CN107620543A - A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method - Google Patents

A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method Download PDF

Info

Publication number
CN107620543A
CN107620543A CN201711155854.7A CN201711155854A CN107620543A CN 107620543 A CN107620543 A CN 107620543A CN 201711155854 A CN201711155854 A CN 201711155854A CN 107620543 A CN107620543 A CN 107620543A
Authority
CN
China
Prior art keywords
door
window
window opening
auxiliary frame
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711155854.7A
Other languages
Chinese (zh)
Inventor
殷俊涛
张龙洋
张俊国
安会丽
马克
刘国全
王肖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201711155854.7A priority Critical patent/CN107620543A/en
Publication of CN107620543A publication Critical patent/CN107620543A/en
Pending legal-status Critical Current

Links

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)

Abstract

A kind of door-window opening waterproofing node structure, described waterproofing node structure setting is at door-window opening, described waterproofing node structure includes anchoring piece, steel auxiliary frame is fixed on door-window opening by anchoring piece, JS waterproof coating layers are provided with the side of steel auxiliary frame and the junction of door-window opening, JS waterproof coating layers outer surface is provided with exterior trim surface layer;Outer door-window opening periphery is optimized for whole concrete structure by the present invention by drawing Deepen Design, during main structure construction, pre-buried 20mm*40mm*1.6mm hot-galvanized steel sides lead on the aluminum alloy pattern plate of hole surrounding side, logical door and window measure list cutting side of pressing of side leads to, anchoring piece is welded with side is logical, the logical both sides in side are blocked using foamed glue, concrete is avoided to flow into, side is logical to be fixed using self-tapping screw with aluminum alloy mould plate, and it is cast in together in agent structure with concrete, led to by steel side pre-buried, avoid pollution of the later stage civil engineering to door and window, damage, corrosion, the generation of leakage passage is prevented, ensure to save cost while construction quality.

Description

A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method
Technical field
The invention belongs to technical field of buildings, and in particular to a kind of door-window opening waterproofing node structure and outer door and window pre-buried steel Secondary frame construction method.
Background technology
In building field, it is a more scabrous common quality defect that the infiltration of exterior wall windowsill, which is damaged, polluted with door and window, and Owner complains one of more quality problems;Continuous development and the maturation of architectural decorative and fitting materialses and construction technology, is built Beyond the region of objective existence vertical-face building way increasingly becomes more meticulous, standardizes and batch production, meanwhile, owner also to its door and window position, size and has It is more and more careful to close functional requirement.
After the door-window opening of building is built up, because the size of door-window opening is not very specification, therefore be difficult essence Door and window processing dimension really is determined, it is also relatively difficult when door-window opening installs doorframe, therefore typically can be in door-window opening position Secondary frame is installed so that play a part of the positioning of scale to door and window, can relatively accurately determine door and window processing dimension, can be with Strengthen the normalization of erection of doors and windows, improve door and window processing efficiency and installation effectiveness;Secondly, prior art is between door and window and secondary frame Sealing requirements it is not high, it is easy to there is the phenomenon to seep water.
The content of the invention
The present invention is in order to solve weak point of the prior art, there is provided one kind can solve the problem that the infiltration of traditional door and window hole and The door-window opening waterproofing node structure of pollution and outer door and window pre-buried steel pair frame construction method.
In order to solve the above technical problems, the present invention adopts the following technical scheme that:A kind of door-window opening waterproofing node structure, institute For the waterproofing node structure setting stated at door-window opening, described waterproofing node structure includes anchoring piece, and steel auxiliary frame passes through anchoring Part is fixed on door-window opening, and JS waterproof coating layers are provided with the side of steel auxiliary frame and the junction of door-window opening, and JS waterproofs apply Bed of material outer surface is provided with exterior trim surface layer, and sash is fixed on steel auxiliary frame by fastening bolt and trip bolt, the side of sash Outer frame lateral section is shaped as convex shape, has gap between the frame of sash and the inwall of door-window opening, is filled in gap There are foaming agent packed layer and the silicone weatherproof sealant for seal foaming agent packed layer.
Described anchoring piece includes the first spiral, and the size of the first spiral is:Long 60mm, diameter 6mm, first Spiral end is welded with long 25mm diameters 6mm the second spiral, and steel auxiliary frame is formed by connecting by steel side is logical, what steel side led to Sectional dimension is 20mm*40mm*1.6mm.
Outer door and window pre-buried steel pair frame exempts to smear closing in construction method, comprises the following steps:
(1), steel side lead to type selecting, stock:Steel auxiliary frame is led to from the steel side of the inside and outside two-sided galvanizing of preservative treatment, its sectional dimension For 20mm*40mm*1.6mm;
(2), according to door and window drawing Deepen Design, draw blanking figure:In the aluminum alloy mould plate Deepen Design stage, with reference to door and window drawing Concrete structure is helped into the in-depth of door-window opening surrounding, and determines the headroom size of door-window opening and the blank size of sash; Anchoring piece is welded with above steel auxiliary frame, anchoring piece uses long 60mm diameters 6mm the first spiral, end reinforced welding length 25mm diameters 6mm the second spiral, anchoring piece spacing are divided equally and are not more than 500mm, the anchoring piece distance steel pair at both ends Frame end 150mm, steel auxiliary frame long edge size add 40mm equal to door-window opening width, and steel auxiliary frame short side dimension is that door-window opening is wide Degree;
(3), steel auxiliary frame processing, make, antirust paint mended at solder joint:Steel auxiliary frame concentrated processing blanking, weld anchor in factory floor Firmware etc. processes operation, and processing must be carried out according to technological requirement, and be checked and accepted through Quality Inspector, and the zinc-plated square tube of acceptance(check) is pressed Cutting scheme in manuscript is cut, and grinding process is carried out to the burr of otch, need to meet to be machined wanting for roughness Ask;
(4), steel auxiliary frame and aluminum alloy mould plate fix it is pre-buried:The self-tapping screw that the steel auxiliary frame processed passes through several diameters 4mm Interim occupy in wall is fixed on aluminum alloy mould plate, and adjacent self-tapping screw spacing is 300mm, sets and drips above door-window opening Line, door-window opening lower section and both sides set sloping layer;
(5), aluminum alloy mould plate installation reinforce:It is noted that pre-buried secondary frame and drip, looking for slope aluminium in aluminum alloy mould plate installation process The finished product protection of piece, prevent it from skew, deformation occur;
(6), concreting shaping:In concreting process, it should be noted that avoid the direct contact beams bottom aluminium alloy mould of vibrating head Plate, prevent steel auxiliary frame from loosening and deviation occur;
(7), aluminum alloy mould plate remove, recycle:Door-window opening aluminum alloy mould plate must treat concrete strength ensure its surface, Corner angle are not damaged because of form removal, can remove, and before aluminum alloy mould plate is removed, lead to connection steel side with electric hand drill closed with aluminium first The self-tapping screw of golden template connection is removed, and then with hammer and hook pin removal pin piece, is taken off to aluminum alloy mould plate and concrete From, forbid to be removed with crowbar and cause concrete corner angle to destroy, be first by aluminium alloy when going to next layer of utilization aluminum alloy mould plate week Template and drip, the concrete looked on the aluminium flake of slope is cleaned out and brushing releasing agent, avoids aluminum alloy mould plate related when removing Damage formation of concrete;
(8), inner-outer wall plastered, sash and bar are then installed.
Step(4)The middle setting line method that drips is by trapezoid cross section(12~20x10)Aluminium side common diameter 6mm rivet It is fixed on aluminum alloy mould plate;The method for setting sloping layer is will to look for slope aluminium flake(Wide 80mx thickness 10mm, there is groove one end)Pass through 6mm rivets are fixed on aluminum alloy mould plate.
Step(8)Middle inner-outer wall is plastered, and the method for installing sash and bar is:
a), brush JS waterproof coating layers:Surrounding repeatedly brushes JS water-repellent paints on the outside of door-window opening, must ensure that its thickness is more than Equal to 1.0mm, JS water-repellent paints total head steel auxiliary frame and must be brushed at the window opening external corner 50mm that moves into one's husband's household upon marriage;
b), exterior trim surface construction:JS water-repellent paints dry after, according to exterior finish way construct exterior trim surface layer, exterior finish finished surface with The frame of steel auxiliary frame is concordant;
c), installation sash:After the completion of exterior finish, sash and steel auxiliary frame are fixed using tapping screw, tapping screw Two wall thickness of steel auxiliary frame are screwed into, fluid sealant must be squeezed into before being screwed into;
d), beat foamed glue at gap between sash and steel auxiliary frame:Foamed glue is beaten in gap between sash and steel auxiliary frame, First gap should be cleaned out, and the winding diaphragm between sash and door-window opening be torn off, unnecessary hair before beating foamed glue Glue is steeped to be cut with blade after forbidding solidification in it solidifies preceding hand or specific purpose tool press-in gap;
e), break fluid sealant outside window:After exterior finish is completed and dried, the hitting property silicon at the inner corner trim of exterior finish Yu sash junction Ketone weather proofing sealant, pressure gate window frame is highly answered to be not less than 5mm;
f), bar installation:Bar and glass wall body surface decorative engineering should start preceding installation indoors;
g), interior Decorative Construction:According to finish coat in the construction of interior coating ways;
h), play window interior sealing glue:After interior facing is completed and dried, the hitting property silicon at the inner corner trim of interior facing Yu sash junction Ketone weather proofing sealant.
Above-mentioned technical proposal is used, the invention has the advantages that:The outer door and window waterproof quality of the present invention is reliable, Before structure construction, external door-window opening node carries out Deepen Design, then door and window connection is deepened, and steel side is logical to be used as outer door and window The pre-buried steel auxiliary frame in hole carries out concentrated processing, and positioning in advance is embedded on aluminum alloy mould plate, is once poured with agent structure concrete Type is pounded, later stage door and window directly using screw riveting installation, eliminates the cement mortar stuff up a crack in door-window opening traditional construction, smeared Ash closes up, and realizes dry operation, reduces later stage gaul, cracking, seepage equivalent risk, therefore the waterproof quality ten of outer door window section position Divide reliable.
Steel auxiliary frame Embedment Construction technique is simple, install convenient:Traditional secondary frame locating mounting method is first interim with timber wedge Fixed joint frame, secondary frame is fixed on concrete wall with expansible anchor of metal afterwards, gap is needed with dry between secondary frame and wall The filling of hydraulic cement mortar is closely knit, and fillet is smeared at surrounding inner corner trim, and mortar takes out interim canting quoin after reaching some strength, And fill out the gap with the closely knit benefit of dry cement mortar, but this construction process is more complicated, be affected by human factors it is larger, and Secondary frame need to be only arranged on by the way of steel auxiliary frame is pre-buried on aluminum alloy pattern plate, technique is simple, simple operation.
Be advantageous to the finished product protection of aluminum alloy doors and windows, avoid the damage or pollution of door and window:Outer door-window opening steel auxiliary frame is straight Connect and be embedded in concrete structure, after structure of the window shaping, aluminum alloy doors and windows can be directly mounted on steel auxiliary frame, therefore aluminium alloy Door and window will not be polluted or damaged by traditional closing in construction of plastering.
Door-window opening can effectively reduce or eliminate outer window frame surrounding using the construction method in the present invention and be plastered secondary Close up construction in issuable leakage problem, avoid plaster receive side when mortar to the issuable pollution of door and window and corruption Erosion, and later period maintenance cost is reduced, the present invention is applied in agent structure using in aluminum alloy mould plate construction, passes through figure first Outer door-window opening periphery is optimized for whole concrete structure by paper Deepen Design, during main structure construction, in hole surrounding side Pre-buried 20mm*40mm*1.6mm hot-galvanized steel sides lead on aluminum alloy pattern plate, and logical door and window measure list cutting side of pressing of side is logical, and side leads to upper weld Anchoring piece is connected to, the logical both sides in side are blocked using foamed glue, avoid concrete from flowing into, and side is logical to use self-tapping screw and aluminum alloy mould plate It is fixed, and be cast in together in agent structure with concrete, led to by steel side pre-buried, avoid later stage civil engineering to door and window Pollution, damage, corrosion, prevented the generation of leakage passage, ensured to save cost while construction quality.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of anchoring piece in the present invention;
Fig. 3 is pre-buried steel auxiliary frame measure figure;
Fig. 4 is door-window opening aluminum alloy mould plate installation node diagram suitable for reading;
Fig. 5 is that mouth aluminum alloy mould plate installs node diagram under door-window opening;
Fig. 6 is door-window opening side port aluminum alloy mould plate installation node diagram.
Embodiment
As shown in figure 1, a kind of door-window opening waterproofing node structure of the present invention, described waterproofing node structure setting is in door At window hole 1, described waterproofing node structure includes anchoring piece 2, and steel auxiliary frame 3 is fixed on door-window opening 1 by anchoring piece 2, JS waterproof coating layers 4 are provided with the side of steel auxiliary frame 3 Yu the junction of door-window opening 1, the outer surface of JS waterproof coating layers 4 is provided with outer Finish coat 5, sash 6 are fixed on steel auxiliary frame 3 by fastening bolt 7 and trip bolt 8, the outer lateral section of frame of sash 6 Be shaped as convex shape, there is gap between the frame of sash 6 and the inwall of door-window opening 1, foaming agent is filled with gap Packed layer 9 and the silicone weatherproof sealant 10 for seal foaming agent packed layer 9.
Described anchoring piece 2 includes the first spiral 11, and the size of the first spiral 11 is:Long 60mm, diameter 6mm, the end of the first spiral 11 are welded with long 25mm diameters 6mm the second spiral 12, and steel auxiliary frame 3 is led to by steel side to be connect Form, the logical sectional dimension in steel side is 20mm*40mm*1.6mm.
A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method, comprise the following steps:
(1), steel side lead to type selecting, stock:Steel auxiliary frame 3 is from the square steel of the inside and outside two-sided galvanizing of preservative treatment, its sectional dimension For 20mm*40mm*1.6mm;
(2), as shown in figure 3, according to door and window drawing Deepen Design, draw blanking figure:In the aluminum alloy mould plate Deepen Design stage, knot Close door and window drawing and concrete structure is helped into the in-depth of the surrounding of door-window opening 1, and determine the headroom size and sash of door-window opening 1 6 blank size;Steel auxiliary frame 3 is welded with anchoring piece 2 above, and anchoring piece 2 uses long 60mm diameters 6mm the first spiral 11, the end reinforced long 25mm diameters 6mm of welding the second spiral 12, the spacing of anchoring piece 2 is divided equally and is not more than 500mm, and two The anchoring piece 2 of end adds 40mm, steel pair apart from the end 150mm of steel auxiliary frame 3, the long edge size of steel auxiliary frame 3 equal to the width of door-window opening 1 The short side dimension of frame 3 is the width of door-window opening 1;
(3), steel auxiliary frame 3 process, make, at solder joint mend antirust paint:Steel auxiliary frame 3 concentrated processing blanking, welding in factory floor The grade of anchoring piece 2 processes operation, and processing must be carried out according to technological requirement, and be checked and accepted through Quality Inspector, by the zinc-plated side of acceptance(check) Pipe is cut by the cutting scheme in manuscript, is carried out grinding process to the burr of otch, need to be met to be machined roughness Requirement;
(4), steel auxiliary frame 3 fixed with aluminum alloy mould plate 13 it is pre-buried:The self tapping that the steel auxiliary frame 3 processed passes through several diameters 4mm Screw occupies in wall temporarily to be fixed on aluminum alloy mould plate 13, and adjacent self-tapping screw spacing is 300mm, and the top of door-window opening 1 is set Drip is put, the lower section of door-window opening 1 and both sides set sloping layer, referring to Fig. 4, Fig. 5 and Fig. 6;
(5), aluminum alloy mould plate 13 installation reinforce:It is noted that pre-buried secondary frame and drip, looking in the installation process of aluminum alloy mould plate 13 The finished product protection of slope aluminium flake, prevent it from skew, deformation etc. occur;
(6), concreting shaping:In concreting process, it should be noted that avoid the direct contact beams bottom aluminium alloy mould of vibrating head Plate 13, prevent steel auxiliary frame 3 from loosening and deviation occur;
(7), aluminum alloy mould plate 13 removes, recycles:The aluminum alloy mould plate 13 of door-window opening 1 must treat that concrete strength ensures it Surface, corner angle are not damaged because of form removal, can remove, and before aluminum alloy mould plate 13 is removed, will connect steel side with electric hand drill first The self-tapping screw that logical and aluminum alloy mould plate 13 connects is removed, then with hammer and hook pin removal pin piece, to aluminum alloy mould plate 13 depart from concrete, forbid to be removed with crowbar and cause concrete corner angle to destroy, aluminum alloy mould plate goes to next layer of utilization for 13 weeks When, first by aluminum alloy mould plate 13 and drip, the concrete looked on the aluminium flake of slope is cleaned out and brushing releasing agent, avoid aluminium from closing Related damage formation of concrete when golden template 13 is removed;
(8), inner-outer wall plastered, sash 6 and bar are then installed.
Step(4)The middle setting line method that drips is by trapezoid cross section(12~20x10)Aluminium side common diameter 6mm rivet It is fixed on aluminum alloy mould plate 13;The method for setting sloping layer is will to look for slope aluminium flake(Wide 80mx thickness 10mm, there is groove one end)It is logical 6mm rivets are crossed to be fixed on aluminum alloy mould plate 13.
Step(8)Middle inner-outer wall is plastered, and the method for installing sash 6 and bar is:
a), brush JS waterproof coating layers 4:JS water-repellent paints are repeatedly brushed in the outside surrounding of door-window opening 1, must ensure that its thickness is big In equal to 1.0mm, JS water-repellent paints total head steel auxiliary frame 3 and must be brushed at the window opening external corner 50mm that moves into one's husband's household upon marriage;
b), exterior trim surface construction:After JS water-repellent paints are dried, constructed exterior trim surface layer 5 according to exterior finish way, exterior finish finished surface with The frame of steel auxiliary frame 3 is concordant;
c), installation sash 6:After the completion of exterior finish, sash 6 and steel auxiliary frame 3 are fixed using tapping screw, self tapping spiral shell Nail is screwed into 3 two wall thickness of steel auxiliary frame, and fluid sealant must be squeezed into before being screwed into;
d), beat foamed glue at gap between sash 6 and steel auxiliary frame 3:Dismissed between sash 6 and steel auxiliary frame 3 in gap Glue is steeped, first should be cleaned out gap before beating foamed glue, and the winding diaphragm between sash 6 and door-window opening 1 is torn off, it is more Remaining foamed glue should be cut in it solidifies preceding hand or specific purpose tool press-in gap after forbidding solidification with blade;
e), break fluid sealant outside window:After exterior finish is completed and dried, the hitting property at the inner corner trim of exterior finish Yu the junction of sash 6 Silicone weatherproof sealant 10, pressure gate window frame 6 is highly answered to be not less than 5mm;
f), bar installation:Bar and glass wall body surface decorative engineering should start preceding installation indoors;
g), interior Decorative Construction:According to finish coat in the construction of interior coating ways;
h), play window interior sealing glue:After interior facing is completed and dried, the hitting property at the inner corner trim of interior facing Yu the junction of sash 6 Silicone weatherproof sealant 10.
The present embodiment is not that the shape to the present invention, material, structure etc. make any formal limitation, every according to this hair Any simple modification, equivalent change and modification that bright technical spirit is made to above example, belongs to the technology of the present invention side The protection domain of case.

Claims (5)

  1. A kind of 1. door-window opening waterproofing node structure, it is characterised in that:Described waterproofing node structure setting at door-window opening, Described waterproofing node structure includes anchoring piece, and steel auxiliary frame is fixed on door-window opening by anchoring piece, in steel auxiliary frame and door and window The side of the junction at hole is provided with JS waterproof coating layers, and JS waterproof coating layers outer surface is provided with exterior trim surface layer, and sash passes through Fastening bolt and trip bolt are fixed on steel auxiliary frame, and the outer lateral section of frame of sash is shaped as convex shape, sash There is gap between frame and the inwall of door-window opening, filled in gap filled with foaming agent packed layer and for seal foaming agent The silicone weatherproof sealant of layer.
  2. A kind of 2. door-window opening waterproofing node structure according to claim 1, it is characterised in that:Described anchoring piece includes First spiral, the size of the first spiral are:Long 60mm, diameter 6mm, the first spiral end is welded with long 25mm Diameter 6mm the second spiral, steel auxiliary frame are formed by connecting by steel side is logical, and the logical sectional dimension in steel side is 20mm*40mm* 1.6mm。
  3. 3. outer door and window pre-buried steel pair frame exempts to smear closing in construction method, it is characterised in that:Comprise the following steps:
    (1), steel side lead to type selecting, stock:Steel auxiliary frame is led to from the steel side of the inside and outside two-sided galvanizing of preservative treatment, its sectional dimension For 20mm*40mm*1.6mm;
    (2), according to door and window drawing Deepen Design, draw blanking figure:In the aluminum alloy mould plate Deepen Design stage, with reference to door and window drawing Concrete structure is helped into the in-depth of door-window opening surrounding, and determines the headroom size of door-window opening and the blank size of sash; Anchoring piece is welded with above steel auxiliary frame, anchoring piece uses long 60mm diameters 6mm the first spiral, end reinforced welding length 25mm diameters 6mm the second spiral, anchoring piece spacing are divided equally and are not more than 500mm, the anchoring piece distance steel pair at both ends Frame end 150mm, steel auxiliary frame long edge size add 40mm equal to door-window opening width, and steel auxiliary frame short side dimension is that door-window opening is wide Degree;
    (3), steel auxiliary frame processing, make, antirust paint mended at solder joint:Steel auxiliary frame concentrated processing blanking, weld anchor in factory floor Firmware etc. processes operation, and processing must be carried out according to technological requirement, and be checked and accepted through Quality Inspector, and the zinc-plated square tube of acceptance(check) is pressed Cutting scheme in manuscript is cut, and grinding process is carried out to the burr of otch, need to meet to be machined wanting for roughness Ask;
    (4), steel auxiliary frame and aluminum alloy mould plate fix it is pre-buried:The self-tapping screw that the steel auxiliary frame processed passes through several diameters 4mm Interim occupy in wall is fixed on aluminum alloy mould plate, and adjacent self-tapping screw spacing is 300mm, sets and drips above door-window opening Line, door-window opening lower section and both sides set sloping layer;
    (5), aluminum alloy mould plate installation reinforce:It is noted that pre-buried secondary frame and drip, looking for slope aluminium in aluminum alloy mould plate installation process The finished product protection of piece, prevent it from skew, deformation occur;
    (6), concreting shaping:In concreting process, it should be noted that avoid the direct contact beams bottom aluminium alloy mould of vibrating head Plate, prevent steel auxiliary frame from loosening and deviation occur;
    (7), aluminum alloy mould plate remove, recycle:Door-window opening aluminum alloy mould plate must treat concrete strength ensure its surface, Corner angle are not damaged because of form removal, can remove, and before aluminum alloy mould plate is removed, lead to connection steel side with electric hand drill closed with aluminium first The self-tapping screw of golden template connection is removed, and then with hammer and hook pin removal pin piece, is taken off to aluminum alloy mould plate and concrete From, forbid to be removed with crowbar and cause concrete corner angle to destroy, be first by aluminium alloy when going to next layer of utilization aluminum alloy mould plate week Template and drip, the concrete looked on the aluminium flake of slope is cleaned out and brushing releasing agent, avoids aluminum alloy mould plate related when removing Damage formation of concrete;
    (8), inner-outer wall plastered, sash and bar are then installed.
  4. 4. outer door and window pre-buried steel pair frame according to claim 3 exempts to smear closing in construction method, it is characterised in that:Step(4) The middle setting line method that drips is by trapezoid cross section(12~20x10)Aluminium side common diameter 6mm rivet be fixed on aluminum alloy mould plate On;The method for setting sloping layer is will to look for slope aluminium flake(Wide 80mx thickness 10mm, there is groove one end)Aluminium is fixed on by 6mm rivets to close In golden template.
  5. 5. outer door and window pre-buried steel pair frame according to claim 3 exempts to smear closing in construction method, it is characterised in that:Step(8) Middle inner-outer wall is plastered, and the method for installing sash and bar is:
    a), brush JS waterproof coating layers:Surrounding repeatedly brushes JS water-repellent paints on the outside of door-window opening, must ensure that its thickness is more than Equal to 1.0mm, JS water-repellent paints total head steel auxiliary frame and must be brushed at the window opening external corner 50mm that moves into one's husband's household upon marriage;
    b), exterior trim surface construction:JS water-repellent paints dry after, according to exterior finish way construct exterior trim surface layer, exterior finish finished surface with The frame of steel auxiliary frame is concordant;
    c), installation sash:After the completion of exterior finish, sash and steel auxiliary frame are fixed using tapping screw, tapping screw Two wall thickness of steel auxiliary frame are screwed into, fluid sealant must be squeezed into before being screwed into;
    d), beat foamed glue at gap between sash and steel auxiliary frame:Foamed glue is beaten in gap between sash and steel auxiliary frame, First gap should be cleaned out, and the winding diaphragm between sash and door-window opening be torn off, unnecessary hair before beating foamed glue Glue is steeped to be cut with blade after forbidding solidification in it solidifies preceding hand or specific purpose tool press-in gap;
    e), break fluid sealant outside window:After exterior finish is completed and dried, the hitting property silicon at the inner corner trim of exterior finish Yu sash junction Ketone weather proofing sealant, pressure gate window frame is highly answered to be not less than 5mm;
    f), bar installation:Bar and glass wall body surface decorative engineering should start preceding installation indoors;
    g), interior Decorative Construction:According to finish coat in the construction of interior coating ways;
    h), play window interior sealing glue:After interior facing is completed and dried, the hitting property silicon at the inner corner trim of interior facing Yu sash junction Ketone weather proofing sealant.
CN201711155854.7A 2017-11-20 2017-11-20 A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method Pending CN107620543A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711155854.7A CN107620543A (en) 2017-11-20 2017-11-20 A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711155854.7A CN107620543A (en) 2017-11-20 2017-11-20 A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method

Publications (1)

Publication Number Publication Date
CN107620543A true CN107620543A (en) 2018-01-23

Family

ID=61098887

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711155854.7A Pending CN107620543A (en) 2017-11-20 2017-11-20 A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method

Country Status (1)

Country Link
CN (1) CN107620543A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505884A (en) * 2018-05-10 2018-09-07 中建铝新材料成都有限公司 The installation method of pre-buried door window auxiliary frame structure, door window auxiliary frame embedded system and pre-buried door window auxiliary frame structure
CN109025277A (en) * 2018-08-28 2018-12-18 中建铝新材料成都有限公司 Secondary frame and its pre-buried structure and method
CN110107190A (en) * 2019-06-04 2019-08-09 东莞市华锋幕墙装饰工程有限公司 A kind of waterproof performance and the good window structure and its construction method of compressive property
CN110397370A (en) * 2019-08-06 2019-11-01 石榴置业集团股份有限公司 A kind of method of anti-leakage of door & window and wall construction using this method
CN112145027A (en) * 2019-06-28 2020-12-29 金鹏节能科技有限公司 Method for mounting and preventing water seepage of aluminum alloy door and window
CN112177479A (en) * 2019-07-01 2021-01-05 金鹏节能科技有限公司 Aluminum alloy door and window installation process capable of improving installation quality
CN112177483A (en) * 2019-07-03 2021-01-05 金鹏节能科技有限公司 Aluminum alloy door and window seam plugging method for coastal region
CN112177485A (en) * 2019-07-01 2021-01-05 金鹏节能科技有限公司 Construction method of aluminum alloy door and window
CN112302474A (en) * 2019-08-02 2021-02-02 金鹏节能科技有限公司 Method for mounting aluminum alloy door and window
CN112593809A (en) * 2020-12-14 2021-04-02 上海云兰建筑装饰工程有限公司 Door and window installation method
CN115012768A (en) * 2022-06-22 2022-09-06 中国建筑第二工程局有限公司 Concrete value burying method for aluminum alloy window subframe
CN116908239A (en) * 2023-09-08 2023-10-20 南通市建筑工程质量检测中心 Door and window heat preservation nature check out test set

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH619023A5 (en) * 1977-12-06 1980-08-29 Dossetto Pierre Framing for openings of buildings
DE29718054U1 (en) * 1997-09-19 1997-12-11 Zich Hardy Three-part steel door frame
CN101936111A (en) * 2010-08-06 2011-01-05 中国二十二冶集团有限公司 External window construction technology for assembling external window steel subframe by plastic-steel connection corner
CN203654999U (en) * 2013-12-25 2014-06-18 中国建筑第四工程局有限公司 Embedded aluminum alloy window
CN106088537A (en) * 2016-07-07 2016-11-09 中国建筑第二工程局有限公司 A kind of window auxiliary frame pre-embedded construction method
CN207499702U (en) * 2017-11-20 2018-06-15 中建二局第二建筑工程有限公司 A kind of door-window opening waterproofing node structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH619023A5 (en) * 1977-12-06 1980-08-29 Dossetto Pierre Framing for openings of buildings
DE29718054U1 (en) * 1997-09-19 1997-12-11 Zich Hardy Three-part steel door frame
CN101936111A (en) * 2010-08-06 2011-01-05 中国二十二冶集团有限公司 External window construction technology for assembling external window steel subframe by plastic-steel connection corner
CN203654999U (en) * 2013-12-25 2014-06-18 中国建筑第四工程局有限公司 Embedded aluminum alloy window
CN106088537A (en) * 2016-07-07 2016-11-09 中国建筑第二工程局有限公司 A kind of window auxiliary frame pre-embedded construction method
CN207499702U (en) * 2017-11-20 2018-06-15 中建二局第二建筑工程有限公司 A kind of door-window opening waterproofing node structure

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505884A (en) * 2018-05-10 2018-09-07 中建铝新材料成都有限公司 The installation method of pre-buried door window auxiliary frame structure, door window auxiliary frame embedded system and pre-buried door window auxiliary frame structure
CN109025277A (en) * 2018-08-28 2018-12-18 中建铝新材料成都有限公司 Secondary frame and its pre-buried structure and method
CN110107190A (en) * 2019-06-04 2019-08-09 东莞市华锋幕墙装饰工程有限公司 A kind of waterproof performance and the good window structure and its construction method of compressive property
CN112145027A (en) * 2019-06-28 2020-12-29 金鹏节能科技有限公司 Method for mounting and preventing water seepage of aluminum alloy door and window
CN112177479A (en) * 2019-07-01 2021-01-05 金鹏节能科技有限公司 Aluminum alloy door and window installation process capable of improving installation quality
CN112177485A (en) * 2019-07-01 2021-01-05 金鹏节能科技有限公司 Construction method of aluminum alloy door and window
CN112177483A (en) * 2019-07-03 2021-01-05 金鹏节能科技有限公司 Aluminum alloy door and window seam plugging method for coastal region
CN112302474A (en) * 2019-08-02 2021-02-02 金鹏节能科技有限公司 Method for mounting aluminum alloy door and window
CN110397370A (en) * 2019-08-06 2019-11-01 石榴置业集团股份有限公司 A kind of method of anti-leakage of door & window and wall construction using this method
CN112593809A (en) * 2020-12-14 2021-04-02 上海云兰建筑装饰工程有限公司 Door and window installation method
CN115012768A (en) * 2022-06-22 2022-09-06 中国建筑第二工程局有限公司 Concrete value burying method for aluminum alloy window subframe
CN116908239A (en) * 2023-09-08 2023-10-20 南通市建筑工程质量检测中心 Door and window heat preservation nature check out test set
CN116908239B (en) * 2023-09-08 2023-11-24 南通市建筑工程质量检测中心 Door and window heat preservation nature check out test set

Similar Documents

Publication Publication Date Title
CN107620543A (en) A kind of door-window opening waterproofing node structure and outer door and window pre-buried steel pair frame construction method
CN101403272B (en) Installation construction method of aluminum alloy window equipped with steel auxiliary frame
CN207499702U (en) A kind of door-window opening waterproofing node structure
CN104047427A (en) Anti-seepage and thermal-insulation construction method for external wall and external window
CN215802343U (en) Plugging structure and painting tool for outer wall screw hole
CN103306383A (en) Infiltration prevention method for bolt hole in outer wall of reinforced concrete shear wall
CN204676714U (en) Water-stopping steel strip and construction joint structure
CN107269001A (en) Concealed distribution box is with the whole construction method poured of concrete wall structure
CN208633535U (en) A kind of concrete component split bolt hole plugging structure
CN112412013A (en) Construction method for plugging reserved hole of structural outer wall
CN109750942A (en) A kind of the door and window pre-buried structure and its construction installation method of assembled architecture
CN104805864A (en) Basement reverse building method outer wall groove and tongue and water-proofing gel combined waterproof construction technology
CN209443765U (en) A kind of steel form of the pouring after settlement shear wall for banketing in advance
CN110805185A (en) Installation method of large-span curved surface special-shaped stone curtain wall
CN101446138A (en) Reconstructed project wall external decoration material anti-seepage construction method
CN109441116A (en) A kind of exterior wall tongue and groove for preventing window from seeping water
CN204590537U (en) A kind of aligning ruler controlling wall plastering planeness
CN201428342Y (en) Aluminum alloy window
CN105317321A (en) Building outer window hole plastering antiseep joint treatment method
CN205476491U (en) Outer wall post template bottom consolidates uses pre -cast screw
CN210483050U (en) Concrete bolt sleeve
CN209779949U (en) Prefabricated assembled profiled steel sheet concrete shear force wall
CN205917889U (en) Building is bullet strip that rises for subsiding crack
CN112609982A (en) Method for manufacturing wall with heat-insulation plate by adopting energy-saving bolt
CN101418640B (en) External window hole leaving construction method for shearing wall of construction concrete

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination