tunnel tunnel shielding portal pre-buried structure according to claim 1, it is characterised in that: the infiltration pervious material Material is rubble, and visiting ground hole (12), shell manway is blocked by string bag package rubble (15) afterwards, and is entered visiting ground hole (12) rear wall side Mouth backfills rubble filtering layer around end.
3. a kind of water discharge tunnel tunnel shielding portal pre-buried structure according to claim 1, it is characterised in that: described dismountable Sealing device includes flange (13), bolt (10) and blind plate (14), and the spy ground hole (12) stretches out portal antetheca and flange (13) It is connected, the blind plate (14) is fixed on flange (13) by bolt (10).
4. a kind of water discharge tunnel tunnel shielding portal pre-buried structure according to claim 1, it is characterised in that: the location hole (2), route hole (3) are that PVC or PPR pipe are pre-buried.
5. a kind of water discharge tunnel tunnel shielding portal pre-buried structure according to claim 1, it is characterised in that: spy ground hole (12) pre-buried for steel pipe, and the antetheca side of portal (1) is stretched out in its outlet end.
CN201920390777.1U 2019-03-26 2019-03-26 A kind of water discharge tunnel tunnel shielding portal pre-buried structure Active CN209654048U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920390777.1U CN209654048U (en) 2019-03-26 2019-03-26 A kind of water discharge tunnel tunnel shielding portal pre-buried structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920390777.1U CN209654048U (en) 2019-03-26 2019-03-26 A kind of water discharge tunnel tunnel shielding portal pre-buried structure

Publications (1)

Publication Number Publication Date
CN209654048U true CN209654048U (en) 2019-11-19

Family

ID=68528124

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920390777.1U Active CN209654048U (en) 2019-03-26 2019-03-26 A kind of water discharge tunnel tunnel shielding portal pre-buried structure

Country Status (1)

Country Link
CN (1) CN209654048U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826643A (en) * 2019-03-26 2019-05-31 江苏建筑职业技术学院 A kind of water discharge tunnel tunnel shielding portal pre-buried structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826643A (en) * 2019-03-26 2019-05-31 江苏建筑职业技术学院 A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN109826643B (en) * 2019-03-26 2024-02-09 江苏建筑职业技术学院 Pre-buried structure of drainage tunnel shield tunnel portal

Similar Documents

Publication Publication Date Title
CN105780793B (en) A kind of high artesian stratum Foundation Pit Pouring emergency processing method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN103821544B (en) Tunneling and underground engineering high-pressure high-flow is dashed forward Water outburst treatment method
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN106837351A (en) Tunnel karst water detection and treatment method
CN108867814A (en) It is newly-built to cut dirty branch pipe and existing sewage network is plugged into engineering method
CN111997639B (en) Method for getting rid of trouble and reinforcing and improving geology of TBM construction tunnel bad geology section card machine
CN111810199A (en) Tunnel water inrush disaster prevention treatment method
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN108194704B (en) One kind wearing river technique
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN104532842A (en) Sleeve rotating friction type breaking pile-extracting construction method
CN111101964A (en) Construction method for blocking receiving tunnel portal by shield method
CN105464194A (en) Water proofing and leak repairing construction method for sewage pipe network below underground water level
CN105257309B (en) In a kind of layer of sand in balancing earth-pressure shielding machine storehouse slip casting tool changing construction method
CN110685272B (en) Method for treating soft foundation settlement overrun by utilizing inclined-hole cloth bag pile
CN111441819A (en) Tunnel advanced exploratory hole karst high-pressure water burst plugging device and method
CN209654048U (en) A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN109555140A (en) Foundation pit and Tunnel Base spring pump drainage method for blocking and device
JP2009068213A (en) Construction method for underground structure using caisson, and caisson with cut-off device
CN201554005U (en) Large-flow and high-speed jet sealing drilling and pouring orifice safety control device under high pressure water
CN109826643A (en) A kind of water discharge tunnel tunnel shielding portal pre-buried structure
CN110030006A (en) There is the shield tunneling method of a large amount of boulders by saturated sand and in layer of sand
CN105221182B (en) Coal uncovering method under the complex geological condition of pole
CN214363571U (en) Underground cavern dewatering system free of influence of obstacles

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant