CN107558793B - Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole - Google Patents

Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole Download PDF

Info

Publication number
CN107558793B
CN107558793B CN201710808627.3A CN201710808627A CN107558793B CN 107558793 B CN107558793 B CN 107558793B CN 201710808627 A CN201710808627 A CN 201710808627A CN 107558793 B CN107558793 B CN 107558793B
Authority
CN
China
Prior art keywords
cross
arm
electric pole
rope
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710808627.3A
Other languages
Chinese (zh)
Other versions
CN107558793A (en
Inventor
张殿越
于洪海
王文博
吴国辉
王宇新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710808627.3A priority Critical patent/CN107558793B/en
Publication of CN107558793A publication Critical patent/CN107558793A/en
Application granted granted Critical
Publication of CN107558793B publication Critical patent/CN107558793B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole, this method includes that steps are as follows: the suspension installation fixed pulley on the cross-arm of electric pole top, and lifting rope is bypassed on fixed pulley;Assembling cross-arm and only a piece bolt of connection on the ground;Two cross-arm both ends are separately connected using dedicated connecting rope;Two cross-arm levels are hoisted to cross-arm installation site by lifting rope and dedicated connecting rope;Two cross-arms are pushed by electric pole side and fixed clamp is on electric pole;Porcelain piece, fitting are put into Special storage box, Special storage box is hoisted at cross-arm by drop-down lifting rope and dedicated connecting rope, by porcelain piece and installation on cross-arm.Beneficial effect is: cross-arm is not necessarily to be participated in that promotion can be completed by operating personnel on bar, promote cross-arm in place can be completed the installation of two cross-arms on electric pole by a people, the workload and labor intensity for reducing operating personnel on electric pole, save the activity duration, improve operating efficiency.

Description

Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole
Technical field
The invention belongs to field of electricity construction, in particular to multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole And its specific purpose tool.
Background technique
Currently, power supply enterprise is when installing multilayer cross-arm on overhead transmission line electric pole, what is generallyd use is the operation on electric pole Personnel pull up cross-arm vertically and transmit material, electric armour clamp, tool etc. using rope, and ground line, insulating glove, electroscope etc. are pacified Full Work tool is carried by stepping on bar personnel, and that there are problems is as follows for this operation mode:
1, not only operation intensity is big when pull-up cross-arm, and cross-arm is easy to fall, and is easy to appear climbers weighing excess load There are damage climbers and lead to the security risk of slide bar in situation;
2, it needs two people mutual cooperation two cross-arms correspondences could be clipped in electric pole two sides when cross-arm is installed to be fixed, two People is inconvenient on electric pole;
3, operating personnel is before rod-rising tower, before doing the measures such as hanging earthing conductor, electrical verification, tool will be taken and take with oneself, This increases burden to step on bar personnel.
4, operating personnel can only transmit a kind of tool or a small amount of material when toward shaft tower tool for transmitting and material every time, Long this back and forth will increase the activity duration surely, the attention of scattering rod the tower operator, and when operation does not want to take the trouble and will whip sometimes It abandons, at will puts, there are high-altitude material working tools to fall the security risk hurted sb.'s feelings.
Summary of the invention
Technical problem to be solved by the invention is to provide multilayer cross-arm lifting installation methods on a kind of overhead transmission line electric pole And its specific purpose tool, this method can not only reduce operation intensity, improve operational security, and step on bar by a people to carry out Cross-arm installation exercise, improves operating efficiency.
Technical scheme is as follows:
Multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole, comprising steps are as follows:
1, the suspension installation fixed pulley on the cross-arm on electric pole top, and lifting rope is bypassed on fixed pulley;
2, the ground over-assemble cross-arm below the electric pole for the cross-arm installed;Only connect between assembling cross-arm Shi Ergen cross-arm Connect a bolt;
3, the vertical bottle mounting hole at two cross-arm both ends is each passed through simultaneously using the cross-arm connection bolt of dedicated connecting rope lower end Fastening;
4, the metal hanging buckle of dedicated connecting rope upper end is hung on the suspension hook of lifting rope one end, is hung by ground construction personnel drop-down It restricts the other end, the cross-arm installation site being hoisted to two cross-arm levels by lifting rope on electric pole;
5, two cross-arms are pushed by the operating personnel on electric pole by electric pole side, are clipped in electric pole between two cross-arms, Another bolt is worn again, by two cross-arm fixed clamps on electric pole;
6, the porcelain piece of installation required on cross-arm, fitting are put into Special storage box, then put down dedicated connecting rope, it will be dedicated Four hooks of connecting rope lower end are hung on the link of Special storage box top surface four corners, by pulling down lifting rope for dedicated storage Object case is hoisted at the cross-arm on electric pole, by the operating personnel on electric pole by Special storage box porcelain piece and installation in cross In load.
7, it repeats the above steps 2~6, is installed until multilayer cross-arm is all promoted.
Specific purpose tool used in multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole, including dedicated connecting rope And Special storage box,
The Special storage box includes the cabinet of a upper end opening, is equipped with a circle tool in its outer rim of cabinet upper end edge and hangs Frame, for hanging power tool;It is respectively equipped with link in box top four corners, for connecting dedicated connecting rope;Under cabinet End four corners are respectively equipped with hook for hanging tools, for hanging power tool;
The dedicated connecting rope includes four connecting ropes, and four connecting rope one ends wounds are merged into one and are connected with metal Hanging buckle, the other end of four connecting ropes are connected separately with hook and connect bolt with cross-arm, for be separately connected Special storage box and Cross-arm.
As further preferred, the box shape is cuboid, and by a cuboid framework and is separately fixed at length The boxboard of cube frame bottom surface and surrounding is constituted.
As further preferred, the hanger for tools includes a rectangular frame as made of reinforcement welding, the rectangle frame Frame is fixed on cabinet upper end periphery, is equipped with the gap 30-50mm between the every reinforcing bar and cabinet outer rim on rectangular frame.
As further preferred, it is evenly equipped between the reinforcing bar and cabinet of each long side along its longitudinal direction on rectangular frame Multiple cross bars, to separate the power tool of suspension.
The beneficial effects of the present invention are:
1, the cross-arm of required installation is not necessarily to be participated in that promotion can be completed by operating personnel on bar, promotes cross-arm in place in electricity The installation that two cross-arms can be completed on bar by a people reduces the workload and labor intensity of operating personnel on electric pole, cross-arm It does not fall out, saves the activity duration, improve operating efficiency.It avoids in traditional work mode by operating personnel people on electric pole The risk that cross-arm is easy to fall is proposed in work.
2, porcelain piece required on cross-arm, fitting once can be all sent on electric pole by Special storage box, is improved Operational security and operating efficiency.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of Special storage box in the present invention.
Fig. 2 is the top view of Fig. 1.
Fig. 3 is the structural schematic diagram of dedicated connecting rope in the present invention.
In figure: cabinet 1, hook for hanging tools 2, hanger for tools 3, link 4, cross bar 5, connecting rope 6, metal hanging buckle 7, cross-arm connection Bolt 8, hook 9.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts all other Embodiment shall fall within the protection scope of the present invention.
Multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole of the present invention, comprising steps are as follows:
1, one fixed pulley of suspension installation on the cross-arm on electric pole top, and lifting rope is bypassed on fixed pulley;
2, the ground over-assemble cross-arm below the electric pole for the cross-arm installed;Only connect between assembling cross-arm Shi Ergen cross-arm Connect a bolt;
3, the vertical bottle mounting hole at two cross-arm both ends is each passed through simultaneously using the cross-arm connection bolt 8 of dedicated connecting rope lower end It is fastened by nut;
4, the metal hanging buckle 7 of dedicated connecting rope upper end is hung on the suspension hook of lifting rope one end, by ground construction, personnel are pulled down The lifting rope other end, the cross-arm installation site being hoisted to two cross-arm levels by lifting rope on electric pole;
5, two cross-arms are pushed by the operating personnel on electric pole by electric pole side, are clipped in electric pole between two cross-arms, Another bolt is worn again, makes two cross-arm fixed clamps on electric pole;
6, the porcelain piece of installation required on cross-arm, fitting are put into Special storage box, then put down dedicated connecting rope, it will be dedicated Four hooks 9 of connecting rope lower end are hung on the link 4 of Special storage box top surface four corners, will be dedicated by drop-down lifting rope Storage tank is hoisted at the cross-arm on electric pole, by the operating personnel on electric pole by Special storage box porcelain piece and installation exist On cross-arm.
7, it repeats the above steps, is installed until multilayer cross-arm is all promoted.
Specific purpose tool used in multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole of the present invention, packet Include dedicated connecting rope and Special storage box;
The Special storage box includes the cabinet 1 of a upper end opening, and 1 shape of cabinet is cuboid, and by one Cuboid framework and the boxboard composition for being separately fixed at cuboid framework bottom surface and surrounding.In 1 upper end edge of cabinet, its outer rim is equipped with One circle hanger for tools 3, for hanging power tool;It is respectively equipped with link 4 in 1 top surface four corners of cabinet, for connecting dedicated company Splicing;It is respectively equipped with hook for hanging tools 2 in 1 lower end four corners of cabinet, for hanging power tool.
The hanger for tools 3 includes a rectangular frame as made of reinforcement welding, which is fixed on cabinet 1 End is peripheral, and the gap 30-50mm is equipped between 1 outer rim of every reinforcing bar and cabinet on rectangular frame.It is located on rectangular frame every Multiple cross bars 5 are uniformly welded with along its longitudinal direction between the reinforcing bar and cabinet 1 of a long side, to separate the power tool of suspension.
The dedicated connecting rope includes four connecting ropes 6, and four 6 one ends wounds of connecting rope are merged into one and are connected with gold Belong to hanging buckle 7, the other end of four connecting ropes 6 is connected separately with hook 9 and connects bolt 8 with cross-arm, for being separately connected dedicated storage Object case and cross-arm.
Although the embodiments of the present invention have been disclosed as above, but its is not only in the description and the implementation listed With it can be fully applied to various fields suitable for the present invention, for those skilled in the art, can be easily Realize other modification, therefore without departing from the general concept defined in the claims and the equivalent scope, the present invention is simultaneously unlimited In specific details and legend shown and described herein.

Claims (4)

1. multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole, it is characterised in that comprising steps are as follows:
1) the suspension installation fixed pulley on the cross-arm on electric pole top, and lifting rope is bypassed on fixed pulley;
2) the ground over-assemble cross-arm below the electric pole for the cross-arm installed;Assemble only connection one between cross-arm Shi Ergen cross-arm Root bolt;
3) the vertical bottle mounting hole at two cross-arm both ends is each passed through using the cross-arm connection bolt of dedicated connecting rope lower end and fasten; The dedicated connecting rope includes four connecting ropes, and four connecting rope one ends wounds are merged into one and are connected with metal hanging buckle, and four The other end of root connecting rope is connected separately with hook and connects bolt with cross-arm, for being separately connected Special storage box and cross-arm;
4) the metal hanging buckle of dedicated connecting rope upper end is hung on the suspension hook of lifting rope one end, it is another to pull down lifting rope by ground construction personnel One end, the cross-arm installation site being hoisted to two cross-arm levels by lifting rope on electric pole;
5) two cross-arms are pushed by the operating personnel on electric pole by electric pole side, are clipped in electric pole between two cross-arms, then wear If another bolt, by two cross-arm fixed clamps on electric pole;
6) porcelain piece of installation required on cross-arm, fitting are put into Special storage box, then put down dedicated connecting rope, by dedicated connection Four hooks of rope lower end are hung on the link of Special storage box top surface four corners, by pulling down lifting rope for Special storage box Be hoisted at the cross-arm on electric pole, by the operating personnel on electric pole by Special storage box porcelain piece and installation on cross-arm ?;
The Special storage box includes the cabinet of a upper end opening, is equipped with a circle hanger for tools in its outer rim of cabinet upper end edge, For hanging power tool;It is respectively equipped with link in box top four corners, for connecting dedicated connecting rope;In cabinet lower end four Hook for hanging tools is respectively equipped at angle, for hanging power tool;
7) repeat the above steps 2)~6), it is installed until multilayer cross-arm is all promoted.
2. multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole according to claim 1, it is characterized in that: described Box shape is cuboid, and by a cuboid framework and is separately fixed at the boxboard structure of cuboid framework bottom surface and surrounding At.
3. multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole according to claim 1, it is characterized in that: described Hanger for tools includes a rectangular frame as made of reinforcement welding, which is fixed on cabinet upper end periphery, rectangle frame The gap 30-50mm is equipped between every reinforcing bar on frame and cabinet outer rim.
4. multilayer cross-arm lifting installation method on a kind of overhead transmission line electric pole according to claim 3, it is characterized in that: in square Multiple cross bars are evenly equipped with along its longitudinal direction between the reinforcing bar and cabinet of each long side on shape frame, to separate the work of suspension Industry tool.
CN201710808627.3A 2017-09-09 2017-09-09 Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole Active CN107558793B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710808627.3A CN107558793B (en) 2017-09-09 2017-09-09 Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710808627.3A CN107558793B (en) 2017-09-09 2017-09-09 Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole

Publications (2)

Publication Number Publication Date
CN107558793A CN107558793A (en) 2018-01-09
CN107558793B true CN107558793B (en) 2019-08-09

Family

ID=60980376

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710808627.3A Active CN107558793B (en) 2017-09-09 2017-09-09 Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole

Country Status (1)

Country Link
CN (1) CN107558793B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108206466A (en) * 2018-02-06 2018-06-26 浙江辉弘光能股份有限公司 A kind of device of photovoltaic plant lifting
CN108756435A (en) * 2018-07-21 2018-11-06 国家电网有限公司 Cross-arm locator

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4048779A (en) * 1975-08-20 1977-09-20 Interpace Corporation Turnbuckle connector useable in a method for replacing an existing utility pole without disturbing hardware mounted thereon
CN201518397U (en) * 2009-06-16 2010-06-30 福建省福州电业局 Tool for replacing line suspension insulation string in 220 KV circuit with charged line
CN103174323A (en) * 2013-04-01 2013-06-26 国家电网公司 Multifunctional hoisting support frame
CN203289011U (en) * 2013-05-17 2013-11-13 国家电网公司 Tension cross arm hoisting device
CN203707659U (en) * 2013-11-30 2014-07-09 国家电网公司 Rapid installation suspender for distribution grid cross arms

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4048779A (en) * 1975-08-20 1977-09-20 Interpace Corporation Turnbuckle connector useable in a method for replacing an existing utility pole without disturbing hardware mounted thereon
CN201518397U (en) * 2009-06-16 2010-06-30 福建省福州电业局 Tool for replacing line suspension insulation string in 220 KV circuit with charged line
CN103174323A (en) * 2013-04-01 2013-06-26 国家电网公司 Multifunctional hoisting support frame
CN203289011U (en) * 2013-05-17 2013-11-13 国家电网公司 Tension cross arm hoisting device
CN203707659U (en) * 2013-11-30 2014-07-09 国家电网公司 Rapid installation suspender for distribution grid cross arms

Also Published As

Publication number Publication date
CN107558793A (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN103715633B (en) Strain insulator single hole yoke plate replacing insulator string method
CN107558793B (en) Multilayer cross-arm lifting installation method and its specific purpose tool on a kind of overhead transmission line electric pole
CN204559002U (en) A kind of bar control somersault is sliding
CN206379675U (en) The yoke plate clamp of electrified replacing linear tower V insulator string wires
CN203660423U (en) Lifting device for overhead ground wire of power transmission line
CN201774208U (en) Suspension counter weight for stabilizing lead jumper of high-voltage line tension corner tower
CN205791238U (en) A kind of 10kV distribution line charged lifter of straightway three-phase conducting wire
CN204349336U (en) Overhead-groundwire lifter
CN102931612A (en) Conducting wire fixer for 10kV live working
CN102255261A (en) Shifting device for two-circuit hot-line work of transmission line
CN104505771A (en) Overhead ground wire lifter
CN103174323A (en) Multifunctional hoisting support frame
CN204760979U (en) Straight line pole combination formula insulator crossarm
CN204012462U (en) A kind of for setting up the suspender of wire
CN202444204U (en) Traction lifting device for high-altitude circuit tools and appliances
CN203699783U (en) Hanging bracket fixed with wire pole
CN206438980U (en) Slide carry insulated hook ladder
CN103615189B (en) Rope ladder connecting structure for aerial cable
CN203756715U (en) Multifunctional pull rod connector
CN204858412U (en) Distribution lines cable and wire tied in a bundle set up and pass through ware with sharp pole
CN203150993U (en) 10kV live working lead fixer
CN209088485U (en) A kind of corner bracing wire anchor ear
CN203967628U (en) A kind of assembly that enters equal potential working region
CN203589536U (en) GW6-type disconnecting switch fast-assembling maintenance support
CN202421168U (en) Hanging clamp of insulator salt consistency value testing bunches

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant