CN107514141B - A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam - Google Patents

A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam Download PDF

Info

Publication number
CN107514141B
CN107514141B CN201610424075.1A CN201610424075A CN107514141B CN 107514141 B CN107514141 B CN 107514141B CN 201610424075 A CN201610424075 A CN 201610424075A CN 107514141 B CN107514141 B CN 107514141B
Authority
CN
China
Prior art keywords
sealing
concrete
plate
prefabricated
aluminum alloy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610424075.1A
Other languages
Chinese (zh)
Other versions
CN107514141A (en
Inventor
张立城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201610424075.1A priority Critical patent/CN107514141B/en
Publication of CN107514141A publication Critical patent/CN107514141A/en
Application granted granted Critical
Publication of CN107514141B publication Critical patent/CN107514141B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of prefabricated prefabricating technique construction technologies of superimposed sheet sealing reversed beam, including aluminum alloy mould plate, sealing beam arrangement of reinforcement, pouring concrete plate and precast concrete afterwards, pouring concrete board bottom portion is equipped with precast concrete after described, the aluminum alloy mould plate and the sealing beam arrangement of reinforcement are set in the middle part of the rear pouring concrete plate, the aluminum alloy mould plate is set on the outside of the sealing beam arrangement of reinforcement, it solves in traditional structure it cannot be guaranteed that the requirement of construction quality, to guarantee that one-time-concreting and the secondary contact surface that pours clean and carry out dabbing in conventional construction method, and vibration compacting, and the human-subject test and constructing operation level of actually construction personnel are difficult to control, therefore, it proposes to be particularly important prefabricated prefabricating technique construction method of superimposed sheet sealing reversed beam at this stage, pass through the preferred of the improvement of construction method and material, Constructing operation can be made easier, more easily guarantee construction quality, to reach the phenomenon that avoiding the occurrence of leakage generation.

Description

A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam
Technical field
The invention belongs to the prefabricating technique constructions of technical field of buildings more particularly to a kind of prefabricated superimposed sheet sealing reversed beam Technique.
Background technique
Prefabricated concrete structure construction technology is on a large scale in China's housing industrialization process of construction, wherein dress It is made of being closed as prefabricated board and cast-in-situ steel reinforced concrete stacking with superimposed sheet in formula concrete structure, lower layer is with reinforcing bar Prefabricated superimposed sheet, upper layer are the cast-in-place concrete structure of after-pouring, two layers of common stress.In prefabricated concrete structure construction In the reversed beam work progress of part, secondary pouring construction leads to the problem of conjunction old and new concret, leads to the work that cannot play sealing beam With, and because the secondary own material properties that pour lead to the phenomenon that seeping water, it is proposed that a kind of prefabricated superimposed sheet sealing reversed beam one Secondary prefabricating technique construction technology.
Summary of the invention
It is an object of the invention to propose a kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam, it is intended to solve It certainly cannot be guaranteed the requirement of construction quality in traditional structure, to guarantee that one-time-concreting is contacted with secondary pour in conventional construction method Dabbing, and vibration compacting are cleaned and carried out in face, and the human-subject test of actually construction personnel and constructing operation level are difficult to control System, therefore, proposes to be particularly important prefabricated prefabricating technique construction method of superimposed sheet sealing reversed beam at this stage, by applying The improvement of work method and material it is preferred, constructing operation can be made easier, more easily guarantee construction quality, avoided out to reach The phenomenon that now leaking.
In order to solve the above-mentioned technical problems, the present invention provides the following technical solutions:
A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam of the present invention, including aluminum alloy mould plate, sealing Beam steel, rear pouring concrete plate and precast concrete, which is characterized in that pouring concrete board bottom portion is equipped with prefabricated mixed after described Solidifying soil component, the aluminum alloy mould plate and the sealing beam steel are set in the middle part of the rear pouring concrete plate, the aluminium alloy mould Plate is set on the outside of the sealing beam steel, method includes the following steps:
Step 1, sealing beam steel is prefabricated, increases reserved sealing beam steel, sealing depth of beam in prefabricated board prefabrication process For 20cm, top controls 2cm concrete cover;
Step 2, sealing beam forms hangs mould, and Screw arbor with nut at both-ends length is 35cm, guarantees that enough length plays the role of to drawing, right Screw rod is drawn to be welded and fixed with sealing beam steel;
Step 3, template uses aluminium alloy mould, and feature forming demoulds lossless to concrete formation without swollen mould phenomenon Evil;
Step 4, first pour rear pouring concrete plate pan section, then to plate face initial set before, pour sealing beam concrete, only Water beam concrete prepares expansive concrete, intensity C25, limited expansion rate using swelling agent " 0.015, swelling agent dosage exists 30KG/m3, no more than 0.5, the slump is controlled in 12-14cm water-cement ratio;
Step 5, it is vibrated using ZV25 vibrating head, mould is hung due to sealing beam forms, so the experienced hand that vibrates is selected, Beam bottom and plate face are vibrated in place, seamless interfacing, do not allow template of vibrating for a long time, and fast insert is pulled out slowly;
Step 6, remove Screw arbor with nut at both-ends screw thread, under fall aluminum alloy mould plate, after pouring 24 hours, carry out demoulding, and water support Shield.
The beneficial effects obtained by the present invention are as follows being: the present invention solves the requirement that cannot be guaranteed construction quality in traditional structure, To guarantee that one-time-concreting and the secondary contact surface that pours clean and carry out dabbing, and vibration compacting in conventional construction method, and it is real The human-subject test of construction personnel and constructing operation level are difficult to control on border, therefore, are proposed at this stage to prefabricated superimposed sheet sealing Prefabricating technique construction method of reversed beam is particularly important, and by the preferred of the improvement of construction method and material, can make to construct The operation is more convenient, mores easily guarantee construction quality, to reach the phenomenon that avoiding the occurrence of leakage generation.
Detailed description of the invention
Attached drawing is used to provide further understanding of the present invention, and constitutes part of specification, with reality of the invention It applies example to be used to explain the present invention together, not be construed as limiting the invention.In the accompanying drawings:
Fig. 1 is a kind of structural schematic diagram of prefabricating technique construction technology of prefabricated superimposed sheet sealing reversed beam of the invention;
Fig. 2 is a kind of flowage structure signal of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam of the present invention Figure;
In figure: 1, aluminum alloy mould plate;2, sealing beam steel;3, rear pouring concrete plate;4, precast concrete.
Specific embodiment
Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings, it should be understood that preferred reality described herein Apply example only for the purpose of illustrating and explaining the present invention and is not intended to limit the present invention.
As shown in Figs. 1-2, the present invention provides a kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam, including Aluminum alloy mould plate 1, sealing beam steel 2, rear pouring concrete plate 3 and precast concrete 4, rear 3 bottom of pouring concrete plate Equipped with precast concrete 4, the aluminum alloy mould plate 1 and the sealing beam steel 2 are set in the rear pouring concrete plate 3 Portion, the aluminum alloy mould plate 1 are set to 2 outside of sealing beam steel, method includes the following steps:
Step 1, sealing beam steel is prefabricated, increases reserved sealing beam steel, sealing depth of beam in prefabricated board prefabrication process For 20cm, top controls 2cm concrete cover;
Step 2, sealing beam forms hangs mould, and Screw arbor with nut at both-ends length is 35cm, guarantees that enough length plays the role of to drawing, right Screw rod is drawn to be welded and fixed with sealing beam steel;
Step 3, template uses aluminium alloy mould, and feature forming demoulds lossless to concrete formation without swollen mould phenomenon Evil;
Step 4, first pour rear pouring concrete plate pan section, then to plate face initial set before, pour sealing beam concrete, only Water beam concrete prepares expansive concrete, intensity C25, limited expansion rate using swelling agent " 0.015, swelling agent dosage exists 30KG/m3, no more than 0.5, the slump is controlled in 12-14cm water-cement ratio;
Step 5, it is vibrated using ZV25 vibrating head, mould is hung due to sealing beam forms, so the experienced hand that vibrates is selected, Beam bottom and plate face are vibrated in place, seamless interfacing, do not allow template of vibrating for a long time, and fast insert is pulled out slowly;
Step 6, remove Screw arbor with nut at both-ends screw thread, under fall aluminum alloy mould plate 1, after pouring 24 hours, carry out demoulding, and water support Shield.
The present invention solves the requirement that cannot be guaranteed construction quality in traditional structure, to guarantee once to pour in conventional construction method It builds and cleans and carry out dabbing, and vibration compacting with the secondary contact surface that pours, and the human-subject test of actually construction personnel and apply Work operation level is difficult to control, and therefore, is proposed at this stage to prefabricating technique construction party Faxian of prefabricated superimposed sheet sealing reversed beam It is particularly important, by the preferred of the improvement of construction method and material, constructing operation can be made easier, more easily guarantee construction matter Amount, to reach the phenomenon that avoiding the occurrence of leakage generation.
Finally, it should be noted that these are only the preferred embodiment of the present invention, it is not intended to restrict the invention, although Present invention has been described in detail with reference to the aforementioned embodiments, for those skilled in the art, still can be right Technical solution documented by foregoing embodiments is modified or equivalent replacement of some of the technical features.It is all Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on should be included in protection of the invention Within the scope of.

Claims (1)

1. a kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam, including aluminum alloy mould plate (1), sealing beam steel (2), rear pouring concrete plate (3) and precast concrete (4), which is characterized in that pouring concrete plate (3) bottom is equipped with after described Precast concrete (4), the aluminum alloy mould plate (1) and the sealing beam steel (2) are set to the rear pouring concrete plate (3) Middle part, the aluminum alloy mould plate (1) are set on the outside of the sealing beam steel (2), method includes the following steps:
Step 1, sealing beam steel is prefabricated, increases reserved sealing beam steel in prefabricated board prefabrication process, and sealing depth of beam is 20cm, top control 2cm concrete cover;
Step 2, sealing beam forms hangs mould, and Screw arbor with nut at both-ends length is 35cm, guarantees that enough length plays the role of to drawing, to drawing spiral shell Bar is welded and fixed with sealing beam steel;
Step 3, template uses aluminium alloy mould, and feature forming demoulds harmless to concrete formation without swollen mould phenomenon;
Step 4, first pour rear pouring concrete plate pan section, then to plate face initial set before, pour sealing beam concrete, sealing beam Concrete prepares expansive concrete, intensity C25, limited expansion rate using swelling agent " 0.015, swelling agent dosage is in 30KG/ m3, no more than 0.5, the slump is controlled in 12-14cm water-cement ratio;
Step 5, it is vibrated using ZV25 vibrating head, since sealing beam forms is to hang mould, so selecting the experienced hand that vibrates, beam bottom It vibrates in place with plate face, seamless interfacing does not allow template of vibrating for a long time, and fast insert is pulled out slowly;
Step 6, remove Screw arbor with nut at both-ends screw thread, under fall aluminum alloy mould plate (1), after pouring 24 hours, carry out demoulding, and water support Shield.
CN201610424075.1A 2016-06-16 2016-06-16 A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam Active CN107514141B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610424075.1A CN107514141B (en) 2016-06-16 2016-06-16 A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610424075.1A CN107514141B (en) 2016-06-16 2016-06-16 A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam

Publications (2)

Publication Number Publication Date
CN107514141A CN107514141A (en) 2017-12-26
CN107514141B true CN107514141B (en) 2019-06-21

Family

ID=60720866

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610424075.1A Active CN107514141B (en) 2016-06-16 2016-06-16 A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam

Country Status (1)

Country Link
CN (1) CN107514141B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109025268A (en) * 2018-08-17 2018-12-18 重庆中科建设(集团)有限公司 Kitchen and toilet concrete flanging construction method
CN109723186B (en) * 2019-01-05 2020-11-24 中国十七冶集团有限公司 Prefabricated part of water-stop back beam and construction method of water-stop back beam
CN112324014A (en) * 2020-09-23 2021-02-05 上海美家美沪装饰科技有限公司 Concrete reinforced ground beam and construction process
CN113914476B (en) * 2021-10-19 2022-10-04 广东宏茂建设管理有限公司 Construction method of long-size overhanging floating plate

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203113782U (en) * 2013-02-06 2013-08-07 山河建设集团有限公司 Reversed beam erecting formwork stationary fixture
CN104652815A (en) * 2015-02-10 2015-05-27 中国十七冶集团有限公司 Construction method for pouring water-stopping upstanding beams in kitchens and toilets
CN104712088A (en) * 2015-01-28 2015-06-17 中国十七冶集团有限公司 Construction method for post-poured concrete of prefabricated composite floor slabs
CN104763150A (en) * 2015-04-01 2015-07-08 四川华西绿舍建材有限公司 Construction method of assembled type prefabricated laminated slab for building
CN204552096U (en) * 2015-02-10 2015-08-12 中国十七冶集团有限公司 A kind of sealing reversed beam template is fixedly connected with positioner
CN205063052U (en) * 2015-10-12 2016-03-02 上海申远建筑装饰工程有限公司 Newly build a wall to personally experience sth. part of body and end water bar structure in bathroom

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203113782U (en) * 2013-02-06 2013-08-07 山河建设集团有限公司 Reversed beam erecting formwork stationary fixture
CN104712088A (en) * 2015-01-28 2015-06-17 中国十七冶集团有限公司 Construction method for post-poured concrete of prefabricated composite floor slabs
CN104652815A (en) * 2015-02-10 2015-05-27 中国十七冶集团有限公司 Construction method for pouring water-stopping upstanding beams in kitchens and toilets
CN204552096U (en) * 2015-02-10 2015-08-12 中国十七冶集团有限公司 A kind of sealing reversed beam template is fixedly connected with positioner
CN104763150A (en) * 2015-04-01 2015-07-08 四川华西绿舍建材有限公司 Construction method of assembled type prefabricated laminated slab for building
CN205063052U (en) * 2015-10-12 2016-03-02 上海申远建筑装饰工程有限公司 Newly build a wall to personally experience sth. part of body and end water bar structure in bathroom

Also Published As

Publication number Publication date
CN107514141A (en) 2017-12-26

Similar Documents

Publication Publication Date Title
CN107514141B (en) A kind of prefabricated prefabricating technique construction technology of superimposed sheet sealing reversed beam
CN100469995C (en) Construction method for after-pouring band beam-slab template
CN208167956U (en) A kind of basement inwall using reverse construction
CN101845889A (en) Concrete casting and tamping method of steel tube concrete structure column
CN104264676A (en) Construction method of mass concrete of high-rise building foundations
CN110331781A (en) A kind of building construction method that integration pours
CN109854051A (en) A kind of large-sized concrete earthing tank segmentation casting method
CN104631677A (en) Construction technology for hollow super-thick concrete terrace
CN110039635A (en) PC component production technology
CN110000892A (en) A kind of production technology of prefabricated component stair
CN218508722U (en) Shock insulation buttress positioning pouring structure
CN102116092A (en) Method for constructing reinforcing band for compensating contraction of concrete and preventing cracks
CN105064500B (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN109208816A (en) A kind of external wall is cast-in-place with prefabricated thermal insulation integral system
CN108582426A (en) A kind of producing device and production method of stiffened column
CN111516096A (en) Precast column concrete pouring method in fabricated building
CN207959643U (en) Plate laminated floor slab drops in electromechanical integration laminated floor slab, toilet
CN105908883A (en) Construction method for preventing upward floating of composite floor system lightweight core formwork
CN109057343A (en) A kind of building concrete pouring procedure
CN106760487B (en) A kind of cast-in-place concrete exterior wall crack resistence Slate hanging construction method
CN210562268U (en) Portable grouting groove structure in fan anchor bolt foundation secondary grouting
CN208163928U (en) A kind of producing device of stiffened column
CN105525751B (en) A kind of connection sleeve pipe component and the method using component construction blow-off line
CN106368128A (en) Construction method of complete sand bottom form of molding flasks combination for supporting hanging side of 10,000 tons turning arc bridge abutment
CN205421718U (en) Semi -prefabricated circular steel tube regeneration mixes concrete column

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant