CN107460889A - Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery - Google Patents
Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery Download PDFInfo
- Publication number
- CN107460889A CN107460889A CN201710855576.XA CN201710855576A CN107460889A CN 107460889 A CN107460889 A CN 107460889A CN 201710855576 A CN201710855576 A CN 201710855576A CN 107460889 A CN107460889 A CN 107460889A
- Authority
- CN
- China
- Prior art keywords
- mould bases
- interior wall
- formwork
- steel
- outside
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种地下综合管廊施工中的整体移动式支架模板及其施工方法,整体移动式支架模板包括有内侧模架和外侧模架,内侧模架是由顶板模架、两组内墙模架和内侧支架拼接而成。本发明的内侧模架在场外拼装完成后进行吊装入坑,避免了繁琐的模板支架搭设作业,且内侧模架和外侧模架均通过行走架进行移动定位,然后进行后续的合模与加固,缩短了工期,降低了施工成本;本发明的内侧模架通过内侧支架进行支撑和加固,保证了内侧模架结构的整体稳定性。
The invention discloses an integral mobile support formwork in the construction of an underground comprehensive pipe gallery and a construction method thereof. The integral mobile support formwork includes an inner formwork and an outer formwork, and the inner formwork consists of a top plate formwork, two inner formwork The wall formwork and the inner bracket are spliced together. The inner formwork of the present invention is hoisted into the pit after being assembled outside the site, which avoids the cumbersome formwork bracket erection operation, and both the inner formwork and the outer formwork are moved and positioned by the walking frame, and then the subsequent mold clamping and reinforcement are carried out. The construction period is shortened, and the construction cost is reduced; the inner formwork of the present invention is supported and reinforced by the inner support, which ensures the overall stability of the inner formwork structure.
Description
技术领域technical field
本发明涉及地下综合管廊施工领域,具体是一种应用于地下综合管廊施工中的整体移动式支架模板及其施工方法。The invention relates to the field of construction of an underground comprehensive pipe gallery, in particular to an integral mobile support formwork and a construction method used in the construction of an underground comprehensive pipe gallery.
背景技术Background technique
随着经济的发展、城市规模的扩大和现代化程度的不断提高,城市地下管网也越来越庞大、密集,其种类也越来越繁多。相对于城市地下管网的快速发展,对城市地下管线的管理却显得滞后,已根本不能适应管网业务的增长需求,并在很大程度上制约了城市发展。目前广西、山东、四川等多地均启动了地下管廊建设项目,我国地下管廊建设已步入加速期。With the development of economy, the expansion of urban scale and the continuous improvement of modernization, the urban underground pipe network is becoming larger and denser, and its types are becoming more and more diverse. Compared with the rapid development of the urban underground pipeline network, the management of the urban underground pipeline is lagging behind. It can no longer meet the growing demand of the pipeline network business, and restricts the development of the city to a large extent. At present, Guangxi, Shandong, Sichuan and many other places have launched underground pipe gallery construction projects, and the construction of underground pipe gallery in my country has entered a period of acceleration.
目前,在地下管廊修建中,主体结构施工多采用方木、模板配合钢管支架体系进行施工,而普通模板支架施工工序繁多,安装拆除时间长,钢管支架租赁成本较高,木模板周转多次以后其施工质量难以保证。At present, in the construction of underground pipe corridors, the main structure is mostly constructed with square wood and formwork with a steel pipe support system. However, ordinary formwork support has many construction procedures, long installation and dismantling time, high rental cost of steel pipe support, and wooden formwork turnover. It is difficult to guarantee the construction quality in the future.
发明内容Contents of the invention
本发明要解决的技术问题是提供一种应用于地下综合管廊施工中的整体移动式支架模板及其施工方法,能快速便捷地进行管廊结构施工作业,以缩短工期并节约成本。The technical problem to be solved by the present invention is to provide an integral mobile support formwork and its construction method used in the construction of underground comprehensive pipe gallery, which can quickly and conveniently carry out the construction work of the pipe gallery structure, so as to shorten the construction period and save costs.
本发明的技术方案为:Technical scheme of the present invention is:
一种应用于地下综合管廊施工中的整体移动式支架模板,包括有内侧模架和外侧模架,所述的内侧模架包括有顶板模架、两组内墙模架和内侧支架;An integral movable support formwork applied in the construction of underground comprehensive utility tunnels, comprising an inner formwork and an outer formwork, the inner formwork comprising a roof formwork, two sets of inner wall formwork and inner supports;
所述的内侧支架包括有多根竖直设置的竖杆、多根水平设置且连接于相邻竖杆之间的横杆、连接于竖杆底端的内侧行走架和多组侧撑调节器;所述的两组内墙模架均包括有竖直设置的内墙防水夹板、多根连接于内墙防水夹板内端面上且从上至下平行设置的内墙钢次梁、以及设置于内墙钢次梁内侧且与内墙钢次梁固定连接的多根内墙蜂巢钢,多根内墙蜂巢钢竖直设置且与内墙钢次梁相互垂直,所述的两组内墙模架的内墙防水夹板内端面相对设置;所述的顶板模架包括有水平设置的顶部防水夹板、多根连接于顶部防水夹板下端面上且从左到右平行设置的顶部钢次梁、以及设置于顶部钢次梁下方且与顶部钢次梁固定连接的多根横向蜂巢钢,多根横向蜂巢钢水平设置且与多根顶部钢次梁相互垂直;所述的内侧支架竖杆的顶端与对应的横向蜂巢钢固定连接;每组侧撑调节器均包括有一个穿过多根竖杆且与多根竖杆固定连接的水平连接杆和两个外螺纹杆,水平连接杆的两端设置有内螺纹孔,两个外螺纹杆的外端分别固定连接于两组内墙模架的内墙蜂巢钢上,两个外螺纹杆的内端分别与水平连接杆的两端螺和连接;The inner support includes a plurality of vertically arranged vertical bars, a plurality of horizontally arranged horizontal bars connected between adjacent vertical bars, an inner walking frame connected to the bottom ends of the vertical bars, and multiple sets of side support adjusters; The two groups of interior wall formworks all include vertically arranged interior wall waterproof splints, a plurality of interior wall steel secondary beams connected to the inner end surface of the interior wall waterproof splints and arranged in parallel from top to bottom, and arranged inside Multiple internal wall honeycomb steels on the inner side of the wall steel secondary beam and fixedly connected with the internal wall steel secondary beam. The multiple internal wall honeycomb steels are vertically arranged and perpendicular to the internal wall steel secondary beam. The two sets of internal wall formwork The inner end faces of the inner wall waterproof splints are relatively arranged; the roof formwork includes a horizontally arranged top waterproof splint, a plurality of top steel secondary beams connected to the lower end surface of the top waterproof splint and arranged in parallel from left to right, and setting A plurality of horizontal honeycomb steels fixedly connected to the top steel secondary beams below the top steel secondary beams, the multiple horizontal honeycomb steels are arranged horizontally and perpendicular to the multiple top steel secondary beams; The horizontal honeycomb steel is fixedly connected; each set of side brace adjusters includes a horizontal connecting rod that passes through multiple vertical rods and is fixedly connected with multiple vertical rods, and two external threaded rods. Internally threaded holes, the outer ends of the two externally threaded rods are respectively fixedly connected to the inner wall honeycomb steel of the two sets of inner wall formwork, and the inner ends of the two externally threaded rods are respectively screwed and connected to the two ends of the horizontal connecting rod;
所述的外侧模架包括有竖直设置的外墙防水夹板、多根连接于外墙防水夹板外端面上且从上至下平行设置的外墙钢次梁、设置于外墙钢次梁外侧且与外墙钢次梁固定连接的多根外墙蜂巢钢、以及连接于外墙蜂巢钢底端的外侧行走架,所述的多根外墙蜂巢钢竖直设置且与多根外墙钢次梁相互垂直。The outer formwork includes a vertically arranged exterior wall waterproof splint, a plurality of exterior wall steel secondary beams connected to the outer end surface of the exterior wall waterproof splint and arranged in parallel from top to bottom, and arranged outside the exterior wall steel secondary beam. And a plurality of outer wall honeycomb steels fixedly connected with the outer wall steel secondary beams, and an outer walking frame connected to the bottom end of the outer wall honeycomb steels, the plurality of outer wall honeycomb steels are vertically arranged and connected with the plurality of outer wall steel secondary beams The beams are perpendicular to each other.
所述的两组内墙模架的内墙蜂巢钢均为两根;所述的顶板模架的横向蜂巢钢均为两根;所述的外侧模架的外墙蜂巢钢均为两根。There are two inner wall honeycomb steels of the two groups of inner wall formworks; two horizontal honeycomb steels of the roof formwork; two outer wall honeycomb steels of the outer formworks.
所述的内侧支架还包括有多根倾斜设置且连接于相邻竖杆之间的加强杆。The inner support also includes a plurality of reinforcing rods arranged obliquely and connected between adjacent vertical rods.
所述的内侧支架的多根竖杆顶端均设置有顶托,每个顶托和对应的横向蜂巢钢均通过两个C型夹和工字梁进行连接,其中一个C型夹将横向蜂巢钢与工字梁的上水平部进行固定连接,另一个C型夹将顶托与工字梁的下水平部进行固定连接。The tops of the multiple vertical rods of the inner support are all provided with jacking brackets, and each jacking bracket and the corresponding horizontal honeycomb steel are connected by two C-shaped clips and I-shaped beams, and one of the C-shaped clips connects the horizontal honeycomb steel It is fixedly connected with the upper horizontal part of the I-beam, and another C-shaped clamp is fixedly connected with the lower horizontal part of the I-beam.
所述的内侧行走架包括有支撑架体、滑动连接于支撑架体上可上下移动的定位套管和连接于支撑架体底部的行走轮,所述的竖杆的底部套装于定位套管内且与定位套管连接。The inner walking frame includes a supporting frame body, a positioning sleeve slidably connected to the supporting frame body to move up and down, and a walking wheel connected to the bottom of the supporting frame body. The bottom of the vertical bar is sleeved in the positioning sleeve and Connect with positioning sleeve.
所述的外墙蜂巢钢的外侧连接有多个外模加固器,每个外模加固器均包括有相互套接的内套管和外套管,内套管的内端固定于外墙蜂巢钢上,内套管的外端部套装于外套管内端部的内圈并固定连接。The outer side of the outer wall honeycomb steel is connected with a plurality of external formwork reinforcements, each external formwork reinforcement includes an inner sleeve and an outer sleeve that are socketed with each other, and the inner end of the inner sleeve is fixed to the outer wall honeycomb steel Above, the outer end of the inner sleeve is sleeved on the inner ring of the inner end of the outer sleeve and fixedly connected.
所述的顶板模架的两端分别与对应内墙模架的顶端通过角隅连接器进行连接。Both ends of the roof formwork are respectively connected to the top of the corresponding interior wall formwork through corner connectors.
一种整体移动式支架模板的施工方法,具体包括有以下步骤:A construction method for an integral mobile support formwork, specifically comprising the following steps:
(1)、将拼装好的内侧支架吊装到基坑内,并通过内侧行走架移动到管廊对应的位置;(1) Hoist the assembled inner support into the foundation pit, and move it to the corresponding position of the pipe gallery through the inner walking frame;
(2)、调节内侧行走架定位套管的高度,使内侧支架顶端的顶板模架达到对应的高度;(2) Adjust the height of the positioning sleeve of the inner walking frame so that the roof formwork at the top of the inner bracket reaches the corresponding height;
(3)、调节角隅连接器的位置,外扩两组内墙模架至设定尺寸,再调整内墙模架的垂直度,使内墙模架置于相应的位置后,最后将水平连接杆与内墙模架上的两个外螺纹杆螺和连接,完成内墙模架的加固;(3) Adjust the position of the corner connector, expand the two sets of interior wall formwork to the set size, and then adjust the verticality of the interior wall formwork to place the interior wall formwork at the corresponding position, and finally place the horizontal The connecting rod is connected with the two external threaded rods on the inner wall formwork to complete the reinforcement of the inner wall formwork;
(4)、按步骤(1)-(3)依次连续安装并调节各单元的内墙模架,完成内墙模架的合模与加固;(4) Continuously install and adjust the interior wall formwork of each unit according to steps (1)-(3), and complete the mold closing and reinforcement of the interior wall formwork;
(5)、吊装外侧模架到预先设置好的导轨上,外侧行走架沿着对应的导轨移动外侧模架到相应的位置。(5) Hoist the outer formwork onto the pre-set guide rails, and the outer walking frame moves the outer formwork to the corresponding position along the corresponding guide rails.
(6)、使用外模加固器调节外侧模架,使外侧模架调节到相应位置保持竖直并加固紧实;(6) Use the external mold reinforcement to adjust the outer formwork, so that the outer formwork can be adjusted to the corresponding position to keep it vertical and firm;
(7)、依次连续安装并调节各单元的外侧模架,完成外侧模架的合模与加固;(7) Continuously install and adjust the outer formwork of each unit in sequence to complete the mold clamping and reinforcement of the outer formwork;
(8)、在支架模板中浇筑混凝土,待混凝土浇筑完成并养护到可拆除的强度之后,开始拆除外侧模架,首先松开外模加固器,将外侧模架沿着导轨移动到下一节段,完成外侧模架的移动。(8) Concrete is poured in the bracket formwork. After the concrete pouring is completed and cured to a removable strength, the outer formwork is removed. First, the outer formwork reinforcement is loosened, and the outer formwork is moved along the guide rail to the next section section to complete the movement of the outer formwork.
(9)、将水平连接杆拆除,并调节角隅连接器的位置,使内墙模架内缩,并调节内侧行走架定位套管的高度,使内侧支架顶端的顶板模架高度下调,完成两组内墙模架与顶板模架的内缩。(9) Remove the horizontal connecting rod, and adjust the position of the corner connector to shrink the inner wall formwork, and adjust the height of the positioning sleeve of the inner walking frame, so that the height of the roof formwork at the top of the inner support is lowered, and the completion The shrinkage of two sets of interior wall formwork and roof formwork.
(10)、内侧行走架沿着对应的导轨移动内侧模架到下一节段,完成内墙模架的移动。(10) The inner walking frame moves the inner formwork to the next segment along the corresponding guide rail to complete the movement of the inner wall formwork.
(11)、重复上述步骤(1)-(10)完成地下综合管廊主体结构的施工。(11) Repeat the above steps (1)-(10) to complete the construction of the main structure of the underground comprehensive pipe gallery.
本发明的优点:Advantages of the present invention:
本发明的内侧模架在场外拼装完成后进行吊装入坑,避免了繁琐的模板支架搭设作业,且内侧模架和外侧模架均通过行走架进行移动定位,然后进行后续的合模与加固,缩短了工期,降低了施工成本;本发明的内侧模架通过内侧支架进行支撑和加固,保证了内侧模架结构的整体稳定性;本发明外侧模架设置有外模加固器,保证了外侧模架固定结构的稳定性。The inner formwork of the present invention is hoisted into the pit after being assembled outside the site, which avoids the cumbersome formwork bracket erection operation, and both the inner formwork and the outer formwork are moved and positioned by the walking frame, and then the subsequent mold clamping and reinforcement are carried out. The construction period is shortened, and the construction cost is reduced; the inner formwork of the present invention is supported and reinforced by the inner bracket, which ensures the overall stability of the inner formwork structure; the outer formwork of the present invention is provided with an outer mold reinforcement, which ensures that the outer formwork The stability of the fixed frame structure.
附图说明Description of drawings
图1是本发明内侧模架的结构示意图。Fig. 1 is a schematic structural view of the inner formwork of the present invention.
图2是本发明内墙模架内端面的结构示意图。Fig. 2 is a structural schematic diagram of the inner end surface of the interior wall formwork of the present invention.
图3是图1中的A部放大图。Fig. 3 is an enlarged view of part A in Fig. 1 .
图4是图1中的B部放大图。Fig. 4 is an enlarged view of part B in Fig. 1 .
图5是图1中的C部放大图。Fig. 5 is an enlarged view of part C in Fig. 1 .
图6是本发明外侧模架的结构示意图。Fig. 6 is a schematic structural view of the outer formwork of the present invention.
图7是图6中的D部放大图。Fig. 7 is an enlarged view of part D in Fig. 6 .
图8是图6中的E部放大图。Fig. 8 is an enlarged view of part E in Fig. 6 .
图9是本发明内侧行走架的结构示意图。Fig. 9 is a schematic structural view of the inner walking frame of the present invention.
具体实施方式detailed description
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
见图1-图9,一种应用于地下综合管廊施工中的整体移动式支架模板,包括有内侧模架和外侧模架,内侧模架包括有顶板模架、两组内墙模架和内侧支架,顶板模架的两端分别与对应内墙模架的顶端通过角隅连接器21进行连接;See Fig. 1-Fig. 9, a kind of overall movable support formwork used in the construction of underground comprehensive pipe gallery, including inner formwork and outer formwork, inner formwork includes roof formwork, two sets of inner wall formwork and The inner bracket, the two ends of the roof formwork are respectively connected to the top of the corresponding inner wall formwork through corner connectors 21;
内侧支架包括有多根竖直设置的竖杆1、多根水平设置且连接于相邻竖杆1之间的横杆2、多根倾斜设置且连接于相邻竖杆1之间的加强杆3、连接于竖杆1底端的内侧行走架4、设置于每根竖杆1顶端的顶托5和多组侧撑调节器;The inner support includes a plurality of vertically arranged vertical bars 1, a plurality of horizontally arranged horizontal bars 2 connected between adjacent vertical bars 1, and a plurality of obliquely arranged reinforcing bars connected between adjacent vertical bars 1 3. The inner walking frame 4 connected to the bottom of the vertical bar 1, the jacking 5 and multiple sets of side support adjusters arranged at the top of each vertical bar 1;
两组内墙模架均包括有竖直设置的内墙防水夹板6、多根连接于内墙防水夹板6内端面上且从上至下平行设置的内墙钢次梁7、以及设置于内墙钢次梁7内侧且与内墙钢次梁7固定连接的两根内墙蜂巢钢8,两根内墙蜂巢钢8竖直设置且与内墙钢次梁7相互垂直,两组内墙模架的内墙防水夹板6内端面相对设置;Both groups of interior wall formworks include a vertically arranged interior wall waterproof splint 6, a plurality of interior wall steel secondary beams 7 connected to the inner end surface of the interior wall waterproof splint 6 and arranged in parallel from top to bottom, and a The two interior wall honeycomb steels 8 inside the wall steel secondary beam 7 and fixedly connected with the interior wall steel secondary beam 7, the two interior wall honeycomb steel 8 are vertically arranged and perpendicular to the interior wall steel secondary beam 7, and the two sets of interior walls The inner end faces of the inner wall waterproof plywood 6 of the formwork are relatively arranged;
顶板模架包括有水平设置的顶部防水夹板9、多根连接于顶部防水夹板9下端面上且从左到右平行设置的顶部钢次梁10、以及设置于顶部钢次梁10下方且与顶部钢次梁10固定连接的两根横向蜂巢钢11,两根横向蜂巢钢11水平设置且与多根顶部钢次梁10相互垂直,内侧支架的每个顶托5和对应的横向蜂巢钢11均通过两个C型夹12和工字梁13进行连接,其中一个C型夹12将横向蜂巢钢11与工字梁13的上水平部进行固定连接,另一个C型夹12将顶托5与工字梁13的下水平部进行固定连接;The roof formwork includes a top waterproof splint 9 arranged horizontally, a plurality of top steel secondary beams 10 connected to the lower end surface of the top waterproof splint 9 and arranged in parallel from left to right, and a top steel secondary beam 10 arranged below the top steel secondary beam 10 and connected to the top. Two transverse honeycomb steels 11 fixedly connected to the steel secondary beams 10, the two transverse honeycomb steels 11 are horizontally arranged and perpendicular to multiple top steel secondary beams 10, each jacking 5 of the inner support and the corresponding horizontal honeycomb steel 11 are Two C-shaped clamps 12 are connected to the I-beam 13, one of which is the C-shaped clamp 12 that connects the horizontal honeycomb steel 11 to the upper horizontal part of the I-beam 13, and the other C-shaped clamp 12 connects the jacking 5 to the upper horizontal part of the I-beam 13. The lower horizontal portion of the I-beam 13 is fixedly connected;
每组侧撑调节器均包括有一个穿过多根竖杆1且与多根竖杆1固定连接的水平连接杆14和两个外螺纹杆15,水平连接杆14的两端设置有内螺纹孔,两个外螺纹杆15的外端分别固定连接于两组内墙模架的内墙蜂巢钢8上,两个外螺纹杆15的内端分别与水平连接杆14的两端螺和连接;Each set of side brace adjusters includes a horizontal connecting rod 14 and two externally threaded rods 15 that pass through a plurality of vertical rods 1 and are fixedly connected with the plurality of vertical rods 1, and the two ends of the horizontal connecting rod 14 are provided with internal threads. holes, the outer ends of the two externally threaded rods 15 are respectively fixedly connected to the inner wall honeycomb steel 8 of the two sets of inner wall formwork, and the inner ends of the two externally threaded rods 15 are respectively screwed and connected to the two ends of the horizontal connecting rod 14 ;
外侧模架包括有竖直设置的外墙防水夹板16、多根连接于外墙防水夹板16外端面上且从上至下平行设置的外墙钢次梁17、设置于外墙钢次梁17外侧且与外墙钢次梁17固定连接的两根外墙蜂巢钢18、连接于外墙蜂巢钢18底端的外侧行走架19和连接于外墙蜂巢钢18外侧的多个外模加固器20,两根外墙蜂巢钢18竖直设置且与多根外墙钢次梁17相互垂直,每个外模加固器20均包括有相互套接的内套管201和外套管202,内套管201的内端固定于外墙蜂巢钢18上,内套管201的外端部套装于外套管202内端部的内圈并固定连接。The outer formwork includes a vertically arranged exterior wall waterproof splint 16, a plurality of exterior wall steel secondary beams 17 connected to the outer end surface of the exterior wall waterproof splint 16 and arranged in parallel from top to bottom, and external wall steel secondary beams 17. Two outer wall honeycomb steels 18 fixedly connected to the outer wall steel secondary beams 17, an outer walking frame 19 connected to the bottom of the outer wall honeycomb steel 18, and a plurality of outer mold reinforcements 20 connected to the outer side of the outer wall honeycomb steel 18 , two external wall honeycomb steels 18 are vertically arranged and are perpendicular to multiple external wall steel secondary beams 17, each external formwork reinforcement 20 includes an inner sleeve 201 and an outer sleeve 202 that are socketed with each other, and the inner sleeve The inner end of the 201 is fixed on the outer wall honeycomb steel 18, and the outer end of the inner casing 201 is sleeved on the inner ring of the inner end of the outer casing 202 and fixedly connected.
其中,内侧行走架4包括有支撑架体41、滑动连接于支撑架体41上可上下移动的定位套管42和连接于支撑架体41底部的行走轮43,竖杆1的底部套装于定位套管42内且与定位套管42连接,当定位套管42上下移动时,从而带动内侧支架顶端的顶板模架进行升降调节。Wherein, the inner walking frame 4 includes a support frame body 41, a positioning sleeve 42 that is slidably connected to the support frame body 41 and can move up and down, and a walking wheel 43 connected to the bottom of the support frame body 41. The bottom of the vertical rod 1 is sleeved on the positioning Inside the sleeve 42 and connected with the positioning sleeve 42, when the positioning sleeve 42 moves up and down, it will drive the roof formwork at the top of the inner support to adjust up and down.
一种整体移动式支架模板的施工方法,具体包括有以下步骤:A construction method for an integral mobile support formwork, specifically comprising the following steps:
(1)、将拼装好的内侧支架吊装到基坑内,并通过内侧行走架4移动到管廊对应的位置;(1) Hoist the assembled inner support into the foundation pit, and move it to the corresponding position of the pipe gallery through the inner walking frame 4;
(2)、调节内侧行走架定位套管42的高度,使内侧支架顶端的顶板模架达到对应的高度;(2) Adjust the height of the positioning sleeve 42 of the inner walking frame so that the roof formwork at the top of the inner support reaches the corresponding height;
(3)、调节角隅连接器21的位置,外扩两组内墙模架至设定尺寸,再调整内墙模架的垂直度,使内墙模架置于相应的位置后,最后将水平连接杆14与内墙模架上的两个外螺纹杆15螺和连接,完成内墙模架的加固;(3) Adjust the position of the corner connector 21, expand the two sets of interior wall formwork to the set size, and then adjust the verticality of the interior wall formwork to place the interior wall formwork at the corresponding position, and finally place the The horizontal connecting rod 14 is screwed and connected with two external threaded rods 15 on the interior wall formwork to complete the reinforcement of the interior wall formwork;
(4)、按步骤(1)-(3)依次连续安装并调节各单元的内墙模架,完成内墙模架的合模与加固;(4) Continuously install and adjust the interior wall formwork of each unit according to steps (1)-(3), and complete the mold closing and reinforcement of the interior wall formwork;
(5)、吊装外侧模架到预先设置好的导轨23上,外侧行走架19沿着对应的导轨22移动外侧模架到相应的位置。(5) Hoist the outer formwork onto the pre-set guide rail 23, and the outer walking frame 19 moves the outer formwork to the corresponding position along the corresponding guide rail 22.
(6)、使用外模加固器20调节外侧模架,使外侧模架调节到相应位置保持竖直并加固紧实;(6) Use the outer mold reinforcement 20 to adjust the outer formwork, so that the outer formwork can be adjusted to the corresponding position to keep it vertical and firm;
(7)、依次连续安装并调节各单元的外侧模架,完成外侧模架的合模与加固;(7) Continuously install and adjust the outer formwork of each unit in sequence to complete the mold clamping and reinforcement of the outer formwork;
(8)、在支架模板中浇筑混凝土,待混凝土浇筑完成并养护到可拆除的强度之后,开始拆除外侧模架,首先松开外模加固器20,将外侧模架沿着导轨22移动到下一节段,完成外侧模架的移动。(8) Concrete is poured in the bracket formwork. After the concrete is poured and cured to a removable strength, the outer formwork is removed. First, loosen the outer formwork reinforcement 20 and move the outer formwork along the guide rail 22 to the lower One segment completes the movement of the outer formwork.
(9)、将水平连接杆14拆除,并调节角隅连接器21的位置,使内墙模架内缩,并调节内侧行走架定位套管42的高度,使内侧支架顶端的顶板模架高度下调,完成两组内墙模架与顶板模架的内缩。(9), remove the horizontal connecting rod 14, and adjust the position of the corner connector 21, so that the inner wall formwork retracts, and adjust the height of the positioning sleeve 42 of the inner walking frame, so that the height of the roof formwork at the top of the inner support Adjust down to complete the retraction of two sets of interior wall formwork and roof formwork.
(10)、内侧行走架4沿着对应的导轨22移动内侧模架到下一节段,完成内墙模架的移动。(10) The inner walking frame 4 moves the inner formwork to the next segment along the corresponding guide rail 22 to complete the movement of the inner wall formwork.
(11)、重复上述步骤(1)-(10)完成地下综合管廊主体结构的施工。(11) Repeat the above steps (1)-(10) to complete the construction of the main structure of the underground comprehensive pipe gallery.
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。Although the embodiments of the present invention have been shown and described, those skilled in the art can understand that various changes, modifications and substitutions can be made to these embodiments without departing from the principle and spirit of the present invention. and modifications, the scope of the invention is defined by the appended claims and their equivalents.
Claims (8)
- A kind of 1. integral movable type rack template in construction applied to underground pipe gallery, it is characterised in that:Include inner side Mould bases and outside mould bases, described inner side mould bases include top plate mould bases, two groups of interior wall mould bases and medial cradle;Described medial cradle include the more montants being vertically arranged, more it is horizontally disposed and be connected between adjacent montant Cross bar, the inner side walker for being connected to montant bottom and multigroup side stay adjuster;Two groups of described interior wall mould bases include perpendicular The interior wall waterproof clamping plate that directly sets, more be connected to the interior wall steel be arrangeding in parallel on interior wall waterproof clamping plate inner face and from top to bottom Secondary beam and it is arranged at more interior wall honeycomb steel being fixedly connected on the inside of interior wall steel secondary beam and with interior wall steel secondary beam, more interior walls Honeycomb steel is vertically arranged and is mutually perpendicular to interior wall steel secondary beam, the interior wall waterproof clamping plate inner face phase of described two groups of interior wall mould bases To setting;Described top plate mould bases include horizontally disposed top waterproof clamping plate, more be connected to top waterproof clamping plate lower end The top steel secondary beam that be arranged in parallel on face and from left to right and it is arranged at below the steel secondary beam of top and is fixed with top steel secondary beam More horizontal honeycomb steel of connection, more horizontal honeycomb steel are horizontally disposed and are mutually perpendicular to more top steel secondary beams;Described The top of medial cradle montant is fixedly connected with corresponding horizontal honeycomb steel;Every group of side stay adjuster includes one through more Root montant and the horizontal brace rod being fixedly connected with more montants and two external thread rods, being provided at both ends with for horizontal brace rod are interior Screwed hole, the outer ends of two external thread rods are respectively fixedly connected with the interior wall honeycomb steel of two groups of interior wall mould bases, two external screw threads Bar it is inner respectively with the both ends spiral shell of horizontal brace rod and being connected;Described outside mould bases include the external wall waterproof clamping plate being vertically arranged, more be connected on external wall waterproof clamping plate outer face And be arranged in parallel from top to bottom exterior wall steel secondary beam, be arranged on the outside of exterior wall steel secondary beam and be fixedly connected with exterior wall steel secondary beam more Root exterior wall honeycomb steel and the outside walker for being connected to exterior wall honeycomb steel bottom, more described exterior wall honeycomb steel are set vertically Put and be mutually perpendicular to more exterior wall steel secondary beams.
- 2. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 1, its It is characterised by:The interior wall honeycomb steel of two groups of described interior wall mould bases is two;The horizontal honeycomb steel of described top plate mould bases is equal For two;The exterior wall honeycomb steel of described outside mould bases is two.
- 3. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 1, its It is characterised by:Described medial cradle also includes the more bracing pieces for being obliquely installed and being connected between adjacent montant.
- 4. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 1, its It is characterised by:More montant tops of described medial cradle are provided with jacking, each jacking and corresponding horizontal honeycomb steel It is attached by two C-type clamps and I-beam, one of C-type clamp enters the upper horizontal part of horizontal honeycomb steel and I-beam Row is fixedly connected, and the lower horizontal part of jacking and I-beam is fixedly connected by another C-type clamp.
- 5. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 1, its It is characterised by:Described inner side walker includes supporting frame, is slidably connected to positioning moving up and down on supporting frame Sleeve pipe and the road wheel for being connected to supporting frame bottom, the bottom of described montant is set in locating sleeve and and locating sleeve Connection.
- 6. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 5, its It is characterised by:Multiple external mold reinforcing devices are connected with the outside of described exterior wall honeycomb steel, each external mold reinforcing device includes phase The inner sleeve and outer tube being mutually socketed, the inner of inner sleeve are fixed on exterior wall honeycomb steel, and the outer end of inner sleeve is set in outside The inner ring of sleeve pipe inner end is simultaneously fixedly connected.
- 7. the integral movable type rack template in a kind of construction applied to underground pipe gallery according to claim 6, its It is characterised by:Top of the both ends of described top plate mould bases respectively with corresponding interior wall mould bases is attached by corner connector.
- A kind of 8. construction method of integral movable type rack template according to claim 7, it is characterised in that:Specifically include There are following steps:(1), assembled good medial cradle is lifted into foundation ditch, and position corresponding to piping lane is moved to by inner side walker;(2), regulation inner side walker locating sleeve height, the top plate mould bases on medial cradle top is reached corresponding height;(3), regulation corner connector position, extend out two groups of interior wall mould bases to being sized, then adjust the vertical of interior wall mould bases Degree, after interior wall mould bases is placed in corresponding position, finally by two external thread rod spiral shells on horizontal brace rod and interior wall mould bases and Connection, complete the reinforcing of interior wall mould bases;(4), by step(1)-(3)Continuously install successively and adjust the interior wall mould bases of each unit, complete interior wall mould bases matched moulds with Reinforce;(5), lifting outside mould bases on the guide rail pre-set, outside walker moves outside mould bases along corresponding guide rail To corresponding position;(6), using external mold reinforcing device adjust outside mould bases, make outside mould bases regulation to relevant position keep it is vertical and reinforce tightly It is real;(7), the outside mould bases continuously installing successively and adjust each unit, complete matched moulds and the reinforcing of outside mould bases;(8), in rack template casting concrete, after treating that concreting is completed and conserves detachable intensity, start Outside mould bases is removed, unclamps external mold reinforcing device first, outside mould bases is moved to next section along guide rail, completes outside mould bases Movement;(9), horizontal brace rod removed, and adjust the position of corner connector, inside contract interior wall mould bases, and adjust inner side and walk The height of frame locating sleeve, the top plate mould bases on medial cradle top is highly lowered, complete two groups of interior wall mould bases and top plate mould bases Inside contract;(10), inner side walker along corresponding guide rail move inner side mould bases arrive next section, completion interior wall mould bases movement;(11), repeat the above steps(1)-(10)Complete the construction of underground pipe gallery agent structure.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710855576.XA CN107460889A (en) | 2017-09-20 | 2017-09-20 | Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710855576.XA CN107460889A (en) | 2017-09-20 | 2017-09-20 | Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN107460889A true CN107460889A (en) | 2017-12-12 |
Family
ID=60552737
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710855576.XA Pending CN107460889A (en) | 2017-09-20 | 2017-09-20 | Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107460889A (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108951699A (en) * | 2018-06-14 | 2018-12-07 | 上海二十冶建设有限公司 | A kind of mobile internal model of the sectional type of pipe gallery and bracket and its application method |
| CN109339435A (en) * | 2018-11-14 | 2019-02-15 | 西南科技大学 | Formwork support adjustment parts and special-shaped cave construction light steel support formwork structure system |
| CN110629787A (en) * | 2019-09-16 | 2019-12-31 | 中铁广州工程局集团深圳工程有限公司 | Core mold for pipe gallery pouring and construction method |
| CN111779025A (en) * | 2020-06-19 | 2020-10-16 | 中国一冶集团有限公司 | In-situ protection structure crossing foundation pit municipal pipe network box culvert and construction method |
| CN112982280A (en) * | 2021-02-07 | 2021-06-18 | 中铁广州工程局集团深圳工程有限公司 | Wharf breast wall pipe gallery formwork structure and construction method |
| CN113338336A (en) * | 2021-06-29 | 2021-09-03 | 中国建筑第四工程局有限公司 | Movable aluminum formwork pipe gallery continuous pouring forming structure and construction method |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08144303A (en) * | 1994-11-17 | 1996-06-04 | Ishikawajima Constr Materials Co Ltd | Form device for forming segments |
| CN203961992U (en) * | 2014-06-16 | 2014-11-26 | 中建七局安装工程有限公司 | Portable full framing chassis |
| CN204876508U (en) * | 2015-07-15 | 2015-12-16 | 徐伟明 | Portable height -adjustable scaffold |
| CN105908777A (en) * | 2016-05-04 | 2016-08-31 | 东北大学 | Comprehensive pipe gallery sliding mold and application method thereof |
| CN107119715A (en) * | 2017-04-28 | 2017-09-01 | 东北大学 | A kind of overall mould bases of pipe gallery and its application method |
| CN207419521U (en) * | 2017-09-20 | 2018-05-29 | 中铁四局集团有限公司 | Integral mobile support formwork in the construction of underground comprehensive pipe gallery |
-
2017
- 2017-09-20 CN CN201710855576.XA patent/CN107460889A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08144303A (en) * | 1994-11-17 | 1996-06-04 | Ishikawajima Constr Materials Co Ltd | Form device for forming segments |
| CN203961992U (en) * | 2014-06-16 | 2014-11-26 | 中建七局安装工程有限公司 | Portable full framing chassis |
| CN204876508U (en) * | 2015-07-15 | 2015-12-16 | 徐伟明 | Portable height -adjustable scaffold |
| CN105908777A (en) * | 2016-05-04 | 2016-08-31 | 东北大学 | Comprehensive pipe gallery sliding mold and application method thereof |
| CN107119715A (en) * | 2017-04-28 | 2017-09-01 | 东北大学 | A kind of overall mould bases of pipe gallery and its application method |
| CN207419521U (en) * | 2017-09-20 | 2018-05-29 | 中铁四局集团有限公司 | Integral mobile support formwork in the construction of underground comprehensive pipe gallery |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108951699A (en) * | 2018-06-14 | 2018-12-07 | 上海二十冶建设有限公司 | A kind of mobile internal model of the sectional type of pipe gallery and bracket and its application method |
| CN108951699B (en) * | 2018-06-14 | 2021-09-21 | 上海二十冶建设有限公司 | Festival segmentation removal centre form and support of utility tunnel |
| CN109339435A (en) * | 2018-11-14 | 2019-02-15 | 西南科技大学 | Formwork support adjustment parts and special-shaped cave construction light steel support formwork structure system |
| CN110629787A (en) * | 2019-09-16 | 2019-12-31 | 中铁广州工程局集团深圳工程有限公司 | Core mold for pipe gallery pouring and construction method |
| CN111779025A (en) * | 2020-06-19 | 2020-10-16 | 中国一冶集团有限公司 | In-situ protection structure crossing foundation pit municipal pipe network box culvert and construction method |
| CN112982280A (en) * | 2021-02-07 | 2021-06-18 | 中铁广州工程局集团深圳工程有限公司 | Wharf breast wall pipe gallery formwork structure and construction method |
| CN113338336A (en) * | 2021-06-29 | 2021-09-03 | 中国建筑第四工程局有限公司 | Movable aluminum formwork pipe gallery continuous pouring forming structure and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107460889A (en) | Integral mobile support formwork and its construction method in the construction of underground comprehensive pipe gallery | |
| CN115369748B (en) | Formwork system construction method for integrated casting of bridge piers and tie beams | |
| WO2021189746A1 (en) | Rapid construction structure and method for secondary lining of multiple variable-cross-section bored tunnels | |
| CN107119715A (en) | A kind of overall mould bases of pipe gallery and its application method | |
| CN109653771B (en) | Integrated secondary lining steel formwork trolley for tunnel arch ring and cable trench side wall | |
| CN110700105A (en) | Synchronous construction method for high pier column and tie beam and template used in same | |
| CN110093948A (en) | Variable cross-section Pipe rack and its construction method suitable for rapid construction | |
| CN108360380B (en) | Bridge pier column construction operation platform and construction method thereof | |
| CN114481874B (en) | Prefabricated door type frame assembled box culvert and construction method | |
| CN111472540A (en) | Integrated formwork system suitable for concrete pouring of pool wall and construction method thereof | |
| CN108035741A (en) | A kind of backform trolley | |
| CN204851287U (en) | Big section moving as a whole formula formwork support | |
| CN112554077A (en) | Steel pipe concrete assembled truss composite beam construction system and construction method | |
| CN111809660A (en) | Rectangular trolley for integrated pipe gallery and construction method | |
| CN115748524A (en) | Cast-in-place concrete drainage box culvert and construction method thereof | |
| CN113047607A (en) | Automatic adjustable and walking formwork system and operation method thereof | |
| CN209799969U (en) | A integrally lift up cantilever formwork device for quick construction shaft lining cutting | |
| CN116084293B (en) | Triangular steel arch formwork system and construction method for cast-in-place concrete main arch ring | |
| CN106285721B (en) | A kind of railway culvert method of construction based on sliding mode system | |
| CN110184915B (en) | Cast-in-place tower column of cable-stayed bridge and its construction method | |
| CN105952140B (en) | Tool-type steel framework Wood-plastic formwork system and its construction technology for cast-in-place concrete | |
| CN116180608A (en) | A multi-point synchronous lifting device and lifting method for a thin-walled hollow pier forming mold | |
| CN110924323A (en) | Culvert template trolley | |
| CN214168790U (en) | Concrete-filled steel tube assembled truss composite beam construction system | |
| CN110714480A (en) | Construction method of pipe gallery |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information |
Address after: Wangjiang Road in Baohe District of Hefei city of Anhui Province, No. 96 230023 Applicant after: CHINA TIESIJU CIVIL ENGINEERING GROUP Co.,Ltd. Applicant after: THE FIRST ENGINEERING CO., LTD. OF CTCE Group Address before: 230023 technical center of China Railway four Bureau, No. 96 Wangjiang East Road, Anhui, 618, Hefei Applicant before: CHINA TIESIJU CIVIL ENGINEERING GROUP Co.,Ltd. Applicant before: THE FIRST ENGINEERING CO., LTD. OF CTCE Group |
|
| CB02 | Change of applicant information | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171212 |
|
| RJ01 | Rejection of invention patent application after publication |