CN206237048U - A kind of easy to operate elevator for lead of power overhauling tower - Google Patents

A kind of easy to operate elevator for lead of power overhauling tower Download PDF

Info

Publication number
CN206237048U
CN206237048U CN201621264565.1U CN201621264565U CN206237048U CN 206237048 U CN206237048 U CN 206237048U CN 201621264565 U CN201621264565 U CN 201621264565U CN 206237048 U CN206237048 U CN 206237048U
Authority
CN
China
Prior art keywords
horizontal stretcher
arm
column
cross
lead
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621264565.1U
Other languages
Chinese (zh)
Inventor
丁红文
董亮
刘跃荣
赵彦文
胡玉军
全龙翔
郭娟
徐新宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Tianchuang Sinuo Mdt Infotech Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Original Assignee
Xinjiang Tianchuang Sinuo Mdt Infotech Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Tianchuang Sinuo Mdt Infotech Ltd, State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Xinjiang Electric Power Co Ltd filed Critical Xinjiang Tianchuang Sinuo Mdt Infotech Ltd
Priority to CN201621264565.1U priority Critical patent/CN206237048U/en
Application granted granted Critical
Publication of CN206237048U publication Critical patent/CN206237048U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a kind of easy to operate elevator for lead of power overhauling tower,Including by cross-arm,The cross-arm is made up of left horizontal stretcher and right horizontal stretcher,The left side of the left horizontal stretcher is fixedly connected with the top of left column,The right side of the right horizontal stretcher is fixedly connected with right column top,The right flank of the left horizontal stretcher connects the left surface of right horizontal stretcher by wire lifting device,The both sides of the wire lifting device are equipped with three grooves side by side,Three pairs of grooves of the wire lifting device are connected by three drum pin movable buckles,The cross-arm lower section is provided with interim crossbeam,The left end of the interim crossbeam is fixedly connected with left column,The right-hand member and right column of the interim crossbeam are flexibly connected by screw rod,The elevator for lead of power overhauling tower,Simple structure,Than traditional electric power first-aid tower convenient transportation,Simplify lifting wire operating process,Do not take considerable time on fixed door pillar.

Description

A kind of easy to operate elevator for lead of power overhauling tower
Technical field
The utility model is related to technical field of power rush-repair, specially a kind of easy to operate electric power first-aid tower lifting wire dress Put.
Background technology
Power grid accident seriously threatens the safe operation of power network caused by major natural disasters.Electric power accident is the calamity of industry Difficulty, pole collapse accident is even more the disaster of electric power accident, and tower not only causes the equipment heavy losses, power failure also to make electric power system stability Point operation is on the hazard, and extensive damage is caused to electric power netting safe running and user security electricity consumption.The North Guangdong ice damage of 2008 is exactly The typical case of the large area accident of falling tower.Power department is after it there is pole collapse accident in power system, it is necessary to be entered with most fast speed Rob and repair, restore electricity and normal system operation mode.
Three transmission pressures tend not to break after the accident of falling tower occurs, and are needed three lifting wires when circuit is rushed to repair It is installed on emergent repairing tower.Traditional emergent repairing tower does not have wire lifting device, it is necessary to fix door pillar by increasing zip, then goes Lifting wire, the method can be expended into many times for rushing to repair work after falling cross-arm, the time that delay restores electricity.
Utility model content
The purpose of this utility model is to provide a kind of easy to operate elevator for lead of power overhauling tower, to solve The problem proposed in above-mentioned background technology.
To achieve the above object, the utility model provides following technical scheme:A kind of easy to operate electric power first-aid tower wire Lifting device, including cross-arm, the cross-arm are made up of left horizontal stretcher and right horizontal stretcher, the left side of the left horizontal stretcher and the top of left column It is fixedly connected, the right side of the right horizontal stretcher is fixedly connected with right column top, the right flank of the left horizontal stretcher passes through lifting wire Device connects the left surface of right horizontal stretcher, and the left and right sides of the wire lifting device is all three grooves side by side, and the wire is carried Three pairs of grooves for rising device are connected by three drum pin movable buckles, and the cross-arm lower section is provided with interim crossbeam, described interim The left end of crossbeam is fixedly connected with left column, and the right-hand member and right column of the interim crossbeam are flexibly connected by screw rod.
Preferably, the screw rod is provided with the swing handle of adjusting screw rod.
Preferably, the notch of three pairs of grooves is all parallel to each other opposition.
Preferably, the cross-arm is strengthened fixing with left column and right column by zip.
Compared with prior art, the beneficial effects of the utility model are:The elevator for lead of power overhauling tower, structure letter It is single, than traditional electric power first-aid tower convenient transportation, simplify lifting wire operating process, without taking considerable time in fixed door pillar On.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model A schematic enlarged-scale views;
Fig. 3 is the utility model B structure enlarged drawing.
In figure:1 zip, 2 left columns, 3 right columns, 4 cross-arms, 41 left horizontal stretchers, 42 right horizontal stretchers, 5 wire lifting devices, 6 are faced When crossbeam, 8 screw rods, 9 swing handles.
Specific embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment for being obtained, belongs to the scope of the utility model protection.
Fig. 1-3 are referred to, the utility model provides a kind of technical scheme:A kind of easy to operate electric power first-aid tower lifting wire Device, including by cross-arm 4, the cross-arm 4 is made up of left horizontal stretcher 41 and right horizontal stretcher 42, the left side of the left horizontal stretcher 41 and left column 2 top is fixedly connected, and the right side of the right horizontal stretcher 42 is fixedly connected with the top of right column 3, and cross-arm 4 is vertical with left column 2 and the right side Post 3 is strengthened fixing by zip 1, and the right flank of the left horizontal stretcher 41 connects a left side for right horizontal stretcher 42 by wire lifting device 5 Side, the left and right sides of the wire lifting device 5 is all three grooves 51 side by side, and the notch of three pairs of grooves 51 is all mutual Parallel opposition, three pairs of grooves 51 of the wire lifting device are connected by three movable buckles of drum pin 52, because cross-arm 4 can To be easily split as very much two halves, thus in the transportation of the emergent repairing tower also can easy access tower put, under the cross-arm 4 Side is provided with interim crossbeam 6, and the left end of the interim crossbeam 6 is fixedly connected with left column 2, the right-hand member of the interim crossbeam 6 and the right side Column 3 is flexibly connected by screw rod 8, and the screw rod 8 is provided with the swing handle 9 of adjusting screw rod, the left end of interim crossbeam 6 with Between right column 3 screw thread of two screwed holes be it is reverse, so by adjust swing handle 9 can just adjust left column 2 with The distance between right column 3.
Operation principle:Repairing electricity tower is set up in the top of electrified wire, when below lifting wire to cross-arm 4, is installed additional Interim crossbeam 6, rotates the swing handle 9 between interim crossbeam 6 and column to finely tune the distance between left column 2 and right column 3, Stop regulation when between groove 51 and drum pin 52 without lateral pull and rotate handle 9, now take out three successively from top to bottom Drum pin 52, now because the top of cross-arm 4 has zip 1 to fix and lower section has interim crossbeam 6 so left horizontal stretcher 41 and the meeting of right horizontal stretcher 42 Keep relative stability, allow wire from the gap between three pairs of grooves 51 by cross-arm 4, treat wire after again by drum pin 52 Put back to successively inside groove 51, now just complete the lifting process of wire.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out various changes in the case where principle of the present utility model and spirit is not departed from, repaiies Change, replace and modification, scope of the present utility model is defined by the appended claims and the equivalents thereof.

Claims (4)

1. a kind of easy to operate elevator for lead of power overhauling tower, including cross-arm (4), the cross-arm (4) is by left horizontal stretcher (41) Constituted with right horizontal stretcher (42), it is characterised in that:The left side of the left horizontal stretcher (41) is fixedly connected with the top of left column (2), institute The right side for stating right horizontal stretcher (42) is fixedly connected with right column (3) top, and the right flank of the left horizontal stretcher (41) passes through lifting wire The left surface of device (5) connection right horizontal stretcher (42), the both sides of the wire lifting device (5) are equipped with three grooves side by side (51), three pairs of grooves (51) of the wire lifting device (5) are connected by three drum pin (52) movable buckles, the cross-arm (4) interim crossbeam (6) is provided with below, the left end of the interim crossbeam (6) is fixedly connected with left column (2), the interim horizontal stroke The right-hand member and right column (3) of beam (6) are flexibly connected by screw rod (8).
2. a kind of easy to operate elevator for lead of power overhauling tower according to claim 1, the screw rod (8) is provided with The swing handle (9) of adjusting screw rod.
3. a kind of easy to operate elevator for lead of power overhauling tower according to claim 1, three pairs of grooves (51) Notch be all parallel to each other opposition.
4. a kind of easy to operate elevator for lead of power overhauling tower according to claim 1, the cross-arm (4) is stood with a left side Post (2), right column (3) are strengthened fixing by zip (1).
CN201621264565.1U 2016-11-24 2016-11-24 A kind of easy to operate elevator for lead of power overhauling tower Active CN206237048U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621264565.1U CN206237048U (en) 2016-11-24 2016-11-24 A kind of easy to operate elevator for lead of power overhauling tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621264565.1U CN206237048U (en) 2016-11-24 2016-11-24 A kind of easy to operate elevator for lead of power overhauling tower

Publications (1)

Publication Number Publication Date
CN206237048U true CN206237048U (en) 2017-06-09

Family

ID=58980799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621264565.1U Active CN206237048U (en) 2016-11-24 2016-11-24 A kind of easy to operate elevator for lead of power overhauling tower

Country Status (1)

Country Link
CN (1) CN206237048U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111017792A (en) * 2019-11-29 2020-04-17 国网山东省电力公司临沂供电公司 Wire lifting device of power first-aid repair tower and use method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111017792A (en) * 2019-11-29 2020-04-17 国网山东省电力公司临沂供电公司 Wire lifting device of power first-aid repair tower and use method thereof
CN111017792B (en) * 2019-11-29 2020-12-29 国网山东省电力公司临沂供电公司 Wire lifting device of power first-aid repair tower and use method thereof

Similar Documents

Publication Publication Date Title
CN206467994U (en) A kind of novel hanging basket support
CN206237048U (en) A kind of easy to operate elevator for lead of power overhauling tower
CN210517683U (en) Municipal works interlude cable special stand
CN204190262U (en) A kind of top line device of angle pole replacing insulator
CN206806164U (en) 10kv outdoor transformers install suspension rod
CN205135076U (en) Change of current of extra -high voltage current conversion station becomes inlet wire rectangle lattice formula " pi " type framework
CN205025154U (en) 330kVGIS distribution device place rigid connection sail formula framework
CN108879475B (en) Special tool for checking double split conductor wiring of power transmission line
CN207782285U (en) A kind of elevator for lead of power overhauling tower
CN203839836U (en) Obstacle-crossing single-line overhead carriage used for overhead power transmission line maintenance
CN206323068U (en) A kind of 10kV needle porcelain bottles wire fixing device
CN212862487U (en) Split mounting type transportation frame for wind power base
CN103956687A (en) Obstacle-crossing single cable fly cart for overhaul of overhead transmission line
CN210577381U (en) Pulley for power construction cable
CN203685006U (en) Insulated rope ladder for overhead power transmission lines
CN211114931U (en) Anti-falling net for power transmission construction
CN208257263U (en) A kind of elevator for lead of power overhauling tower
CN208939455U (en) A kind of drainage plate fever processing specific purpose tool
CN204703578U (en) Bar stepped on by gate framework type cable
CN206619824U (en) A kind of architectural electricity power distribution cabinet
CN205283055U (en) 110kV overhead line
CN218070561U (en) Corner frame structure for transformer substation
CN204928040U (en) Type type weight piece
CN212773763U (en) High-low voltage distribution cabinet safety protective guard
CN205081357U (en) Be applicable to indoor GIS electric substation engineering roof framework of being qualified for next round of competitions

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant