CN107401125A CN201710660086.4A CN201710660086A CN107401125A CN 107401125 A CN107401125 A CN 107401125A CN 201710660086 A CN201710660086 A CN 201710660086A CN 107401125 A CN107401125 A CN 107401125A
Authority
CN
China
Prior art keywords
wavelike steel
steel webplate
section
hanging basket
running gear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710660086.4A
Other languages
Chinese (zh)
Other versions
CN107401125B (en
Inventor
张建东
刘朵
徐剑
李明
高子健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Tech University
JSTI Group Co Ltd
Original Assignee
Nanjing Tech University
JSTI Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Tech University, JSTI Group Co Ltd filed Critical Nanjing Tech University
Priority to CN201710660086.4A priority Critical patent/CN107401125B/en
Publication of CN107401125A publication Critical patent/CN107401125A/en
Application granted granted Critical
Publication of CN107401125B publication Critical patent/CN107401125B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention discloses a kind of mobile trolley used running gear and application method, it is made up of main couple, Hanging Basket lifting parts, running part, template portion and anchoring section, the main couple realizes the fixation of movable hanging basket, the main couple connects the top of the Hanging Basket lifting parts, the Hanging Basket lifting parts bottom is connected with template portion, the movement of movable hanging basket is realized by running part, and the running part is fixed on the anchoring section.Mobile trolley used running gear template portion proposed by the present invention does not include roof plate template and flange plate template, alleviates the weight of movable hanging basket itself, there is provided job stability and security;Temporary support crossbeam is provided between left Wavelike steel webplate and right Wavelike steel webplate, to ensure that Wavelike steel webplate has enough horizontal and vertical rigidity;The setting of anticollision barrier ensures that Hanging Basket uses the security of process.The movable hanging basket overcomes the limitation of SCC self-supporting construction method movable hanging baskets, goes in random waveform steel web pre-stressed bridge, adds practicality, expand the scope of application.

Description

A kind of mobile trolley used running gear and application method
Technical field
The present invention relates to a kind of bridge construction device, more particularly to a kind of mobile trolley used running gear and application method.
Background technology
Wavelike steel webplate prestressed concrete bridge has good anti-seismic performance, easy construction, better economy etc. a series of excellent Point, with the theoretical development with practical application, Wavelike steel webplate prestressed concrete box-beam bridge is increasingly by science of bridge building teacher Concern.Prestressed Concrete Box-Girder Bridges with Corrugated Steel Webs can use the various construction methods of similar PC bridges depending on bridge type difference, as support cast-in-place is applied Work, mobile formwork be hole-specifically cast-in-place, prefabricated installation, cantilever pouring, incremental launching construction etc..For the Wavelike steel webplate PC casees that span is larger The environment that staking is had any problem under beam bridge or bridge, the construction of generally use Cantilever Construction Method.
To overcome the shortcomings of traditional cantilever-construction cradle assembly is cumbersome, stability is insufficient, long construction period, SCC self-supportings Heavy dressing engineering method is arisen at the historic moment.Load-carrying members of the construction method by the use of Wavelike steel webplate as Hanging Basket, are greatly reduced Hanging Basket Deadweight, improves stability, and shorten construction period.But maximum being limited in that of the construction method is only applicable to waveform Steel web connecting members use the situation of Double Opening connector.When Wavelike steel webplate uses other connectors, the construction method It can not just use.
In view of limitation existing for above-mentioned SCC self-supporting weighing methods, so a kind of simplified construction procedure is provided, is applicable model Wide mobile trolley used running gear is enclosed to have a great deal of practical meanings.
The content of the invention
It is a primary object of the present invention to, the defects of overcoming existing Hanging Basket to exist, and a kind of mobile trolley used row is provided Walking apparatus and application method, mitigate weight, improve stability, thus more suitable for practicality, and with the value in industry.
The object of the invention to solve the technical problems is realized using following technical scheme.Itd is proposed according to the present invention Mobile trolley used running gear, be made up of main couple, Hanging Basket lifting parts, running part, template portion and anchoring section,
The main couple realizes the fixation of movable hanging basket, and the main couple connects the top of the Hanging Basket lifting parts, the Hanging Basket Lifting parts bottom is connected with template portion, the movement of movable hanging basket is realized by running part, and the running part is fixed on the anchoring In portion.
Foregoing mobile trolley used running gear, the main couple are made up of entablature, longeron and Hanging Basket supporting leg;
The longeron is arranged on below the entablature, and longeron setting orthogonal with the entablature is simultaneously mutually fixed;
The longeron is mutually fixedly connected with Hanging Basket supporting leg.
Foregoing mobile trolley used running gear, the Hanging Basket lifting parts are suspension rod, and the suspension rod is more, the suspension rod Bottom connects the template portion, and at the link position in the suspension rod with the template portion setting is identical and/or different size Jack.
Foregoing mobile trolley used running gear, the anchoring section are backing plate, and the backing plate is anchored at the waveform steel abdomen On the steel plate of plate top flange.
Foregoing mobile trolley used running gear, the running part are made up of track, and the track is anchored at the backing plate On.
Foregoing mobile trolley used running gear, the backing plate are Π type backing plates.
Foregoing mobile trolley used running gear, the track are i section steel beam.
Foregoing mobile trolley used running gear, the template portion are arranged on the lower section of Wavelike steel webplate, including end template And it is arranged on the side form of the end template both sides.
Foregoing mobile trolley used running gear, also include workbench, the workbench bottom and the Hanging Basket Lifting parts lower end is connected, and is arranged at the both sides in the template portion, and anticollision is respectively arranged with the outside of the workbench Guardrail.
Foregoing mobile trolley used running gear, the Wavelike steel webplate include left Wavelike steel webplate and right waveform steel abdomen Plate, temporary support crossbeam is provided between the left Wavelike steel webplate and right Wavelike steel webplate.
Foregoing mobile trolley used running gear application method, comprises the following steps,
1)The construction of bridge pier and No. zero block is carried out, after No. zero block and the construction of (N-0) section Wavelike steel webplate are completed, lifts (N- 1) section Wavelike steel webplate, Wavelike steel webplate section between section by high strength exploitation together with.Two side waveform steel Web(9)Cross-brace is provided between transverse direction(10);
2)In (N-1) Wavelike steel webplate top flange steel plate(5)Upper anchoring Π type backing plates(7), in backing plate(7)The upper I-shaped rail of anchoring Road(6), Hanging Basket is arranged on track(6), arrange end template(12)And side form(11), by (N-1) section Wavelike steel webplate bottom plate In reinforcing bar be fixed together with Wavelike steel webplate shear connector, pour (N-1) section underplate concrete and conserved;
3)While (N-1) section concrete floor is made, (N-2) section Wavelike steel webplate is installed;
4)After treating that (N-1) section Wavelike steel webplate underplate concrete reaches design strength requirement, end template is removed(12), (N-2) section Wavelike steel webplate top flange steel plate(5)Upper anchoring Π type backing plates(7)With I-shaped track(6), after hanging basket advancing, Remove (N-1) section Wavelike steel webplate top flange steel plate(5)On Π type backing plates(7)With I-shaped track(6), synchronous construction (N-1) section Wavelike steel webplate concrete roof and (N-2) section Wavelike steel webplate concrete floor;
5)Treat that (N-1) section Wavelike steel webplate concrete roof and (N-2) section Wavelike steel webplate underplate concrete reach design After intensity requirement, (N-1) section Wavelike steel webplate top plate and (N-2) section Wavelike steel webplate bottom plate are removed, is removed (N-1) Section Wavelike steel webplate cross-brace and (N-2) section Wavelike steel webplate cross-brace, difference tensioning (N-1) section waveform steel Web top plate deformed bar and (N-2) section Wavelike steel webplate baseboard prestress reinforcing bar, mud jacking;At the same time (N-3 is installed) Section Wavelike steel webplate;
6)Hanging basket advancing, circulate and construct according to sequence described above, until completing.
By above-mentioned technical proposal, mobile trolley used running gear of the invention and application method are at least with following excellent Point:
Mobile trolley used running gear proposed by the present invention and application method, by main couple, Hanging Basket lifting parts, running part, template Portion and anchoring section composition, template portion do not include roof plate template and flange plate template, alleviate the mobile trolley used weight of itself, there is provided Job stability and security;Temporary support crossbeam is provided between left Wavelike steel webplate and right Wavelike steel webplate, to protect Demonstrate,proving Wavelike steel webplate has enough horizontal and vertical rigidity;The setting of anticollision barrier ensures that Hanging Basket uses the security of process. The movable hanging basket overcomes the limitation of SCC self-supporting construction method movable hanging baskets, goes for random waveform steel web and in advance should In power bridge, practicality is added, expands the scope of application.
Described above is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, And can be practiced according to the content of specification, described in detail below with presently preferred embodiments of the present invention as after.
Brief description of the drawings
Fig. 1 is the cross-sectional structure schematic diagram of the mobile trolley used running gear of the present invention;
Fig. 2 is the left view of the mobile trolley used running gear of the present invention;
Mark meaning in figure:1. entablature, 2. suspension rods, 3. longerons, 4. Hanging Basket supporting legs, 5. Wavelike steel webplate top flange steel plates, 6. Track, 7. backing plates, 8. pegs, 9. Wavelike steel webplates, 10. temporary support crossbeams, 11. side forms, 12. end templates, 13. anticollisions shield Column, 14. workbenches, 15. inverse buckling wheels.
Embodiment
Further to illustrate the present invention to reach the technological means and effect that predetermined goal of the invention is taken, to according to this The mobile trolley used running gear proposed and application method its embodiment, feature and its effect are invented, is described in detail such as Afterwards.
Embodiment 1
As shown in Figure 1 and 2, mobile trolley used running gear of the invention, by main couple, Hanging Basket lifting parts, running part, template portion Formed with anchoring section, main couple realizes the fixation of movable hanging basket, and main couple is connected to the top of Hanging Basket lifting parts, Hanging Basket lifting parts Bottom is connected with template portion, the movement of movable hanging basket is realized by running part, and running part is fixed on anchoring section.
Wherein main couple is made up of entablature 1, longeron 3 and Hanging Basket supporting leg 4, and longeron 3 is arranged on the lower section of entablature 1, longeron 3 Setting orthogonal with entablature 1 is simultaneously mutually fixed, and entablature 1 and longeron 3 are connected by welding between the two;Longeron 3 and extension The phase of basket supporting leg 4 is fixedly connected.Hanging Basket supporting leg 4 is arranged between longeron 3 and track 6, with welding between Hanging Basket supporting leg 4 and longeron 3 Mode connect, connected between Hanging Basket supporting leg 4 and track 6 with inverse buckling wheel 15, Hanging Basket supporting leg plays the overall Hanging Basket knot of support The effect of structure.
Hanging Basket lifting parts are suspension rod 2, and suspension rod 2 is more, the bottom of suspension rod 2 connection template portion, the company in suspension rod 2 Yu template portion Connect opening position and identical and/or different size jack is set, different size is set according to stress size at each suspension centre Jack, rapidly to adjust bottom formwork elevation measuring in time, production efficiency is improved, shortens construction period.
Anchoring section is Π types backing plate 7, and backing plate 7 is anchored on Wavelike steel webplate top flange steel plate 5, Wavelike steel webplate top flange Peg 8 is connected on steel plate 5, platform is provided for Hanging Basket walking track 6.Running part is made up of track 6, and track 6 is I-shaped Girder steel, track 6 are anchored on backing plate 7.
Template portion is arranged on the lower section of Wavelike steel webplate 9, including end template 12 and the side for being arranged on the both sides of end template 12 Mould 11, the bottom of workbench 14 is connected with Hanging Basket lifting parts lower end, and is arranged at the both sides in template portion, in workbench 14 Outside is respectively arranged with anticollision barrier 13.
Wavelike steel webplate 9 includes left Wavelike steel webplate and right Wavelike steel webplate, in left Wavelike steel webplate and right waveform steel abdomen Temporary support crossbeam 10 is provided between plate, to ensure that Wavelike steel webplate has enough horizontal and vertical rigidity.
The mobile trolley used running gear application method of the present invention comprises the following steps:
The construction of bridge pier and No. zero block is carried out first, and No. zero block and (N-0) section Wavelike steel webplate are constructed simultaneously;Bridge pier and No. zero After block construction is completed, (N-1) section Wavelike steel webplate is lifted, passes through high intensity spiral shell between Wavelike steel webplate section and section Tether and be connected together, cross-brace 10 is provided between Wavelike steel webplate transverse direction, to ensure its stability;
Using Wavelike steel webplate as load-carrying members, Π types backing plate 7, the anchor on backing plate 7 are anchored on the steel plate of Wavelike steel webplate top flange Gu I-shaped track 6, this Novel movable Hanging Basket is arranged on track 6.After Hanging Basket installation, the bottom model section of Hanging Basket is utilized The production process of (N-1) section bottom plate is carried out, end template 12 and side form 11 are arranged, by the reinforcing bar and ripple in the bottom plate of (N-1) section The web shear connector colligation of shape steel welds together, and pours (N-1) section underplate concrete and is conserved;
While (N-1) section concrete floor is made, the Wavelike steel webplate of (N-2) section, Wavelike steel webplate section are lifted Between section by high strength exploitation together with, cross-brace is provided between Wavelike steel webplate transverse direction, to ensure it Stability;
After treating that (N-1) section Wavelike steel webplate underplate concrete reaches design strength requirement, end template 12 is removed, at (N-2) Anchor Π types backing plate 7 and I-shaped track 6 on section Wavelike steel webplate top flange steel plate 5, after hanging basket advancing, remove (N-1) section Π types backing plate 7 and I-shaped track 6 on section Wavelike steel webplate top flange steel plate 5, synchronous construction (N-1) section Wavelike steel webplate Concrete roof and (N-2) section Wavelike steel webplate concrete floor;
After (N-1) section concrete roof and (N-2) section underplate concrete reach design strength requirement, (N-1) section is removed Section top plate and (N-2) section bottom plate, (N-1), (N-2) section Wavelike steel webplate falsework are removed, respectively tensioning (N-1) Top plate, (N-2) section baseboard prestress reinforcing bar, mud jacking;At the same time (N-3 is installed)Section Wavelike steel webplate, it is suitable more than Sequence circulation construction.
Mobile trolley used running gear proposed by the present invention, template portion do not include roof plate template and flange plate template, mitigate The weight of movable hanging basket itself, there is provided job stability and security;Left Wavelike steel webplate and right Wavelike steel webplate it Between be provided with temporary support crossbeam, to ensure that Wavelike steel webplate has enough horizontal and vertical rigidity;The setting of anticollision barrier Ensure that Hanging Basket uses the security of process.The limitation of SCC self-supporting construction method movable hanging baskets is overcome, is gone for any In Wavelike steel webplate pre-stressed bridge, practicality is added, expands the scope of application.
The above described is only a preferred embodiment of the present invention, any formal limitation not is made to the present invention, though So the present invention is disclosed above with preferred embodiment, but is not limited to the present invention, any to be familiar with this professional technology people Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification For the equivalent embodiment of equivalent variations, as long as being the content without departing from technical solution of the present invention, the technical spirit according to the present invention Any simple modification, equivalent change and modification made to above example, in the range of still falling within technical solution of the present invention.

Claims (10)

  1. A kind of 1. mobile trolley used running gear, it is characterised in that:By main couple, Hanging Basket lifting parts, running part, template portion and anchor Gu portion forms,
    The main couple realizes the fixation of movable hanging basket, and the main couple connects the top of the Hanging Basket lifting parts, the Hanging Basket Lifting parts bottom is connected with template portion, the movement of movable hanging basket is realized by running part, and the running part is fixed on the anchoring In portion.
  2. 2. mobile trolley used running gear according to claim 1, it is characterised in that:The main couple is by entablature(1)、 Longeron(3)With Hanging Basket supporting leg(4)Composition;
    The longeron(3)It is arranged on the entablature(1)Lower section, the longeron(3)With the entablature(1)It is orthogonal to set Put and mutually fix;
    The longeron(3)With Hanging Basket supporting leg(4)Mutually it is fixedly connected.
  3. 3. mobile trolley used running gear according to claim 1, it is characterised in that:The Hanging Basket lifting parts are suspension rod (2), the suspension rod(2)For more, the suspension rod(2)Bottom connects the template portion, in the suspension rod(2)With the template portion Link position at identical and/or different size jack is set.
  4. 4. mobile trolley used running gear according to claim 1, it is characterised in that:The anchoring section is backing plate(7), institute State backing plate(7)It is anchored at Wavelike steel webplate top flange steel plate(5)On.
  5. 5. mobile trolley used running gear according to claim 4, it is characterised in that:The running part is by track(6)Group Into the track(6)It is anchored at the backing plate(7)On.
  6. 6. the mobile trolley used running gear according to claim 4 or 5, it is characterised in that:The backing plate(7)For Π type pads Plate(7).
  7. 7. mobile trolley used running gear according to claim 5, it is characterised in that:The track(6)For I-steel Beam.
  8. 8. mobile trolley used running gear according to claim 1, it is characterised in that:The template portion is arranged on waveform steel Web(9)Lower section, including end template(12)And it is arranged on the end template(12)The side form of both sides(11);The waveform steel Web(9)Including left Wavelike steel webplate and right Wavelike steel webplate, set between the left Wavelike steel webplate and right Wavelike steel webplate It is equipped with temporary support crossbeam(10).
  9. 9. mobile trolley used running gear according to claim 1, it is characterised in that:Also include workbench(14), The workbench(14)Bottom is connected with the Hanging Basket lifting parts lower end, and is arranged at the both sides in the template portion, in institute State workbench(14)Outside be respectively arranged with anticollision barrier(13).
  10. 10. the mobile trolley used running gear application method according to any one of claim 1 ~ 5, it is characterised in that:Including Following steps,
    1)The construction of bridge pier and No. zero block is carried out, after No. zero block and the construction of (N-0) section Wavelike steel webplate are completed, lifts (N- 1) section Wavelike steel webplate, adjacent Wavelike steel webplate(9)Cross-brace is provided between transverse direction(10);
    2)In (N-1) Wavelike steel webplate top flange steel plate(5)Upper anchoring Π type backing plates(7), in backing plate(7)Upper anchoring is I-shaped Track(6), Hanging Basket is arranged on track(6), arrange end template(12)And side form(11), by (N-1) section Wavelike steel webplate bottom Reinforcing bar in plate is fixed together with Wavelike steel webplate shear connector, pours (N-1) section underplate concrete and is conserved;
    3)While (N-1) section concrete floor is made, (N-2) section Wavelike steel webplate is lifted;
    4)After treating that (N-1) section Wavelike steel webplate underplate concrete reaches design strength requirement, end template is removed(12), (N-2) section Wavelike steel webplate top flange steel plate(5)Upper anchoring Π type backing plates(7)With I-shaped track(6), after hanging basket advancing, Remove (N-1) section Wavelike steel webplate top flange steel plate(5)On Π type backing plates(7)With I-shaped track(6), synchronous construction (N-1) section Wavelike steel webplate concrete roof and (N-2) section Wavelike steel webplate concrete floor;
    5)Treat that (N-1) section Wavelike steel webplate concrete roof and (N-2) section Wavelike steel webplate underplate concrete reach design After intensity requirement, (N-1) section Wavelike steel webplate top plate and (N-2) section Wavelike steel webplate bottom plate are removed, is removed (N-1) Section Wavelike steel webplate falsework and (N-2) section Wavelike steel webplate falsework, difference tensioning (N-1) section waveform steel Web top plate deformed bar and (N-2) section Wavelike steel webplate baseboard prestress reinforcing bar, mud jacking;At the same time (N-3 is installed) Section Wavelike steel webplate;
    6)Hanging basket advancing, circulate and construct according to sequence described above, until completing.
CN201710660086.4A 2017-08-04 2017-08-04 Traveling device of mobile trolley and using method Active CN107401125B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710660086.4A CN107401125B (en) 2017-08-04 2017-08-04 Traveling device of mobile trolley and using method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710660086.4A CN107401125B (en) 2017-08-04 2017-08-04 Traveling device of mobile trolley and using method

Publications (2)

Publication Number Publication Date
CN107401125A true CN107401125A (en) 2017-11-28
CN107401125B CN107401125B (en) 2022-12-09

Family

ID=60402687

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710660086.4A Active CN107401125B (en) 2017-08-04 2017-08-04 Traveling device of mobile trolley and using method

Country Status (1)

Country Link
CN (1) CN107401125B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589558A (en) * 2018-02-09 2018-09-28 安徽兰兮工程技术开发有限公司 A kind of overpass outer wall facility maintenance holder
CN110184889A (en) * 2019-06-19 2019-08-30 苏交科集团股份有限公司 The composite bridge and its erection method of corrugated web receiving construction loads
CN110593107A (en) * 2019-09-23 2019-12-20 中国建筑股份有限公司 Movable cantilever hanging basket for steel box girder construction and construction method
CN111455873A (en) * 2020-04-10 2020-07-28 中铁十一局集团第二工程有限公司 Suspension system of hanging basket

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4003473A (en) * 1974-08-30 1977-01-18 Ryan Ramp, Inc. Combined marine ramp transfer and mooring system
JP2006022595A (en) * 2004-07-09 2006-01-26 Taisei Corp Main pilot girder, main girder structure for erection of box girder bridge and erection method of the box girder bridge
CN201665823U (en) * 2009-12-04 2010-12-08 中国第一冶金建设有限责任公司 Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail
CN204940123U (en) * 2015-08-24 2016-01-06 中铁六局集团有限公司 Construction operation coaster below continuous beam frange plate
CN205062678U (en) * 2015-10-09 2016-03-02 中交第二航务工程局有限公司 Be applied to construction of case roof beam of wave form steel web structure and hang basket
CN105421249A (en) * 2015-12-15 2016-03-23 中铁十四局集团第二工程有限公司 Novel dragging- hoisting combined type hanging basket structure and construction method
CN205116038U (en) * 2015-11-18 2016-03-30 四川路桥桥梁工程有限责任公司 Basket is hung to wave form steel web bearing formula
CN105625195A (en) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN105804385A (en) * 2016-04-15 2016-07-27 中铁五局集团有限公司 Hollow type walking track structure for hanging basket
CN206070393U (en) * 2016-09-20 2017-04-05 中交武汉港湾工程设计研究院有限公司 A kind of asynchronous construction hanging basket of Wavelike steel webplate composite beam bridge
CN106758872A (en) * 2017-02-22 2017-05-31 河南大建桥梁钢构股份有限公司 Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution
CN207244447U (en) * 2017-08-04 2018-04-17 苏交科集团股份有限公司 A kind of steel reinforced concrete combined bridge movable hanging basket

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4003473A (en) * 1974-08-30 1977-01-18 Ryan Ramp, Inc. Combined marine ramp transfer and mooring system
JP2006022595A (en) * 2004-07-09 2006-01-26 Taisei Corp Main pilot girder, main girder structure for erection of box girder bridge and erection method of the box girder bridge
CN201665823U (en) * 2009-12-04 2010-12-08 中国第一冶金建设有限责任公司 Bridge hanging basket cast-in-situ construction triangular rear anchor inverse buckling wheel enhanced type rail
CN204940123U (en) * 2015-08-24 2016-01-06 中铁六局集团有限公司 Construction operation coaster below continuous beam frange plate
CN205062678U (en) * 2015-10-09 2016-03-02 中交第二航务工程局有限公司 Be applied to construction of case roof beam of wave form steel web structure and hang basket
CN205116038U (en) * 2015-11-18 2016-03-30 四川路桥桥梁工程有限责任公司 Basket is hung to wave form steel web bearing formula
CN105421249A (en) * 2015-12-15 2016-03-23 中铁十四局集团第二工程有限公司 Novel dragging- hoisting combined type hanging basket structure and construction method
CN105625195A (en) * 2016-03-16 2016-06-01 河南大建桥梁钢构股份有限公司 Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN105804385A (en) * 2016-04-15 2016-07-27 中铁五局集团有限公司 Hollow type walking track structure for hanging basket
CN206070393U (en) * 2016-09-20 2017-04-05 中交武汉港湾工程设计研究院有限公司 A kind of asynchronous construction hanging basket of Wavelike steel webplate composite beam bridge
CN106758872A (en) * 2017-02-22 2017-05-31 河南大建桥梁钢构股份有限公司 Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution
CN207244447U (en) * 2017-08-04 2018-04-17 苏交科集团股份有限公司 A kind of steel reinforced concrete combined bridge movable hanging basket

Non-Patent Citations (7)

* Cited by examiner, † Cited by third party
Title
唐治军等: "某高速铁路大跨度连续梁桥三角挂篮的整体及局部受力状态分析", 《铁道建筑》 *
杨文: "大跨径刚构桥的施工技术及控制探究", 《科技创新导报》 *
贺茂生等: "大跨度波形钢腹板PC组合连续梁悬臂作业桁车设计", 《现代交通技术》 *
郭勇: "波形钢腹板承重式挂篮施工技术在波形钢腹板PC箱梁桥中的应用", 《工程建设与设计》 *
钟威: "浅谈采用菱形挂篮对称悬臂浇注施工方法", 《城市道桥与防洪》 *
雷政等: "波形钢腹板组合梁桥的SCC悬臂施工法", 《山西建筑》 *
颉明军: "错位法施工在波形钢腹板预应力混凝土箱梁桥中的应用", 《铁道建筑》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589558A (en) * 2018-02-09 2018-09-28 安徽兰兮工程技术开发有限公司 A kind of overpass outer wall facility maintenance holder
CN110184889A (en) * 2019-06-19 2019-08-30 苏交科集团股份有限公司 The composite bridge and its erection method of corrugated web receiving construction loads
CN110593107A (en) * 2019-09-23 2019-12-20 中国建筑股份有限公司 Movable cantilever hanging basket for steel box girder construction and construction method
CN110593107B (en) * 2019-09-23 2024-02-06 中国建筑股份有限公司 Movable cantilever hanging basket for steel box girder construction and construction method
CN111455873A (en) * 2020-04-10 2020-07-28 中铁十一局集团第二工程有限公司 Suspension system of hanging basket

Also Published As

Publication number Publication date
CN107401125B (en) 2022-12-09

Similar Documents

Publication Publication Date Title
CN105625195B (en) Wave forms steel web SCC engineering methods movable hanging basket and its construction method
CN207244447U (en) A kind of steel reinforced concrete combined bridge movable hanging basket
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN107401125A (en) A kind of mobile trolley used running gear and application method
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN105735141B (en) A kind of box beam side form slide device and its construction method
KR20140084107A (en) Self-Launching Movable Scaffolding System
CN203049470U (en) Hanging basket walking system
CN109267490B (en) Long guide beam type movable formwork and construction method thereof
CN105568870B (en) For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction
CN107201719B (en) Viaduct anti-collision wall template hoisting transfer machine and anti-collision wall construction method
CN203393639U (en) Diamond self-anchored hanging basket for road and bridge construction
CN105714692A (en) Cast-in-cantilever beam concrete filled steel tube temporary concretion system
CN105887658A (en) Multi-purpose continuous construction temporary beam structure and construction method thereof
CN110820602A (en) Single-segment box girder bridge girder erection machine and operation method thereof
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN106758872A (en) Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution
CN210288140U (en) Simple and easy prefabricated decking hoist and mount platform truck
CN210049103U (en) High-grade high-speed highway bracket spanned by large-span cast-in-place box girder
CN104963295A (en) Support frame for non-ground internal-force balanced cast-in-place beam and construction method thereof
CN112726411B (en) Integral dragging construction method for single-hole large cantilever steel truss girder
CN206570671U (en) Based on the prestressed assembled corrugated steel web plate composite box girder of mixing
CN206680994U (en) Assembled steel reinforced cage descending frame
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN210766417U (en) Pier-spanning lifting beam support device at side position of bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant