CN107366302A - A kind of construction technology of reinforced concrete retaining wall - Google Patents

A kind of construction technology of reinforced concrete retaining wall Download PDF

Info

Publication number
CN107366302A
CN107366302A CN201710530242.5A CN201710530242A CN107366302A CN 107366302 A CN107366302 A CN 107366302A CN 201710530242 A CN201710530242 A CN 201710530242A CN 107366302 A CN107366302 A CN 107366302A
Authority
CN
China
Prior art keywords
concrete
foundation
wall body
parts
foundation trench
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710530242.5A
Other languages
Chinese (zh)
Other versions
CN107366302B (en
Inventor
黄秀飞
虞和登
罗贤武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUAHENG CONSTRUCTION GROUP CO Ltd
Original Assignee
HUAHENG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUAHENG CONSTRUCTION GROUP CO Ltd filed Critical HUAHENG CONSTRUCTION GROUP CO Ltd
Priority to CN201710530242.5A priority Critical patent/CN107366302B/en
Publication of CN107366302A publication Critical patent/CN107366302A/en
Application granted granted Critical
Publication of CN107366302B publication Critical patent/CN107366302B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/08Restraining of underground water by employing open ditches arranged below the level of the water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Retaining Walls (AREA)

Abstract

A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:S1, along tall earth fill bottom of slope edge foundation trench is excavated out, and gutter and catch pit are set;S2, treat that bottom land without ponding, lays blotter, and be rammed into foundation soil to bottom land;S3, the prefabricated foundation reinforcing bar in foundation trench, and formwork erection pours base concrete;S4, after base concrete reaches some strength, vertical wall body reinforcing bar is installed in base concrete;S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and cleaned up with water;S6, erect wall body template, the cast-in-place wall body concrete into template, treat that the intensity of wall body concrete reaches a timing, swell fixture is squeezed into wall body towards the one side of tall earth fill, foundation pile is squeezed into tall earth fill afterwards, swell fixture and foundation pile are tensed into connection with reinforcing bar rope.This kind of technique is built into retaining wall, and not only intensity is high, and efficiency of construction is also higher.

Description

A kind of construction technology of reinforced concrete retaining wall
Technical field
The present invention relates to construction field, more particularly to a kind of construction technology of reinforced concrete retaining wall.
Background technology
During construction, often because landform reason forms tall earth fill, especially enter in mountain area Row construction, then it is particularly evident.And the soil block and rubble on tall earth fill are possible to tumble down from side slope, and then just It is possible to influence being normally carried out for construction working.
And in the prior art, workmen often first erects one of earth-retaining before construction at tall earth fill Wall, and stop with this downslide of soil block and rubble.Meanwhile when the difference in height for running into embankment side slope is excessive, in order to Ensureing retaining wall has enough abilities to balance the thrust of embankment side slope, and prior art would generally be built using armored concrete Retaining wall, or even retaining wall internal force can be improved using increase reinforced concrete retaining wall thickness, but so need significantly Increase construction costs;Another method is encryption counterfort intercolumniation, but the existing embankment side slope discrepancy in elevation is all very big, with depth Increase, soil pressure increase, the construction method of encryption counterfort intercolumniation are difficult to effectively lower construction costs.
The content of the invention
It is an object of the invention to provide a kind of construction technology of reinforced concrete retaining wall, it is not only easy for construction, and Also the intensity of reinforced concrete retaining wall is effectively enhanced.
The present invention above-mentioned purpose technical scheme is that:A kind of reinforced concrete retaining wall is applied Work technique, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, and formwork erection pours base concrete into foundation trench;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, erect wall body template, the cast-in-place wall body concrete into template, treat wall body concrete intensity reach 2.7Mpa~ During 2.9Mpa, swell fixture is squeezed into wall body towards the one side of tall earth fill, foundation pile is squeezed into tall earth fill afterwards, uses Swell fixture and foundation pile are tensed connection by reinforcing bar rope.
By using above-mentioned technical proposal, gutter and catch pit are set during foundation trench excavates, so can and When discharge ponding in foundation trench, be so to advantageously ensure that so as to ensure that working face is dry and substrate is not flooded Efficiency of construction, be advantageous to improve the intensity on basis again.Meanwhile foundation trench bottom lay blotter, can so reduce from Erosion degree of the water that underground is oozed out to basis.In addition, the prefabricated foundation reinforcing bar in foundation trench, can so improve basis after pouring Intensity.Also, before walling body is poured, first the faying face of wall body and base concrete is poured, so can be wall body Pour and set support level, it is stable so as to improve wall body.And the processing before being constructed to faying face, it can so carry In high-wall body casting process, concrete is spilt between template and faying face, and then reduces the waste of concrete.It is moreover, sharp Reinforced concrete retaining wall and tall earth fill are fixed together with reinforcing bar rope, reinforced concrete retaining wall can so be risen To tightening force, so as to be advantageous to improve compression strength.
Preferably, reinforcement foundation includes two layers in S3, and one layer is set close to foundation trench bottom, and another layer is close to the centre of foundation trench Highly set.
By using above-mentioned technical proposal, the setting of such two layers of reinforcement foundation, it is mixed that basis after pouring can be greatly improved Coagulate the intensity of soil.
Preferably, after the reinforcement foundation of foundation trench bottom is installed, the pouring of concrete is first carried out, until height reaches The centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and final grouting coagulation Soil is until foundation trench completely fills out.
By using above-mentioned technical proposal, basis is set using the mode of two-step pouring, so on the one hand originally to base When the bottom casting concrete of groove, the stop of upper strata reinforcement foundation can be avoided, so as to also it is avoided that upper strata reinforcement foundation Damage, on the other hand can also ensure that reinforcement foundation evenly distributes to the stress of base concrete, so as to be advantageous to carry The high intensity of base concrete.
Preferably, in S6 before wall body concrete is poured, presently in connection with face brush one layer of cement mortar or pad one layer 2~ 3 centimeters thick 1:2 cement mortar.
, can be after wall body have been poured by using above-mentioned technical proposal, faying face and wall body can more integrally Change, so as to be advantageous to improve the intensity of wall body.
Preferably, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and perpendicular a tree, used in making timber for boats is with 8 × 10cm a tree, used in making timber for boats spacing 40cm, is enclosed stupefied with steel pipe, is supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, and side form is positioned with ф 16 bolt to drawing, bolt Spacing is 80cm, and bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 water Cement mortar blocks bolt hole.
By using above-mentioned technical proposal, it is more smooth so on the one hand can to ensure that wall can ensure after pouring State, be on the other hand also convenient for the dismounting work of template.
Preferably, the component of the concrete includes by weight:372~437 parts of cement, 175~193 parts of water, sand 564~582 parts, 5~6 parts of air entraining agent, 10~18 parts of phosphoamide, 12~15 parts of neopelex, emery wheel ash 25~35 Part, 5~9 parts of water reducer.
Preferably, the component of the concrete includes by weight:405 parts of cement, 184 parts of water, 573 parts of sand, bleed 5.5 parts of agent, 14 parts of phosphoamide, 13.5 parts of neopelex, emery wheel grey 30 parts, 7 parts of water reducer.
By using above-mentioned technical proposal, part urea can free reaction with the rusty stain carried originally on reinforcing bar, form network Compound, and the surface of reinforcing bar is attached to, become diaphragm, so as to also just improve the oxidation resistant ability of reinforcing bar.Meanwhile by It can be burrowed in Some Insects on concrete, and during this, urea and neopelex in concrete It can be drawn into vivo by insect, at this moment urea will destroy insect body wall chitin, and neopelex can be by body wall Wax coat dissolves, and it is waterproof to be attached to formation above.An air-locked tunic, so as to which also insect air-hole blockage just can be made simultaneously Death by suffocation, so as to also just reduce destruction of the insect to coagulation figure.Furthermore neopelex is exactly that surface is lived originally Property agent, so as to be advantageous to strengthen concrete in each raw material degree of mixing.
And emery wheel ash refer to emery wheel processing polishing casting when, particulate waste caused by phase mutual friction, if discharge Environment will be polluted into environment, therefore, add it in concrete the pollution that can just reduce to environment, together When, its Main Ingredients and Appearance is silica, and its granularity compare it is small, so it can be to the small spaces in concrete Play a part of filling, improve the density of concrete.
Preferably, the air entraining agent is rosin soap RS-I air entraining agents.
By using above-mentioned technical proposal, mix this kind of air entraining agent its can be introduced during concrete mixes and stirs uniformly and Stable independent micro-bubble, blocks the path of water, the anti-permeability performance of concrete is increased.Simultaneously as in concrete The presence of micro-bubble, the workability and mobility of concrete can be improved, reduce bleeding, improve the durability of concrete.
Preferably, the water reducer is MH-JS-102 polycarboxylate water-reducers.
By using above-mentioned technical proposal, MH-JS-102 polycarboxylate water-reducers use methyl polyethylene glycol(MPEG)With it is different Cyclobutenyl polyethylene glycol(VPEG)APEO polymeric monomer and unsaturated acids form through radical polymerization, and its inside has comb shape Structure, it is polyoxyethylene groups long-chain that using in molecule, which has longer length, so that has bigger steric hindrance effect and electrostatic Repulsion is acted on, and bigger dispersed and higher water-reducing rate is provided for cement.
In summary, the invention has the advantages that:
1st, when foundation trench is excavated, and gutter and catch pit are provided with, can so accelerate the discharge of ponding in foundation trench, protected Being normally carried out for construction process is demonstrate,proved;
2nd, before wall body is poured, first to one layer of cement mortar of one layer of faying face brush or pad, so when wall body is poured, energy Enough ensure the integraty of wall body and faying face;
3rd, after wall body has poured, wall and tall earth fill are fixed together using reinforcing bar rope, so can be further Improve the ability of wall body resistance soil pressure.
Brief description of the drawings
Fig. 1 is a kind of construction technology of reinforced concrete retaining wall.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing 1.
Embodiment one,
A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, wherein, reinforcement foundation includes two layers, and one layer is set close to foundation trench bottom, another layer Intermediate altitude close to foundation trench is set, and after the reinforcement foundation of foundation trench bottom is installed, first carries out the pouring of concrete, until Highly reach the centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and it is secondary Placing concrete is until foundation trench completely fills out;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, before wall body concrete is poured, presently in connection with face brush one layer of cement mortar, afterwards erect wall body template, Xiang Mo Cast-in-place wall body concrete in plate, when the intensity of wall body concrete reaches 2.7Mpa~2.9Mpa, swell fixture is squeezed into wall body Towards the one side of tall earth fill, foundation pile is squeezed into tall earth fill afterwards, is tensed swell fixture and foundation pile with reinforcing bar rope Connection.
Herein, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, Enclosed with steel pipe stupefied, be supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, side form is positioned with ф 16 bolt to drawing, pitch of bolts For 80cm, bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 cement bonded sands Slurry blocks bolt hole.
In addition, the composition of concrete used in the present embodiment one is cement 372Kg, water 175Kg, sand 564Kg, rosin soap Class RS-I air entraining agents 5Kg, phosphoamide 10Kg, neopelex 12Kg, emery wheel ash 25Kg, MH-JS-102 polycarboxylic acids subtract Aqua 5Kg.Wherein, MH-JS-102 polycarboxylate water-reducers are produced by Hunan Ming Huang developments in science and technology Co., Ltd.
Embodiment two,
A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, wherein, reinforcement foundation includes two layers, and one layer is set close to foundation trench bottom, another layer Intermediate altitude close to foundation trench is set, and after the reinforcement foundation of foundation trench bottom is installed, first carries out the pouring of concrete, until Highly reach the centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and it is secondary Placing concrete is until foundation trench completely fills out;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, before wall body concrete is poured, presently in connection with face pad one layer 2~3 centimeters thick 1:2 cement mortar, after-frame Wall body template, the cast-in-place wall body concrete into template, will be swollen when the intensity of wall body concrete reaches 2.7Mpa~2.9Mpa Swollen screw squeezes into wall body towards the one side of tall earth fill, squeezes into foundation pile in tall earth fill afterwards, will be expanded with reinforcing bar rope Screw and foundation pile tense connection.
Herein, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, Enclosed with steel pipe stupefied, be supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, side form is positioned with ф 16 bolt to drawing, pitch of bolts For 80cm, bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 cement bonded sands Slurry blocks bolt hole.
In addition, the composition of concrete used in the present embodiment one is cement 437Kg, water 193Kg, sand 582Kg, rosin soap Class RS-I air entraining agents 6Kg, phosphoamide 18Kg, neopelex 15Kg, emery wheel ash 35Kg, MH-JS-102 polycarboxylic acids subtract Aqua 9Kg.
Embodiment three,
A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, wherein, reinforcement foundation includes two layers, and one layer is set close to foundation trench bottom, another layer Intermediate altitude close to foundation trench is set, and after the reinforcement foundation of foundation trench bottom is installed, first carries out the pouring of concrete, until Highly reach the centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and it is secondary Placing concrete is until foundation trench completely fills out;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, before wall body concrete is poured, presently in connection with face brush one layer of cement mortar, afterwards erect wall body template, Xiang Mo Cast-in-place wall body concrete in plate, when the intensity of wall body concrete reaches 2.7Mpa~2.9Mpa, swell fixture is squeezed into wall body Towards the one side of tall earth fill, foundation pile is squeezed into tall earth fill afterwards, is tensed swell fixture and foundation pile with reinforcing bar rope Connection.
Herein, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, Enclosed with steel pipe stupefied, be supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, side form is positioned with ф 16 bolt to drawing, pitch of bolts For 80cm, bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 cement bonded sands Slurry blocks bolt hole.
In addition, the composition of concrete used in the present embodiment one is cement 405Kg, water 184Kg, sand 573Kg, rosin soap Class RS-I air entraining agents 5.5Kg, phosphoamide 14Kg, neopelex 13.5Kg, the poly- carboxylics of emery wheel ash 30Kg, MH-JS-102 Sour water reducer 7Kg.
Example IV,
A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, wherein, reinforcement foundation includes two layers, and one layer is set close to foundation trench bottom, another layer Intermediate altitude close to foundation trench is set, and after the reinforcement foundation of foundation trench bottom is installed, first carries out the pouring of concrete, until Highly reach the centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and it is secondary Placing concrete is until foundation trench completely fills out;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, before wall body concrete is poured, presently in connection with face pad one layer 2~3 centimeters thick 1:2 cement mortar, after-frame Wall body template, the cast-in-place wall body concrete into template, will be swollen when the intensity of wall body concrete reaches 2.7Mpa~2.9Mpa Swollen screw squeezes into wall body towards the one side of tall earth fill, squeezes into foundation pile in tall earth fill afterwards, will be expanded with reinforcing bar rope Screw and foundation pile tense connection.
Herein, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, Enclosed with steel pipe stupefied, be supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, side form is positioned with ф 16 bolt to drawing, pitch of bolts For 80cm, bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 cement bonded sands Slurry blocks bolt hole.
In addition, the composition of concrete used in the present embodiment one is cement 405Kg, water 193Kg, sand 564Kg, rosin soap Class RS-I air entraining agents 5.5Kg, phosphoamide 14Kg, neopelex 15Kg, emery wheel ash 30Kg, MH-JS-102 polycarboxylic acids Water reducer 9Kg.
Embodiment five,
A kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, wherein, reinforcement foundation includes two layers, and one layer is set close to foundation trench bottom, another layer Intermediate altitude close to foundation trench is set, and after the reinforcement foundation of foundation trench bottom is installed, first carries out the pouring of concrete, until Highly reach the centre position of foundation trench, and after intensity reaches 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and it is secondary Placing concrete is until foundation trench completely fills out;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, before wall body concrete is poured, presently in connection with face pad one layer 2~3 centimeters thick 1:2 cement mortar, after-frame Wall body template, the cast-in-place wall body concrete into template, will be swollen when the intensity of wall body concrete reaches 2.7Mpa~2.9Mpa Swollen screw squeezes into wall body towards the one side of tall earth fill, squeezes into foundation pile in tall earth fill afterwards, will be expanded with reinforcing bar rope Screw and foundation pile tense connection.
Herein, the template of wall body formwork erection is assembled using the clamping plate of smooth surface seven in S6, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, Enclosed with steel pipe stupefied, be supported with 8 × 10cm wooden a tree, used in making timber for boats as diagonal brace, side form is positioned with ф 16 bolt to drawing, pitch of bolts For 80cm, bolt penetration hole can use hard plastic tube of the internal diameter for 20~25cm, and during form removal, bolt is extracted, then with 1:2 cement bonded sands Slurry blocks bolt hole.
In addition, the composition of concrete used in the present embodiment one is cement 372Kg, water 184Kg, sand 573Kg, rosin soap Class RS-I air entraining agents 6Kg, phosphoamide 18Kg, neopelex 12Kg, emery wheel ash 30Kg, MH-JS-102 polycarboxylic acids subtract Aqua 7Kg.
By in embodiment one to embodiment five reinforced concrete retaining wall carry out compression strength test, obtain with Lower data:Institute according to detection method be GB50107-2010
Embodiment one Embodiment two Embodiment three Example IV Embodiment five
Compression strength/Mpa 4.834 5.681 5.062 4.947 4.894
By upper table as can be seen that the requirement of retaining wall can be fully achieved in the construction method of the present invention, and also greatly improve Efficiency of construction.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.

Claims (9)

1. a kind of construction technology of reinforced concrete retaining wall, comprises the following steps:
S1, a foundation trench is excavated out along tall earth fill bottom of slope edge, and gutter and catch pit are set at the edge of foundation trench, entered Row draining;
S2, when foundation trench bottom is without ponding, lay blotter to the bottom of foundation trench, and be rammed into foundation soil with ramming machine;
S3, the prefabricated foundation reinforcing bar in foundation trench, and formwork erection pours base concrete into foundation trench;
S4, after the intensity of base concrete is put into 2.4Mpa~2.6Mpa, vertical wall body steel is installed in base concrete Muscle;
S5, cast-in-place wall body and base concrete faying face, the concrete of the loose portions at faying face and laitance are cut, and Cleaned up with water;
S6, erect wall body template, the cast-in-place wall body concrete into template, treat wall body concrete intensity reach 2.7Mpa~ During 2.9Mpa, swell fixture is squeezed into wall body towards the one side of tall earth fill, foundation pile is squeezed into tall earth fill afterwards, uses Swell fixture and foundation pile are tensed connection by reinforcing bar rope.
A kind of 2. construction technology of reinforced concrete retaining wall according to claim 1, it is characterised in that:Basic steel in S3 Muscle includes two layers, and one layer is set close to foundation trench bottom, and another layer is set close to the intermediate altitude of foundation trench.
A kind of 3. construction technology of reinforced concrete retaining wall according to claim 2, it is characterised in that:Installing base After the reinforcement foundation of trench bottom, the pouring of concrete is first carried out, until height reaches the centre position of foundation trench, and when intensity reaches To after 2Mpa~2.2Mpa, then second layer reinforcement foundation is installed, and final grouting concrete is until foundation trench completely fills out.
A kind of 4. construction technology of reinforced concrete retaining wall according to claim 1, it is characterised in that:Poured in S6 Before wall body concrete, presently in connection with face brush one layer of cement mortar or pad one layer 2~3 centimeters thick 1:2 cement mortar.
A kind of 5. construction technology of reinforced concrete retaining wall according to claim 1, it is characterised in that:Wall body is stood in S6 The template of mould is assembled using the clamping plate of smooth surface seven, and it is 40cm to erect a tree, used in making timber for boats with 8 × 10cm a tree, used in making timber for boats spacing, enclosed with steel pipe it is stupefied, with 8 × 10cm's Wooden a tree, used in making timber for boats is supported as diagonal brace, and side form is positioned with ф 16 bolt to drawing, and pitch of bolts 80cm, bolt penetration hole can use internal diameter For 20~25cm hard plastic tube, during form removal, bolt is extracted, then with 1:2 cement mortar block bolt hole.
A kind of 6. construction technology of reinforced concrete retaining wall according to claim 1, it is characterised in that the concrete Component include by weight:
372~437 parts of cement
175~193 parts of water
564~582 parts of sand
5~6 parts of air entraining agent
10~18 parts of phosphoamide
12~15 parts of neopelex
25~35 parts of emery wheel ash
5~9 parts of water reducer.
A kind of 7. construction technology of reinforced concrete retaining wall according to claim 6, it is characterised in that the concrete Component include by weight:
405 parts of cement
184 parts of water
573 parts of sand
5.5 parts of air entraining agent
14 parts of phosphoamide
13.5 parts of neopelex
30 parts of emery wheel ash
7 parts of water reducer.
A kind of 8. construction technology of reinforced concrete retaining wall according to claim 6 or 7, it is characterised in that:It is described to draw Gas agent is rosin soap RS-I air entraining agents.
A kind of 9. construction technology of reinforced concrete retaining wall according to claim 6 or 7, it is characterised in that:It is described to subtract Aqua is MH-JS-102 polycarboxylate water-reducers.
CN201710530242.5A 2017-06-27 2017-06-27 A kind of construction technology of reinforced concrete retaining wall Active CN107366302B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710530242.5A CN107366302B (en) 2017-06-27 2017-06-27 A kind of construction technology of reinforced concrete retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710530242.5A CN107366302B (en) 2017-06-27 2017-06-27 A kind of construction technology of reinforced concrete retaining wall

Publications (2)

Publication Number Publication Date
CN107366302A true CN107366302A (en) 2017-11-21
CN107366302B CN107366302B (en) 2019-02-05

Family

ID=60306649

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710530242.5A Active CN107366302B (en) 2017-06-27 2017-06-27 A kind of construction technology of reinforced concrete retaining wall

Country Status (1)

Country Link
CN (1) CN107366302B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109986732A (en) * 2017-12-29 2019-07-09 宁波荣玛塑胶有限公司 A kind of rotational moulding preparation process blowing ground machine shell
CN110387885A (en) * 2019-07-30 2019-10-29 杭州江润科技有限公司 The construction method that prefabricated PC temporarily covers

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090042395A (en) * 2007-10-26 2009-04-30 김동립 Retainning wall and its construction method
CN103469815A (en) * 2013-09-23 2013-12-25 江苏省交通科学研究院股份有限公司 Construction method for protecting slope of reinforced-concrete retaining wall
CN104195911A (en) * 2014-08-26 2014-12-10 德州市公路工程总公司 Widened embankment structure with beside-water cliff high retaining wall fill section and construction method of widened embankment structure
CN204225147U (en) * 2014-11-04 2015-03-25 深圳市勘察研究院有限公司 Concrete half gravity reinforced retaining wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090042395A (en) * 2007-10-26 2009-04-30 김동립 Retainning wall and its construction method
CN103469815A (en) * 2013-09-23 2013-12-25 江苏省交通科学研究院股份有限公司 Construction method for protecting slope of reinforced-concrete retaining wall
CN104195911A (en) * 2014-08-26 2014-12-10 德州市公路工程总公司 Widened embankment structure with beside-water cliff high retaining wall fill section and construction method of widened embankment structure
CN204225147U (en) * 2014-11-04 2015-03-25 深圳市勘察研究院有限公司 Concrete half gravity reinforced retaining wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
凌玲: "低承载力地基条件下轻型挡土墙结构体系的应用研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109986732A (en) * 2017-12-29 2019-07-09 宁波荣玛塑胶有限公司 A kind of rotational moulding preparation process blowing ground machine shell
CN110387885A (en) * 2019-07-30 2019-10-29 杭州江润科技有限公司 The construction method that prefabricated PC temporarily covers

Also Published As

Publication number Publication date
CN107366302B (en) 2019-02-05

Similar Documents

Publication Publication Date Title
CN105887837B (en) A kind of construction method of field ground stirring concrete earth pile
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN107989032A (en) A kind of construction method of punching interlocking pile
CN105239561A (en) Long spiral mix spray pre-grouting press concrete post-inserted steel reinforcement cage cast-in-place pile construction process
CN206070508U (en) Device for reinforcing foundation
CN107366302B (en) A kind of construction technology of reinforced concrete retaining wall
KR101135163B1 (en) Grout injection and replacement device and the soft ground foundation concrete pile using the same method
CN114277779A (en) Construction method of concrete diaphragm wall in high-moisture-content mucky soil body
KR101066587B1 (en) Construction method of inner filling structure using liquid ultrahigh viscosity and flowable grout material
CN102839647B (en) Stirring pile-permeable concrete pile compound foundation and treatment method thereof
CN106545008A (en) A kind of cast-in-situ bored pile pile making method
CN107460873B (en) Manual digging pile construction method
CN107447754A (en) The new plant stake technique of prefabricated tubular pile and the pile body formed
CN109653223A (en) River anti-floating weighting board construction method
JP3676441B2 (en) Pit and construction method of basement using it
CN105888702B (en) Waterproofing Technology of Underground Works method
CN107059884A (en) A kind of construction method of building foundation pit grouting support stake
CN107780424A (en) A kind of mud riverbed earth rock cofferdam and its construction method
CN204662480U (en) The permanent embed-type elastic bottom template structure of a kind of grade beam
CN208533543U (en) Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance
CN206768731U (en) A kind of armoured type lightweight dock structure
JP2004225453A (en) Construction method of civil engineering structure
CN105672245B (en) Flow the method that the high strength cement soil body is formed in plasticity weak soil
CN205530816U (en) Modular separate sand wall
JP2005076305A (en) Segment and method of manufacturing segment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant