CN107524140A - A kind of artificial digging pile concrete support device - Google Patents
A kind of artificial digging pile concrete support device Download PDFInfo
- Publication number
- CN107524140A CN107524140A CN201710746758.3A CN201710746758A CN107524140A CN 107524140 A CN107524140 A CN 107524140A CN 201710746758 A CN201710746758 A CN 201710746758A CN 107524140 A CN107524140 A CN 107524140A
- Authority
- CN
- China
- Prior art keywords
- groove
- hole
- connection box
- template
- rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of artificial digging pile concrete support device,Including four templates and hole,Four templates join end to end and are placed in hole,The present invention is by adding transverse support bar,Head rod,Hole,The second connection structure such as box and filling concrete groove,Be powered the second electromagnet,So that the second electromagnet attracts permanent magnet,So that the second connecting rod departs from the first groove,So as to remove the 3rd connection box,Simultaneously,Due to the disengaging of the second connecting rod,Second conducting strip no longer contacts with the first conducting strip,First electromagnet no longer attracts iron,The first screw rod and the second screw rod are screwed out again,Iron departs from the 3rd groove in the presence of the first spring,Template loses support,The template of left and right ends is set to be separated with the template of upper and lower ends,Next section of concrete support can quickly be entered,It is not only convenient and swift,And improve operating efficiency.
Description
Technical field
The present invention relates to supporting field, specially a kind of artificial digging pile concrete support device.
Background technology
With development of the country to new district, particularly town road and science of bridge building, artificial digging pile is because easy for construction, fast
Degree is very fast, does not need the more low advantage of heavy mechanical equipment, cost to be used widely.Due to caisson underground work condition
Difference, bad environments, labor intensity are big, and safety and quality are even more important.As the continuous intensification of artificial digging pile, workmen are past
Larger security risk is brought toward ignorance retaining wall quality, as mechanization degree is constantly lifted, it is a kind of more convenient to find, more
The artificial digging pile concrete support device of safety is particularly important.
The content of the invention
It is an object of the invention to provide a kind of artificial digging pile concrete support device, to solve in above-mentioned background technology
The problem of proposition.
A kind of artificial digging pile concrete support device, including four templates and hole, four templates join end to end
It is placed in hole, the upper end of the template offers filling concrete groove, and the both ends of the relative template of one pair of which are fixed
The first connection box is connected with, the both ends of the relative template of another pair have been fixedly connected with the second connection box, in same template
Two first connection boxes connected by transverse support bar, the both ends of the support bar are connected to the first company by the 5th screw rod
The upper surface of box is connect, two in same template second connect the relative one end of box and are fixedly connected with the one of head rod
End, the other end of the head rod offer the first groove, and the bottom of first groove is connected with by second spring
First conducting strip, the both ends of first groove offer the 3rd threaded passage, and the 3rd threaded passage internal thread is connected with
3rd screw rod, in first groove activity be plugged with the second connecting rod, second connecting rod is located at one in the first groove
End is fixedly connected with the second conducting strip, and the second connecting rod offers the first tapped through hole matched with the 3rd screw rod, and described the
One tapped through hole is connected with the 3rd screw flight, and two the second connecting rod activities are plugged on the both ends of the 3rd connection box, the
Two connecting rods connect one section in box positioned at the 3rd and offer the second tapped through hole, and the second tapped through hole internal thread is connected with
4th threaded rod, the both ends of the 3rd connection box offer the 4th threaded passage matched with the 4th threaded rod, and the 4th
Threaded passage is threadedly coupled with the 4th threaded rod, and the one end of second connecting rod in the 3rd connection box is fixedly connected with second
The side of electromagnet, the opposite sides of two second electromagnet are connected to up and down the two of permanent magnet by the 3rd spring
Side, the permanent magnet are fixedly connected with the 3rd intracavity sidewall for being connected box;
The second connection box offers the second groove close to one end of the first connection box, and the first connection box is close to the
One end of two connection boxes offers the 3rd groove, and the bottom of second groove connects one end of iron, institute by the first spring
The other end activity for stating iron is plugged in the 3rd groove, and be located in the second groove one section of the iron offers the 3rd screw thread
Through hole, the both ends of second groove offer the first threaded passage, and the first threaded passage and the 3rd equal spiral shell of tapped through hole
Line connects the first screw rod, and be located in the 3rd groove one section of the iron offers the 4th tapped through hole, the 3rd groove
Both ends offer the second threaded passage, and the second threaded passage is threadedly coupled the second screw rod with the 4th tapped through hole, described
The bottom of 3rd groove is fixedly connected with the first electromagnet.
Preferably, the filling concrete groove is located at the upper center of template.
Preferably, the 3rd connection box is rectangular frame.
Preferably, the filling concrete groove is in ball coronal structure.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is by adding transverse support bar, the first connection
Bar, hole, the second connection structure such as box and filling concrete groove, staff by filling concrete groove to template and hole it
Between space be irrigated, by connecting external power source, when needing to carry out next section of perfusion, screw out the 3rd screw rod and the 4th spiral shell
Bar, be powered the second electromagnet, so that the second electromagnet attracts permanent magnet, so that the second connecting rod departs from the first groove,
So as to remove the 3rd connection box, simultaneously as the disengaging of the second connecting rod, the second conducting strip no longer contacts with the first conducting strip,
So as to which the first electromagnet be powered off, the first electromagnet no longer attracts iron, then screws out the first screw rod and the second screw rod, and iron is the
Departing from the 3rd groove in the presence of one spring, template loses support, the template of left and right ends is separated with the template of upper and lower ends,
Next section of concrete support can quickly be entered, it is not only convenient and swift, and improve operating efficiency.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is top view of the present invention;
Fig. 3 is A portions structure enlargement diagram;
Fig. 4 is B portions structure enlargement diagram.
In figure:Template 1, first connects box 2, transverse support bar 3, head rod 4, hole 5, second and connects box 6, coagulation
Soil perfusion groove 7, the first spring 8, iron 9, the first screw rod 10, the first electromagnet 11, the 3rd screw rod 12, second spring 13, first
Conducting strip 14, the second conducting strip 15, the second connecting rod 16, the second electromagnet 17, the 3rd spring 18, permanent magnet 19, the 5th screw rod
20th, the 3rd connection box 21.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other under the premise of creative work is not made
Embodiment, belong to the scope of protection of the invention.
Fig. 1-4 are referred to, the present invention provides a kind of technical scheme:
A kind of artificial digging pile concrete support device, including four templates 1 and hole 5, four templates 1 join end to end and put
To put in hole 5, the upper end of template 1 offers filling concrete groove 7, and filling concrete groove 7 is located at the upper center of template 1,
Filling concrete groove 7 is in ball coronal structure, is easy to pour into concrete, the both ends of the relative template 1 of one pair of which are fixedly connected with
There is the first connection box 2, the both ends of the relative template 1 of another pair have been fixedly connected with the second connection box 6, in same template 1
Two first connection boxes 2 connected by transverse support bar 3, the both ends of support bar 3 are connected to first by the 5th screw rod 20
The upper surface of box 2 is connected, two second relative one end of connection box 6 in same template 1 are fixedly connected with the first connection
One end of bar 4, the other end of head rod 4 offer the first groove, and the bottom of the first groove is connected by second spring 13
There is the first conducting strip 14, the both ends of the first groove offer the 3rd threaded passage, and the 3rd threaded passage internal thread is connected with the 3rd
Screw rod 12, in the first groove activity be plugged with the second connecting rod 16, one end that the second connecting rod 16 is located in the first groove is fixed
The second conducting strip 15 is connected with, and the second connecting rod 16 offers the first tapped through hole matched with the 3rd screw rod 12, the first spiral shell
Line through hole is threadedly coupled with the 3rd screw rod 12, two activities of the second connecting rod 16 be plugged on the 3rd connection box 21 both ends, the 3rd
Connection box 21 is rectangular frame, and the second connecting rod 16 connects one section in box 21 positioned at the 3rd and offers the second tapped through hole, the
Two tapped through hole internal threads are connected with the 4th threaded rod, and the both ends of the 3rd connection box 21 offer what is matched with the 4th threaded rod
4th threaded passage, and the 4th threaded passage is threadedly coupled with the 4th threaded rod, the second connecting rod 16 is positioned at the 3rd connection box 21
Interior one end is fixedly connected with the side of the second electromagnet 17, and the opposite side of two the second electromagnet 17 is distinguished by the 3rd spring 18
The both sides up and down of permanent magnet 19 are connected to, permanent magnet 19 is fixedly connected with the 3rd intracavity sidewall for being connected box 21;
Second connection box 6 offers the second groove close to one end of the first connection box 2, and the first connection box 2 connects close to second
The one end for connecing box 6 offers the 3rd groove, and the bottom of the second groove connects one end of iron 9 by the first spring 8, iron 9
Other end activity is plugged in the 3rd groove, and be located in the second groove one section of iron 9 offers the 3rd tapped through hole, and second is recessed
The both ends of groove offer the first threaded passage, and the first threaded passage and the 3rd tapped through hole are threadedly coupled the first screw rod
10, be located in the 3rd groove one section of iron 9 offers the 4th tapped through hole, and the both ends of the 3rd groove offer the second screw thread
Duct, and the second threaded passage is threadedly coupled the second screw rod with the 4th tapped through hole, the bottom of the 3rd groove is fixedly connected with
First electromagnet 11.
Operation principle:Staff is irrigated by filling concrete groove 7 to the space between template 1 and hole 5, is led to
Connection external power source is crossed, when needing to carry out next section of perfusion, screws out the 3rd screw rod 12 and the 4th screw rod, be powered the second electromagnet
17, so that the second electromagnet 17 attracts permanent magnet 19, so that the second connecting rod 16 departs from the first groove, so as to remove the
Three connection boxes 21, simultaneously as the disengaging of the second connecting rod 16, the second conducting strip 15 no longer contacts with the first conducting strip 14, from
And power off the first electromagnet 11, the first electromagnet 11 no longer attracts iron 9, then screws out the first screw rod 10 and the second screw rod, iron
Bar 9 departs from the 3rd groove in the presence of the first spring 8, and template 1 loses support, makes the template 1 and upper and lower ends of left and right ends
Template 1 separate, can quickly enter next section of concrete support, it is not only convenient and swift, and improve operating efficiency.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of changes, modification can be carried out to these embodiments, replace without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (4)
1. a kind of artificial digging pile concrete support device, including four templates (1) and hole (5), it is characterised in that:Four institutes
To state template (1) and join end to end and be placed in hole (5), the upper end of the template (1) offers filling concrete groove (7), wherein
The both ends of a pair of relative templates (1) have been fixedly connected with the first connection box (2), and the both ends of the relative template of another pair (1) are equal
The second connection box (6) is fixedly connected with, the two first connection boxes (2) in same template (1) pass through transverse support bar (3)
Connection, the both ends of the support bar (3) are connected to the upper surface of the first connection box (2) by the 5th screw rod (20), positioned at same
Two second in one template (1) relative one end of connection box (6) are fixedly connected with one end of head rod (4), and described the
The other end of one connecting rod (4) offers the first groove, and the bottom of first groove is connected with by second spring (13)
One conducting strip (14), the both ends of first groove offer the 3rd threaded passage, the 3rd threaded passage internal thread connection
Have the 3rd screw rod (12), in first groove activity be plugged with the second connecting rod (16), second connecting rod (16) is located at
One end in first groove is fixedly connected with the second conducting strip (15), and the second connecting rod (16) offers and the 3rd screw rod (12)
First tapped through hole of matching, first tapped through hole are threadedly coupled with the 3rd screw rod (12), two second connecting rods
(16) activity is plugged on the both ends of the 3rd connection box (21), and the second connecting rod (16) connects one section in box (21) positioned at the 3rd and opened
Provided with the second tapped through hole, the second tapped through hole internal thread is connected with the 4th threaded rod, the 3rd connection box (21)
Both ends offer the 4th threaded passage matched with the 4th threaded rod, and the 4th threaded passage connects with the 4th threaded rod screw thread
Connecing, the one end of second connecting rod (16) in the 3rd connection box (21) is fixedly connected with the side of the second electromagnet (17),
The opposite side of two second electromagnet (17) is connected to the both sides up and down of permanent magnet (19) by the 3rd spring (18),
The intracavity sidewall that the permanent magnet (19) is connected box (21) with the 3rd is fixedly connected;
The second connection box (6) offers the second groove, the first connection box (2) close to one end of the first connection box (2)
The 3rd groove is offered close to one end of the second connection box (6), the bottom of second groove connects iron by the first spring (8)
One end of bar (9), the other end activity of the iron (9) are plugged in the 3rd groove, and the iron (9) is located in the second groove
One section offer the 3rd tapped through hole, the both ends of second groove offer the first threaded passage, and the first screwed hole
Road and the 3rd tapped through hole are threadedly coupled the first screw rod (10), and be located in the 3rd groove one section of the iron (9) offers
4th tapped through hole, the both ends of the 3rd groove offer the second threaded passage, and the second threaded passage and the 4th screw thread
Through hole is threadedly coupled the second screw rod, and the bottom of the 3rd groove is fixedly connected with the first electromagnet (11).
A kind of 2. artificial digging pile concrete support device according to claim 1, it is characterised in that:The concrete fills
Note groove (7) is located at the upper center of template (1).
A kind of 3. artificial digging pile concrete support device according to claim 1, it is characterised in that:3rd connection
Box (21) is rectangular frame.
A kind of 4. artificial digging pile concrete support device according to claim 1, it is characterised in that:The concrete fills
It is in ball coronal structure to note groove (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710746758.3A CN107524140A (en) | 2017-08-27 | 2017-08-27 | A kind of artificial digging pile concrete support device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710746758.3A CN107524140A (en) | 2017-08-27 | 2017-08-27 | A kind of artificial digging pile concrete support device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107524140A true CN107524140A (en) | 2017-12-29 |
Family
ID=60682696
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710746758.3A Pending CN107524140A (en) | 2017-08-27 | 2017-08-27 | A kind of artificial digging pile concrete support device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107524140A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112435568A (en) * | 2020-12-04 | 2021-03-02 | 天津商业大学 | Simulation device for artificial intelligence teaching |
CN113882401A (en) * | 2021-09-13 | 2022-01-04 | 中铁大桥勘测设计院集团有限公司武汉分公司 | Construction system applied to slide-resistant pile retaining wall structure |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08326468A (en) * | 1995-06-02 | 1996-12-10 | Chubu Electric Power Co Inc | Temporary earth retaining concrete form device |
CN205732030U (en) * | 2016-05-24 | 2016-11-30 | 南安上远玻璃有限公司 | A kind of glass cleaning cleans device with efficient fine motion |
CN207143932U (en) * | 2017-08-27 | 2018-03-27 | 贵州新联爆破工程集团有限公司 | A kind of artificial digging pile concrete support device |
-
2017
- 2017-08-27 CN CN201710746758.3A patent/CN107524140A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08326468A (en) * | 1995-06-02 | 1996-12-10 | Chubu Electric Power Co Inc | Temporary earth retaining concrete form device |
CN205732030U (en) * | 2016-05-24 | 2016-11-30 | 南安上远玻璃有限公司 | A kind of glass cleaning cleans device with efficient fine motion |
CN207143932U (en) * | 2017-08-27 | 2018-03-27 | 贵州新联爆破工程集团有限公司 | A kind of artificial digging pile concrete support device |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112435568A (en) * | 2020-12-04 | 2021-03-02 | 天津商业大学 | Simulation device for artificial intelligence teaching |
CN113882401A (en) * | 2021-09-13 | 2022-01-04 | 中铁大桥勘测设计院集团有限公司武汉分公司 | Construction system applied to slide-resistant pile retaining wall structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107524140A (en) | A kind of artificial digging pile concrete support device | |
CN207143932U (en) | A kind of artificial digging pile concrete support device | |
CN207218161U (en) | A kind of cable bridge | |
CN204517238U (en) | A kind of insulated isolated device | |
CN106946141A (en) | A kind of sucked type plays hanging box paw | |
CN207196008U (en) | A kind of construction positioner | |
CN206792043U (en) | A kind of adjustable student's drawing table | |
CN205669322U (en) | A kind of building-supporting device | |
CN202324212U (en) | Device for arranging equipment pipe-trenches by using structural joints | |
CN212076147U (en) | Non-excavation drilling rod screw thread surface nitrogenize hoist device | |
CN208945219U (en) | Drilling tool and hole-drilling system for the drilling of rail washer | |
CN205629956U (en) | Electric power communication staple bolt processing equipment of acting as go -between | |
CN207672582U (en) | A kind of slope protection structure | |
CN206488978U (en) | A kind of rock-like materials cuboid sample sample preparation stage apparatus | |
CN207502797U (en) | A kind of tool for gluing pedestal | |
CN206859830U (en) | A kind of portable municipal guardrail | |
CN206832854U (en) | Insulating bar hanger bracket | |
CN206831270U (en) | A kind of seamless spliced wall lamp | |
CN204753642U (en) | Municipal administration is with combination formula inspection shaft | |
CN205348931U (en) | Novel steel pylons base | |
CN206237048U (en) | A kind of easy to operate elevator for lead of power overhauling tower | |
CN207026220U (en) | A kind of punch press panel for being easy to open | |
CN204876756U (en) | But reuse's power transmission line iron tower | |
CN203231053U (en) | Supporting plate special for tractor rack | |
CN206941876U (en) | A kind of hoisting prefabricated wall of ACC building blocks assembling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171229 |