CN107504962A - 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法 - Google Patents

一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法 Download PDF

Info

Publication number
CN107504962A
CN107504962A CN201710513263.6A CN201710513263A CN107504962A CN 107504962 A CN107504962 A CN 107504962A CN 201710513263 A CN201710513263 A CN 201710513263A CN 107504962 A CN107504962 A CN 107504962A
Authority
CN
China
Prior art keywords
pier stud
plummet apparatus
template
laser plummet
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710513263.6A
Other languages
English (en)
Inventor
赵培庆
武帅帅
宋国春
李庚�
刘江天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical No 4 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority to CN201710513263.6A priority Critical patent/CN107504962A/zh
Publication of CN107504962A publication Critical patent/CN107504962A/zh
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • G01C15/10Plumb lines
    • G01C15/105Optical plumbing

Abstract

本发明是一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,具体步骤为:a、首次架立模板之前,用全站仪将墩柱的墩身十字中线坐标定点在承台的顶面,弹出墩柱的轮廓线;b、支设模板,模板顶端外侧安装有测量平台;c、在承台顶面弹出的墩柱的四个轮廓线外选取多个测量点,保证测量点距离轮廓线的距离一致,记为D;在测量点处架设激光铅垂仪,激光铅垂仪向上发射激光束,测量人员在测量平台上调整刻度尺边线与激光铅垂仪发射的激光束的十字线重合,测量出模板顶激光束到模板内边的距离,记为M;保证|M‑D|≤20mm,符合要求之后进行混凝土浇筑施工。本发明提高了施工效率,投入少;操作简单,造成误差的因素减少,提高了准确度。

Description

一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法
技术领域
本发明涉及公路工程中桥梁上下截面一致的墩柱垂直度施工控制领域,尤其涉及一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法。
背景技术
目前国内在桥梁高墩柱施工中,多数采用滑膜、翻模等施工技术,而模板在提上过程中,难免由于施工操作产生偏移误差。这时多数采用垂线法以及全站仪测量中线的方法控制垂直度,即通过在模板顶部立设圆棱镜,全站仪测设高程、坐标等数据。
但针对高墩柱(30-100m)垂直度的控制,以上方法在准确度、施工效率、安全性以及操作的简易程度上均有很大的局限性,往往造成施工不便以及测量精度较差的现象,对施工高墩柱进行垂直度控制效果较差。
发明内容
本发明旨在解决现有技术的不足,而提供一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法。
本发明为实现上述目的,采用以下技术方案:
一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,具体步骤为:
a、首次架立模板之前,用全站仪将墩柱的墩身十字中线坐标定点在承台的顶面,弹出墩柱的轮廓线;
b、按照弹出的墩柱的轮廓线,支设模板,模板顶端外侧安装有测量平台;
c、支模完成后采用激光铅垂仪测量模板的垂直度,测量的具体方法为:
在承台顶面弹出的墩柱的四个轮廓线外选取多个测量点,保证测量点距离轮廓线的距离一致,记为D;
在测量点处架设激光铅垂仪,激光铅垂仪向上发射激光束,测量人员在测量平台上调整刻度尺边线与激光铅垂仪发射的激光束的十字线重合,测量出模板顶激光束到模板内边的距离,记为M;
保证|M-D|≤20mm,符合要求之后进行混凝土浇筑施工。
支模完成后采用激光铅垂仪测量模板垂直度的过程中,测量点共计八个点,墩柱四个轮廓线外分别设有两个测量点,两个测量点关于墩柱中心线对称设置。
当模板安装到墩柱的墩身顶部时,除墩柱中线坐标外,还要精确测出墩柱顶面标高,保证出墩柱位置和高度的准确。
本发明的有益效果是:本发明提高了施工效率,投入少;操作简单,造成误差的因素减少,提高了准确度。
附图说明
图1为本发明的施工示意图;
图2为墩柱的墩身轮廓线及测量点布置图;
图中:1-承台;2-墩柱;3-激光铅垂仪;4-模板;5-测量平台;
以下将结合本发明的实施例参照附图进行详细叙述。
具体实施方式
下面结合附图和实施例对本发明作进一步说明:
具体实施例如图1和图2所示,一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,具体步骤为:
a、首次架立模板4之前,用全站仪将墩柱2的墩身十字中线坐标定点在承台1的顶面,弹出墩柱2的轮廓线;
b、按照弹出的墩柱2的轮廓线,支设模板4,模板4顶端外侧安装有测量平台5;
c、支模完成后采用激光铅垂仪3测量模板4的垂直度,测量的具体方法为:
在承台1顶面弹出的墩柱2的四个轮廓线外选取多个测量点,保证测量点距离轮廓线的距离一致,记为D;
在测量点处架设激光铅垂仪3,激光铅垂仪3向上发射激光束,测量人员在测量平台5上调整刻度尺边线与激光铅垂仪3发射的激光束的十字线重合,测量出模板4顶激光束到模板4内边的距离,记为M;
保证|M-D|为20mm,符合要求之后进行混凝土浇筑施工。
支模完成后采用激光铅垂仪3测量模板4垂直度的过程中,测量点共计八个点,墩柱2四个轮廓线外分别设有两个测量点,两个测量点关于墩柱中心线对称设置。
当模板4安装到墩柱2的墩身顶部时,除墩柱2中线坐标外,还要精确测出墩柱2顶面标高,保证出墩柱2位置和高度的准确。
本发明提高了施工效率,现场技术员掌握操作要求之后,即可随时进行模板4的校核,测量班组只需进行定期的复测,单柱的施工进度由0.75m/日提升到1.2m/日;操作简单,造成误差的因素减少,从而提高了准确度,70m高墩垂直度最大误差可以控制在15mm以内;投入少,一套激光铅垂仪的价格在1500元左右,但在提高施工效率及人员的投入上有较大的施工效益。
上面结合附图对本发明进行了示例性描述,显然本发明具体实现并不受上述方式的限制,只要采用了本发明的方法构思和技术方案进行的各种改进,或未经改进直接应用于其它场合的,均在本发明的保护范围之内。

Claims (3)

1.一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,其特征在于,具体步骤为:
a、首次架立模板(4)之前,用全站仪将墩柱(2)的墩身十字中线坐标定点在承台(1)的顶面,弹出墩柱(2)的轮廓线;
b、按照弹出的墩柱(2)的轮廓线,支设模板(4),模板(4)顶端外侧安装有测量平台(5);
c、支模完成后采用激光铅垂仪(3)测量模板(4)的垂直度,测量的具体方法为:
在承台(1)顶面弹出的墩柱(2)的四个轮廓线外选取多个测量点,保证测量点距离轮廓线的距离一致,记为D;
在测量点处架设激光铅垂仪(3),激光铅垂仪(3)向上发射激光束,测量人员在测量平台(5)上调整刻度尺边线与激光铅垂仪(3)发射的激光束的十字线重合,测量出模板(4)顶激光束到模板(4)内边的距离,记为M;
保证|M-D|≤20mm,符合要求之后进行混凝土浇筑施工。
2.根据权利要求1所述的一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,其特征在于,支模完成后采用激光铅垂仪(3)测量模板(4)垂直度的过程中,测量点共计八个点,墩柱(2)四个轮廓线外分别设有两个测量点,两个测量点关于墩柱中心线对称设置。
3.根据权利要求2所述的一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法,其特征在于,当模板(4)安装到墩柱(2)的墩身顶部时,除墩柱(2)中线坐标外,还要精确测出墩柱(2)顶面标高,保证出墩柱(2)位置和高度的准确。
CN201710513263.6A 2017-06-29 2017-06-29 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法 Withdrawn CN107504962A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710513263.6A CN107504962A (zh) 2017-06-29 2017-06-29 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710513263.6A CN107504962A (zh) 2017-06-29 2017-06-29 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法

Publications (1)

Publication Number Publication Date
CN107504962A true CN107504962A (zh) 2017-12-22

Family

ID=60679538

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710513263.6A Withdrawn CN107504962A (zh) 2017-06-29 2017-06-29 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法

Country Status (1)

Country Link
CN (1) CN107504962A (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108824204A (zh) * 2018-07-12 2018-11-16 宁波市建设集团股份有限公司 墩柱施工方法及墩柱施工装配式操作平台
CN109352019A (zh) * 2018-11-19 2019-02-19 青岛海西重机有限责任公司 一种起重机行走平衡梁轴孔加工方法
CN109900214A (zh) * 2019-04-17 2019-06-18 大学士工程管理有限公司 一种建筑工地施工用抹灰面厚度实时监测仪
CN109944272A (zh) * 2019-04-12 2019-06-28 中铁七局集团有限公司 一种地铁施工用多功能测量基站结构
CN111272157A (zh) * 2020-03-16 2020-06-12 中铁大桥局集团第二工程有限公司 一种预制变截面高墩身的垂直度测量方法
CN111749124A (zh) * 2018-06-25 2020-10-09 杜春 一种装配式桥梁结构
CN112066958A (zh) * 2020-08-27 2020-12-11 中铁大桥局第七工程有限公司 一种围堰内结构物定位的方法及系统
CN112227213A (zh) * 2020-10-16 2021-01-15 中国矿业大学 一种装配式盖梁与立柱预制拼装导向定位方法、导向架
CN112286089A (zh) * 2020-09-27 2021-01-29 中铁七局集团有限公司 高墩大跨桥梁施工过程智能监测系统
CN112414384A (zh) * 2019-08-03 2021-02-26 无锡交通建设工程集团有限公司 测量定位装置及用于桥梁预制立柱安装的测量定位方法
CN112782715A (zh) * 2021-01-11 2021-05-11 西安热工研究院有限公司 一种风力发电塔筒安装垂直度快速检测方法和装置
CN115162732A (zh) * 2022-07-11 2022-10-11 上海宝冶集团有限公司 一种独立异形清水混凝土柱的建造方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103344214A (zh) * 2013-07-05 2013-10-09 中南大学 一种1.6次抛物线型特大桥墩测量及墩身线形控制方法
CN104120656A (zh) * 2014-07-30 2014-10-29 中交一公局第四工程有限公司 桥梁高墩施工垂直度自动控制方法
CN105113413A (zh) * 2015-08-26 2015-12-02 中交第一公路工程局有限公司 手摇线锤装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103344214A (zh) * 2013-07-05 2013-10-09 中南大学 一种1.6次抛物线型特大桥墩测量及墩身线形控制方法
CN104120656A (zh) * 2014-07-30 2014-10-29 中交一公局第四工程有限公司 桥梁高墩施工垂直度自动控制方法
CN105113413A (zh) * 2015-08-26 2015-12-02 中交第一公路工程局有限公司 手摇线锤装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
师建博: ""薄壁高墩竖直度控制方法"", 《筑路机械与施工机械化》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111749124A (zh) * 2018-06-25 2020-10-09 杜春 一种装配式桥梁结构
CN111764262A (zh) * 2018-06-25 2020-10-13 杜春 一种装配式桥梁结构的施工方法
CN111764262B (zh) * 2018-06-25 2022-04-01 杜春 一种装配式桥梁结构的施工方法
CN108824204A (zh) * 2018-07-12 2018-11-16 宁波市建设集团股份有限公司 墩柱施工方法及墩柱施工装配式操作平台
CN109352019A (zh) * 2018-11-19 2019-02-19 青岛海西重机有限责任公司 一种起重机行走平衡梁轴孔加工方法
CN109352019B (zh) * 2018-11-19 2019-09-24 青岛海西重机有限责任公司 一种起重机行走平衡梁轴孔加工方法
CN109944272A (zh) * 2019-04-12 2019-06-28 中铁七局集团有限公司 一种地铁施工用多功能测量基站结构
CN109900214A (zh) * 2019-04-17 2019-06-18 大学士工程管理有限公司 一种建筑工地施工用抹灰面厚度实时监测仪
CN112414384A (zh) * 2019-08-03 2021-02-26 无锡交通建设工程集团有限公司 测量定位装置及用于桥梁预制立柱安装的测量定位方法
CN112414384B (zh) * 2019-08-03 2022-04-22 无锡交通建设工程集团有限公司 测量定位装置及用于桥梁预制立柱安装的测量定位方法
CN111272157A (zh) * 2020-03-16 2020-06-12 中铁大桥局集团第二工程有限公司 一种预制变截面高墩身的垂直度测量方法
CN112066958A (zh) * 2020-08-27 2020-12-11 中铁大桥局第七工程有限公司 一种围堰内结构物定位的方法及系统
CN112286089B (zh) * 2020-09-27 2022-02-15 中铁七局集团有限公司 高墩大跨桥梁施工过程智能监测系统
CN112286089A (zh) * 2020-09-27 2021-01-29 中铁七局集团有限公司 高墩大跨桥梁施工过程智能监测系统
CN112227213B (zh) * 2020-10-16 2021-07-23 中国矿业大学 一种装配式盖梁与立柱预制拼装导向定位方法、导向架
CN112227213A (zh) * 2020-10-16 2021-01-15 中国矿业大学 一种装配式盖梁与立柱预制拼装导向定位方法、导向架
CN112782715A (zh) * 2021-01-11 2021-05-11 西安热工研究院有限公司 一种风力发电塔筒安装垂直度快速检测方法和装置
CN112782715B (zh) * 2021-01-11 2024-02-06 西安热工研究院有限公司 一种风力发电塔筒安装垂直度快速检测方法和装置
CN115162732A (zh) * 2022-07-11 2022-10-11 上海宝冶集团有限公司 一种独立异形清水混凝土柱的建造方法

Similar Documents

Publication Publication Date Title
CN107504962A (zh) 一种采用激光铅垂仪控制桥梁高墩柱垂直度的方法
CN102874376B (zh) 用于船体建造的余量线及检验线划线装置
CN103175506A (zh) 大型桥梁净空高度测量方法
CN102407520A (zh) 一种划线装置
CN203785674U (zh) 测量仪器新型对中整平基座
CN205843555U (zh) 一种楼板厚度测量工具
CN208921129U (zh) 一种隧道内接触网无轨施工测量仪器
CN206002038U (zh) 一种墙柱模板垂直测量仪
CN208313310U (zh) 塔吊垂直度测量系统
CN110307957B (zh) 一种风洞洞体高精度无棱镜放样工艺
CN108532984B (zh) 一种支撑胎架高精度安装方法
CN203440721U (zh) 直角式线梁偏心及道砟厚度检测尺
CN205679225U (zh) 矩形柱倾斜度测量装置
CN202329634U (zh) 测钉
CN208721066U (zh) 一种公路横断面测量的简易便捷工具
CN209802378U (zh) 一种简易便携的模板垂直度测量靠尺
CN207540537U (zh) 新型水平尺
CN204826647U (zh) 一种墙柱模板安装位置及垂直度检测尺
CN208476256U (zh) 一种便携式转点盘测量装置
CN208139978U (zh) 一种地铁车站站台门测量放线装置
CN210401652U (zh) 一种移动可调式激光测距固定装置
CN203811172U (zh) 建筑用垂直度测试仪
CN211042182U (zh) 一种用于防撞护栏施工的测量装置
CN203672378U (zh) 一种预埋件测量定位装置
CN204373614U (zh) 一种桥梁跨度的激光测量装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20171222

WW01 Invention patent application withdrawn after publication