CN107604903A - A kind of miniature steel pipe isolation pile reinforced construction method - Google Patents

A kind of miniature steel pipe isolation pile reinforced construction method Download PDF

Info

Publication number
CN107604903A
CN107604903A CN201710799540.4A CN201710799540A CN107604903A CN 107604903 A CN107604903 A CN 107604903A CN 201710799540 A CN201710799540 A CN 201710799540A CN 107604903 A CN107604903 A CN 107604903A
Authority
CN
China
Prior art keywords
steel pipe
pipe
hole
drilling
drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710799540.4A
Other languages
Chinese (zh)
Inventor
甄西东
张宵
潘金刚
李书伟
夏映贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Urban Construction Group Co Ltd
Original Assignee
Jinan Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Urban Construction Group Co Ltd filed Critical Jinan Urban Construction Group Co Ltd
Priority to CN201710799540.4A priority Critical patent/CN107604903A/en
Publication of CN107604903A publication Critical patent/CN107604903A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to tunnel excavation technical field of construction; specifically related to it is a kind of for city tunnel tunneling prevent along building destruction miniature steel pipe isolation pile guard method; using down-the-hole drill drilling and its boring method; a large amount of dregs, mud will not be produced; effect on environment is small, and reduces the destruction to road structure layer.And this boring method short construction period, speed is fast, and occupied ground is small, facilitates traffic organization, small to resident's interference, and a large amount of machineries and energy consumptions have been saved compared to traditional bore mode;Down-the-hole drill installs dry collector additional, improves rig service behaviour, and pollution source is controlled, effectively controls airborne dust to produce, ensures clean manufacturing;Ground compactness can be increased using cement mortar, the slip casting of waterglass dual slurry, supporting course is formed, avoid the influence of collapsible loess, the security of building structure can be ensured.

Description

A kind of miniature steel pipe isolation pile reinforced construction method
Technical field
The invention belongs to city tunnel Mined field, and in particular to be used for one kind along tunnel excavation prevents The miniature steel pipe isolation pile guard method of building destruction.
Background technology
The general buried depth in urban road tunnel is shallower, while is passed through under original road, along both sides present situation building structures compared with More, the boring construction in tunnel can cause the larger differential settlement in ground, and larger safety is brought to building structures along the line Hidden danger, the lighter cause differential settlement crack occur, and severe one causes inclination or deformation, forms high tower, cause larger economic damage Become estranged bad social influence.To prevent such phenomenon from occurring, construction reinforced concrete filling pile is used typically between tunnel and building, Protected, prevent differential settlement.But such a way is not easy to implement in city, and cost is high, has greater environmental impacts. To intend holing using isolation pile, to carry out cut-off with Existing reinforced concrete bridge building be a kind of relatively effective reduction constructing tunnel to both There is the method for building deformation effect.Isolation pile reinforcement principle is the big characteristic of ratio of rigidity soil using stake, makes stake top and stake bottom Soil body sedimentation reaches unanimity;Isolation pile is primarily subjected to rub caused by soil lateral pressure caused by excavation construction and ground difference simultaneously The development of deformation of the soil body, reduces the deformation of the soil body after isolation pile after resistance limitation stake.
And during existing isolation pile construction, construction drill is routinely bored using circulation drilling machine, large-scale percussive drill or geology Machine, long construction period take larger place, it is necessary to prepare or produce a large amount of mud, the construction infection resident trip in city, Boring procedure produces a large amount of dust, forms harm to city dweller's health, while larger pollution is caused to environment, consume in addition compared with The big energy, city dweller is disturbed also larger.In addition, existing isolation pile construction method runs into collapsible loess soil property When, the security of building building structure can not be protected.
The content of the invention
The present invention is solution the deficiencies in the prior art, there is provided a kind of miniature steel pipe isolation pile reinforced construction method.
The present invention is achieved by the following technical solutions:A kind of miniature steel pipe isolation pile reinforced construction method, including such as Lower step:
(1)Drill hole of drilling machine:Drilled using down-the-hole drill, dry collector is installed on down-the-hole drill additional, when down-the-hole drill works The tight cover down-the-hole drill aperture of dust hood of dry collector.First, after down-the-hole drill is fixed in place by guide pipe design attitude, edge Guide pipe applies brill, and drilling diameter 130mm, down-the-hole drill, which gently forces down, before 1.0m is crept into turns, and normal drilling rate is transferred to after creeping into 1.0m. Two row hole drillings are set between tunneling and existing building, the adjacent spacing of wells is 0.5m, and drilling array pitch is 1.0m, is used Apply the 1 jump stake sequence construction drilling every 2.It is 3m that the drilling rod of down-the-hole drill, which often saves length, extension bar in boring procedure, extension bar it is specific Method is as follows:First segment drilling rod pierces rock-soil layer, stops drilling during afterbody residue 20-30cm, manually uses pipe wrench clamping drilling rod, Then down-the-hole drill low speed and reverse, drilling rod is disengaged;When down-the-hole drill is stepped back along guide rail, manually load second drilling rod, second Drilling rod front end installs coupling sleeve, and second drilling rod low speed is delivered into first drilling rod afterbody, direction pair by down-the-hole drill It is coupled after standard integral.Each extension drill rod, carried out by above-mentioned extension bar method.Last down-the-hole drill drilling to completion, is moved back Drilling rod pore-forming borehole cleaning;
(2)Send pipe:Borehole cleaning terminate after immediately using crane insertion steel pipe, steel pipe uses Φ 108mm hot rolled seamless steel tubes, outside steel pipe Expose trench bottom 30cm, to connect Grouting Pipe;
(3)Steel pipe spreading:To dock steel pipe, when the first segment pipe in every hole is set, 3m and 4.5m steel is used in odd, even hole respectively Pipe, often saves and uses long 4.5m steel pipes later.First previous steel pipe is headed into the hole being drilled during steel pipe spreading, using inner sleeve It is coupled.When in previous steel pipe advancement holes, outside hole during remaining 30-40cm, hand fit's crane loads onto later section steel pipe, manually Later section steel pipe is bound up on inner sleeve, joined together two section steel pipes using long 15cm screw thread;
(4)Mixing dual slurry:Dual slurry is made up of cement mortar and waterglass, wherein slip casting when cement mortar and waterglass volume Than for 1:1, the wherein ratio of mud of cement mortar is 0.6:1, cement mortar carries out mixing using mortar mixer, the good cement of mixing Slurry is put into 1m × 1m × 1m ash-pits of steel, and waterglass is put into another ash-pit.Grouting Pipe is directly connected to steel by slip casting machine On the slip casting link steel pipe of pile tube, interface is connected using silk mouth, and Grouting Pipe is conveyed using rubber tube;
(5)Slip casting:Dual slurry is irrigated into steel pipe with Double-liquid mud-injection pump, when irrigating dual slurry, the volume of cement mortar and waterglass Than for 1:1, grouting pressure 0.2MPa, carry out during slip casting, 2 hours after first time slip casting, after slurries initial set, carry out in two times Secondary pressure slip casting, untill filling, after slip casting wouldn't tube drawing, untill cement mortar flows out outside pipe, extract Grouting Pipe Sealed steel pipe end.
Further, in step(1)In, down-the-hole drill scene is equipped with two drill bits.
Further, in step(2)In, lifted by crane using during crane insertion steel pipe lifting steel pipe using some colligations.
Beneficial effects of the present invention are:
First, using down-the-hole drill drilling and its boring method, a large amount of dregs, mud will not be produced, effect on environment is small, and reduces Destruction to road structure layer.And this boring method short construction period, speed is fast, and occupied ground is small, facilitates traffic organization, right Resident's interference is small, and a large amount of machineries and energy consumption have been saved compared to traditional bore mode;
2nd, down-the-hole drill installs dry collector additional, improves rig service behaviour, and pollution source is controlled, and effectively control is raised Dirt produces, and ensures clean manufacturing;
3rd, ground compactness can be increased using cement mortar, the slip casting of waterglass dual slurry, forms supporting course, avoid collapsible loess Influence, the security of building structure can be ensured;
4th, double insulation blocking stake is formed using φ 108mm steel pipes and slip casting, structure is more firm;
5th, steel-pipe pile construction drill is using applying the 1 jump stake sequence construction every 2, avoids during drilling and mortar depositing construction to building Build perturbing and producing larger valve pit subsidence for thing basis.
Embodiment
Specific embodiment of the invention given below is, it is necessary to which explanation is that the invention is not limited in implement in detail below Example, all equivalents done on the basis of technical scheme each fall within protection scope of the present invention.
A kind of miniature steel pipe isolation pile reinforced construction method, comprises the following steps:
(1)Drill hole of drilling machine
Drilled using down-the-hole drill, install dry collector on down-the-hole drill additional, install dry collector additional on down-the-hole drill Belong to prior art in the art, no longer its structure, principle and installation method are repeated here.Down-the-hole drill installs additional dry After formula deduster, down-the-hole drill service behaviour is substantially improved, effective control has been carried out to pollution source, has been effectively controlled Airborne dust produces, and ensures clean manufacturing.By the tight cover down-the-hole drill aperture of the dust hood of dry collector during work, bottom hole soil particle, Rock dust is blown to aperture by dust discharge blast, then under the suction collective effect of dedusting fan, dust enters Gas inlet tube by dust hood, warp Dust removal by filtration and final dusting, dust are collected by ash bucket, and purification air is discharged into air by air flue, and dry collector is also this area Interior known device, its working process and principle is also repeated no more here.
Down-the-hole drill is debugged first before drilling, it is ensured that after each side reaches requirement, down-the-hole drill is set by guide pipe Count position it is fixed in place after, apply brill along guide pipe, drilling diameter 130mm, before 1.0m is crept into, down-the-hole drill low pressure low speed rotation It is dynamic, to ensure perforate quality, normal drilling rate is transferred to after creeping into 1.0m.Two gang drills are set between tunneling and existing building Hole, the adjacent spacing of wells are 0.5m, and drilling array pitch is 1.0m, using apply 1 every 2 jump stake sequence construction drill.Accomplish during drilling Just, pile body is straight, when applying brill, prevents excessive flutter effect from applying brill precision for stake position.It is 3m that the drilling rod of down-the-hole drill, which often saves length, drilling Shi Bixu extension bars.The specific method of extension bar is as follows:First segment drilling rod pierces rock-soil layer, stops boring during afterbody residue 20-30cm Enter, manually use pipe wrench clamping drilling rod, pay attention to here must not filament threaded port, then down-the-hole drill low speed and reverse, disengage drilling rod;Work as down-the-hole Rig is stepped back along guide rail, manually loads second drilling rod, and installs coupling sleeve in second drilling rod front end, passes through down-the-hole drill Second drilling rod low speed is delivered into first drilling rod afterbody, is coupled after the alignment of direction integral.Each extension drill rod, by above-mentioned Extension bar method is carried out.
To ensure that down-the-hole drill is worked continuously, scene is equipped with two drill bits.
When drilling drilling to completion, drilling rod pore-forming borehole cleaning is moved back.
(2)Send pipe
Borehole cleaning need to insert steel pipe in hole after terminating, steel pipe uses Φ 108mm hot rolled seamless steel tubes, can concentrate on machining area and add Work, scene is transported to using dump truck or platform trailer, unloaded with crane in stake machine side, by piling sequencing and stake it is supporting It is required that stacking, and pay attention to direction.Crane is lifted by crane steel pipe and lifted by crane using some colligations, waits that hanging stake position carries out pitching pile, borehole cleaning terminates Immediately using crane insertion steel pipe, steel pipe exposes outside trench bottom 30cm, to connect Grouting Pipe.
(3)Steel pipe spreading
To dock steel pipe, when the first segment pipe in every hole is set, 3m and 4.5m steel pipe is used in odd, even hole respectively, is often saved later Use long 4.5m steel pipes.First previous steel pipe is headed into the hole being drilled during steel pipe spreading, is coupled using inner sleeve.When previous In root steel pipe advancement holes, outside hole during remaining 30-40cm, later section steel pipe is manually loaded onto, hand fit's crane is by later section steel pipe It is bound up on inner sleeve, is joined together two section steel pipes using long 15cm screw thread.
(4)Mixing dual slurry
Dual slurry is made up of cement mortar and waterglass, wherein slip casting when cement mortar and waterglass volume ratio be 1:1, its reclaimed water The ratio of mud of mud is 0.6:1, cement mortar carries out mixing using mortar mixer, the good cement mortar of mixing is put into the 1m of steel In × 1m × 1m ash-pits, waterglass is put into another ash-pit.The slip casting that Grouting Pipe is directly connected to steel-pipe pile by slip casting machine links On steel pipe, interface is connected using silk mouth, and Grouting Pipe is conveyed using rubber tube;
(5)Slip casting
Before slip casting, grouting equipment and material should be checked comprehensively, including Double-liquid mud-injection pump, mix slurry storage slurry system, high pressure madjack pipe, pressure Power table etc., and with clear water pump testing.After being drilled into designing pile length, tripping in steel pipe, is irrigated with Double-liquid mud-injection pump into steel pipe immediately Dual slurry, untill filling, to prevent collapse hole using the pipe-slip casting continuous productive process that drills-send.
Slip casting should first carry out slip casting field test, and single hole grouting amount is determined according to actual conditions.It is nonvoluntary after formal slip casting Interrupt, make every effort to work continuously, to ensure grouting quality.Because once grouting is difficult to reach the full requirement of slurries, in order to ensure slip casting Quality and effect, carry out in two times during slip casting, 2 hours after once grouting, after first time injects slurries initial set, carry out secondary pressure Power slip casting.Slip casting uses cement mortar with waterglass volume ratio for 1:The ratio of mud of 1 dual slurry, wherein cement mortar is 0.6:1, i.e., The volume ratio of cement mortar and waterglass is 1 when being irrigated with Double-liquid mud-injection pump:1, grouting pressure 0.2MPa, grouting pump need to install pressure Power table, pressure gage measuring range 0-1.0Mpa, after slip casting wouldn't tube drawing, untill cement mortar flows out outside pipe, extract Grouting Pipe Sealed steel pipe end.
One kind of embodiment described above, simply more preferably embodiment of the invention, those skilled in the art The usual variations and alternatives that member is carried out in the range of technical solution of the present invention should all include within the scope of the present invention.

Claims (3)

  1. A kind of 1. miniature steel pipe isolation pile reinforced construction method, it is characterised in that:Comprise the following steps:
    (1)Drill hole of drilling machine:Drilled using down-the-hole drill, dry collector is installed on down-the-hole drill additional, when down-the-hole drill works The tight cover down-the-hole drill aperture of dust hood of dry collector, first, after down-the-hole drill is fixed in place by guide pipe design attitude, edge Guide pipe applies brill, and drilling diameter 130mm, down-the-hole drill, which gently forces down, before 1.0m is crept into turns, and normal drilling rate is transferred to after creeping into 1.0m, Two row hole drillings are set between tunneling and existing building, the adjacent spacing of wells is 0.5m, and drilling array pitch is 1.0m, is used 1 is applied to drill every 2 jump stake sequence construction, it is 3m that the drilling rod of down-the-hole drill, which often saves length, extension bar in boring procedure, extension bar it is specific Method is as follows:First segment drilling rod pierces rock-soil layer, stops drilling during afterbody residue 20-30cm, manually uses pipe wrench clamping drilling rod, Then down-the-hole drill low speed and reverse, drilling rod is disengaged;When down-the-hole drill is stepped back along guide rail, manually load second drilling rod, second Drilling rod front end installs coupling sleeve, and second drilling rod low speed is delivered into first drilling rod afterbody, direction pair by down-the-hole drill It is coupled integral, each extension drill rod after standard, by the progress of above-mentioned extension bar method, last down-the-hole drill drilling to completion, moves back Drilling rod pore-forming borehole cleaning;
    (2)Send pipe:Borehole cleaning terminate after immediately using crane insertion steel pipe, steel pipe uses Φ 108mm hot rolled seamless steel tubes, outside steel pipe Expose trench bottom 30cm, to connect Grouting Pipe;
    (3)Steel pipe spreading:To dock steel pipe, when the first segment pipe in every hole is set, 3m and 4.5m steel is used in odd, even hole respectively Pipe, often saves and uses long 4.5m steel pipes later, first heads into previous steel pipe in the hole being drilled during steel pipe spreading, using inner sleeve It is coupled, when in previous steel pipe advancement holes, outside hole during remaining 30-40cm, hand fit's crane loads onto later section steel pipe, manually Later section steel pipe is bound up on inner sleeve, joined together two section steel pipes using long 15cm screw thread;
    (4)Mixing dual slurry:Dual slurry is made up of cement mortar and waterglass, wherein slip casting when cement mortar and waterglass volume Than for 1:1, the wherein ratio of mud of cement mortar is 0.6:1, cement mortar carries out mixing using mortar mixer, the good cement of mixing Slurry is put into 1m × 1m × 1m ash-pits of steel, and waterglass is put into another ash-pit, and Grouting Pipe is directly connected to steel by slip casting machine On the slip casting link steel pipe of pile tube, interface is connected using silk mouth, and Grouting Pipe is conveyed using rubber tube;
    (5)Slip casting:Dual slurry is irrigated into steel pipe with Double-liquid mud-injection pump, and the volume ratio of cement mortar and waterglass is 1 during perfusion:1, Grouting pressure is 0.2MPa, carries out in two times during slip casting, 2 hours after first time slip casting, after slurries initial set, carries out secondary pressure Slip casting, untill filling, after slip casting wouldn't tube drawing, untill cement mortar flows out outside pipe, extract Grouting Pipe sealed steel pipe End.
  2. 2. miniature steel pipe isolation pile reinforced construction method according to claim 1, it is characterised in that:In step(1)In, dive Drilling machine scene is equipped with two drill bits.
  3. 3. miniature steel pipe isolation pile reinforced construction method according to claim 1, it is characterised in that:In step(2)In, adopt Lifted by crane with during crane insertion steel pipe lifting steel pipe using some colligations.
CN201710799540.4A 2017-09-07 2017-09-07 A kind of miniature steel pipe isolation pile reinforced construction method Pending CN107604903A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710799540.4A CN107604903A (en) 2017-09-07 2017-09-07 A kind of miniature steel pipe isolation pile reinforced construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710799540.4A CN107604903A (en) 2017-09-07 2017-09-07 A kind of miniature steel pipe isolation pile reinforced construction method

Publications (1)

Publication Number Publication Date
CN107604903A true CN107604903A (en) 2018-01-19

Family

ID=61062629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710799540.4A Pending CN107604903A (en) 2017-09-07 2017-09-07 A kind of miniature steel pipe isolation pile reinforced construction method

Country Status (1)

Country Link
CN (1) CN107604903A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677924A (en) * 2018-07-13 2018-10-19 武汉市市政建设集团有限公司 Double miniature steel pipe pile slip casting is at wall partition-type structures and method
CN110219666A (en) * 2019-06-10 2019-09-10 中交隧道工程局有限公司 Method for tunnel construction and loess tunnel
CN113529830A (en) * 2021-07-05 2021-10-22 山东建筑大学 Shallow tunnel adjacent building isolation-underpinning combined reinforcement structure and construction process thereof
CN113585319A (en) * 2021-08-30 2021-11-02 中庆建设有限责任公司 Pile foundation construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3946570A (en) * 1973-10-02 1976-03-30 S.E.F.I. Sondages-Etanchements-Forages-Injections Support and foundation composite pile for various works and method for manufacturing the same
KR101026188B1 (en) * 2010-06-17 2011-03-31 토양건영 주식회사 Pile made by using grouting method and construction method for as the same
CN102635368A (en) * 2011-05-09 2012-08-15 上海申通地铁集团有限公司 Dual-liquid micro-disturbance grouting strengthening method for soft-soil subway tunnel
CN203008826U (en) * 2013-01-11 2013-06-19 张家口维克特机械有限公司 Dust collector for down-the-hole drill
CN203891008U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Miniature isolation pile
CN104805842A (en) * 2015-04-20 2015-07-29 中铁建设集团有限公司 Steel flower pipe segmented grouting system and construction method thereof
CN205857201U (en) * 2016-07-28 2017-01-04 兰州理工大学 A kind of anchor pole mini pile multistage support structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3946570A (en) * 1973-10-02 1976-03-30 S.E.F.I. Sondages-Etanchements-Forages-Injections Support and foundation composite pile for various works and method for manufacturing the same
KR101026188B1 (en) * 2010-06-17 2011-03-31 토양건영 주식회사 Pile made by using grouting method and construction method for as the same
CN102635368A (en) * 2011-05-09 2012-08-15 上海申通地铁集团有限公司 Dual-liquid micro-disturbance grouting strengthening method for soft-soil subway tunnel
CN203008826U (en) * 2013-01-11 2013-06-19 张家口维克特机械有限公司 Dust collector for down-the-hole drill
CN203891008U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Miniature isolation pile
CN104805842A (en) * 2015-04-20 2015-07-29 中铁建设集团有限公司 Steel flower pipe segmented grouting system and construction method thereof
CN205857201U (en) * 2016-07-28 2017-01-04 兰州理工大学 A kind of anchor pole mini pile multistage support structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
于宝池: "《现代水泥矿山工程手册》", 31 October 2013 *
甄西东等: ""城市超浅埋隧道微型钢管桩隔离保护建筑物应用研究"", 《安徽建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677924A (en) * 2018-07-13 2018-10-19 武汉市市政建设集团有限公司 Double miniature steel pipe pile slip casting is at wall partition-type structures and method
CN110219666A (en) * 2019-06-10 2019-09-10 中交隧道工程局有限公司 Method for tunnel construction and loess tunnel
CN113529830A (en) * 2021-07-05 2021-10-22 山东建筑大学 Shallow tunnel adjacent building isolation-underpinning combined reinforcement structure and construction process thereof
CN113585319A (en) * 2021-08-30 2021-11-02 中庆建设有限责任公司 Pile foundation construction method

Similar Documents

Publication Publication Date Title
CN107604903A (en) A kind of miniature steel pipe isolation pile reinforced construction method
CN104806272B (en) Tunnel shunting combined type guarded drainage integrated system and construction method and using method
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN108166486B (en) Deep buried pipe type prefabricated energy pipe pile and construction process thereof
CN104747075A (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN109630151A (en) Rectangular top pipe tunneling construction method
CN107035376B (en) One kind common law in huge thick bedrock aquifer digs shaft construction method
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN104832082A (en) Pneumatic DTH hammer reverse circulation slagging construction process for rotary drilling rig
CN108797621A (en) A kind of water sealing structure and its construction method in rich water depth ovum gravel erratic boulder stratum front pre-grouting
CN109989756B (en) Method for preventing water inrush and sand collapse of thick-surface-soil thin-bedrock drilling shaft
CN112855029B (en) Goaf drilling external pipe expansion construction method
CN107059876A (en) A kind of quick slip casting rig of Novel underground level
CN204920977U (en) Spray tube canopy construction equipment is revolved in advance to percussion drilling formula
CN112942441A (en) Pre-grouting water-stop construction method for water-rich silt stratum
CN110130325B (en) Construction method for rock drilling and grouting
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN107975027B (en) Construction method for reinforcing soil body at shield launching and arrival end
CN110805035A (en) Construction process of anti-floating anchor rod in complex stratum and air intake and exhaust grouting pipeline system
CN211115872U (en) Rotary drilling and filling dry operation gas purging hole cleaning machine
CN202989919U (en) Pressure-bearing water-sand-layer anchor rod mounting structure
CN102758443B (en) Novel enclosing structure applicable to connection change between new pipes and old pipes and construction method thereof
CN111042820B (en) Construction method for sand layer with oversized pilot hole by vertical shaft raise-shaft method
CN210857202U (en) Broken pile and pile connecting structure of cast-in-situ bored pile
CN114607272A (en) Construction method for passing existing water delivery tunnel under tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180119