Prior art keywords
earthing
fault
nmax0
grounding means
phase transfer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710716976.2A
Other languages
Chinese (zh)
Other versions
CN109038513B (en
Inventor
李景禄
李政洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710716976.2A priority Critical patent/CN109038513B/en
Publication of CN109038513A publication Critical patent/CN109038513A/en
Application granted granted Critical
Publication of CN109038513B publication Critical patent/CN109038513B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/08Locating faults in cables, transmission lines, or networks
    • G01R31/081Locating faults in cables, transmission lines, or networks according to type of conductors
    • G01R31/086Locating faults in cables, transmission lines, or networks according to type of conductors in power transmission or distribution networks, i.e. with interconnected conductors

Abstract

It is a kind of for failure phase transfer earthing or grounding means broken string ground connection intelligent processing method, in power network neutral point displacement voltage UNStable reaches UN≥UQWhen, then judge whether to meet UN≥UN2, the transfer processing program of ground fault is directly entered if meeting;Such as UN≥UN2, then measure and find out maximum zero-sequence current I in each feeder linenmax0If Inmax0≥I01Into the transfer processing program of ground fault, if not satisfied, the Δ T that is then delayed1Judge I again afterwardsnmax0Whether I is metnmax0≥I01, if satisfied, then entering the transfer processing program of ground fault;If not satisfied, then more whether meeting I againnmax0≥I02, if not satisfied, being then determined as the phase to phase fault that breaks, device issues break alarm signal at this time;If meeting Inmax0≥I01, then be delayed Δ T2Judge whether to meet I again afterwardsnmax0≥I01, the transfer processing program of ground fault is carried out if meeting, if being unsatisfactory for the high resistance earthing fault for being judged to being not suitable for fail-over conditions, device only carries out earthing wire-selecting processing, select earth fault line without failure transfer processing at this time.

Description

A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means
Technical field
The present invention is the troubleshooting field of power distribution network single-phase earthing, is mainly used for failure phase transfer earthing or grounding means to distribution The Intelligent treatment of the complex grounding fault with interruption of net.
Background technique
There are many types for the failure of power distribution network, but mainly have power distribution network single-phase disconnection and the complex grounding fault with interruption, power distribution network hair When raw asymmetry disconnection fault, the asymmetry of each phase voltage of power distribution network will cause, when especially distribution line head end breaks, It is asymmetric the most serious.The excessive resistance ground fault as caused by conducting wire landing after if broken string occurs, when excessive resistance value After reaching certain value, due to asymmetric influence, the judgement rule of ground fault phase is broken, and is connect so that it cannot be appropriately determined Earth fault phase.Failure phase transfer earthing or grounding means is mainly by finding out ground fault phase, passing through when singlephase earth fault occurs The correspondence phase earthing switch of device closes a floodgate over the ground, shifts ground fault to carry out troubleshooting, after distribution line broken string It is grounded asymmetric influence, the judgement rule of ground fault phase is broken, and can not be appropriately determined ground fault phase, and it is wrong to be easy choosing Phase, it is asymmetric the most serious especially when distribution line head end breaks, it is easiest to select misphase.In distribution line head end When breaking, device, which selects misphase to close a floodgate over the ground, will cause phase fault, belong near region short trouble, to electric substation, especially A kind of intelligence maximum, thus that broken string ground connection for failure phase transfer earthing or grounding means must be found is threatened caused by main transformer Energy processing method, carries out Intelligent treatment when the complex grounding fault with interruption occurs for power distribution network.
Summary of the invention
In view of the above-mentioned problems, having invented a kind of Intelligent treatment side of broken string ground connection for failure phase transfer earthing or grounding means Method, in power network neutral point displacement voltage UNStable reaches UN≥UQWhen, then judge whether to meet UN≥UN2, straight if meeting Tap into the transfer processing program into ground fault;Such as UN≥UN2, then measure and find out maximum zero-sequence current I in each feeder linenmax0, If Inmax0≥I01Into the transfer processing program of ground fault, if not satisfied, the Δ T that is then delayed1Judge I again afterwardsnmax0Whether meet Inmax0≥I01, if satisfied, then entering the transfer processing program of ground fault;If not satisfied, then more whether meeting I againnmax0≥ I02, if not satisfied, being then determined as the phase to phase fault that breaks, device issues break alarm signal at this time;If meeting Inmax0≥I01, Then be delayed Δ T2Judge whether to meet I again afterwardsnmax0≥I01, the transfer processing program of ground fault is carried out if meeting, if discontented High resistance earthing fault that is sufficient then being judged to being not suitable for fail-over conditions, device is only carried out without failure transfer processing at this time Earthing wire-selecting is handled, and maximum zero-sequence current I occurs in each feeder linenmax0Route be earth fault line.
UQFor the fault initiating voltage of failure phase transfer earthing or grounding means, different failure phase transfer earthing or grounding means can be carried out not Same setting, but should be greater than the maximum neutral point displacement voltage of isolated neutral system power grid permission, UQ>UФ5%, UФIt is mutually electric for power grid Pressure. UN2For the maximum feeder line of zero-sequence current in power grid head end break when caused by neutral point displacement voltage, can by calculate or The method of field measurement obtains.
I01Minimum earth current when high resistance earthing fault, i.e. earth-fault current are handled for failure phase transfer earthing or grounding means Failure phase transfer earthing or grounding means correctly can carry out transfer processing, different failure phase transfers to ground fault when reaching the value Earthing or grounding means has different minimum earth currents.I02When the high resistance ground that can reliably detect for failure phase transfer earthing or grounding means Zero-sequence current, the electric current are less than minimum earth current I when failure phase transfer earthing or grounding means processing high resistance earthing fault01, connecing Earth fault electric current is I02When, failure phase transfer earthing or grounding means cannot carry out transfer processing to ground fault, can only carry out ground connection choosing Line can be selected by the method for route selection and cut off faulty line.I02It should be greater than generating most in feeder line when route head end broken string Big zero-sequence current.
ΔT1The maximum duration landed from broken string to conducting wire for power distribution network;ΔT2By unstable ground connection after being landed for conducting wire Develop to the time of quiet earth.
The present invention has an advantage that
1, the present invention solves the key technology that failure phase transfer earthing or grounding means selects misphase in processing power distribution network the complex grounding fault with interruption Problem, that is, solve the problems, such as that can failure phase transfer earthing or grounding means use in power grid security.
2, the intelligent processing method of present invention application broken string ground connection, solves power distribution network broken line fault and the complex grounding fault with interruption Accurate judgement prevent error action of device from causing near region short circuit accident, so that fault spread is jeopardized equipment safety.
3, the present invention according to the active development of power distribution network the complex grounding fault with interruption point ground resistance and the differentiation of earth fault at Reason method solves the processing problem of high resistance ground.
Detailed description of the invention
Fig. 1 is the logic chart of the intelligent processing method of the broken string ground connection of failure phase transfer earthing or grounding means.
Specific embodiment
When using failure phase transfer earthing or grounding means processing one-phase earthing failure in electric distribution network, electricity is displaced in power network neutral point Press UNStable reaches UN≥UQWhen, then judge whether to meet UN≥UN2, the transfer processing of ground fault is directly entered if meeting Program;Such as UN≥UN2, then measure and find out maximum zero-sequence current I in each feeder linenmax0If Inmax0≥I01Into ground fault Transfer processing program, if not satisfied, the Δ T that is then delayed1Judge I again afterwardsnmax0Whether I is metnmax0≥I01, if satisfied, then entering The transfer processing program of ground fault;If not satisfied, then more whether meeting I againnmax0≥I02, if not satisfied, being then judged to breaking Line phase to phase fault, device issues break alarm signal at this time;If meeting Inmax0≥I01, then be delayed Δ T2Judge whether again afterwards full Sufficient Inmax0≥I01, the transfer processing program of ground fault is carried out if meeting, if being unsatisfactory for being judged to being not suitable for failure transfer The high resistance earthing fault of condition, device only carries out earthing wire-selecting processing, occurs in each feeder line without failure transfer processing at this time Maximum zero-sequence current Inmax0Route be earth fault line.
UQFor the fault initiating voltage of failure phase transfer earthing or grounding means, different failure phase transfer earthing or grounding means can be carried out not Same setting, but should be greater than the maximum neutral point displacement voltage of isolated neutral system power grid permission, UQ>UФ5%, UФIt is mutually electric for power grid Pressure. UN2For the maximum feeder line of zero-sequence current in power grid head end break when caused by neutral point displacement voltage, can by calculate or The method of field measurement obtains.
I01Minimum earth current when high resistance earthing fault, i.e. earth-fault current are handled for failure phase transfer earthing or grounding means Failure phase transfer earthing or grounding means correctly can carry out transfer processing, different failure phase transfers to ground fault when reaching the value Earthing or grounding means has different minimum earth currents.I02When the high resistance ground that can reliably detect for failure phase transfer earthing or grounding means Zero-sequence current, the electric current are less than minimum earth current I when failure phase transfer earthing or grounding means processing high resistance earthing fault01, connecing Earth fault electric current is I02When, failure phase transfer earthing or grounding means cannot carry out transfer processing to ground fault, can only carry out ground connection choosing Line can be selected by the method for route selection and cut off faulty line.I02It should be greater than generating most in feeder line when route head end broken string Big zero-sequence current.
ΔT1The maximum duration landed from broken string to conducting wire for power distribution network;ΔT2By unstable ground connection after being landed for conducting wire Develop to the time of quiet earth.
The above is only a preferred embodiment of the present invention, protection scope of the present invention is not limited merely to above-mentioned implementation Example, all technical solutions belonged under thinking of the present invention all belong to the scope of protection of the present invention.It should be pointed out that for the art Those of ordinary skill for, several improvements and modifications without departing from the principles of the present invention also should be regarded as guarantor of the invention Protect range.

Claims (6)

1. a kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means, it is characterised in that: in power distribution network Neutral point displacement voltage UNStable reaches UN≥UQWhen, then judge whether to meet UN≥UN2, ground connection event is directly entered if meeting The transfer processing program of barrier;Such as UN≥UN2, then measure and find out maximum zero-sequence current I in each feeder linenmax0If Inmax0≥I01 Into the transfer processing program of ground fault, if not satisfied, the Δ T that is then delayed1Judge I again afterwardsnmax0Whether I is metnmax0≥I01, If satisfied, then entering the transfer processing program of ground fault;If not satisfied, then more whether meeting I againnmax0≥I02If discontented Foot, then be determined as the phase to phase fault that breaks, and device issues break alarm signal at this time;If meeting Inmax0≥I01, then be delayed Δ T2 Judge whether to meet I again afterwardsnmax0≥I01, the transfer processing program of ground fault is carried out if meeting, if being unsatisfactory for being determined as Be not suitable for the high resistance earthing fault of fail-over conditions, device only carries out at earthing wire-selecting without failure transfer processing at this time It manages, maximum zero-sequence current I occurs in each feeder linenmax0Route be earth fault line.
2. a kind of intelligent processing method of broken string ground connection for failure phase transfer earthing or grounding means according to claim 1, It is characterized by: UQFor the fault initiating voltage of failure phase transfer earthing or grounding means, different failure phase transfer earthing or grounding means can be into The different setting of row, but should be greater than the maximum neutral point displacement voltage of isolated neutral system power grid permission, UQ>UФ5%, UФFor power grid Phase voltage.
3. a kind of intelligent processing method of broken string ground connection for failure phase transfer earthing or grounding means according to claim 1, It is characterized by: UN2For the maximum feeder line of zero-sequence current in power grid head end break when caused by neutral point displacement voltage, can lead to The method for crossing calculating or field measurement obtains.
4. a kind of intelligent processing method of broken string ground connection for failure phase transfer earthing or grounding means according to claim 1, It is characterized by: I01Minimum earth current when high resistance earthing fault, i.e. ground fault are handled for failure phase transfer earthing or grounding means Failure phase transfer earthing or grounding means correctly can carry out transfer processing, different failure phases to ground fault when electric current reaches the value Transfer earthing or grounding means has different minimum earth currents.
5. a kind of intelligent processing method of broken string ground connection for failure phase transfer earthing or grounding means according to claim 1, It is characterized by: I02The zero-sequence current when high resistance ground that can reliably detect for failure phase transfer earthing or grounding means, the electric current are small Minimum earth current I when failure phase transfer earthing or grounding means handles high resistance earthing fault01, it is I in earth-fault current02When, Failure phase transfer earthing or grounding means cannot carry out transfer processing to ground fault, can only carry out earthing wire-selecting, can pass through the side of route selection Faulty line, I are selected and cut off to method02It should be greater than the maximum zero sequence current generated in feeder line when route head end broken string.
6. a kind of intelligent processing method of broken string ground connection for failure phase transfer earthing or grounding means according to claim 1, It is characterized by: Δ T1The maximum duration landed from broken string to conducting wire for power distribution network;ΔT2To be connect after conducting wire landing by unstable Develop to the time of quiet earth in ground.
CN201710716976.2A 2017-08-21 2017-08-21 A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means Active CN109038513B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710716976.2A CN109038513B (en) 2017-08-21 2017-08-21 A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710716976.2A CN109038513B (en) 2017-08-21 2017-08-21 A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means

Publications (2)

Publication Number Publication Date
CN109038513A true CN109038513A (en) 2018-12-18
CN109038513B CN109038513B (en) 2019-09-10

Family

ID=64629397

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710716976.2A Active CN109038513B (en) 2017-08-21 2017-08-21 A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means

Country Status (1)

Country Link
CN (1) CN109038513B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110098600A (en) * 2019-05-08 2019-08-06 天津大学 A kind of cable monopolar grounding fault guard method based on line capacitance transfer charge
CN111929531A (en) * 2020-07-20 2020-11-13 南方电网科学研究院有限责任公司 Power distribution network fault section positioning method and system based on ground fault transfer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1355585A (en) * 2000-10-20 2002-06-26 施魏策尔工程实验公司 Failure type selecting system for identificating failure in electric system
CN102231517A (en) * 2011-06-09 2011-11-02 航天科工深圳(集团)有限公司 Method and system for determining and isolating power distribution network fault
CN106872852A (en) * 2017-01-13 2017-06-20 济南大学 The multiple fault type diagnostic method of power distribution network single-phase disconnection ground connection based on residual voltage

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1355585A (en) * 2000-10-20 2002-06-26 施魏策尔工程实验公司 Failure type selecting system for identificating failure in electric system
CN102231517A (en) * 2011-06-09 2011-11-02 航天科工深圳(集团)有限公司 Method and system for determining and isolating power distribution network fault
CN106872852A (en) * 2017-01-13 2017-06-20 济南大学 The multiple fault type diagnostic method of power distribution network single-phase disconnection ground connection based on residual voltage

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110098600A (en) * 2019-05-08 2019-08-06 天津大学 A kind of cable monopolar grounding fault guard method based on line capacitance transfer charge
CN110098600B (en) * 2019-05-08 2021-02-26 天津大学 Cable single-pole ground fault protection method based on line capacitance transferred charge
CN111929531A (en) * 2020-07-20 2020-11-13 南方电网科学研究院有限责任公司 Power distribution network fault section positioning method and system based on ground fault transfer
CN111929531B (en) * 2020-07-20 2021-07-27 南方电网科学研究院有限责任公司 Power distribution network fault section positioning method and system based on ground fault transfer

Also Published As

Publication number Publication date
CN109038513B (en) 2019-09-10

Similar Documents

Publication Publication Date Title
EP2856590B1 (en) Method of fault clearance
US8502416B2 (en) Method and circuit arrangement for connecting at least one string of a photovoltaic system to an inverter
CN107438929B (en) Method for being protected in combined power transmission line
CN107534296B (en) Bipolar DC power transmission structure
US20100202092A1 (en) Differential Protection Method, System And Device
CN103837798B (en) The quick diagnosis device of one-phase earthing failure in electric distribution network character
CN106501683A (en) One kind is without main website power distribution network one-way earth fault localization method
EP4046249A1 (en) High voltage overhead electric transmission line equipped with switchgear unit
CN109038513B (en) A kind of intelligent processing method of the broken string ground connection for failure phase transfer earthing or grounding means
CN105529681B (en) The earth leakage protective implementation method of low voltage ungrounded system
CN109031035A (en) A kind of otherness one-phase earthing failure in electric distribution network property and fault recovery judgment method
CN109787195A (en) A kind of personal safety facture of power network neutral point intelligent electric resistance earthing mode
CN106970289A (en) The method for detecting the interruption of the active conductor of ungrounded DC-voltage supply system
CN108008236A (en) A kind of method for detecting electrical equipment fault
Reyna et al. Transmission line single-pole tripping: field experience in the western transmission area of Mexico
CN104009453B (en) A kind of fault detection method for micro-capacitance sensor off-grid operation situation
CN108254650A (en) A kind of quick distinguishing method of substation busbars singlephase earth fault
CN108718078A (en) The exchange micro-capacitance sensor route protection algorithm of impedance variations is measured based on circuit both ends
Venkata et al. Advanced and adaptive protection for active distribution grid
CN203911463U (en) Single-phase earthing circuit protection device of power distribution network for arc-suppression coil-based neutral-point earthing system
DE202009007389U1 (en) FI tripping protection for overvoltages
CN107678478B (en) Circuit and method for monitoring working state of secondary neutral point valve plate of voltage transformer
RU167199U1 (en) PROTECTION DEVICE FOR SINGLE-PHASE EARTH CIRCUITS IN THE CONNECTION OF EARTHING DEVICES
CN108683157A (en) A kind of busbar grounding intelligent decision method for shifting grounding device
US11728638B2 (en) Normally open tie pulse testing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant