CN107620485A - Building cylinder reparation template framework and construction method - Google Patents
Building cylinder reparation template framework and construction method Download PDFInfo
- Publication number
- CN107620485A CN107620485A CN201711064279.XA CN201711064279A CN107620485A CN 107620485 A CN107620485 A CN 107620485A CN 201711064279 A CN201711064279 A CN 201711064279A CN 107620485 A CN107620485 A CN 107620485A
- Authority
- CN
- China
- Prior art keywords
- template
- cross bar
- building cylinder
- hole
- reparation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 10
- 239000012530 fluid Substances 0.000 claims abstract description 11
- 239000000565 sealant Substances 0.000 claims abstract description 11
- 230000000903 blocking effect Effects 0.000 claims abstract description 7
- 238000007789 sealing Methods 0.000 claims abstract description 5
- 239000004567 concrete Substances 0.000 claims description 12
- 239000011372 high-strength concrete Substances 0.000 claims description 7
- 238000007711 solidification Methods 0.000 claims description 7
- 230000008023 solidification Effects 0.000 claims description 7
- 229920000049 Carbon (fiber) Polymers 0.000 claims description 5
- 239000004917 carbon fiber Substances 0.000 claims description 5
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 claims description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000000835 fiber Substances 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000000034 method Methods 0.000 claims description 2
- 230000010412 perfusion Effects 0.000 description 3
- 239000002689 soil Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000021615 conjugation Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention discloses a kind of building cylinder reparation template framework, including four pieces of templates, plug hole is at least carried in one piece of template, blocking is configured with plug hole, banding has cross bar in template, the both ends of cross bar carry through hole, the through hole of Screw arbor with nut at both-ends through previous cross bar and rear side cross bar connected to drawing, the template of each pair Relative distribution is at least configured with two pairs of cross bars along short transverse and coordinates Screw arbor with nut at both-ends to be fixedly clamped, and strengthens sealing using seal with elastometic washer and using fluid sealant between template at the cooperation of template and damaged surface.Present invention also offers the construction method for repairing building cylinder with template framework using above-mentioned building cylinder reparation.Building cylinder reparation provided by the invention can repair cylinder more securely with template framework and construction method.
Description
Technical field
The present invention relates to a kind of building cylinder reparation template framework.The invention further relates to use building cylinder reparation
The construction method of building cylinder is repaired with template framework.
Background technology
During traditional architecture thing cylinder is repaired, generally it is fixed using common templates, concrete perfusion in template inner chamber, but
It is that new-old concrete is difficult strong bonded, causes the concrete of repairing easily to come off, and the structural strength of cylinder is helped not
Greatly.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of can repair more securely and build cylinder breakage
Building cylinder reparation template framework.Present invention also offers built using above-mentioned building cylinder reparation with template framework reparation
The construction method of buildings column body.
The technical solution adopted in the present invention is:Building cylinder reparation template framework, including four pieces of templates, at least one
Plug hole is carried in block template, blocking is configured with plug hole, banding has cross bar in template, and the both ends of cross bar carry through hole, right
The through hole of screw rod through previous cross bar and rear side cross bar is drawn connected to drawing, the template of each pair Relative distribution is along short transverse
At least being configured with two pairs of cross bars coordinates Screw arbor with nut at both-ends to be fixedly clamped, and is used between template at the cooperation of template and damaged surface
Seal with elastometic washer simultaneously strengthens sealing using fluid sealant.
Present invention also offers the construction party for repairing building cylinder with template framework using above-mentioned building cylinder reparation
Method, comprise the following steps:
A, the crisp concrete of building cylinder breakage is removed, until exposing the new face of hard structure;
B, template is covered in main body breakage, adjacent forms clamp pre-determined bit using grab, then use two cross bars to drawing
Screw rod clamps the template being oppositely arranged, and the template of each pair Relative distribution is at least configured with two pairs of cross bars cooperations pair along short transverse
Screw rod is drawn to be fixedly clamped;
C, fluid sealant is irrigated at the cooperation between the template and damaged surface and template and template, and waits fluid sealant complete
Solidification;
D, the blocking in template is opened, the grouting pipe end of high-pressure grouting machine is docked with plug hole, grouting pipe end and cast
Ensure to seal at the cooperation in hole, open high-pressure grouting machine and be blended with the high-strength concrete of steel fibre and be filled into template and surround to be formed
Die cavity in;
E, form removal after the tentatively solidification of wait high-strength concrete, and conserved.
The present invention has the following effects that:
1st, it is fixed using template using a pair of cross bars and Screw arbor with nut at both-ends, fastening force is very big, can be preferably by the mixed of perfusion
Solidifying soil paste pins, and is advantageous to the combination of new-old concrete;
2nd, sealing, energy are strengthened using seal with elastometic washer and using fluid sealant between template at the cooperation of template and damaged surface
Enough mortar leakage preventions, enable the concrete grout that perfusion enters to keep high pressure, are advantageous to conjunction old and new concret, make mixed after solidification
Solidifying soil is finer and close, is advantageous to lift intensity;
3rd, the high-strength concrete for being mixed with steel fibre is poured into the die cavity that template is surrounded, the concrete strength for making newly to irrigate is carried
Rise, can significantly lift the structural strength of the cylinder after repairing.
Brief description of the drawings
Fig. 1 is the structure schematic cross-sectional view of building cylinder reparation template framework provided by the invention.
Fig. 2 is the structural plan schematic diagram of building cylinder reparation template framework provided by the invention.
Embodiment
Shown in reference picture 1, Fig. 2, building cylinder reparation template framework provided by the invention, including four pieces of templates 1, extremely
Plug hole 2 is carried in few one piece of template 1, blocking is configured with plug hole 2, banding has cross bar 3, the both ends band of cross bar 3 in template 1
There is through hole, the through hole of Screw arbor with nut at both-ends 4 through previous cross bar 3 and rear side cross bar 3 connected to drawing, the template of each pair Relative distribution
1 is at least configured with two pairs of cross bars 3 along short transverse coordinates Screw arbor with nut at both-ends 4 to be fixedly clamped, at the cooperation of template 1 and damaged surface
Sealed between template using rubber ring 5 and sealing is strengthened using fluid sealant.
It is shown shown in reference picture 1, Fig. 2, on the basis of above-mentioned technical proposal, in order to more stably set cross bar 3,
The position cross direction profiles of the cross bar 3 are set in the template 1 at least two fixture blocks 7 with neck 6, and the cross bar 3 is embedded in
In the neck 6.
Shown in reference picture 1, Fig. 2, present invention also offers built using above-mentioned building cylinder reparation with template framework reparation
The construction method of buildings column body, comprises the following steps:
A, the crisp concrete of building cylinder breakage 8 is removed, until exposing the new face of hard structure;
B, template 1 is covered in main body breakage 8, adjacent forms 1 clamp pre-determined bit using grab, then use two cross bars 3
Screw arbor with nut at both-ends 4 clamps the template 1 being oppositely arranged, and the template 1 of each pair Relative distribution is at least configured with two pairs of horizontal strokes along short transverse
Bar 3 coordinates Screw arbor with nut at both-ends 4 to be fixedly clamped;
C, fluid sealant is irrigated at the cooperation between the template 1 and damaged surface and template 1 and template 1, and waits fluid sealant
Solidification completely;
D, the blocking in template 1 is opened, the grouting pipe end of high-pressure grouting machine is docked with plug hole 2, grouting pipe end is with pouring
Ensure to seal at the cooperation of orifice 2, the high-strength concrete that opening high-pressure grouting machine is blended with steel fibre 9 is filled into template encirclement
In the die cavity of formation;
E, form removal 1 after the tentatively solidification of wait high-strength concrete, and conserved.
, will first in the holes drilled through 11 of cylinder breakage 8 between the step A and step B when main body breakage area is larger
Carbon fiber 10 passes through through hole 11, and the both ends of carbon fiber 10 leave one section in breakage.Carbon fiber 10 can make new-old concrete, post
Effectively connection is realized between the novel concrete of body both sides, improves the conjugation of the concrete newly poured and cylinder.
Claims (4)
1. a kind of building cylinder reparation template framework, it is characterized in that:Including four pieces of templates, carry and pour at least in one piece of template
Orifice, is configured with blocking at plug hole, and banding has a cross bar in template, and the both ends of cross bar carry through hole, and Screw arbor with nut at both-ends is through previous
The through hole of cross bar and rear side cross bar connected to drawing, and the template of each pair Relative distribution is at least configured with two pairs along short transverse
Cross bar coordinates Screw arbor with nut at both-ends to be fixedly clamped, and uses seal with elastometic washer between template at the cooperation of template and damaged surface and adopts
Strengthen sealing with fluid sealant.
2. building cylinder reparation template framework according to claim 1, it is characterized in that:Described in being set in the template
The position cross direction profiles of cross bar have at least two fixture blocks with neck, and the cross bar is embedded in the neck.
3. a kind of construction method for repairing building cylinder with template framework using building cylinder reparation described in claim 1,
It is characterized in that:Comprise the following steps:
A, the crisp concrete of building cylinder breakage is removed, until exposing the new face of hard structure;
B, template is covered in main body breakage, adjacent forms clamp pre-determined bit using grab, then use two cross bars to drawing
Screw rod clamps the template being oppositely arranged, and the template of each pair Relative distribution is at least configured with two pairs of cross bars cooperations pair along short transverse
Screw rod is drawn to be fixedly clamped;
C, fluid sealant is irrigated at the cooperation between the template and damaged surface and template and template, and waits fluid sealant complete
Solidification;
D, the blocking in template is opened, the grouting pipe end of high-pressure grouting machine is docked with plug hole, grouting pipe end and cast
Ensure to seal at the cooperation in hole, open high-pressure grouting machine and be blended with the high-strength concrete of steel fibre and be filled into template and surround to be formed
Die cavity in;
E, form removal after the tentatively solidification of wait high-strength concrete, and conserved.
4. the construction party according to claim 3 for repairing building cylinder with template framework using the reparation of building cylinder
Method, it is characterized in that:When main body breakage area is larger, first in cylinder breakage holes drilled through between the step A and step B,
Carbon fiber is passed through into through hole, the both ends of carbon fiber leave one section in breakage.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711064279.XA CN107620485A (en) | 2017-11-02 | 2017-11-02 | Building cylinder reparation template framework and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711064279.XA CN107620485A (en) | 2017-11-02 | 2017-11-02 | Building cylinder reparation template framework and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107620485A true CN107620485A (en) | 2018-01-23 |
Family
ID=61092340
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711064279.XA Pending CN107620485A (en) | 2017-11-02 | 2017-11-02 | Building cylinder reparation template framework and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107620485A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108797384A (en) * | 2018-06-13 | 2018-11-13 | 刘玲玲 | A kind of bridge pier clears up repair apparatus and its cleaning reparation construction technique automatically |
CN111441609A (en) * | 2020-06-02 | 2020-07-24 | 孔庆珍 | Building bearing column repairing method based on big data |
CN112663989A (en) * | 2021-01-07 | 2021-04-16 | 上海肯叩实业有限公司 | Efficient balcony stone guardrail prosthetic devices |
CN114165072A (en) * | 2021-12-31 | 2022-03-11 | 余世好 | Device and method for repairing house building damaged by bottom frame column vibration |
CN114293810A (en) * | 2022-02-23 | 2022-04-08 | 李荣路 | Method for reinforcing stone micro-pressure concrete filled structure |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2545132A1 (en) * | 1983-04-28 | 1984-11-02 | Renofors France | Method for securing stone constructions |
CN201176709Y (en) * | 2008-04-25 | 2009-01-07 | 中冶京唐建设有限公司 | Calibration column stirrup mold for frame column |
CN102733350A (en) * | 2012-06-19 | 2012-10-17 | 山东高速青岛公路有限公司 | Repairing method for local defect of concrete in water level change region and repairing device |
CN103938886A (en) * | 2014-05-05 | 2014-07-23 | 葛洲坝集团第六工程有限公司 | Method for repairing concrete defects of side wall |
CN105019675A (en) * | 2015-06-09 | 2015-11-04 | 杭州江润科技有限公司 | Repairing construction method for grey brick outer wall of ancient building |
CN205116720U (en) * | 2015-09-29 | 2016-03-30 | 中国建筑股份有限公司 | Stupefied connector of back of body |
CN207485013U (en) * | 2017-11-02 | 2018-06-12 | 泰昌建设有限公司 | Building cylinder reparation template framework |
-
2017
- 2017-11-02 CN CN201711064279.XA patent/CN107620485A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2545132A1 (en) * | 1983-04-28 | 1984-11-02 | Renofors France | Method for securing stone constructions |
CN201176709Y (en) * | 2008-04-25 | 2009-01-07 | 中冶京唐建设有限公司 | Calibration column stirrup mold for frame column |
CN102733350A (en) * | 2012-06-19 | 2012-10-17 | 山东高速青岛公路有限公司 | Repairing method for local defect of concrete in water level change region and repairing device |
CN103938886A (en) * | 2014-05-05 | 2014-07-23 | 葛洲坝集团第六工程有限公司 | Method for repairing concrete defects of side wall |
CN105019675A (en) * | 2015-06-09 | 2015-11-04 | 杭州江润科技有限公司 | Repairing construction method for grey brick outer wall of ancient building |
CN205116720U (en) * | 2015-09-29 | 2016-03-30 | 中国建筑股份有限公司 | Stupefied connector of back of body |
CN207485013U (en) * | 2017-11-02 | 2018-06-12 | 泰昌建设有限公司 | Building cylinder reparation template framework |
Non-Patent Citations (2)
Title |
---|
于辉等: "《桥涵维护与加固技术》", 31 March 2013, 郑州:黄河水利出版社 * |
刘咏梅编: "《水闸除险加固实用技术》", 30 June 2016, 郑州:黄河水利出版社 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108797384A (en) * | 2018-06-13 | 2018-11-13 | 刘玲玲 | A kind of bridge pier clears up repair apparatus and its cleaning reparation construction technique automatically |
CN111441609A (en) * | 2020-06-02 | 2020-07-24 | 孔庆珍 | Building bearing column repairing method based on big data |
CN112663989A (en) * | 2021-01-07 | 2021-04-16 | 上海肯叩实业有限公司 | Efficient balcony stone guardrail prosthetic devices |
CN114165072A (en) * | 2021-12-31 | 2022-03-11 | 余世好 | Device and method for repairing house building damaged by bottom frame column vibration |
CN114293810A (en) * | 2022-02-23 | 2022-04-08 | 李荣路 | Method for reinforcing stone micro-pressure concrete filled structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107620485A (en) | Building cylinder reparation template framework and construction method | |
CN203113627U (en) | Nodular cast iron grout sleeve for connecting longitudinal steel bars | |
CN103422620A (en) | Prefabricated hollow steel-reinforced concrete column and splicing structure and splicing method thereof | |
CN206233596U (en) | Building block exterior wall constructional column concrete casting device | |
CN204326248U (en) | A kind of steel reinforcement abutting joints with the concavo-convex rib of spirality connects grout sleeve | |
CN110306537A (en) | Filling pile head construction method | |
CN106760496A (en) | A kind of floor beam plate post-cast strip template support system and its construction method | |
CN103741949B (en) | Treatment of juncture between vertical structure and horizontal structure | |
CN206220512U (en) | Split bolt and pouring template system thereof | |
CN203284735U (en) | Anti-blocking grouting device for cast-in-place continuous beam vertical prestressing rib metal corrugated pipe | |
CN207485013U (en) | Building cylinder reparation template framework | |
CN112593978B (en) | Secondary lining vault anti-disengaging device and construction method | |
CN205976447U (en) | Scaffold frame of connecting with straight screw sleeve links wall spare | |
CN105839851B (en) | Using the construction method for the prefabricated frame trestle that segmentation connection is formed | |
CN103103981B (en) | Construction method of prestress wedge-shaped pipe pile joint | |
CN104878741B (en) | Post-grouting waterproof structure for wall joint of underground diaphragm wall and waterproof method thereof | |
CN209649032U (en) | A kind of bearing platform prefabrication concrete mould plate structure | |
CN204024068U (en) | A kind of hoisting steel pipe pillar concrete connection control device | |
CN205875146U (en) | Reinforced structure of disconnected stake | |
CN108798024A (en) | A kind of anti-backflow concrete filled steel tube jacking interface arrangement and its construction method | |
CN107859350B (en) | Repairing process of old concrete column and template structure used by repairing process | |
CN211572616U (en) | Pouring device for constructional column | |
CN204690731U (en) | A kind of ground-connecting-wall width wall seam post jacking waterproof construction | |
CN204491596U (en) | Pile for prestressed pipe end plate exempts from welding structure | |
CN205399744U (en) | Assembly steel bars of shear wall muffjoint packer grouting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180123 |