CN107460879A - A kind of fixed structure of flare template - Google Patents
A kind of fixed structure of flare template Download PDFInfo
- Publication number
- CN107460879A CN107460879A CN201710803742.1A CN201710803742A CN107460879A CN 107460879 A CN107460879 A CN 107460879A CN 201710803742 A CN201710803742 A CN 201710803742A CN 107460879 A CN107460879 A CN 107460879A
- Authority
- CN
- China
- Prior art keywords
- flare
- casting concrete
- template
- steel form
- fixed structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 25
- 239000010959 steel Substances 0.000 claims abstract description 25
- 238000005266 casting Methods 0.000 claims abstract description 23
- 238000004873 anchoring Methods 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 4
- 239000002362 mulch Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 7
- 238000009435 building construction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
Abstract
The invention discloses a kind of fixed structure of flare template, it includes casting concrete layer, the both sides of casting concrete layer are provided with side template longitudinally disposed therealong and flare steel form, side template is connected with flare steel form, multiple connection columns longitudinally disposed therealong are provided with casting concrete layer, each connect coaxially is connected with multiple lacing wires on column;Lacing wire one end and casting concrete layer are affixed, and the other end and flare steel form are affixed.The present invention is simple in construction, easy to use, and the support erection scheme that the temporary project amount of input is more traditional is much smaller, saves man-hour, convenient construction, meets safety, quality and construction period.
Description
Technical field
The present invention relates to a kind of fixing device of template, belongs to technical field of building construction, more particularly to a kind of flare mould
The fixed structure of plate.
Background technology
In the realm of building construction, often the part pouring reinforcement concrete outside stressing main structure, such as sluice pier
The top flare bracket part of body.Because concrete structure deadweight is often larger, to be considered how when constructing projecting segments solid
Determine punching block, ensure safety and the problems such as Reducing distortion value, traditional way is to do support from ground, and the template of flare is propped up
Support, then casting concrete, temporary project amount is often bigger, especially in the case where works is very high from the ground.
The content of the invention
Present invention aim to solve the deficiency in above-mentioned background technology, there is provided a kind of fixed knot of flare template
Structure.Device directly can directly securely fix the template of flare, be supported without additionally setting up support from ground, subtract significantly
Small temporary project amount.
In order to solve the above technical problems, present invention employs the fixed structure of such a flare template, it includes having poured
Concrete layer is built, the both sides of casting concrete layer are provided with side template longitudinally disposed therealong and flare steel form, side template
It is connected with flare steel form, has been provided with multiple connection columns longitudinally disposed therealong on casting concrete layer, each connection is vertical
Multiple lacing wires are coaxially connected with post;Lacing wire one end and casting concrete layer are affixed, and the other end and flare steel form are affixed.
In a kind of preferred embodiment of the present invention, connect be provided with by column for the anchoring backing plate that connects lacing wire and
Anchor bolt;Anchoring backing plate and anchor bolt are embedded in casting concrete layer in advance.
In a kind of preferred embodiment of the present invention, the Surface mulch of casting concrete layer has bar-mat reinforcement.
In a kind of preferred embodiment of the present invention, each lacing wire is coaxially wrapped on connection column and welded with it solid
It is fixed.
In a kind of preferred embodiment of the present invention, each lacing wire is through flare steel form and by anchoring backing plate and anchor
Fixing bolt is connected with flare steel form.
In a kind of preferred embodiment of the present invention, connection column is cylinder steel pipe.
The beneficial effects of the invention are as follows:The present invention is simple in construction, easy to use, the more traditional branch of the temporary project amount of input
Frame erection scheme is much smaller, saves man-hour, convenient construction, meets safety, quality and construction period;It is by pouring
The pre-buried connection column with lacing wire of concrete layer, it is achieved thereby that being connected to the oblique pull of flare steel form, it efficiently avoid
Conventional stent erection scheme bring it is time-consuming, uneconomical the shortcomings of.
Brief description of the drawings
Fig. 1 is a kind of structural front view of the fixed structure of flare template of the embodiment of the present invention;
Fig. 2 is a kind of structure top view of the fixed structure of flare template of the embodiment of the present invention;
Fig. 3 is a kind of flare steel form of the fixed structure of flare template of the embodiment of the present invention
With lacing wire attachment structure schematic diagram;
Fig. 4 be the embodiment of the present invention a kind of flare template fixed structure concrete layer with
Lacing wire attachment structure schematic diagram.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples
The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only to explain the present invention, not
For limiting the present invention.
From a kind of structural representation of pressure head centering accessory for oil sealing mo(u)ldenpress shown in Figure of description,
A kind of fixed structure of flare template of the present invention includes casting concrete layer 7, and the both sides of casting concrete layer 7 are provided with edge
Its side template being longitudinally arranged and flare steel form 5, side template is connected with flare steel form 5, is set on casting concrete layer 7
There are multiple connection columns 1 longitudinally disposed therealong, each connect coaxially is connected with multiple lacing wires 2 on column 1;The one end of lacing wire 2 with
Casting concrete layer 7 is affixed, and the other end and flare steel form 5 are affixed.It is provided with by each connection column 1 for connecting lacing wire
2 anchoring backing plate 3 and anchor bolt 4;Anchoring backing plate 3 and pre- be embedded in of anchor bolt 4 (connect column 1 in casting concrete layer 7
It can also be embedded in casting concrete layer 7).The Surface mulch of casting concrete layer 7 has bar-mat reinforcement 6.Each lacing wire 2 is same
Axle is wrapped on connection column 1 and is welded and fixed with it, and the both ends of each lacing wire 2 are respectively with flare steel form 5 and having poured mixed
Solidifying soil layer 7 is fixed and at an angle.Each lacing wire 2 through flare steel form 5 and by anchor backing plate 3 and anchor bolt 4 with
Flare steel form 5 connects.Connection column 1 is cylinder steel pipe.
Flare steel form can be directly fixed using the fixed structure of the flare template of the present invention, removes outside support from and sets up
With dismounting process, the duration has been saved, has greatly reduced the expense of temporary project construction.
It should be appreciated that the embodiment of the present invention is these are only, but protection scope of the present invention is not limited to
In this, any those skilled in the art disclosed herein technical scope in, the change that can readily occur in or replace
Change, should all be included within the scope of the present invention.
Claims (6)
1. a kind of fixed structure of flare template, including casting concrete layer (7), the two of the layer of casting concrete (7)
Side is provided with side template longitudinally disposed therealong and flare steel form (5), and the side template connects with the flare steel form (5)
Connect, it is characterised in that:Multiple connection columns (1) longitudinally disposed therealong are provided with the layer of casting concrete (7), it is described
Multiple lacing wires (2) are coaxially connected with each connection column (1);Described lacing wire (2) one end and the layer of casting concrete (7)
Affixed, the other end and the flare steel form (5) are affixed.
A kind of 2. fixed structure of flare template according to claim 1, it is characterised in that:Each connection column
(1) the other anchoring backing plate (3) and anchor bolt (4) being provided with for connecting the lacing wire (2);The anchoring backing plate (3) and institute
Anchor bolt (4) is stated to be embedded in advance in the casting concrete layer (7).
A kind of 3. fixed structure of flare template according to claim 1, it is characterised in that:The casting concrete layer
(7) Surface mulch has bar-mat reinforcement (6).
A kind of 4. fixed structure of flare template according to claim 1, it is characterised in that:Each lacing wire (2) is same
Axle is wrapped on the connection column (1) and is welded and fixed with it.
A kind of 5. fixed structure of flare template according to claim 1, it is characterised in that:Each lacing wire (2) is worn
Cross the flare steel form (5) and be connected by anchoring backing plate (3) and anchor bolt (4) with the flare steel form (5).
A kind of 6. fixed structure of flare template according to claim 1, it is characterised in that:It is described connection column (1) be
Cylinder steel pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710803742.1A CN107460879A (en) | 2017-09-08 | 2017-09-08 | A kind of fixed structure of flare template |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710803742.1A CN107460879A (en) | 2017-09-08 | 2017-09-08 | A kind of fixed structure of flare template |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107460879A true CN107460879A (en) | 2017-12-12 |
Family
ID=60552265
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710803742.1A Pending CN107460879A (en) | 2017-09-08 | 2017-09-08 | A kind of fixed structure of flare template |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107460879A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112051081A (en) * | 2020-09-08 | 2020-12-08 | 安徽工业大学 | Large-cantilever safe intelligent construction system and method for directly guiding construction by experimental data |
CN112065042A (en) * | 2020-09-08 | 2020-12-11 | 安徽工业大学 | Large-cantilever safe and intelligent construction system and method for flow and template displacement control |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104763051A (en) * | 2015-02-12 | 2015-07-08 | 安徽水利开发股份有限公司 | Mass concrete cantilever structure construction method |
CN207314348U (en) * | 2017-09-08 | 2018-05-04 | 中交第二航务工程局有限公司 | A kind of fixed structure of flare template |
-
2017
- 2017-09-08 CN CN201710803742.1A patent/CN107460879A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104763051A (en) * | 2015-02-12 | 2015-07-08 | 安徽水利开发股份有限公司 | Mass concrete cantilever structure construction method |
CN207314348U (en) * | 2017-09-08 | 2018-05-04 | 中交第二航务工程局有限公司 | A kind of fixed structure of flare template |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112051081A (en) * | 2020-09-08 | 2020-12-08 | 安徽工业大学 | Large-cantilever safe intelligent construction system and method for directly guiding construction by experimental data |
CN112065042A (en) * | 2020-09-08 | 2020-12-11 | 安徽工业大学 | Large-cantilever safe and intelligent construction system and method for flow and template displacement control |
CN112065042B (en) * | 2020-09-08 | 2022-03-29 | 安徽工业大学 | Large-cantilever safe and intelligent construction system and method for flow and template displacement control |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207512793U (en) | Buried steel side waterstop fixing device for installing in one kind | |
CN106014446B (en) | A kind of reinforcement means of enhancing high ground stress soft rock stress tunnel inverted arch structural stability | |
CN102605785A (en) | Prestressing pile sealing device for statically pressed piles of anchor bars | |
CN103088842A (en) | Rubble retaining wall reinforced single-face pattern plate support system and construction method | |
CN107460879A (en) | A kind of fixed structure of flare template | |
CN108360814A (en) | The unilateral erecting device of adjustable steel tube and its installation method | |
CN205501843U (en) | Consolidate rigid framed arch bridge | |
CN107313787A (en) | A kind of tunnel lining trolley end mould and construction method | |
CN109944278A (en) | Support construction and rear pouring tape construction method are exempted from a kind of post-cast strip | |
CN108590680A (en) | A kind of construction method that launching shaft foundation pit vertical section pours | |
CN202644531U (en) | Pressure-preloading pile sealing device for static pressure pile of anchor rod | |
CN207314348U (en) | A kind of fixed structure of flare template | |
CN104746434B (en) | Closure segment formwork system without dismantling outer formwork | |
CN207092104U (en) | A kind of steel-pipe pile attachment structure | |
CN109853948A (en) | The integrated template system and mold method of the cast-in-place overhanging windowsill of secondary structure | |
CN207143746U (en) | Support beam template system under concrete support trestle plate | |
CN205976447U (en) | Scaffold frame of connecting with straight screw sleeve links wall spare | |
CN106638679B (en) | A kind of precast concrete pipe gallery connection method | |
CN215052265U (en) | Reinforced concrete thin wall body reinforced structure | |
CN208168339U (en) | The unilateral erecting device of adjustable steel tube | |
CN105196405B (en) | Supporting equipment for bridge precast hollow slab lateral mould and using method of supporting equipment | |
CN207761049U (en) | A kind of assembly concrete frame beam column connection structure | |
CN207277864U (en) | A kind of concrete temporary support moulding bed for large-scale steel structure assembly | |
CN208219724U (en) | A kind of bracing means for preventing diaphram wall from settling | |
CN107299596A (en) | Support beam template system and its construction method under concrete support trestle plate |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20171212 |
|
RJ01 | Rejection of invention patent application after publication |