CN110219666A - Method for tunnel construction and loess tunnel - Google Patents

Method for tunnel construction and loess tunnel Download PDF

Info

Publication number
CN110219666A
CN110219666A CN201910498828.7A CN201910498828A CN110219666A CN 110219666 A CN110219666 A CN 110219666A CN 201910498828 A CN201910498828 A CN 201910498828A CN 110219666 A CN110219666 A CN 110219666A
Authority
CN
China
Prior art keywords
tunnel
isolation pile
height
isolation
stake holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910498828.7A
Other languages
Chinese (zh)
Inventor
高向宇
周锋
张永兴
周杰
孙兴亮
康飞
刘凤超
霍晓斌
周辉
杨凡杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Institute of Rock and Soil Mechanics of CAS
CCCC Tunnel Engineering Co Ltd
Original Assignee
Wuhan Institute of Rock and Soil Mechanics of CAS
CCCC Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Institute of Rock and Soil Mechanics of CAS, CCCC Tunnel Engineering Co Ltd filed Critical Wuhan Institute of Rock and Soil Mechanics of CAS
Priority to CN201910498828.7A priority Critical patent/CN110219666A/en
Publication of CN110219666A publication Critical patent/CN110219666A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides a kind of method for tunnel construction and loess tunnels, are related to technical field of tunnel construction, and method for tunnel construction provided by the invention is the following steps are included: judge whether spacing is less than 10m between the first tunnel and the second tunnel;If spacing is less than 10m between the first tunnel and the second tunnel, isolation pile is set between the first tunnel and the second tunnel.Method for tunnel construction provided by the invention can prevent movement load in the first tunnel from the soil property in the second tunnel being caused to loosen and collapse, and then be conducive to improve working security.

Description

Method for tunnel construction and loess tunnel
Technical field
The present invention relates to technical field of tunnel construction, more particularly, to a kind of method for tunnel construction and loess tunnel.
Background technique
Parallel tunnels usually are built by existing tunnel for increased transport capacity, however are closed on train load in tunnel It influences, the difficulty of construction of newly built tunnels increases.In addition, the Canal in Loess Area soft in soil property, small-pitch parallel tunnels construction Safety is difficult to ensure.In practice, parallel tunnels construction lacks specific construction reference, is influenced by train operation in existing tunnel, There are very big security risks for newly built tunnels construction.
Summary of the invention
The purpose of the present invention is to provide a kind of method for tunnel construction and loess tunnels, to reduce parallel tunnels work progress In security risk.
In a first aspect, method for tunnel construction provided by the invention is the following steps are included: judge the first tunnel and the second tunnel Between spacing whether be less than 10m;If spacing is less than 10m between first tunnel and second tunnel, described first Isolation pile is set between tunnel and second tunnel.
With reference to first aspect, the present invention provides the first possible embodiments of first aspect, wherein the tunnel Construction method include: excavate stake holes downwards from earth's surface, and make the stake holes be located at first tunnel and second tunnel it Between;Into the stake holes, casting concrete is to form the isolation pile.
The possible embodiment of with reference to first aspect the first, second the present invention provides first aspect are possible Embodiment, wherein the stake holes basal surface position height be lower than the second tunnel basal surface position height, and difference in height be greater than etc. In 5m.
The possible embodiment of with reference to first aspect the first, the third the present invention provides first aspect are possible Embodiment, wherein the position height of the isolation pile top surface is higher than the first tunnel roof position height, and difference in height is big In equal to 5m;Alternatively, the isolation pile extends to earth's surface from the stake holes bottom.
With reference to first aspect, the present invention provides the 4th kind of possible embodiments of first aspect, wherein along described The extending direction in one tunnel is equipped at intervals with multiple isolation piles, the distance between isolation pile described in arbitrary neighborhood range be 2m~ 3m。
With reference to first aspect, the present invention provides the 5th kind of possible embodiments of first aspect, wherein the isolation The diameter range of stake is 0.5m~1m.
With reference to first aspect, the present invention provides the 6th kind of possible embodiments of first aspect, wherein the tunnel Construction method further include: the default extending direction along second tunnel, which is segmented, to be excavated, to form second tunnel;Wherein, Tunnel support is carried out after the completion of one section of excavation, and carries out next section of excavation after the completion of tunnel support.
The 6th kind of possible embodiment with reference to first aspect, the 7th kind the present invention provides first aspect are possible Embodiment, wherein the method for tunnel construction further include: according to formula u=u1-u2Calculate the deformation ginseng in second tunnel Number;Wherein, u is deformation parameter, unit m;u1For the settling height of second tunnel top monitoring point, unit m;u2For The settling height of the second tunnel upper earth's surface, unit m;The opposite sinking of vault is determined according to Grades of Surrounding Rock and edpth of tunnel Ratio value;According to formula u0=ah calculates datum of deformation value;Wherein, u0For datum of deformation value, unit m;A is vault phase To the ratio value of sinking;H is the height dimension in second tunnel, unit m;If u <u0/ 3, the excavation in second tunnel Drilling depth range is 2.8m~3.2m;If u0/3≤u<u0/ 2, the excavation drilling depth range in second tunnel is 1.4m~1.6m;If u0/2≤u<u02/3, the excavation drilling depth range in second tunnel is 0.7m~0.8m.
Second aspect, loess tunnel provided by the invention, comprising: the first tunnel, the second tunnel and isolation pile;Described first Tunnel and second tunnel are along equidirectional extension, and the distance between first tunnel and second tunnel are less than 10m; The isolation pile is arranged between first tunnel and second tunnel.
In conjunction with second aspect, the present invention provides the first possible embodiments of second aspect, wherein the isolation Stake is formed by concreting, and the isolation pile is equipped with the second reinforcing rib of more first reinforcing ribs and Duo Gen;Described in more First reinforcing rib is parallel to the axis of the isolation pile, and being provided at circumferentially spaced around the isolation pile;More described second add Strengthening tendons extend along the circumferencial direction of the isolation pile respectively, and are arranged along the axially spaced-apart of the isolation pile.
The embodiment of the present invention brings following the utility model has the advantages that by judging between the first tunnel and the second tunnel whether is spacing Less than 10m, if between the first tunnel and the second tunnel spacing be less than 10m, between the first tunnel and the second tunnel setting every From stake, the vibration between the first tunnel and the second tunnel is obstructed by isolation pile and is transmitted, and then can prevent from transporting in the first tunnel Dynamic loading causes the soil property in the second tunnel to loosen and collapse, and then is conducive to improve working security.
To enable the above objects, features and advantages of the present invention to be clearer and more comprehensible, preferred embodiment is cited below particularly, and cooperate Appended attached drawing, is described in detail below.
Detailed description of the invention
Technical solution in order to illustrate more clearly of the specific embodiment of the invention or in the related technology, below will be to specific Attached drawing needed in embodiment or description of Related Art is briefly described, it should be apparent that, it is described below Attached drawing is some embodiments of the present invention, for those of ordinary skill in the art, before not making the creative labor It puts, is also possible to obtain other drawings based on these drawings.
Fig. 1 is the flow chart of method for tunnel construction provided in an embodiment of the present invention;
Fig. 2 is the cross-sectional view one of loess tunnel provided in an embodiment of the present invention;
Fig. 3 is the cross-sectional view two of loess tunnel provided in an embodiment of the present invention;
Fig. 4 is the schematic diagram one in the second tunnel of loess tunnel provided in an embodiment of the present invention;
Fig. 5 is the schematic diagram two in the second tunnel of loess tunnel provided in an embodiment of the present invention;
Fig. 6 is the cross-sectional view in the second tunnel of loess tunnel provided in an embodiment of the present invention;
Fig. 7 is the schematic diagram of the isolation pile of loess tunnel provided in an embodiment of the present invention.
Icon: the first tunnel 1-;The second tunnel 2-;Monitoring point at the top of 201-;202- earth's surface monitoring point;The first side 203- prison Measuring point;204- second side monitoring point;21- top bar;211- vault;22- gets out of a predicament or an embarrassing situation;221- inverted arch;23- Core Soil;3- isolation Stake;The first reinforcing rib of 31-;The second reinforcing rib of 32-;321- supporting rib;322- stirrup.
Specific embodiment
Technical solution of the present invention is clearly and completely described below in conjunction with attached drawing, it is clear that described implementation Example is a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, ordinary skill Personnel's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", "vertical", The orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" be based on the orientation or positional relationship shown in the drawings, merely to Convenient for description the present invention and simplify description, rather than the device or element of indication or suggestion meaning must have a particular orientation, It is constructed and operated in a specific orientation, therefore is not considered as limiting the invention.In addition, term " first ", " second ", " third " is used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood at this with concrete condition Concrete meaning in invention.
Embodiment one
As depicted in figs. 1 and 2, method for tunnel construction provided in an embodiment of the present invention, comprising the following steps: judge the first tunnel Whether spacing is less than 10m between road 1 and the second tunnel 2;If spacing is less than 10m between the first tunnel 1 and the second tunnel 2, Isolation pile 3 is set between first tunnel 1 and the second tunnel 2.
Specifically, the first tunnel 1 is original tunnel, and the second tunnel 2 is the newly built tunnels parallel with the first tunnel 1;Alternatively, First tunnel 1 and the second tunnel 2 are the newly built tunnels of concurrent construction.When distance is less than between the first tunnel 1 and the second tunnel 2 When 10m, the vibration that movement load generates in the first tunnel 1 is transferred in the second tunnel 2, thus easily causes the second tunnel in construction Road 2 collapses.By taking the soft Canal in Loess Area of soil property as an example, when distance is less than 10m between the first tunnel 1 and the second tunnel 2, then the By pouring or pre-buried isolation pile 3 between one tunnel 1 and the second tunnel 2, and prolong the axis of isolation pile 3 along plummet direction It stretches, to be supported by isolation pile 3 to soil between the first tunnel 1 and the second tunnel 2, to avoid in the first tunnel 1 The soil property that movement load causes the second tunnel 2 loosens.
In embodiments of the present invention, method for tunnel construction includes: to excavate stake holes downwards from earth's surface, and stake holes is made to be located at first Between tunnel 1 and the second tunnel 2;Into stake holes, casting concrete is to form isolation pile 3.Specifically, the first tunnel 1 and the second tunnel Multiple stake holes are excavated at interval between road 2, and pour isolation pile 3 respectively in multiple stake holes;The isolation pile 3 formerly poured gradually coagulates Gu so that preset structure intensity is gradually approached, when the isolation pile 3 when formerly pour reaches the 70% of preset structure intensity, with one Set a distance is that next stake holes is excavated at interval, and constructs isolation pile 3 by concreting.
Further, stake holes basal surface position height is lower than 2 basal surface position height of the second tunnel, and difference in height is more than or equal to 5m.Wherein, after the completion of stake holes excavation, surface dust inside stake holes, and the casting concrete into stake holes is removed, isolation pile thus can be made 3 basal surface position is lower than 2 basal surface position of the second tunnel.Along plummet direction, the lower end of isolation pile 3 is lower than 2 bottom surface of the second tunnel, and Distance is more than or equal to 5m, increases isolation pile 3 and pours depth, reinforces soil by isolation pile 3, so as to further increase the The stability of soil layer construction between one tunnel 1 and the second tunnel 2, and then improve the working security in the second tunnel 2.
Further, the position height of 3 top surface of isolation pile is higher than 1 top side location height of the first tunnel, and difference in height is greater than Equal to 5m;Alternatively, isolation pile 3 extends to earth's surface from stake holes bottom.Specifically, if 1 top surface of the first tunnel is located at below earth's surface greatly In 5m, after the completion of pouring isolation pile 3, can banket into stake holes to bury isolation pile 3;If between 1 top surface of the first tunnel and earth's surface Away from 5m is less than, then pours to the top surface of isolation pile 3 and be in the same plane with earth's surface.It, can for the structural strength for improving isolation pile 3 In handling steel reinforcement cage to stake holes, ensure that concrete and rebar cage comes into full contact with by vibrating during casting concrete.
Further, into stake holes, casting concrete uses placement layer by layer mode, and along stake holes axial direction, every layer pours size model It encloses for 1.4m~1.6m.By taking every layer pours 1.5m as an example, after lower-layer concrete solidification, continue to pour above the concrete of solidification It builds, so on circulate until pouring to preset height.
As shown in figure 3, the extending direction along the first tunnel 1 is equipped at intervals with multiple isolation piles 3, arbitrary neighborhood isolation pile 3 it Between distance range be 2m~3m.Multiple stake holes are excavated at extending direction interval along the first tunnel 1, and are poured respectively into stake holes Concrete is to form multiple isolation piles 3.Axis spacing between adjacent stake holes may be set to 2.2m, 2.5m or 2.7m, in soil property Soft Canal in Loess Area can reduce the axis spacing between adjacent stake holes, by improving the concentration of isolation pile 3, Jin Erzeng The stability of strong soil texture.
Further, the diameter range of isolation pile 3 is 0.5m~1m.Specifically, stake holes diameter range is 0.5m~1m, stake The isolation pile 3 of diameter range 0.5m~1m is formed in hole full of concrete.Wherein, the diameter of isolation pile 3 may be set to 0.6m, 0.8m or 0.9m.
Further, method for tunnel construction further include: the default extending direction along the second tunnel 2, which is segmented, to be excavated, to be formed Second tunnel 2;Wherein, tunnel support is carried out after the completion of one section of excavation, and carries out next section of excavation after the completion of tunnel support.
As shown in Figure 5 and Figure 6, the default extending direction along the second tunnel 2 is excavated using benching tunneling method segmentation, top bar 21 height value is 5m, and the size range that digs into of top bar 21 is 3m~5m;Get out of a predicament or an embarrassing situation 22 height value range be 3m~ 4m, get out of a predicament or an embarrassing situation 22 dig into size range be 2m~3m;23 height of Core Soil is 3m.The default extending direction in the second tunnel 2 with The extending direction in the first tunnel 1 is parallel.After the completion of one section of excavation, it is to the inner-wall spraying strength grade in the second tunnel 2 first The concrete of C25, concrete thickness are more than or equal to 50mm;Then the hollow grouting anchor for installing 3m long, if distance is small between tunnel When 3m, then rock-bolt length, pressure injection cement mortar, grouting pressure 0.5Mpa~1.0Mpa are adjusted according to actual range;Meanwhile pacifying Steel mesh and spacing are filled as the bracing members of 75cm;Finally, multiple pneumatically placed concrete, guarantees that steel mesh spray concrete cover thickness is big after multiple spray In being equal to 2cm, bracing members outer rim protective layer thickness is more than or equal to 4cm, and inner edge protective layer thickness is more than or equal to 2cm.To tunnel branch After the completion of shield, start next section of digging operation.
As shown in Figure 4 and Figure 5, method for tunnel construction further include: according to formula u=u1-u2Calculate the deformation in the second tunnel 2 Parameter;Wherein, u is deformation parameter, unit m;u1For the settling height of 2 top monitoring point 201 of the second tunnel, unit m;u2 For the settling height of 2 top earth's surface monitoring point 202 of the second tunnel, unit m;Earth's surface monitoring point 202 is equipped with multiple, and is adjacent to 202 spacing 2m~5m of table monitoring point.The ratio value of the opposite sinking of vault 211 is determined according to Grades of Surrounding Rock and edpth of tunnel;According to Formula u0=ah calculates datum of deformation value;Wherein, u0For datum of deformation value, unit m;A is the ratio of the opposite sinking of vault 211 Example value;H is the height dimension in the second tunnel 2, unit m;If u <u0/ 3, the excavation drilling depth range in the second tunnel 2 be 2.8m~ 3.2m;If u0/3≤u<u0/ 2, the excavation drilling depth range in the second tunnel 2 is 1.4m~1.6m;If u0/2≤u<u02/3, second The excavation drilling depth range in tunnel 2 is 0.7m~0.8m.The height dimension in the second tunnel 2 is top monitoring point 201 and 221 bottom of inverted arch The distance between portion.
Specifically, according to Grades of Surrounding Rock and edpth of tunnel by the value range for available datum of deformation value of tabling look-up, for For the constructing tunnel of Canal in Loess Area, datum of deformation value should choose bigger numerical or level off to the upper limit of value range.It constructed After the completion of one section of constructing tunnel monitoring point, monitoring certain time deformation ginseng can be arranged in this section of tunnel top and earth's surface in Cheng Zhong Number, and next section of excavation drilling depth is adjusted according to deformation parameter.For example, working as u <u0/ 3, the excavation drilling depth in the second tunnel 2 takes Value 1.5m;Work as u0/3≤u<u0/ 2, the excavation drilling depth value 3m in the second tunnel 2;Work as u0/2≤u<u02/3, the second tunnel 2 Excavate drilling depth value 0.75m.
As shown in Figure 4 and Figure 5, in the horizontal direction, 211 bottom of vault in the second tunnel 2 be equipped with the first side monitoring point 203 with And second side monitoring point 204 opposite with the first side monitoring point 203, between the first side monitoring point 203 and second side monitoring point 204 Distance is tunnel width.Deformation parameter should also be converted according to the spacing between monitoring point and excavation face multiplied by certain proportion coefficient, When distance is equal to one times of tunnel width between monitoring point and excavation face, proportionality coefficient value is 0.65, i.e. u0=0.65 u0;When distance is equal to two times of tunnel width between monitoring point and excavation face, proportionality coefficient value is 0.9, i.e. u0=0.9 u0;When between monitoring point and excavation face distance farther out, such as between monitoring point and excavation face distance be greater than three times tunnel width When, proportionality coefficient value is 1.
Embodiment two
As shown in Figures 2 and 3, loess tunnel provided in an embodiment of the present invention, comprising: the first tunnel 1,2 and of the second tunnel Isolation pile 3;First tunnel 1 and the second tunnel 2 are along equidirectional extension, and the distance between the first tunnel 1 and the second tunnel 2 are less than 10m;Isolation pile 3 is arranged between the first tunnel 1 and the second tunnel 2.Wherein, the axis of isolation pile 3 is arranged along plummet direction, and Isolation pile 3 is equipped with multiple, the multiple interval of isolation piles 3 2m~3m, to divide through the first tunnel 1 of reinforcing of isolation pile 3 and the second tunnel Soil between road 2.
As shown in fig. 7, isolation pile 3 is formed by concreting, and isolation pile 3 is equipped with more first reinforcing ribs 31 and more The second reinforcing rib of root 32;More first reinforcing ribs 31 are parallel to the axis of isolation pile 3, and being provided at circumferentially spaced around isolation pile 3; More second reinforcing ribs 32 extend along the circumferencial direction of isolation pile 3 respectively, and are arranged along the axially spaced-apart of isolation pile 3.Wherein, One reinforcing rib 31 selects the HRB400 reinforcing bar of diameter 25mm, is provided at circumferentially spaced 28 along isolation pile 3;Second reinforcing rib 32 packet Include: supporting rib 321 and stirrup 322, supporting rib 321 is annular in shape, and more first reinforcing ribs 31 are arranged in and enclose in the region set, binds round Muscle 322 is set in 31 outside of more first reinforcing ribs;Multiple supporting ribs 321 are spaced along isolation pile 3 to be arranged, and adjacent supports muscle 321 spacing 150cm, supporting rib 321 select the HRB400 reinforcing bar of diameter 20mm;Multiple stirrups 322 are spaced along isolation pile 3 to be arranged, And adjacent 322 spacing 25cm of stirrup, stirrup 322 select the HRB300 reinforcing bar of diameter 25cm.It can be by the first reinforcing rib by binding 31, supporting rib 321 and the connection of stirrup 322 form steel reinforcement cage, are fixed on steel reinforcement cage inside isolation pile 3 by concreting, To improve the structural strength of isolation pile 3.
Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention., rather than its limitations;To the greatest extent Pipe present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: its according to So be possible to modify the technical solutions described in the foregoing embodiments, or to some or all of the technical features into Row equivalent replacement;And these are modified or replaceed, various embodiments of the present invention technology that it does not separate the essence of the corresponding technical solution The range of scheme.

Claims (10)

1. a kind of method for tunnel construction, which comprises the following steps:
Judge whether spacing is less than 10m between the first tunnel (1) and the second tunnel (2);
If spacing is less than 10m between first tunnel (1) and second tunnel (2), in first tunnel (1) and institute State setting isolation pile (3) between the second tunnel (2).
2. method for tunnel construction according to claim 1, which is characterized in that the method for tunnel construction includes:
Stake holes is excavated downwards from earth's surface, and makes the stake holes between first tunnel (1) and second tunnel (2);
Into the stake holes, casting concrete is to form the isolation pile (3).
3. method for tunnel construction according to claim 2, which is characterized in that the stake holes basal surface position height is lower than described Second tunnel (2) basal surface position height, and difference in height is more than or equal to 5m.
4. method for tunnel construction according to claim 2, which is characterized in that the position height of isolation pile (3) top surface Higher than the first tunnel (1) top side location height, and difference in height is more than or equal to 5m;
Alternatively, the isolation pile (3) extends to earth's surface from the stake holes bottom.
5. method for tunnel construction according to claim 1, which is characterized in that along the extending direction of first tunnel (1) Multiple isolation piles (3) are equipped at intervals with, the distance between isolation pile (3) described in arbitrary neighborhood range is 2m~3m.
6. method for tunnel construction according to claim 1, which is characterized in that the diameter range of the isolation pile (3) is 0.5m~1m.
7. method for tunnel construction according to claim 1, which is characterized in that the method for tunnel construction further include:
It is segmented and excavates along the default extending direction of second tunnel (2), to form second tunnel (2);
Wherein, tunnel support is carried out after the completion of one section of excavation, and carries out next section of excavation after the completion of tunnel support.
8. method for tunnel construction according to claim 7, which is characterized in that the method for tunnel construction further include:
According to formula u=u1-u2Calculate the deformation parameter of second tunnel (2);Wherein, u is deformation parameter, unit m;u1 For the settling height of the top monitoring point (201) of second tunnel (2), unit m;u2Above second tunnel (2) The settling height of earth's surface, unit m;
The ratio value of vault (211) opposite sinking is determined according to Grades of Surrounding Rock and edpth of tunnel;
According to formula u0=ah calculates datum of deformation value;Wherein, u0For datum of deformation value, unit m;A is vault (211) phase To the ratio value of sinking;H is the height dimension of second tunnel (2), unit m;
If u <u0/ 3, the excavation drilling depth range of second tunnel (2) is 2.8m~3.2m;
If u0/3≤u<u0/ 2, the excavation drilling depth range of second tunnel (2) is 1.4m~1.6m;
If u0/2≤u<u02/3, the excavation drilling depth range of second tunnel (2) is 0.7m~0.8m.
9. a kind of loess tunnel characterized by comprising the first tunnel (1), the second tunnel (2) and isolation pile (3);
First tunnel (1) and second tunnel (2) are along equidirectional extension, and first tunnel (1) and described second The distance between tunnel (2) is less than 10m;
The isolation pile (3) is arranged between first tunnel (1) and second tunnel (2).
10. loess tunnel according to claim 9, which is characterized in that the isolation pile (3) is formed by concreting, And the isolation pile (3) is equipped with more first reinforcing rib (31) the second reinforcing ribs of He Duogen (32);More described first are reinforced Muscle (31) is parallel to the axis of the isolation pile (3), and being provided at circumferentially spaced around the isolation pile (3);More described second Reinforcing rib (32) extends along the circumferencial direction of the isolation pile (3) respectively, and is arranged along the axially spaced-apart of the isolation pile (3).
CN201910498828.7A 2019-06-10 2019-06-10 Method for tunnel construction and loess tunnel Pending CN110219666A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910498828.7A CN110219666A (en) 2019-06-10 2019-06-10 Method for tunnel construction and loess tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910498828.7A CN110219666A (en) 2019-06-10 2019-06-10 Method for tunnel construction and loess tunnel

Publications (1)

Publication Number Publication Date
CN110219666A true CN110219666A (en) 2019-09-10

Family

ID=67816090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910498828.7A Pending CN110219666A (en) 2019-06-10 2019-06-10 Method for tunnel construction and loess tunnel

Country Status (1)

Country Link
CN (1) CN110219666A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905529A (en) * 2019-11-30 2020-03-24 中铁二十局集团有限公司 Construction method of loess tunnel penetrating through landslide mass

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425423A (en) * 2011-12-31 2012-04-25 上海市机械施工有限公司 Constructing method for shield entering into hole while passing through pipeline
CN206298896U (en) * 2016-12-06 2017-07-04 中铁第一勘察设计院集团有限公司 A kind of Tunnel Passing structures steel pipe isolation pile stratum consolidation system
CN107604903A (en) * 2017-09-07 2018-01-19 济南城建集团有限公司 A kind of miniature steel pipe isolation pile reinforced construction method
CN207109805U (en) * 2017-08-14 2018-03-16 中铁第一勘察设计院集团有限公司 Wear the compound isolation pile of bridge pier in a kind of tunnel side
CN109577991A (en) * 2018-10-25 2019-04-05 南宁轨道交通集团有限责任公司 A kind of tunnel structure that more tunnels are parallel and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425423A (en) * 2011-12-31 2012-04-25 上海市机械施工有限公司 Constructing method for shield entering into hole while passing through pipeline
CN206298896U (en) * 2016-12-06 2017-07-04 中铁第一勘察设计院集团有限公司 A kind of Tunnel Passing structures steel pipe isolation pile stratum consolidation system
CN207109805U (en) * 2017-08-14 2018-03-16 中铁第一勘察设计院集团有限公司 Wear the compound isolation pile of bridge pier in a kind of tunnel side
CN107604903A (en) * 2017-09-07 2018-01-19 济南城建集团有限公司 A kind of miniature steel pipe isolation pile reinforced construction method
CN109577991A (en) * 2018-10-25 2019-04-05 南宁轨道交通集团有限责任公司 A kind of tunnel structure that more tunnels are parallel and its construction method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
王东升等: "《水利水电工程施工安全生产技术》", 30 April 2018, 中国矿业大学出版社 *
王家维: "《高速铁路工程检验批填写手册》", 31 December 2014, 中国铁道出版社 *
铁路工程技术标准所: "《铁路工程建设标准汇编》", 30 September 2009, 中国铁道出版社 *
铁道部第二工程局教育处: "《钢筋混凝土工程基础知识》", 30 November 1986, 中国铁道出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110905529A (en) * 2019-11-30 2020-03-24 中铁二十局集团有限公司 Construction method of loess tunnel penetrating through landslide mass
CN110905529B (en) * 2019-11-30 2021-02-05 中铁二十局集团有限公司 Construction method of loess tunnel penetrating through landslide mass

Similar Documents

Publication Publication Date Title
CN103195076B (en) Muddy Bottoms deep-excavation tower crane foundation construction method
CN108412503B (en) Bias shallow-buried tunnel portal construction protection structure and construction method thereof
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN208088288U (en) The big areas grain size shiver stone Gao Tian pile foundation fast pore-creating structure
CN109667985A (en) The method that push-bench is docked with received well steel sleeve in jacking construction
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN108316289A (en) Big grain size shiver stone Gao Tian area&#39;s pile foundation fast pore-creating structures and its construction technology
JP2010255237A (en) Method and structure for tunnel reinforcement
CN113503166B (en) Reinforced disposal structure of karst cave at middle and lower parts of tunnel and construction method thereof
CN104453915B (en) Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method
CN110219666A (en) Method for tunnel construction and loess tunnel
CN209228377U (en) A kind of multistage set arch structure and pipe canopy set arch structure for tunnel portal supporting
CN108265733A (en) Build-in soil body restricted type pile slab supporting structure and construction method before stake
CN106968241A (en) Continuous underground wall structure and retaining design construction method
CN214660200U (en) Stiffening beam disposal structure of tunnel bottom karst cave
CN115595979A (en) Construction method for treating karst cave by bridge pile foundation under geological condition of strong development of karst
CN110410082B (en) Tunnel excavation advance support method
CN209622195U (en) Push-bench and received well steel sleeve docking structure in a kind of jacking construction
CN207143970U (en) A kind of foundation pit enclosure stake
CN109268030A (en) A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting
CN213682076U (en) Dado-free hollow bored pile
CN218667505U (en) Ultra-high large-span karst cave bridge pile foundation construction dado based on manual hole digging pile technology
CN215801568U (en) Bored concrete pile structure for reducing filling coefficient in ultra-deep silt geology
CN214940189U (en) Large-span foundation pit inner supporting structure
CN216305957U (en) Construction structure for restraining sinking amount of primary support of tunnel based on step method excavation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190910