CN107401125B - Traveling device of mobile trolley and using method - Google Patents
Traveling device of mobile trolley and using method Download PDFInfo
- Publication number
- CN107401125B CN107401125B CN201710660086.4A CN201710660086A CN107401125B CN 107401125 B CN107401125 B CN 107401125B CN 201710660086 A CN201710660086 A CN 201710660086A CN 107401125 B CN107401125 B CN 107401125B
- Authority
- CN
- China
- Prior art keywords
- corrugated steel
- steel web
- hanging basket
- template
- backing plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/30—Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种桥梁施工用装置,尤其涉及一种移动台车的行走装置及使用方法。The invention relates to a bridge construction device, in particular to a traveling device and a using method of a mobile trolley.
背景技术Background technique
波形钢腹板预应力混凝土桥具有抗震性能好、施工简便、经济性较好等一系列优点,随着理论与实际应用的开展,波形钢腹板预应力混凝土箱梁桥越来越受到桥梁工程师的关注。波形钢腹板PC箱梁桥视桥型不同可采用类似PC桥的各种施工方法,如支架现浇施工、移动模架逐孔现浇、预制安装、悬臂浇筑、顶推施工等。对于跨度较大的波形钢腹板PC箱梁桥或桥下立支架有困难的环境,通常采用悬臂施工方法施工。Prestressed concrete bridges with corrugated steel webs have a series of advantages such as good seismic performance, simple construction, and good economy. With the development of theory and practical applications, prestressed concrete box girder bridges with corrugated steel webs are more and more popular among bridge engineers. s concern. Corrugated steel web PC box girder bridges can adopt various construction methods similar to PC bridges depending on the bridge type, such as support cast-in-place construction, mobile formwork cast-in-place hole by hole, prefabricated installation, cantilever pouring, jacking construction, etc. For PC box girder bridges with corrugated steel webs with large spans or environments where the vertical support under the bridge is difficult, the cantilever construction method is usually used for construction.
为克服传统悬臂施工法挂篮拼装繁琐、稳定性不足、施工周期长等缺点,SCC自承重施工法应运而生。该施工方法利用波形钢腹板作为挂篮的承重结构,大幅度减轻了挂篮自重,提高了稳定性,并且缩短了施工周期。但该施工方法最大的局限性在于仅适用于波形钢腹板连接件采用双开孔连接件的情况。当波形钢腹板采用其他的连接件时,该施工方法就无法采用。In order to overcome the shortcomings of the traditional cantilever construction method such as cumbersome assembly of hanging baskets, insufficient stability, and long construction period, the SCC self-supporting construction method came into being. The construction method uses corrugated steel webs as the load-bearing structure of the hanging basket, which greatly reduces the dead weight of the hanging basket, improves stability, and shortens the construction period. However, the biggest limitation of this construction method is that it is only applicable to the case where the corrugated steel web connectors use double-hole connectors. When other connectors are used for the corrugated steel web, this construction method cannot be used.
有鉴于上述的SCC自承重方法存在的局限性,故而提供一种简化施工步骤、适用范围广的移动台车的行走装置具有很大的实际意义。In view of the limitations of the above-mentioned SCC self-supporting method, it is of great practical significance to provide a traveling device for a mobile trolley that simplifies the construction steps and has a wide application range.
发明内容Contents of the invention
本发明的主要目的在于,克服现有的挂篮存在的缺陷,而提供一种移动台车的行走装置及使用方法,减轻重量,提高稳定性,从而更加适于实用,且具有产业上的利用价值。The main purpose of the present invention is to overcome the defects of the existing hanging baskets, and provide a traveling device and using method of the mobile trolley, which reduces weight and improves stability, so that it is more suitable for practical use and has industrial application. value.
本发明的目的及解决其技术问题是采用以下技术方案来实现的。依据本发明提出的移动台车的行走装置,由主桁架、挂篮提升部、行走部、模板部和锚固部组成,The purpose of the present invention and the solution to its technical problems are achieved by adopting the following technical solutions. According to the walking device of the mobile trolley proposed by the present invention, it is composed of a main truss, a hanging basket lifting part, a walking part, a template part and an anchoring part,
所述主桁架实现移动挂篮的固定,所述主桁架连接所述挂篮提升部的顶部,所述挂篮提升部底部连接有模板部、通过行走部实现移动挂篮的移动,所述行走部固定在所述锚固部上。The main truss realizes the fixing of the mobile hanging basket. The main truss is connected to the top of the lifting part of the hanging basket. The part is fixed on the anchor part.
前述的移动台车的行走装置,所述主桁架由上横梁、纵梁和挂篮支腿组成;In the aforementioned traveling device of the mobile trolley, the main truss is composed of upper beams, longitudinal beams and legs of the hanging basket;
所述纵梁设置在所述上横梁下方,所述纵梁与所述上横梁互相垂直设置、并相固定;The longitudinal beam is arranged under the upper beam, and the longitudinal beam and the upper beam are vertically arranged and fixed;
所述纵梁和挂篮支腿相固定连接。The longitudinal beam is fixedly connected with the legs of the hanging basket.
前述的移动台车的行走装置,所述挂篮提升部为吊杆,所述吊杆为多根,所述吊杆底部连接所述模板部,在所述吊杆与所述模板部的连接位置处设置相同和/或不同规格的千斤顶。In the aforementioned traveling device of the mobile trolley, the lifting part of the hanging basket is a suspension rod, and there are multiple suspension rods, and the bottom of the suspension rod is connected to the template part, and the connection between the suspension rod and the template part Jacks of the same and/or different specifications are set at the positions.
前述的移动台车的行走装置,所述锚固部为垫板,所述垫板锚固在所述波形钢腹板上翼缘钢板上。In the aforementioned traveling device of the mobile trolley, the anchoring part is a backing plate, and the backing plate is anchored on the flange steel plate on the corrugated steel web.
前述的移动台车的行走装置,所述行走部由轨道组成,所述轨道锚固在所述垫板上。In the aforementioned running device of the mobile trolley, the running part is composed of rails, and the rails are anchored on the backing plate.
前述的移动台车的行走装置,所述垫板为Π型垫板。In the aforementioned traveling device of the mobile trolley, the backing plate is a Π-shaped backing plate.
前述的移动台车的行走装置,所述轨道为工字形钢梁。In the aforementioned traveling device of the mobile trolley, the track is an I-shaped steel beam.
前述的移动台车的行走装置,所述模板部设置在波形钢腹板的下方,包括底模板以及设置在所述底模板两侧的侧模。In the aforementioned traveling device of the mobile trolley, the formwork part is arranged under the corrugated steel web, and includes a bottom formwork and side forms arranged on both sides of the bottom formwork.
前述的移动台车的行走装置,还包括有工作平台,所述工作平台底部与所述挂篮提升部下端相连接,并设置于所述模板部的两侧,在所述工作平台的外侧分别设置有防撞护栏。The aforementioned traveling device of the mobile trolley also includes a working platform, the bottom of the working platform is connected to the lower end of the lifting part of the hanging basket, and is arranged on both sides of the template part, and the outer sides of the working platform are respectively Equipped with crash barriers.
前述的移动台车的行走装置,所述波形钢腹板包括左波形钢腹板和右波形钢腹板,在所述左波形钢腹板和右波形钢腹板之间设置有临时支撑横梁。In the traveling device of the aforementioned mobile trolley, the corrugated steel web includes a left corrugated steel web and a right corrugated steel web, and a temporary support beam is arranged between the left corrugated steel web and the right corrugated steel web.
前述移动台车的行走装置使用方法,包括如下步骤,The method for using the running device of the aforementioned mobile trolley comprises the following steps,
1)进行桥墩和零号块的施工,零号块和(N-0)节段波形钢腹板施工完成以后,吊装(N-1) 节段波形钢腹板,波形钢腹板节段与节段之间通过高强度螺栓连接在一起。两侧波形钢腹板(9)横向之间设置有横向支撑(10);1) Carry out the construction of the bridge pier and No. 0 block. After the construction of the No. 0 block and (N-0) section corrugated steel web is completed, hoist the (N-1) section corrugated steel web, and the corrugated steel web section and The segments are connected together by high-strength bolts. Horizontal supports (10) are provided between the corrugated steel webs (9) on both sides;
2)在(N-1)波形钢腹板上翼缘钢板(5)上锚固Π型垫板(7),在垫板(7)上锚固工字形轨道(6),将挂篮安装在轨道(6),布置底模板(12)和侧模(11),将(N-1)节段波形钢腹板底板中的钢筋与波形钢腹板抗剪连接件固定在一起,浇筑(N-1)节段底板混凝土并进行养护;2) Anchor the Π-shaped backing plate (7) on the flange steel plate (5) on the corrugated steel web (N-1), anchor the I-shaped track (6) on the backing plate (7), and install the hanging basket on the track (6), arrange the bottom formwork (12) and side formwork (11), fix the steel bars in the (N-1) section corrugated steel web bottom plate and the corrugated steel web shear connectors together, pour (N- 1) Segment floor concrete and maintenance;
3)在制作(N-1)节段混凝土底板的同时,安装(N-2)节段波形钢腹板;3) Install (N-2) segmental corrugated steel web while making (N-1) segmental concrete floor;
4)待(N-1)节段波形钢腹板底板混凝土达到设计强度要求之后,拆除底模板(12),在(N-2)节段波形钢腹板上翼缘钢板(5)上锚固Π型垫板(7)和工字形轨道(6),挂篮前移后,拆除(N-1)节段波形钢腹板上翼缘钢板(5)上的Π型垫板(7)和工字形轨道(6),同步施工(N-1)节段波形钢腹板混凝土顶板和(N-2)节段波形钢腹板混凝土底板;4) After the concrete of the corrugated steel web bottom slab of the (N-1) segment reaches the design strength requirements, the bottom formwork (12) is removed, and the flange steel plate (5) on the corrugated steel web of the (N-2) segment is anchored Π-shaped backing plate (7) and I-shaped track (6), after the hanging basket moves forward, remove the Π-shaped backing plate (7) and I-shaped track (6), simultaneous construction of (N-1) segmental corrugated steel web concrete top slab and (N-2) segmental corrugated steel web concrete bottom slab;
5)待(N-1)节段波形钢腹板顶板混凝土和(N-2)节段波形钢腹板底板混凝土达到设计强度要求后,拆除(N-1)节段波形钢腹板顶板和(N-2)节段波形钢腹板底板模板,拆除(N-1) 节段波形钢腹板横向支撑和(N-2)节段波形钢腹板横向支撑,分别张拉(N-1) 节段波形钢腹板顶板预应力钢筋和(N-2)节段波形钢腹板底板预应力钢筋,压浆;与此同时安装(N-3)节段波形钢腹板;5) After the (N-1) section corrugated steel web top slab concrete and (N-2) section (N-2) section corrugated steel web bottom slab concrete meet the design strength requirements, remove the (N-1) section corrugated steel web top slab and (N-2) Segmental corrugated steel web bottom slab formwork, remove (N-1) segmental corrugated steel web lateral support and (N-2) segmental corrugated steel web lateral support, respectively tension (N-1 ) Segmental corrugated steel web top plate prestressed reinforcement and (N-2) segmental corrugated steel web bottom plate prestressed reinforcement, grouting; at the same time install (N-3) segmental corrugated steel web;
6)挂篮前移,按照以上顺序循环施工,直到完成。6) The hanging basket moves forward, and the construction is repeated in the above sequence until it is completed.
借由上述技术方案,本发明的移动台车的行走装置及使用方法至少具有下列优点:By means of the above-mentioned technical solution, the traveling device and the use method of the mobile trolley of the present invention have at least the following advantages:
本发明提出的移动台车的行走装置及使用方法,由主桁架、挂篮提升部、行走部、模板部和锚固部组成,模板部不包括顶板模板和翼缘板模板,减轻了移动台车自身的重量,提供了工作稳定性和安全性;在左波形钢腹板和右波形钢腹板之间设置有临时支撑横梁,以保证波形钢腹板具有足够的横向和纵向刚度;防撞护栏的设置保证挂篮使用过程的安全性。该移动挂篮克服了SCC自承重施工法移动挂篮的局限性,可以适用于任意波形钢腹板预应力桥梁中,增加了实用性,扩大了适用范围。The traveling device and using method of the mobile trolley proposed by the present invention are composed of a main truss, a hanging basket lifting part, a walking part, a formwork part and an anchoring part. Its own weight provides working stability and safety; a temporary support beam is set between the left corrugated steel web and the right corrugated steel web to ensure that the corrugated steel web has sufficient transverse and longitudinal rigidity; anti-collision guardrail The settings ensure the safety of the hanging basket during use. The mobile hanging basket overcomes the limitation of the mobile hanging basket of the SCC self-supporting construction method, and can be applied to prestressed bridges with arbitrary corrugated steel webs, which increases practicability and expands the scope of application.
上述说明仅是本发明技术方案的概述,为了能够更清楚了解本发明的技术手段,并可依照说明书的内容予以实施,以下以本发明的较佳实施例详细说明如后。The above description is only an overview of the technical solutions of the present invention. In order to understand the technical means of the present invention more clearly and implement them according to the contents of the description, the preferred embodiments of the present invention will be described in detail below.
附图说明Description of drawings
图1为本发明移动台车的行走装置的横截面结构示意图;Fig. 1 is the cross-sectional structure schematic diagram of the walking device of mobile trolley of the present invention;
图2为本发明移动台车的行走装置的左视图;Fig. 2 is the left side view of the traveling device of mobile trolley of the present invention;
图中标记含义:1.上横梁,2.吊杆,3.纵梁,4.挂篮支腿,5.波形钢腹板上翼缘钢板,6.轨道,7.垫板,8.栓钉,9.波形钢腹板,10.临时支撑横梁,11.侧模,12.底模板,13.防撞护栏,14.工作平台,15.反扣轮。Meanings of marks in the figure: 1. Upper beam, 2. Suspension rod, 3. Longitudinal beam, 4. Hanging basket leg, 5. Flange steel plate on corrugated steel web, 6. Track, 7. Backing plate, 8. Bolt Nails, 9. Corrugated steel webs, 10. Temporary support beams, 11. Side forms, 12. Bottom formwork, 13. Anti-collision barriers, 14. Working platforms, 15. Buckle wheels.
具体实施方式detailed description
为更进一步阐述本发明为达成预定发明目的所采取的技术手段及功效,对依据本发明提出的移动台车的行走装置及使用方法其具体实施方式、特征及其功效,详细说明如后。In order to further elaborate the technical means and effects adopted by the present invention to achieve the intended purpose of the invention, the specific implementation, features and effects of the traveling device and method of use of the mobile trolley proposed according to the present invention are described in detail below.
实施例1Example 1
如图1~2所示,本发明的移动台车的行走装置,由主桁架、挂篮提升部、行走部、模板部和锚固部组成,主桁架实现移动挂篮的固定,主桁架连接在挂篮提升部的顶部,挂篮提升部底部连接有模板部、通过行走部实现移动挂篮的移动,行走部固定在锚固部上。As shown in Figures 1 to 2, the running device of the mobile trolley of the present invention is composed of a main truss, a hanging basket lifting part, a walking part, a template part and an anchoring part, the main truss realizes the fixing of the mobile hanging basket, and the main truss is connected to the The top of the lifting part of the hanging basket and the bottom of the lifting part of the hanging basket are connected with a template part, and the movement of the mobile hanging basket is realized through the walking part, and the walking part is fixed on the anchoring part.
其中主桁架由上横梁1、纵梁3和挂篮支腿4组成,纵梁3设置在上横梁1下方,纵梁3与上横梁1互相垂直设置、并相固定,上横梁1和纵梁3两者之间通过焊接来连接;纵梁3和挂篮支腿4相固定连接。挂篮支腿4设置在纵梁3和轨道6之间,挂篮支腿4和纵梁3之间以焊接的方式来连接,挂篮支腿4和轨道6之间用反扣轮15来连接,挂篮支腿起到支撑整体挂篮结构的作用。Wherein the main truss is composed of the upper beam 1, the longitudinal beam 3 and the hanging basket leg 4, the longitudinal beam 3 is set under the upper beam 1, the longitudinal beam 3 and the upper beam 1 are mutually vertically arranged and fixed, the upper beam 1 and the longitudinal beam 3. The two are connected by welding; the longitudinal beam 3 is fixedly connected with the legs 4 of the hanging basket. The hanging basket leg 4 is arranged between the longitudinal beam 3 and the
挂篮提升部为吊杆2,吊杆2为多根,吊杆2底部连接模板部,在吊杆2与模板部的连接位置处设置相同和/或不同规格的千斤顶, 在每个吊点处根据受力大小设置不同规格的千斤顶,以便及时快速地调整底部模板标高,提高生产效率,缩短施工周期。The lifting part of the hanging basket is a
锚固部为Π型垫板7,垫板7锚固在波形钢腹板上翼缘钢板5上,波形钢腹板上翼缘钢板5之上连接了栓钉8,为挂篮行走轨道6提供平台。行走部由轨道6组成,轨道6为工字形钢梁,轨道6锚固在垫板7上。The anchoring part is a Π-shaped
模板部设置在波形钢腹板9的下方,包括底模板12以及设置在底模板12两侧的侧模11,工作平台14底部与挂篮提升部下端相连接,并设置于模板部的两侧,在工作平台14的外侧分别设置有防撞护栏13。The formwork part is set under the
波形钢腹板9包括左波形钢腹板和右波形钢腹板,在左波形钢腹板和右波形钢腹板之间设置有临时支撑横梁10,以保证波形钢腹板具有足够的横向和纵向刚度。The
本发明移动台车的行走装置使用方法包括如下步骤:The method for using the running device of the mobile trolley of the present invention comprises the following steps:
首先进行桥墩和零号块的施工,零号块和(N-0)节段波形钢腹板同时施工;桥墩和零号块施工完成以后,吊装(N-1) 节段波形钢腹板,波形钢腹板节段与节段之间通过高强度螺栓连接在一起,波形钢腹板横向之间设置有横向支撑10,以保证其稳定性;First of all, the construction of the bridge pier and the zero block is carried out, and the zero block and the (N-0) section corrugated steel web are constructed simultaneously; after the construction of the bridge pier and the zero block is completed, the (N-1) section corrugated steel web is lifted, Corrugated steel web segments are connected together by high-strength bolts, and
以波形钢腹板为承重结构,在波形钢腹板上翼缘钢板上锚固Π型垫板7,在垫板7上锚固工字形轨道6,将本新型移动挂篮安装在轨道6上。挂篮安装完成之后,利用挂篮的底模部进行(N-1)节段底板的制作工序,布置底模板12和侧模11,将(N-1)节段底板中的钢筋与波形钢腹板抗剪连接件绑扎或焊接在一起,浇筑(N-1)节段底板混凝土并进行养护;Take the corrugated steel web as the load-bearing structure, anchor the Π-shaped
在制作(N-1)节段混凝土底板的同时,吊装(N-2)节段的波形钢腹板,波形钢腹板节段与节段之间通过高强度螺栓连接在一起,波形钢腹板横向之间设置有横向支撑,以保证其稳定性;While making the concrete floor of the (N-1) section, hoist the corrugated steel web of the (N-2) section, the corrugated steel web sections are connected by high-strength bolts, and the corrugated steel web Horizontal supports are set between the plates to ensure their stability;
待(N-1)节段波形钢腹板底板混凝土达到设计强度要求之后,拆除底模板12,在(N-2)节段波形钢腹板上翼缘钢板5上锚固Π型垫板7和工字形轨道6,挂篮前移后,拆除(N-1)节段波形钢腹板上翼缘钢板5上的Π型垫板7和工字形轨道6,同步施工(N-1)节段波形钢腹板混凝土顶板和(N-2)节段波形钢腹板混凝土底板;After the concrete of the corrugated steel web bottom slab of section (N-1) reaches the design strength requirement, the
待(N-1)节段顶板混凝土和(N-2)节段底板混凝土达到设计强度要求后,拆除(N-1)节段顶板和(N-2)节段底板模板,拆除(N-1)、(N-2)节段波形钢腹板临时支架,分别张拉(N-1)顶板、(N-2)节段底板预应力钢筋,压浆;与此同时安装(N-3)节段波形钢腹板,按照以上顺序循环施工。After the (N-1) section top slab concrete and (N-2) section bottom slab concrete meet the design strength requirements, the (N-1) section top slab and (N-2) section bottom slab formwork are removed, and the (N-2) section bottom slab formwork is removed. 1), (N-2) segmental corrugated steel web temporary support, tensioning (N-1) top plate, (N-2) segmental bottom plate prestressed reinforcement respectively, and grouting; at the same time install (N-3 ) Segmental corrugated steel webs shall be constructed cyclically in accordance with the above sequence.
本发明提出的移动台车的行走装置,模板部不包括顶板模板和翼缘板模板,减轻了移动挂篮自身的重量,提供了工作稳定性和安全性;在左波形钢腹板和右波形钢腹板之间设置有临时支撑横梁,以保证波形钢腹板具有足够的横向和纵向刚度;防撞护栏的设置保证挂篮使用过程的安全性。克服了SCC自承重施工法移动挂篮的局限性,可以适用于任意波形钢腹板预应力桥梁中,增加了实用性,扩大了适用范围。In the walking device of the mobile trolley proposed by the present invention, the formwork part does not include the top plate formwork and the flange plate formwork, which reduces the weight of the mobile hanging basket itself and provides work stability and safety; the left corrugated steel web and the right corrugated Temporary support beams are set between the steel webs to ensure that the corrugated steel webs have sufficient transverse and longitudinal rigidity; the setting of anti-collision guardrails ensures the safety of the hanging basket during use. It overcomes the limitations of the mobile hanging basket of the SCC self-supporting construction method, and can be applied to prestressed bridges with arbitrary corrugated steel webs, which increases the practicality and expands the scope of application.
以上所述,仅是本发明的较佳实施例而已,并非对本发明作任何形式上的限制,虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明,任何熟悉本专业的技术人员,在不脱离本发明技术方案范围内,当可利用上述揭示的技术内容做出些许更动或修饰为等同变化的等效实施例,但凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所作的任何简单修改、等同变化与修饰,均仍属于本发明技术方案的范围内。The above description is only a preferred embodiment of the present invention, and does not limit the present invention in any form. Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. Anyone familiar with this field Those skilled in the art, without departing from the scope of the technical solution of the present invention, may use the technical content disclosed above to make some changes or modify them into equivalent embodiments with equivalent changes. Technical Essence of the Invention Any simple modifications, equivalent changes and modifications made to the above embodiments still fall within the scope of the technical solutions of the present invention.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710660086.4A CN107401125B (en) | 2017-08-04 | 2017-08-04 | Traveling device of mobile trolley and using method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710660086.4A CN107401125B (en) | 2017-08-04 | 2017-08-04 | Traveling device of mobile trolley and using method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN107401125A CN107401125A (en) | 2017-11-28 |
| CN107401125B true CN107401125B (en) | 2022-12-09 |
Family
ID=60402687
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710660086.4A Active CN107401125B (en) | 2017-08-04 | 2017-08-04 | Traveling device of mobile trolley and using method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107401125B (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108589558B (en) * | 2018-02-09 | 2020-04-10 | 安庆中巨机电科技有限公司 | Viaduct outer wall facility maintenance support |
| CN110184889A (en) * | 2019-06-19 | 2019-08-30 | 苏交科集团股份有限公司 | Composite structure bridge with corrugated web bearing construction load and erection method thereof |
| CN110593107B (en) * | 2019-09-23 | 2024-02-06 | 中国建筑股份有限公司 | Movable cantilever hanging basket for steel box girder construction and construction method |
| CN111455873A (en) * | 2020-04-10 | 2020-07-28 | 中铁十一局集团第二工程有限公司 | Suspension system of hanging basket |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006022595A (en) * | 2004-07-09 | 2006-01-26 | Taisei Corp | Main girder construction, main girder structure for box girder bridge construction, and box girder bridge construction method |
| CN201665823U (en) * | 2009-12-04 | 2010-12-08 | 中国第一冶金建设有限责任公司 | Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail |
| CN205062678U (en) * | 2015-10-09 | 2016-03-02 | 中交第二航务工程局有限公司 | Be applied to construction of case roof beam of wave form steel web structure and hang basket |
| CN105421249A (en) * | 2015-12-15 | 2016-03-23 | 中铁十四局集团第二工程有限公司 | Novel dragging- hoisting combined type hanging basket structure and construction method |
| CN205116038U (en) * | 2015-11-18 | 2016-03-30 | 四川路桥桥梁工程有限责任公司 | Basket is hung to wave form steel web bearing formula |
| CN105625195A (en) * | 2016-03-16 | 2016-06-01 | 河南大建桥梁钢构股份有限公司 | Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket |
| CN105804385A (en) * | 2016-04-15 | 2016-07-27 | 中铁五局集团有限公司 | Hollow type walking track structure for hanging basket |
| CN207244447U (en) * | 2017-08-04 | 2018-04-17 | 苏交科集团股份有限公司 | Movable hanging basket for steel-concrete composite bridge |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4003473A (en) * | 1974-08-30 | 1977-01-18 | Ryan Ramp, Inc. | Combined marine ramp transfer and mooring system |
| CN204940123U (en) * | 2015-08-24 | 2016-01-06 | 中铁六局集团有限公司 | Construction operation coaster below continuous beam frange plate |
| CN206070393U (en) * | 2016-09-20 | 2017-04-05 | 中交武汉港湾工程设计研究院有限公司 | A kind of asynchronous construction hanging basket of Wavelike steel webplate composite beam bridge |
| CN106758872A (en) * | 2017-02-22 | 2017-05-31 | 河南大建桥梁钢构股份有限公司 | Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution |
-
2017
- 2017-08-04 CN CN201710660086.4A patent/CN107401125B/en active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006022595A (en) * | 2004-07-09 | 2006-01-26 | Taisei Corp | Main girder construction, main girder structure for box girder bridge construction, and box girder bridge construction method |
| CN201665823U (en) * | 2009-12-04 | 2010-12-08 | 中国第一冶金建设有限责任公司 | Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail |
| CN205062678U (en) * | 2015-10-09 | 2016-03-02 | 中交第二航务工程局有限公司 | Be applied to construction of case roof beam of wave form steel web structure and hang basket |
| CN205116038U (en) * | 2015-11-18 | 2016-03-30 | 四川路桥桥梁工程有限责任公司 | Basket is hung to wave form steel web bearing formula |
| CN105421249A (en) * | 2015-12-15 | 2016-03-23 | 中铁十四局集团第二工程有限公司 | Novel dragging- hoisting combined type hanging basket structure and construction method |
| CN105625195A (en) * | 2016-03-16 | 2016-06-01 | 河南大建桥梁钢构股份有限公司 | Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket |
| CN105804385A (en) * | 2016-04-15 | 2016-07-27 | 中铁五局集团有限公司 | Hollow type walking track structure for hanging basket |
| CN207244447U (en) * | 2017-08-04 | 2018-04-17 | 苏交科集团股份有限公司 | Movable hanging basket for steel-concrete composite bridge |
Non-Patent Citations (4)
| Title |
|---|
| 大跨度波形钢腹板PC组合连续梁悬臂作业桁车设计;贺茂生等;《现代交通技术》;20101026(第05期);全文 * |
| 波形钢腹板承重式挂篮施工技术在波形钢腹板PC箱梁桥中的应用;郭勇;《工程建设与设计》;20170130(第02期);全文 * |
| 浅谈采用菱形挂篮对称悬臂浇注施工方法;钟威;《城市道桥与防洪》;20070315(第02期);全文 * |
| 错位法施工在波形钢腹板预应力混凝土箱梁桥中的应用;颉明军;《铁道建筑》;20170420(第04期);全文 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN107401125A (en) | 2017-11-28 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105625195B (en) | Wave forms steel web SCC engineering methods movable hanging basket and its construction method | |
| JP7429940B2 (en) | Construction method of steel concrete main girder of cable-stayed bridge | |
| CN207244447U (en) | Movable hanging basket for steel-concrete composite bridge | |
| KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
| CN105803947B (en) | A kind of cast-in-situ box girder gate-type full framing whole lateral moving system and method for traversing | |
| CN102704406B (en) | Roadbed slab non-tensile stress construction method based on combined channel girder | |
| CN103410101B (en) | Tower crane conversion method for construction of parabola-shaped ultrahigh pier | |
| CN105155428B (en) | Across railway in operation large-scale prefabricated PC concrete continuous T beam construction method | |
| CN109267490B (en) | A kind of long guide beam type mobile formwork and construction method thereof | |
| CN107401125B (en) | Traveling device of mobile trolley and using method | |
| CN203174515U (en) | Self-propelled dual-running track triangular hanging basket | |
| CN205257790U (en) | Fixed high -low leg handle portal crane | |
| CN102659027B (en) | Variable-span transit method for girder-erecting gantry crane | |
| CN203795315U (en) | High pier cable-stayed bridge No.0 block non-bracket construction structure | |
| CN112726411B (en) | Integral dragging construction method for single-hole large cantilever steel truss girder | |
| CN110453614A (en) | Self-lifting corrugated steel web cast-in-place box girder hanging basket | |
| CN211596455U (en) | A kind of fast construction hanging basket for double-layer flange concrete box girder bridge | |
| CN116397555A (en) | A construction method for cast-in-place box girders of cable-stayed bridges | |
| CN111851307A (en) | Construction method of large-span prefabricated corrugated web composite box girder transport frame | |
| CN207749417U (en) | A Concrete Tower Column Inner Mold Stiffness Skeleton | |
| CN222990595U (en) | Multifunctional portal for suspension bridge construction | |
| CN110983985B (en) | Double-layer flange plate box-type concrete structure construction hanging basket and construction method thereof | |
| CN205382425U (en) | Railway T type bridge adds builds sound barrier beam mold plate girder unwheeling | |
| CN105088962B (en) | A kind of integral hoisting method of Wavelike steel webplate part | |
| CN205711780U (en) | Wave forms steel web SCC engineering method movable hanging basket |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |