CN107513996A - A kind of anchorage and its construction method of recoverable prestressed anchor cable - Google Patents

A kind of anchorage and its construction method of recoverable prestressed anchor cable Download PDF

Info

Publication number
CN107513996A
CN107513996A CN201710983624.3A CN201710983624A CN107513996A CN 107513996 A CN107513996 A CN 107513996A CN 201710983624 A CN201710983624 A CN 201710983624A CN 107513996 A CN107513996 A CN 107513996A
Authority
CN
China
Prior art keywords
anchor
steel strand
strand wires
bearing plate
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710983624.3A
Other languages
Chinese (zh)
Inventor
李家红
胡宝山
赖欣
张敏杰
刘喜林
马乐平
刘长伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhiping Foundation Engineering Co Ltd
Original Assignee
Shanghai Zhiping Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhiping Foundation Engineering Co Ltd filed Critical Shanghai Zhiping Foundation Engineering Co Ltd
Priority to CN201710983624.3A priority Critical patent/CN107513996A/en
Publication of CN107513996A publication Critical patent/CN107513996A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • E02D5/765Anchorings for bulkheads or sections thereof in as much as specially adapted therefor removable

Abstract

The invention discloses a kind of anchor set and its construction method of recoverable prestressed anchor cable, it is characterized in that the anchorage forms multistage adjustable detachable prestress anchorage cable by double end anchor and at least one or more than one single head anchor, the double end anchor is made up of two anchor heads and its steel strand wires connected respectively with one-level bearing plate and two level bearing plate;The anchor head by base, connection sleeve pipe, move back anchor mandrel, anchor cable intermediate plate, spring and tap web sleeve and form;During the steel strand tension, steel strand wires are engaged and locked by anchor cable intermediate plate;Steel strand wires need to be only pushed into anchor hole bottom, steel strand wires are departed from into unblock realizes recycling during unblock;Its construction method includes excavating the steps such as pore-forming, anchor cable installation, slip casting maintenance, tensioning fixation and recovery steel strand wires.The present invention has simple in construction compared with prior art, and anchor force is big, and the recovery utilization rates of steel strand wires is high, make, installation it is all very convenient, further reduce engineering cost.

Description

A kind of anchorage and its construction method of recoverable prestressed anchor cable
Technical field
The present invention relates to the prestress anchorage cable technical field of pattern foundation pit supporting structure, especially a kind of anchor of recoverable prestressed anchor cable Tool and its construction method.
Background technology
At present, Recyclable anchor rope mainly has mechanical Recyclable anchor rope, hot melten type Recyclable anchor rope, the recyclable anchor of mechanics formula The types such as rope, wherein particularity of the mechanical Recyclable anchor rope due to anchor head assembly, causes waste of material in use(Such as n+1 Type), wire rod steel strand wires in the case where subduing loading are easily damaged;Heat molten type Recyclable anchor rope Inner bolt head installation accuracy requires very tight Lattice, hot melt system is easily damaged, influences the rate of recovery, and constructing operation requires very high.
The Recyclable anchor rope species of prior art is more, but anchor force deficiency, the rate of recovery are low, fragile after wire rod stress, Cause the wasting of resources, it is impossible to well adapt to underground space energy-conserving and environment-protective, the idea of development of green construction.
The content of the invention
The purpose of the present invention be in view of the shortcomings of the prior art and provide a kind of recoverable prestressed anchor cable anchorage and Its construction method, using the anchor head assembly of self-locking structure, effectively solve the waste of anchor cable steel strand wires material excess, wire rod stress The fragile afterwards, adverse effect such as anchor force is insufficient, the rate of recovery is low, is resources conservation, green construction provides a kind of recyclable anchor Rope Inner bolt head device, simple in construction, making, installation are all very convenient, anchor cable cost economic, steel strand wires recoverable, subtract significantly Low engineering cost, work and material use efficiency high.
The object of the present invention is achieved like this:A kind of anchorage of recoverable prestressed anchor cable, be characterized in the anchorage by Double end anchor and the multistage adjustable detachable prestress anchorage cable of at least one or more than one single head anchor composition, The double end anchor is made up of two anchor heads and its steel strand wires connected respectively with one-level bearing plate and two level bearing plate;It is described Two anchor heads are symmetricly set on one-level bearing plate side and by guiding cap sealings;The two level bearing plate is by being sleeved on steel strand wires Front support tube is set with a bearing plate for spacing;The single head anchor by another anchor head and its steel strand wires of connection with it is another Level bearing plate and two level bearing plate composition;Another grade of bearing plate is by the another front support tube being sleeved on steel strand wires and another two level Bearing plate is set for spacing;The single head anchor is by the middle stay tube that is sleeved on steel strand wires and double end anchor or single head Anchor is set for spacing;The anchor head by connection sleeve pipe, move back anchor mandrel, base, anchor cable intermediate plate, jump ring, spring and tap web Sleeve forms;The anchor mandrel front end of moving back is the nose cone provided with neck, and its rear end is the jack provided with flange;The anchor cable folder Piece is the bayonet socket gear wheel of three taper crescent moon intermediate plate compositions, and its port is provided with caulking groove and seal groove;The spring is with moving back anchor core Axle sleeve is in connection sleeve pipe;Described connection sleeve pipe one end is connected with the whorl of base provided with chamber, the other end and suit anchor cable The tap web bush whorl connection of intermediate plate, anchor cable intermediate plate are sleeved on by caulking groove on the flange of Tui Mao core back-ends, and close by being arranged on " O " type sealing ring on sealing groove is fixed;The jump ring is disposed at the chamber of base by the groove of connection sleeve pipe port On;The one-level bearing plate and two level bearing plate are the porous plate for circumferentially setting several slip castings or twisted wire hole;The steel strand wires Revealed section is provided with anchor plate, and the seat stay by being sleeved on steel strand wires is set with single head anchor for spacing;The anchor Backing plate is provided with the outer anchorage of conical pipe;The conical pipe is set with slip casting or twisted wire hole to correspond;The steel strand wires by Conical pipe on outer anchorage respectively enters the anchor cable intermediate plate of double end anchor and several single head anchors by anchor plate Interior, when steel strand tension stress, anchor cable intermediate plate is interference fit with tap web sleeve, and steel strand wires are engaged and locked;Pushed away during unblock Dynamic steel strand wires revealed section, make to move back anchor mandrel front end into the chamber of base, and neck is pinned by jump ring, spring-compressed makes to move back anchor core The anchor cable intermediate plate of shaft rear end coordinates with conical sleeve for gap, discharges the snap-lock to steel strand wires, realizes the recovery of steel strand wires Utilize.
The aperture in the slip casting or twisted wire hole is less than tap web sleeve diameter, and is more than steel strand wires diameter;Outside the steel strand wires Provided with corrugated protective conduits and PE protection pipes.
A kind of construction method of recoverable prestressed Anchor Cable Anchorage, be characterized in this method include excavation of foundation pit and pore-forming, Anchor cable installation, slip casting maintenance, tensioning fixation and recovery steel strand wires, Specific construction are carried out in the steps below:
A, excavation of foundation pit and pore-forming
Pit earthwork is excavated to anchor cable construction operating surface, is crept into using rig in the soil body into anchor hole, the aperture of anchor hole for 0.13 ~ 0.30m, bore angle deviation ≯ 1 °, the discrepancy in elevation ≯ 50mm, hole depth are more than 0.3 ~ 0.5m of design length of anchor cable.
B, anchor cable is installed
The length of each stay tube is determined according to design requirement, to ensure that single head anchor fills with double end anchor and single head anchoring The spacing put is set, the projected depth position multistage adjustable detachable prestress anchorage cable assembled being placed in anchor hole, About 500mm is drawn outside when double end anchor is put into anchor hole bottom, it is ensured that guiding cap has certain space with anchor hole bottom.
C, slip casting conserves
Grouting Pipe passes sequentially through anchor plate by outer anchorage and one-level bearing plate, two level bearing plate enter anchor hole, the water that will be prepared Cement mortar injects anchor hole by Grouting Pipe, and slip casting is since bottom hole, and untill slurries are overflowed in aperture, slip casting carries out slurry after terminating Maintenance.
D, anchorage cable stretching locks
After injecting cement paste intensity reaches design load, first by single steel strand pretension tensioning, then remaining steel strand wires is carried out overall Tensioning, the load of tensioning press 10%, 50%, 75%, 100%, 110% or 120% carry out grading tension incremented by successively, it is stretched to 1.1 ~ 1.2 anchor cable stretching resistance characteristic values(Tak)When, lotus 10min is held to sandy soil layer, lotus 15min is held to cohesive soil, is then offloaded to and sets The tensile load locking that meter requires, loading speed are not more than 0.1NK/min.
E, steel strand wires are reclaimed
Anchor cable promotes steel strand wires revealed section after the completion of branch protective function, and the neck for making to move back anchor mandrel is locked by jump ring, anchor cable folder The bayonet socket gear wheel release steel strand wires off-load of piece, you can pull out steel strand wires recovery and use.
The present invention has simple in construction compared with prior art, and anchor force is big, and the recovery utilization rates of steel strand wires is high, make, All very convenient, anchor cable cost economic is installed, the anchor cable recoverable of supporting, further reduces engineering cost.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is Fig. 1 A-A sectional views;
Fig. 3 is Fig. 1 B-B sectional views;
Fig. 4 is Fig. 1 C-C sectional views;
Fig. 5 is anchor head structural representation;
Fig. 6 is to move back anchor core shaft structure schematic diagram;
Fig. 7 is connection sleeve pipe structural representation;
Fig. 8 is anchor cable intermediate plate and moves back anchor mandrel assembling schematic diagram.
Embodiment
Refering to 1 ~ Fig. 4 of accompanying drawing, the present invention is by double end anchor 1 and at least one or more than one single head anchor The multistage adjustable detachable prestress anchorage cable of 2 compositions, the double end anchor 1 are twisted by two anchor heads 11 and its steel connected respectively Line 3 forms with one-level bearing plate 4 and two level bearing plate 5;Two anchor head 11 is symmetricly set on the side of one-level bearing plate 4 and by leading To the sealing of cap 19;The two level bearing plate 5 is set by the front support tube 9 being sleeved on steel strand wires 3 with one-level bearing plate 4 for spacing; The single head anchor 2 is by another anchor head 11 and its steel strand wires 3 of connection and 5 groups of another grade of bearing plate 4 and two level bearing plate Into;Another grade of bearing plate 4 is set by the another front support tube 9 being sleeved on steel strand wires 3 with another two level bearing plate 5 for spacing; The single head anchor 2 is fixed by the middle stay tube 8 and double end anchor 1 or single head anchor 2 being sleeved on steel strand wires 3 Away from setting;The anchor head 11 by connection sleeve pipe 12, move back anchor mandrel 13, base 14, anchor cable intermediate plate 15, jump ring 16, spring 17 and cone Heart sleeve 18 forms;The front end of anchor mandrel 13 of moving back is the nose cone provided with neck 31, and its rear end is the jack provided with flange 32; The anchor cable intermediate plate 15 is the bayonet socket gear wheel of three taper crescent moon intermediate plate compositions, and its port is provided with caulking groove 51 and seal groove 52; The spring 17 is sleeved in connection sleeve pipe 14 with moving back anchor mandrel 13;Described one end of connection sleeve pipe 12 and the base provided with chamber 21 14 threaded connections, the other end are threadedly coupled with being set with the tap web sleeve 18 of anchor cable intermediate plate 15, and anchor cable intermediate plate 15 is set with by caulking groove 51 On the flange 32 for moving back the rear end of anchor mandrel 13, and " O " the type sealing ring 53 by being arranged on seal groove 52 is fixed;The card Spring 16 is disposed on the chamber 21 of base 14 by the groove 23 of the port of connection sleeve pipe 12;The one-level bearing plate 4 and two level Bearing plate 5 is the porous plate for circumferentially setting several slip castings or twisted wire hole 41;The revealed section of steel strand wires 3 is provided with anchor plate 6, Anchor plate 6 is set by the seat stay 7 being sleeved on steel strand wires 3 with single head anchor 2 for spacing;The anchor plate 6 is provided with The outer anchorage 62 of conical pipe 61;The conical pipe 61 is set with slip casting or twisted wire hole 41 to correspond;The steel strand wires 3 are by outer Conical pipe 61 on anchorage 62 respectively enters the anchor cable of double end anchor 1 and several single head anchors 2 by anchor plate 6 In intermediate plate 15, when 3 tensioning stress of steel strand wires, anchor cable intermediate plate 15 is interference fit with tap web sleeve 18, by the occlusion lock of steel strand wires 3 Tightly;The revealed section of steel strand wires 3 is promoted during unblock, makes to move back the front end of anchor mandrel 13 into the chamber 21 of base 14, and pinned by jump ring 16 Neck 31, spring 17, which compresses, makes the anchor cable intermediate plate 15 for moving back the rear end of anchor mandrel 13 coordinate with conical sleeve 18 for gap, discharges to steel The snap-lock of twisted wire 3, realize the recycling of steel strand wires 3.
Refering to accompanying drawing 5, the anchor head 11 by connection sleeve pipe 12, move back anchor mandrel 13, base 14, jump ring 16, spring 17 and cone Heart sleeve 18 and the steel strand wires 3 being connected with anchor cable intermediate plate 15, one-level bearing plate 4, two level bearing plate 5 form;It is described to move back anchor core The front end of axle 13 is the nose cone provided with neck 31, and its rear end is the jack provided with flange 32;The anchor cable intermediate plate 15 is three cones The bayonet socket gear wheel of shape crescent moon intermediate plate composition, its port is provided with caulking groove 51 and seal groove 52;The spring 17 is with moving back anchor mandrel 13 It is sleeved in connection sleeve pipe 14;Described one end of connection sleeve pipe 12 is threadedly coupled with the base 14 provided with chamber 21, the other end and set The tap web sleeve 18 of dress anchor cable intermediate plate 15 is threadedly coupled, and anchor cable intermediate plate 15 is sleeved on the flange for moving back the rear end of anchor mandrel 13 by caulking groove 51 On 32, and " O " the type sealing ring 53 by being arranged on seal groove 52 is fixed;The base 14 is steel base, limits steel Twisted wire 3 prevents steel strand wires 3 from stretching into long and anchor moving back anchor mandrel 13 in the interior edge anchor cable axis direction displacement of chamber 21 of base 14 Cord clip piece 15, tap web sleeve 18 and the sub-assembly of one-level bearing plate 4 depart from;The aperture in the slip casting or twisted wire hole 41 is less than tap web set 18 diameters of cylinder, and it is more than the diameter of steel strand wires 3;The steel strand wires 3 are externally provided with corrugated protective conduits 33 and PE protection pipes 32;The one-level Between the spacing and single head anchor 2 and double end anchor 1 or single head anchor 2 of bearing plate 4 and two level bearing plate 5 Distance can be set and be regulated and controled according to geological conditions.
Refering to accompanying drawing 6, the front end of anchor mandrel 13 of moving back is the nose cone provided with neck 31, and its rear end is provided with flange 32 Jack.
Refering to accompanying drawing 7, the Single port of connection sleeve pipe 2 is provided with groove 23.
Refering to accompanying drawing 8, the anchor cable intermediate plate 15 is the bayonet socket gear wheel of three taper crescent moon intermediate plate compositions, and its port is provided with Caulking groove 51 and seal groove 52, anchor cable intermediate plate 15 are sleeved on by caulking groove 51 on the flange 32 for moving back the rear end of anchor mandrel 13.
Embodiment 1
The construction method of the present invention is carried out in the steps below:
A, excavation of foundation pit and pore-forming
Pit earthwork is excavated to anchor cable construction operating surface, is crept into using rig in the soil body into anchor hole, hole depth and is more than anchor cable 0.3 ~ 0.5m of design length, the angle of anchor cable pore-forming are determined according to clay distribution, environmental requirement and equipment situation, typically 15 ~ 35 ° are taken, anchoring section is arranged in cohesive soil, silty soil or sandy soil stratum, a diameter of 150mm of anchor hole.
B, anchor cable is installed
Pore-forming is placed by double end anchor 1 and at least one or more than one single head after finishing acceptance(check) in anchor hole Anchor 2 forms multistage adjustable detachable prestress anchorage cable to projected depth position, the guiding cap 19 of double end anchor 1 500mm is withdrawn after touching anchor hole bottom, guiding cap 19 is left certain space with anchor hole bottom, anchor is being put to anchor hole During such as drag penalty when must be drawn off, to anchor hole dredge placement and the peace for carrying out anchor cable after processing again Dress.This anchor set has three-level spacing:Spacing one-level is base 14, controls the stroke in the chamber 21 of base 14 of steel strand wires 3 Length is simultaneously fixed by jump ring 16;Two level is spacing to move back anchor mandrel 13 in connection sleeve pipe 12 and connection sleeve pipe 12;Three-level is spacing For middle stay tube 8, by steel strand wires 3 and one-level bearing plate 4 formed good fixation with it is spacing.
C, slip casting conserves
Anchor set carries out slip casting after installing, Grouting Pipe passes through anchor plate 6, Yi Jiyi by the conical pipe 61 of outer anchorage 62 Level bearing plate 4 and slip casting on two level bearing plate 5 or twisted wire hole 41 penetrate anchor hole and colligation is firm, the cement mortar that will be prepared Anchor hole is injected by Grouting Pipe, slip casting is since bottom hole, untill slurries are overflowed in aperture.The ratio of mud of neat slurry takes 0.45 ~ 0.5, during according to cement mortar, cement-sand ratio 1:0.5~1:1, mix and stir and select medium coarse sand with sand, in cement mortar or cement mortar The additive for improving grouting soil early strength or microdilatancy can be mixed, its incorporation is determined by field test.Slip casting pipe end Portion to the distance of bottom hole is not more than 200mm, when declining in slip casting rear slurry face, carries out aperture and mends slurry, using secondary pressure slip casting When, Grouting Pipe sets injected hole in the range of l/4 ~ l/3 of anchorage end, and pitch of holes takes 500 ~ 800mm, each slip casting interface Injected hole takes two, and secondary grouting is the cement paste of the ratio of mud 0.5 ~ 0.55, is carried out after cement initial set, before final set, slip casting Pressure is not less than 1.5MPa, and the maintenance of slurry is carried out after slip casting.
D, tensioning fixation
After injecting cement paste intensity reaches design load, first by the pretension tensioning of single steel strand 3, then remaining steel strand wires 3 is carried out Integral tension, the load of tensioning are pressed 10%, 50%, 75%, 100%, 110% or 120% carry out grading tension incremented by successively, are stretched to 1.1 ~ 1.2 anchor cable stretching resistance characteristic values(Tak)When, lotus 10min is held to sandy soil layer, lotus 15min is held to cohesive soil, is then unloaded Tensile load to design requirement locks, and loading speed is not more than 0.1NK/min.
E, steel strand wires are reclaimed
Anchor cable after the completion of branch protective function, promote the revealed section of steel strand wires 3, by steel strand wires 3 along anchor hole direction toward hole in push 15 ~ 20mm distances, make to move back the chamber 21 that the front end of anchor mandrel 13 enters base 14, and neck 31 is pinned by jump ring 16, the compression of spring 17 makes The anchor cable intermediate plate 15 for moving back the rear end of anchor mandrel 13 exits conical sleeve 18, loses the snap-lock to steel strand wires 3, and steel strand wires 3 unlock Success, then pull out steel strand wires 3 and complete recovery.
Simply the present invention will be further described above, and is not used to limit patent of the present invention, all for the equivalent reality of the present invention Apply, be intended to be limited solely by within the right of patent of the present invention.

Claims (3)

1. a kind of recoverable prestressed Anchor Cable Anchorage, it is characterised in that the anchorage is by double end anchor and at least one or one More than the multistage adjustable detachable prestress anchorage cable of single head anchor composition, the double end anchor by two anchor heads and its The steel strand wires connected respectively form with one-level bearing plate and two level bearing plate;Two anchor head is symmetricly set on one-level bearing plate one Side and by guiding cap sealing;The two level bearing plate is set by the front support tube being sleeved on steel strand wires with one-level bearing plate for spacing Put;The single head anchor is made up of another anchor head and its steel strand wires of connection with another grade of bearing plate and two level bearing plate; Another grade of bearing plate is set by the another front support tube being sleeved on steel strand wires with another two level bearing plate for spacing;The single head Anchor is set by the middle stay tube being sleeved on steel strand wires with double end anchor or single head anchor for spacing;The anchor Head by connection sleeve pipe, move back anchor mandrel, base, anchor cable intermediate plate, jump ring, spring and tap web sleeve and form;It is described to move back anchor mandrel front end For the nose cone provided with neck, its rear end is the jack provided with flange;The anchor cable intermediate plate is that three taper crescent moon intermediate plates form Bayonet socket gear wheel, its port is provided with caulking groove and seal groove;The spring is with Tui Mao core sleeves in connection sleeve pipe;The company Female connector pipe one end is connected with the whorl of base provided with chamber, and the other end is connected with being set with the tap web bush whorl of anchor cable intermediate plate, anchor Cord clip piece is sleeved on by caulking groove on the flange of Tui Mao core back-ends, and " O " type sealing ring by being arranged on seal groove is consolidated It is fixed;The jump ring is disposed on the chamber of base by the groove of connection sleeve pipe port;The one-level bearing plate and two level are held Pressing plate is the porous plate for circumferentially setting several slip castings or twisted wire hole;The steel strand wires revealed section is provided with anchor plate, and by covering Seat stay on steel strand wires is set with single head anchor for spacing;The anchor plate is provided with the outer anchorage of conical pipe; The conical pipe is set with slip casting or twisted wire hole to correspond;The steel strand wires pass through anchor pad by the conical pipe on outer anchorage Plate, respectively enter double end and anchor in the anchor cable intermediate plate of dress and several single head anchors, when steel strand tension stress, anchor cable folder Piece is interference fit with tap web sleeve, and steel strand wires are engaged and locked;Steel strand wires revealed section is promoted during unblock, makes to move back anchor mandrel front end Neck is pinned into the chamber of base, and by jump ring, the anchor cable intermediate plate of spring-compressed Shi Tui anchors core back-end is with conical sleeve Gap coordinates, and discharges the snap-lock to steel strand wires, realizes the recycling of steel strand wires.
2. recoverable prestressed Anchor Cable Anchorage according to claim 1, it is characterised in that the aperture in the slip casting or twisted wire hole Less than tap web sleeve diameter, and it is more than steel strand wires diameter;The steel strand wires are externally provided with corrugated protective conduits and PE protection pipes.
3. the construction method of recoverable prestressed Anchor Cable Anchorage described in a kind of claim 1, it is characterised in that this method includes base Hole is excavated and pore-forming, anchor cable installation, slip casting maintenance, tensioning fixation and recovery steel strand wires, Specific construction are carried out in the steps below:
A, excavation of foundation pit and pore-forming
Pit earthwork is excavated to anchor cable construction operating surface, is crept into using rig in the soil body into anchor hole, the aperture of anchor hole for 0.13 ~ 0.30m, bore angle deviation ≯ 1 °, the discrepancy in elevation ≯ 50mm, hole depth are more than 0.3 ~ 0.5m of design length of anchor cable;
B, anchor cable is installed
The length of each stay tube is determined according to design requirement, to ensure that single head anchor fills with double end anchor and single head anchoring The spacing put is set, the projected depth position multistage adjustable detachable prestress anchorage cable assembled being placed in anchor hole, About 500mm is drawn outside when double end anchor is put into anchor hole bottom, it is ensured that guiding cap has certain space with anchor hole bottom;
C, slip casting conserves
Grouting Pipe passes sequentially through anchor plate by outer anchorage and one-level bearing plate, two level bearing plate enter anchor hole, the water that will be prepared Cement mortar injects anchor hole by Grouting Pipe, and slip casting is since bottom hole, and untill slurries are overflowed in aperture, slip casting carries out slurry after terminating Maintenance;
D, anchorage cable stretching locks
After injecting cement paste intensity reaches design load, first by single steel strand pretension tensioning, then remaining steel strand wires is carried out overall Tensioning, the load of tensioning press 10%, 50%, 75%, 100%, 110% or 120% carry out grading tension incremented by successively, it is stretched to 1.1 ~ 1.2 anchor cable stretching resistance characteristic values(Tak)When, lotus 10min is held to sandy soil layer, lotus 15min is held to cohesive soil, is then offloaded to and sets The tensile load locking that meter requires, loading speed are not more than 0.1NK/min;
E, steel strand wires are reclaimed
Anchor cable promotes steel strand wires revealed section after the completion of branch protective function, and the neck for making to move back anchor mandrel is locked by jump ring, anchor cable intermediate plate Bayonet socket gear wheel release steel strand wires off-load, you can pull out steel strand wires recovery use.
CN201710983624.3A 2017-10-20 2017-10-20 A kind of anchorage and its construction method of recoverable prestressed anchor cable Pending CN107513996A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710983624.3A CN107513996A (en) 2017-10-20 2017-10-20 A kind of anchorage and its construction method of recoverable prestressed anchor cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710983624.3A CN107513996A (en) 2017-10-20 2017-10-20 A kind of anchorage and its construction method of recoverable prestressed anchor cable

Publications (1)

Publication Number Publication Date
CN107513996A true CN107513996A (en) 2017-12-26

Family

ID=60726040

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710983624.3A Pending CN107513996A (en) 2017-10-20 2017-10-20 A kind of anchorage and its construction method of recoverable prestressed anchor cable

Country Status (1)

Country Link
CN (1) CN107513996A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108396741A (en) * 2018-03-30 2018-08-14 重庆诺为生态环境工程有限公司 A kind of stable soil body from anchor device
CN109098185A (en) * 2018-09-29 2018-12-28 沈阳建筑大学 From the application method of fragmentation type sulfur cement mortar anchorage mortar in anchor pole or anchorage cable anchoring section
CN109555546A (en) * 2019-01-21 2019-04-02 中国水利水电第十工程局有限公司 It faces upward the lower rope device of anchor cable for deep hole wide-angle
CN109653218A (en) * 2019-01-09 2019-04-19 河南省交通规划设计研究院股份有限公司 A kind of existing engineering prestressd anchor cable measuring method and its dedicated anchoring measurement device
CN109853543A (en) * 2019-03-29 2019-06-07 华侨大学 A kind of assembled guiding cap for anchor pole
CN109853548A (en) * 2019-03-29 2019-06-07 华侨大学 A kind of T-type plug and the anchor pole using the T-type plug
CN109914406A (en) * 2019-04-08 2019-06-21 重庆大学 The novel antiskid bearing pile of vertical anchor precompressed can be recycled in one kind
CN110004827A (en) * 2019-04-02 2019-07-12 中国建筑第二工程局有限公司 A kind of anchor cable tripper
CN110067246A (en) * 2019-05-29 2019-07-30 建研地基基础工程有限责任公司 Anchorage, anchor cable locking and the recovery method of Recyclable anchor rope
CN110397035A (en) * 2019-08-20 2019-11-01 浙江中桥预应力设备有限公司 A kind of recoverable version anchor cable
CN112962593A (en) * 2021-02-22 2021-06-15 大连理工大学 Construction method of recyclable anchor rod
CN113136872A (en) * 2021-04-13 2021-07-20 沈阳工业大学 Mechanical type knob detachable prestressed anchorage cable structure of solid useless grout material
CN113174977A (en) * 2021-05-19 2021-07-27 核工业华南花都建设工程公司 Slope support construction process
CN113266006A (en) * 2021-05-25 2021-08-17 宜宾学院 Basalt fiber prestressed anchor cable component and anchoring system thereof
CN114319347A (en) * 2022-02-22 2022-04-12 厦门铖知新材科技有限公司 Recoverable anchor cable
CN114753375A (en) * 2022-03-25 2022-07-15 山东旭瑞环境岩土工程勘察设计有限公司 Construction method applying recoverable anchor cable
CN114922177A (en) * 2022-06-28 2022-08-19 中铁十八局集团有限公司 Recoverable prestressed anchor cable for foundation pit support and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638892A (en) * 2008-08-02 2010-02-03 柳州欧维姆机械股份有限公司 Pressure-yielding anchorage device and reclaimable anchor cable
CN201502061U (en) * 2009-08-11 2010-06-09 湖北中建三局建筑工程技术有限责任公司 Recoverable prestressing anchor rope with double anchor heads
CN202247873U (en) * 2011-03-11 2012-05-30 王立明 Detachable recoverable anchor rod
CN204059365U (en) * 2014-08-07 2014-12-31 青岛海川建设集团有限公司 A kind of deep foundation ditch Prestressed anchor rope with pressure dispersing bracing means
WO2015176614A1 (en) * 2014-05-21 2015-11-26 苏州市能工基础工程有限责任公司 Construction method and structure of pressure dispersing expansion head anchor rod
CN205088679U (en) * 2015-10-15 2016-03-16 刘建连 Removable ground tackle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638892A (en) * 2008-08-02 2010-02-03 柳州欧维姆机械股份有限公司 Pressure-yielding anchorage device and reclaimable anchor cable
CN201502061U (en) * 2009-08-11 2010-06-09 湖北中建三局建筑工程技术有限责任公司 Recoverable prestressing anchor rope with double anchor heads
CN202247873U (en) * 2011-03-11 2012-05-30 王立明 Detachable recoverable anchor rod
WO2015176614A1 (en) * 2014-05-21 2015-11-26 苏州市能工基础工程有限责任公司 Construction method and structure of pressure dispersing expansion head anchor rod
CN204059365U (en) * 2014-08-07 2014-12-31 青岛海川建设集团有限公司 A kind of deep foundation ditch Prestressed anchor rope with pressure dispersing bracing means
CN205088679U (en) * 2015-10-15 2016-03-16 刘建连 Removable ground tackle

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108396741A (en) * 2018-03-30 2018-08-14 重庆诺为生态环境工程有限公司 A kind of stable soil body from anchor device
CN109098185A (en) * 2018-09-29 2018-12-28 沈阳建筑大学 From the application method of fragmentation type sulfur cement mortar anchorage mortar in anchor pole or anchorage cable anchoring section
CN109653218A (en) * 2019-01-09 2019-04-19 河南省交通规划设计研究院股份有限公司 A kind of existing engineering prestressd anchor cable measuring method and its dedicated anchoring measurement device
CN109653218B (en) * 2019-01-09 2023-12-19 河南省交通规划设计研究院股份有限公司 Existing engineering anchor cable prestress determination method and special anchor determination device thereof
CN109555546B (en) * 2019-01-21 2024-04-09 中国水利水电第十工程局有限公司 Cable unloading device for deep hole large-angle upward-leaning anchor cable
CN109555546A (en) * 2019-01-21 2019-04-02 中国水利水电第十工程局有限公司 It faces upward the lower rope device of anchor cable for deep hole wide-angle
CN109853548B (en) * 2019-03-29 2024-02-23 华侨大学 T-shaped plug and anchor rod adopting same
CN109853548A (en) * 2019-03-29 2019-06-07 华侨大学 A kind of T-type plug and the anchor pole using the T-type plug
CN109853543B (en) * 2019-03-29 2024-02-23 华侨大学 Assembled guide cap for anchor rod
CN109853543A (en) * 2019-03-29 2019-06-07 华侨大学 A kind of assembled guiding cap for anchor pole
CN110004827A (en) * 2019-04-02 2019-07-12 中国建筑第二工程局有限公司 A kind of anchor cable tripper
CN110004827B (en) * 2019-04-02 2024-01-16 中国建筑第二工程局有限公司 Anchor rope unlocking device
CN109914406A (en) * 2019-04-08 2019-06-21 重庆大学 The novel antiskid bearing pile of vertical anchor precompressed can be recycled in one kind
CN109914406B (en) * 2019-04-08 2024-02-13 重庆大学 Novel anti-slip bearing pile capable of recycling vertical anchor prepressing
CN110067246B (en) * 2019-05-29 2024-01-23 建研地基基础工程有限责任公司 Anchor device capable of recycling anchor cable, anchor cable locking and recycling method
CN110067246A (en) * 2019-05-29 2019-07-30 建研地基基础工程有限责任公司 Anchorage, anchor cable locking and the recovery method of Recyclable anchor rope
CN110397035B (en) * 2019-08-20 2024-04-12 浙江中桥预应力设备有限公司 Recoverable anchor rope
CN110397035A (en) * 2019-08-20 2019-11-01 浙江中桥预应力设备有限公司 A kind of recoverable version anchor cable
CN112962593A (en) * 2021-02-22 2021-06-15 大连理工大学 Construction method of recyclable anchor rod
CN113136872A (en) * 2021-04-13 2021-07-20 沈阳工业大学 Mechanical type knob detachable prestressed anchorage cable structure of solid useless grout material
CN113174977A (en) * 2021-05-19 2021-07-27 核工业华南花都建设工程公司 Slope support construction process
CN113174977B (en) * 2021-05-19 2022-05-10 核工业华南花都建设工程公司 Slope support construction process
CN113266006A (en) * 2021-05-25 2021-08-17 宜宾学院 Basalt fiber prestressed anchor cable component and anchoring system thereof
CN114319347B (en) * 2022-02-22 2023-12-22 厦门铖知新材科技有限公司 Recoverable anchor rope
CN114319347A (en) * 2022-02-22 2022-04-12 厦门铖知新材科技有限公司 Recoverable anchor cable
CN114753375B (en) * 2022-03-25 2024-02-02 山东旭瑞环境岩土工程勘察设计有限公司 Construction method using recyclable anchor cable
CN114753375A (en) * 2022-03-25 2022-07-15 山东旭瑞环境岩土工程勘察设计有限公司 Construction method applying recoverable anchor cable
CN114922177A (en) * 2022-06-28 2022-08-19 中铁十八局集团有限公司 Recoverable prestressed anchor cable for foundation pit support and construction method thereof

Similar Documents

Publication Publication Date Title
CN107513996A (en) A kind of anchorage and its construction method of recoverable prestressed anchor cable
CN106498943B (en) Disposable high-pressure rotary-spray type enlarged footing Prestressed Soil anchor pole construction method
CN101886393B (en) Construction method of combined foundation ditch support
CN200961263Y (en) Fixed valve locking type reclaimable rockbolt
CN105422128A (en) Method for preventing goaf gas leakage in deep shaft gob-side entry driving
CN107012875A (en) Basement supporting
CN104863108B (en) A kind of ground-connecting-wall soil lateral pressure box embedded device
CN108301428A (en) The pre- tensioning post-tensioning pile foundation of stake top and construction technology
CN205171547U (en) Recoverable miniature stock wall
CN108842792B (en) Layered lifting and unloading type ground pulling anchor rod and construction method
CN209586373U (en) The support system of the lower rock compound cross-section stratum jacking construction inlet and outlet cave of upper soil
CN102660948A (en) Steel tube locked anchor rod construction method
CN208545747U (en) It is segmented reaming pressure anchor wire structure
CN109854281A (en) The method for protecting support of the lower rock compound cross-section stratum jacking construction of upper soil
CN103883339B (en) A kind of cable bolting method repeating Shi Hanzhang
CN113982033B (en) Method for repairing hydraulic retaining wall with inclination trend by using water in post-construction structure without damage to wall
CN202989919U (en) Pressure-bearing water-sand-layer anchor rod mounting structure
CN107059872B (en) Inclined cable pile pulling method and inclined cable pile pulling system
CN203716145U (en) Orientation steel pipe locking prestress multiple anchor rope
CN106223344A (en) A kind of ground line piled anchor framework foundation pit supporting method
CN108301400B (en) Hollow drainage anchoring anti-slide pile and construction method thereof
CN113027487A (en) Rich water tunnel tubular prestressing force concreties cementer
CN105952381A (en) Anchor rod drill bit capable of recycling anchor cable
CN112538859A (en) Construction method of steel pipe pile anti-sliding continuous wall
CN220014569U (en) Comprehensive type inclined building deviation rectifying and reinforcing structure

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Liu Xilin

Inventor after: Hu Baoshan

Inventor after: Zhang Minjie

Inventor after: Ma Leping

Inventor after: Liu Changwei

Inventor after: Lai Xin

Inventor after: Li Jiahong

Inventor before: Li Jiahong

Inventor before: Hu Baoshan

Inventor before: Lai Xin

Inventor before: Zhang Minjie

Inventor before: Liu Xilin

Inventor before: Ma Leping

Inventor before: Liu Changwei

CB03 Change of inventor or designer information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171226

WD01 Invention patent application deemed withdrawn after publication