CN107552991A CN201710959771.7A CN201710959771A CN107552991A CN 107552991 A CN107552991 A CN 107552991A CN 201710959771 A CN201710959771 A CN 201710959771A CN 107552991 A CN107552991 A CN 107552991A
Authority
CN
China
Prior art keywords
iron pipe
welding
cable
cable jacket
earth work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710959771.7A
Other languages
Chinese (zh)
Inventor
乔国林
乔玉司司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI JIANKE TECHNICAL ASSESSMENT OF CONSTRUCTION CO Ltd
Original Assignee
SHANGHAI JIANKE TECHNICAL ASSESSMENT OF CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI JIANKE TECHNICAL ASSESSMENT OF CONSTRUCTION CO Ltd filed Critical SHANGHAI JIANKE TECHNICAL ASSESSMENT OF CONSTRUCTION CO Ltd
Priority to CN201710959771.7A priority Critical patent/CN107552991A/en
Publication of CN107552991A publication Critical patent/CN107552991A/en
Pending legal-status Critical Current

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The welding method of cable jacket iron pipe, is related to cable jacket iron pipe welding technology field in a kind of earth work of the present invention.The present invention includes implementing the protection to cable (1) and the selection of ground connection overcoat iron pipe (2) ground connection pad, and it includes step:When A. constructing, stopping cable (1) transmits electric power or transmission signal;B. confirm job site without inflammable, explosive factor;C. pad is selected;D. paint removal or processing of rust removing are carried out to overcoat iron pipe (2) weld;... G. is by enforcement of regulations ground connection welding operation;H. welding quality is detected;I. remove wet burlap everywhere and carry out japanning processing;J. terminate.Pass through the inventive method, realize and avoid dismantling, operate the welding that efficient, economic, easy cable jacket iron pipe is grounded or parallel cable overcoat iron pipe is bridged or iron pipe seam crossing is electrically connected, be that lightning wave protection works, the electrostatic protection engineering of electrical equipment, electromagnetic interference shielding improvement project etc. provide strong technical support.

Description

The welding method of cable jacket iron pipe in a kind of earth work
Technical field
The present invention relates to cable jacket iron pipe welding technology field, refers specifically to cable jacket iron pipe in a kind of earth work Welding method.
Background information
From Franklin《It is electric identical with ours by sky lightning》Paper.By 1754, lightning rod started to apply. In more than 260 years of Franklin's invention shocking preventing technology, in the construction of substantial amounts of anti-induction thunder ENG land, often meet To prevent that various irregular pulses from attacking electrical equipment or prevention lightning wave is propagated, cable jacket iron pipe earthing method is used. The purpose of cable jacket iron pipe is not only to destroy from external force for cable, and more important is connect by cable jacket iron pipe Ground, or the bridging of parallel cable overcoat iron pipe, or the electrical connection of iron pipe seam crossing, prevent various irregular pulses from attacking electrical equipment Or prevention lightning wave is propagated or potential difference.So that the protection steel pipe of cable is grounded as an example, national standard GB50168《Electric device is installed Engineering cable line construction and acceptance specification》1992,2006,2016 versions, all for cable jacket iron pipe ground connection have clearly Regulation " when being grounded using the protection steel pipe of cable, should first weld ground wire, then cabling ".
At the same time, the consideration of cable is not splashed for spark caused by welding, people will recognize that and cool naturally, aqueous phase The welding of pass.Learnt from many documents, cooling welding, water cooling welding, Underwater Welding, the common feature with water welding manner are Cooling, and cool main purpose be welding when prevent welded article body deform, but can not prevent or eliminate welding caused by fire Flower.
Because design problem or construction are omitted, cable jacket iron pipe not ground connection or earth point deficiency, or simultaneously are tended to occur Distance is not bridged in prescribed limit between row cable jacket iron pipe, or iron pipe seam crossing is not electrically connected.Such electricity Cable overcoat iron pipe can not play the filtering of high pulse voltage as caused by thunderbolt or switching overvoltage or pressure acts on, and also cannot Ensure the electric current quality or communication quality of cable.Therefore, cable jacket iron pipe is grounded, or the bridging of parallel cable overcoat iron pipe, or The electrical connection of iron pipe seam crossing turns into the problem of indispensable in Lightning Transformation engineering.
Really, cable jacket iron pipe ground connection, or the bridging of parallel cable overcoat iron pipe, or the electrical connection of iron pipe seam crossing are implemented It can be welded by pipe collar and directly.Pipe collar electrical connection is ineffective, does not use generally, and it is best electric insertion hand to weld Section.After being so molded for cable jacket iron pipe, cable is included in iron pipe, and it is one kind side that cable extraction is implemented into welding again Method, but this for improvement project, so construction is nearly impossible, because if so construction, former electrical engineering It will again come, and can not only bring debugging again and possible newborn failure problems, user will not also allow.For that can not influence to weld Connect, and do not change original Cable layout and reliably working, in the case where avoiding dismantling, operate efficient, economic, easy theory, how Implement cable jacket iron pipe ground connection, bridging, connection by welding, it is desirable to a kind of method for solving this problem.
The content of the invention
It is an object of the invention to overcome missing existing for prior art and deficiency, propose in a kind of earth work outside cable The welding method of iron pipe is covered, including implements the protection to cable and the selection of ground connection overcoat iron pipe ground connection pad, it also includes Step:
When A. constructing, stop cable transfer electric power or transmission signal;
B. confirm job site without inflammable, explosive factor;
C. pad is selected;
D. paint removal or derusting are carried out to overcoat iron pipe weld;
E. at overcoat iron pipe port, the gap between cable and iron pipe, anti-welding spark is taken to be splashed into measure;
F. the cable exposed in nearly iron pipe port, anti-welding spark measure is taken;
G. by enforcement of regulations ground connection welding operation;
H. welding quality is detected;
I. remove wet burlap everywhere and carry out japanning processing;
J. terminate.
The welding method of cable jacket iron pipe, construction meet in a kind of earth work of the present invention:
1. China State Bureau of Quality and Technical Supervision, The Ministry of Construction of the People's Republic of China, MOC's joint are issued《Building lightning protection design rule Model》GB50057-2010.
2. The Ministry of Construction of the People's Republic of China, MOC, State Administration for Quality Supervision and Inspection and Quarantine's joint are issued《Building electronics Information system design code for lightning-proof》GB50343-2012.
As described above, the inventive method can need not dismantle original cable, make to cause cable to destroy due to welding procedure Risk substantially reduces.Solves the problems, such as site operation with this method.Be grounded for lightning protection improvement project cable jacket iron pipe, Electrically insertion construction provides strong technical support for bridging, connection.
Brief description of the drawings
Fig. 1 is welding procedure drawing schematic diagram;
Fig. 2 is the welding method FB(flow block) of cable jacket iron pipe in a kind of earth work of the present invention.
Embodiment
Below in conjunction with drawings and examples, the invention will be further described
The welding method of cable jacket iron pipe in a kind of earth work, including implement the protection to cable 1 and ground connection overcoat Iron pipe 2 is grounded the selection (as shown in Figure 1) of pad.
Its method and step is following (as shown in Figure 2):
The first step, during construction, stop cable 1 and transmit electric power or transmission signal.
Second step, confirm job site without inflammable, explosive factor.
3rd step, select pad.
4th step, paint removal or derusting are carried out to the weld of overcoat iron pipe 2;
5th step, at the port of overcoat iron pipe 2, gap is taken anti-welding spark to be splashed into and arranged between cable 1 and iron pipe 2 Apply;
6th step, in the cable that the nearly port of iron pipe 2 is exposed, take anti-welding spark measure;
7th step, welding operation is grounded by enforcement of regulations;
8th step, detect welding quality;
9th step, remove wet burlap everywhere and carry out japanning processing;
Tenth step, terminate.
Wherein, the 3rd step selection pad, apart from the port of iron pipe 2, distance is not more than 0.02m.
The anti-welding spark of 5th step is splashed into measure, i.e., wet burlap is filled between cable 1 and iron pipe 2 in gap, its Depth is more than 0.07m.
6th step takes anti-welding spark measure, and packages length is 0.1m-0.15m wet burlap on cable 1.
7th step implements welding, and during using bonding jumper band steel, three face weldings, weld arc length degree is the 2 of band steel width Times;
During using bonding jumper round steel, two-sided welding, weld arc length degree is 6 times of round steel diameter.
8th step detects welding quality, and detection electrical connection state is tested using equipotential instrument;
Grounding resistance is detected using earth resistance tester.
Further, in the 7th step, connect for iron pipe seam crossing (welding), be symmetrical with using 2-3 bar welding metal bars Iron pipe axle center implements to weld in iron pipe outer surface, can so reach the purpose of uniform conductive lightning current or Overcurrent.
In summary, the inventive method is implemented, and is ensureing around construction without under inflammable and explosive conditions.This method is adapted to Improvement project, the electrostatic protection improvement project of electrical equipment, electromagnetic interference shielding improvement project are protected in lightning wave;Avoiding tearing open Unload, operate efficiently, it is economical, easy in the case of implement cable jacket iron pipe ground connection or the bridging of parallel cable overcoat iron pipe or iron pipe The welding of seam crossing electrical connection, it can be achieved do not endanger cable, do not destroy cable iron pipe form and layout.In many lightning protection works Solves the problems, such as site operation with this method in journey, pipe engineering.Pass through on-the-spot test and temporal inspection, this construction skill Art has obtained good effect, while has also obtained the accreditation of user;Be grounded for lightning protection improvement project cable jacket iron pipe, Electrically insertion construction provides strong technical support for bridging, connection.

Claims (6)

1. the welding method of cable jacket iron pipe in a kind of earth work, including implement the protection to cable (1) and ground connection overcoat Iron pipe (2) is grounded the selection of pad, it is characterised in that also comprises the following steps:
When A. constructing, stopping cable (1) transmits electric power or transmission signal;
B. confirm job site without inflammable, explosive factor;
C. pad is selected;
D. paint removal or derusting are carried out to overcoat iron pipe (2) weld;
E. at overcoat iron pipe (2) port, gap takes anti-welding spark to be splashed into measure between cable (1) and iron pipe (2);
F. the cable exposed in nearly iron pipe (2) port, takes anti-welding spark measure;
G. by enforcement of regulations ground connection welding operation;
H. welding quality is detected;
I. remove wet burlap everywhere and carry out japanning processing;
J. terminate.
2. the welding method of cable jacket iron pipe in a kind of earth work as claimed in claim 1, it is characterised in that the step Rapid C. selections pad, apart from iron pipe (2) port, distance is not more than 0.02m.
3. the welding method of cable jacket iron pipe in a kind of earth work as claimed in claim 1, it is characterised in that the step The rapid anti-welding sparks of E. are splashed into measure, i.e., wet burlap are filled between cable (1) and iron pipe (2) in gap, its depth is more than 0.07m。
4. the welding method of cable jacket iron pipe in a kind of earth work as claimed in claim 1, it is characterised in that the step Rapid F. takes anti-welding spark measure, and packages length is 0.1m-0.15m wet burlap on cable (1).
5. the welding method of cable jacket iron pipe in a kind of earth work as claimed in claim 1, it is characterised in that the step Rapid G. implements welding, and during using bonding jumper band steel, three face weldings, weld arc length degree is 2 times of band steel width;
During using bonding jumper round steel, two-sided welding, weld arc length degree is 6 times of round steel diameter.
6. the welding method of cable jacket iron pipe in a kind of earth work as claimed in claim 1, it is characterised in that the step Rapid H. detections welding quality, detection electrical connection situation is tested using equipotential instrument;Detected and be grounded using earth resistance tester Resistance value.
CN201710959771.7A 2017-10-16 2017-10-16 The welding method of cable jacket iron pipe in a kind of earth work Pending CN107552991A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710959771.7A CN107552991A (en) 2017-10-16 2017-10-16 The welding method of cable jacket iron pipe in a kind of earth work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710959771.7A CN107552991A (en) 2017-10-16 2017-10-16 The welding method of cable jacket iron pipe in a kind of earth work

Publications (1)

Publication Number Publication Date
CN107552991A true CN107552991A (en) 2018-01-09

Family

ID=60985968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710959771.7A Pending CN107552991A (en) 2017-10-16 2017-10-16 The welding method of cable jacket iron pipe in a kind of earth work

Country Status (1)

Country Link
CN (1) CN107552991A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108747106A (en) * 2018-06-04 2018-11-06 长沙格力暖通制冷设备有限公司 A kind of the welding protective tooling and its production process of valve body

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87212776U (en) * 1987-11-10 1988-09-28 郑传云 Combined welding cable
US5050958A (en) * 1989-03-06 1991-09-24 Telephone Cables Limited Optical fibre cable
DE10156656A1 (en) * 2001-11-17 2003-06-05 Gunnar Buerkner Current connection cable, for a welding burner, has a tubular structure to carry the copper strands in rings around a thinner tube section to be covered by sleeves and a rubber hose, for a gas/coolant to flow through the center
CN200987062Y (en) * 2006-12-29 2007-12-05 中国南车集团成都机车车辆厂 Electric cable connector
CN201556466U (en) * 2009-09-28 2010-08-18 浙江天杰实业有限公司 Underground armored aluminium tube coaxial cable
CN101832435A (en) * 2010-04-27 2010-09-15 武汉一冶机电工程有限责任公司 Method for butting buried cable steel tube on site during construction
CN103774766A (en) * 2014-01-10 2014-05-07 葛加君 Thunder and lightning pro-control construction method for intelligent building

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN87212776U (en) * 1987-11-10 1988-09-28 郑传云 Combined welding cable
US5050958A (en) * 1989-03-06 1991-09-24 Telephone Cables Limited Optical fibre cable
DE10156656A1 (en) * 2001-11-17 2003-06-05 Gunnar Buerkner Current connection cable, for a welding burner, has a tubular structure to carry the copper strands in rings around a thinner tube section to be covered by sleeves and a rubber hose, for a gas/coolant to flow through the center
CN200987062Y (en) * 2006-12-29 2007-12-05 中国南车集团成都机车车辆厂 Electric cable connector
CN201556466U (en) * 2009-09-28 2010-08-18 浙江天杰实业有限公司 Underground armored aluminium tube coaxial cable
CN101832435A (en) * 2010-04-27 2010-09-15 武汉一冶机电工程有限责任公司 Method for butting buried cable steel tube on site during construction
CN103774766A (en) * 2014-01-10 2014-05-07 葛加君 Thunder and lightning pro-control construction method for intelligent building

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《建筑施工手册》(第四版)编写组: "《建筑施工手册第四版》", 30 June 2003, 中国建筑工业出版社 *
范伟: "《城市桥梁工程施工案例》", 30 November 2013, 中国矿业大学出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108747106A (en) * 2018-06-04 2018-11-06 长沙格力暖通制冷设备有限公司 A kind of the welding protective tooling and its production process of valve body
CN108747106B (en) * 2018-06-04 2020-07-07 长沙格力暖通制冷设备有限公司 Welding protection tool for valve body and manufacturing process thereof

Similar Documents

Publication Publication Date Title
WO2018141259A1 (en) Grounding monitoring system, method and device, and computer-readable storage medium
CN105262075B (en) A kind of method that utilization detection means realizes deformation of transformer winding live detection
CN103323751A (en) High-voltage short-cable insulation terminal partial discharge testing device and using method
CN105790211A (en) Method for protecting earth electrode line
CN107552991A (en) The welding method of cable jacket iron pipe in a kind of earth work
JP4784324B2 (en) Lightning damage protection equipment for overhead power lines and its construction method
CN205304237U (en) Earth potential counterattack protection grounding box
CN104852349A (en) Overvoltage protective device used for natural gas pipeline system
Lopes et al. A procedure to evaluate the risk of failure of distribution transformers insulation due to lightning induced voltages
CN209344514U (en) The device of steel tower tower head overvoltage when a kind of inhibition transmission line lightning stroke
CN103926493B (en) A kind of monitoring method and apparatus for high voltage single-core cable sheath protector
Agrawal et al. Lightning phenomena and its effect on transmission line
CN202103417U (en) Lightning protection device for integrated logging instrument
CN204497723U (en) A kind of over-pressure safety device for Natural gas pipeline system
CN205081467U (en) Be applied to end screen protection circuit that electric -examination of transformer winding deformation band was surveyed
JP2008130986A (en) Lightning protection method for electric facility
CN109038513A (en) A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means
CN205941700U (en) Safety monitoring's digital earthing pole
CN208062733U (en) A kind of cross interconnected case based on barrier blocks
CN202563012U (en) Large-scale power station grounding net impedance parameter measuring device
CN201600999U (en) Grounding transformer capable of detecting zero sequence transformer
Ito et al. Two case studies on energy and protection level coordination of an SPD system
CN103457046B (en) A kind of earth lead protection device
CN205385116U (en) Portable ground connection stake
CN107611956A (en) A kind of small high voltage switch cubicle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180109

WD01 Invention patent application deemed withdrawn after publication