CN107338816A - A kind of high artesian post-cast strip is depressured leak-blocking construction method - Google Patents

A kind of high artesian post-cast strip is depressured leak-blocking construction method Download PDF

Info

Publication number
CN107338816A
CN107338816A CN201710798402.4A CN201710798402A CN107338816A CN 107338816 A CN107338816 A CN 107338816A CN 201710798402 A CN201710798402 A CN 201710798402A CN 107338816 A CN107338816 A CN 107338816A
Authority
CN
China
Prior art keywords
stainless steel
post
steel tube
cast strip
leak
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710798402.4A
Other languages
Chinese (zh)
Inventor
张立哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Original Assignee
China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Shanghai Corp Ltd filed Critical China Construction Seventh Engineering Bureau Shanghai Corp Ltd
Priority to CN201710798402.4A priority Critical patent/CN107338816A/en
Publication of CN107338816A publication Critical patent/CN107338816A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of high artesian post-cast strip to be depressured leak-blocking construction method, drainage and step-down is carried out to post-cast strip (A) leakage using stainless steel tube (1), suction hose (2), ring flange (11), water pump etc., the stainless steel tube (1) is directly embedded in below late poured band (A) place again, closes the concrete of existing leak stopping point and hypotensive point.Compared with prior art, present invention process is simple, and speed of application is fast;Built-in fitting is fixed reliably, especially for the higher area of some level of ground water hydraulic pressure, is fully able to meet design and construction code requirement using the construction of this method.

Description

A kind of high artesian post-cast strip is depressured leak-blocking construction method
Technical field
The invention belongs to building field, is related in water under high pressure area basement bottom board seepage reduction technology field, especially relates to A kind of and high artesian post-cast strip decompression leak-blocking construction method.
Background technology
In building construction concrete structure construction, basement post-pouring zone construction processing emphasis, handle not in work progress When different degrees of Seepage, especially higher in level of ground water and larger hydraulic pressure area will occur, after there is seepage Due to water pressure problem, very big puzzlement is caused to blocking construction, the quality of leak stopping is not easy to ensure and causes repeatedly to do over again.Once side Method is improper, and not only can't resolve leakage problems can also increase the construction time limit indefinite duration.Particularly level of ground water higher area from Right hydraulic pressure is higher, deals with improperly, makes because basement floor has been molded, post-cast strip has poured completion, during post empiricism Into part and large-scale water leakage, do not reach requirement and design, delay the duration.Trace it to its cause when being post-cast strip concrete construction Decompression processing is not carried out, and the cement mortar in the concrete of construction is washed away loss by head, is caused inside concrete structure into honeycomb Shape, formed compared with mass-flow seepage.
The content of the invention
Goal of the invention:Decompression tube caused by order to solve traditional construction technique, which can not fill, forms new seepage at reality and decompression tube The defects of point, spy develop a kind of high artesian post-cast strip decompression leak-blocking construction method, and technique is simple, and speed of application is fast, built-in fitting It is fixed reliable, meet design and construction code requirement.
Technical scheme:A kind of high artesian post-cast strip is depressured leak-blocking construction method, utilizes stainless steel tube, suction hose, method Blue disk, water pump etc. carry out drainage and step-down to post-cast strip leakage, then stainless steel tube is directly embedded in lower section at late poured band, The concrete of the existing leak stopping point of closing and hypotensive point.
Comprise the following steps that:
1st, at the post-cast strip for seepage occur, 100~200mm width is added to chisel operation well by every side, the straight angle in both sides Chisel to structure reinforcing bars position, and carry ring flange high-pressure water head position occur and bury a 50~200mm of diameter and one end Stainless steel tube, the pipe surrounding concrete tight closure of the stainless steel tube, if necessary, using waterproof apron to described stainless Steel pipe is closed;
The diameter of the stainless steel tube need to be adjusted and determine according to drainage and step-down amount;
2nd, described stainless steel tube one end is connected with suction hose by flange, the suction hose and the water pump phase of outside Even, do not shut down by water pump pressure draw water, draining, until the post-cast strip surface without bright water, then carry out breakthrough repairing, Plugging operation;
3rd, after the completion for the treatment of plugging operation, then continue not shut down pressure and draw water, until artesian water can not be flat to operation well surrounding 2 It is non-corrosive in square rice, after other positions to be verified repairing is intact, remove the suction hose that is connected with stainless steel tube flange and Outside water pump;
4th, at the ring flange of described stainless steel tube one end, sealed with the stainless steel plate and waterproof apron in strap bolt hole It is stifled;
5th, after the completion of blocking, in the concrete of preparation pouring practice well, appropriate micro-expanding agent will be added and label is tied than former Structure concrete improves a label, and operation well is poured and closed.
Beneficial effects of the present invention:Compared with prior art, present invention process is simple, and speed of application is fast;Built-in fitting is fixed Reliably, especially for the higher area of some level of ground water hydraulic pressure, using the construction of this method be fully able to meet design with Job specfication requirement.
Brief description of the drawings
Fig. 1 is drainage and step-down process diagrammatic cross-section in post-cast strip of the present invention;
Fig. 2 is that post-cast strip drainage and step-down of the present invention completes diagrammatic cross-section.
Embodiment
In order that the object, technical solutions and advantages of the present invention are clearer, below in conjunction with the accompanying drawings with specific embodiment pair The present invention is described in detail.
Embodiment:
A kind of high artesian post-cast strip is depressured leak-blocking construction method, using stainless steel tube 1, suction hose 2, ring flange 11, Water pump etc. carries out drainage and step-down to post-cast strip A leakages, then stainless steel tube 1 is directly embedded in into lower section at late poured band A, envelope Close the concrete of existing leak stopping point and hypotensive point.
Comprise the following steps that:
1st, at the post-cast strip A for seepage occur, 100mm width is added to chisel operation well B by every side, the straight angle chisels in both sides To structure reinforcing bars position, and there is the stainless steel that a diameter 50mm is buried in high-pressure water head position and one end carries ring flange 11 Pipe 1, the pipe surrounding concrete tight closure of the stainless steel tube 1, if necessary, the stainless steel tube is entered using waterproof apron Row closing;
2nd, described one end of stainless steel tube 1 is connected with suction hose 2 by flange, the suction hose 2 and outside water Pump is connected, do not shut down by water pump pressure draw water, draining, until the post-cast strip surface without bright water, then carries out breakthrough Repairing, plugging operation;
As shown in figure 1, it is post-cast strip drainage and step-down process diagrammatic cross-section;
3rd, after the completion for the treatment of plugging operation, then continue not shut down pressure and draw water, until artesian water can not be flat to operation well surrounding 2 It is non-corrosive in square rice, after other positions repairing to be verified is intact, remove the suction hose 2 being connected with the flange of stainless steel tube 1 And outside water pump;
4th, at the ring flange 11 of described one end of stainless steel tube 1, entered with the stainless steel plate 12 and waterproof apron in strap bolt hole Row closure;
5th, after the completion of blocking, in preparation pouring practice well B concrete, appropriate micro-expanding agent will be added and label is tied than former Structure concrete improves a label, and operation well B is poured and closed.
As shown in Fig. 2 complete diagrammatic cross-section for post-cast strip drainage and step-down.
The foregoing is only the present invention preferred embodiments, be not intended to limit the invention, the present invention spirit and Any modification, equivalent substitution and improvements made within principle etc., it should be included within the system architecture and method of the present invention.

Claims (2)

1. a kind of high artesian post-cast strip is depressured leak-blocking construction method, it is characterised in that utilizes stainless steel tube (1), suction hose (2), ring flange (11), water pump etc. carry out drainage and step-down to post-cast strip (A) leakage, then the stainless steel tube (1) is directly buried Below late poured band (A) place, the concrete of existing leak stopping point and hypotensive point is closed.
2. high artesian post-cast strip according to claim 1 is depressured leak-blocking construction method, it is characterised in that its specific steps It is as follows:
1) at post-cast strip (A) place for seepage occur, add 100~200mm width to chisel operation well (B) by every side, put down in both sides Angle is chiselled to structure reinforcing bars position, and carries flange high-pressure water head position occur and bury a 50~100mm of diameter and one end The stainless steel tube (1) of disk (11), the pipe surrounding concrete tight closure of the stainless steel tube (1), or use waterproof apron pair The stainless steel tube (1) is closed;
2) stainless steel tube (1) one end is connected with suction hose (2) by flange, the suction hose (2) and outside Water pump is connected, do not shut down by water pump pressure draw water, draining, until the post-cast strip surface is without bright water, then carry out breakthrough Repairing, plugging operation;
3) after the completion for the treatment of plugging operation, then continue not shut down pressure and draw water, until artesian water can not be 2 square metres to operation well surrounding It is interior non-corrosive, after other positions repairing to be verified is intact, remove the suction hose (2) being connected with stainless steel tube (1) flange And outside water pump;
4) at ring flange (11) place of the stainless steel tube (1) one end, with the stainless steel plate (12) and waterproof apron in strap bolt hole Blocked;
5) after the completion of blocking, in the concrete at preparation pouring practice well (B) place, appropriate micro-expanding agent will be added and label is tied than former Structure concrete improves a label, and operation well (B) is poured and closed.
CN201710798402.4A 2017-09-07 2017-09-07 A kind of high artesian post-cast strip is depressured leak-blocking construction method Pending CN107338816A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710798402.4A CN107338816A (en) 2017-09-07 2017-09-07 A kind of high artesian post-cast strip is depressured leak-blocking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710798402.4A CN107338816A (en) 2017-09-07 2017-09-07 A kind of high artesian post-cast strip is depressured leak-blocking construction method

Publications (1)

Publication Number Publication Date
CN107338816A true CN107338816A (en) 2017-11-10

Family

ID=60214728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710798402.4A Pending CN107338816A (en) 2017-09-07 2017-09-07 A kind of high artesian post-cast strip is depressured leak-blocking construction method

Country Status (1)

Country Link
CN (1) CN107338816A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643050A (en) * 2018-05-22 2018-10-12 宁夏路桥工程股份有限公司 A kind of method for blocking in wall-through pull rod hole
CN114809592A (en) * 2022-05-19 2022-07-29 中建五局第三建设(深圳)有限公司 Post-cast strip wall formwork structure and construction method for advanced water stop of outer wall post-cast strip

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926682A (en) * 2016-05-13 2016-09-07 广西建工集团第二安装建设有限公司 Basement baseplate post-cast strip construction method with pressure bearing water and higher water pressure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105926682A (en) * 2016-05-13 2016-09-07 广西建工集团第二安装建设有限公司 Basement baseplate post-cast strip construction method with pressure bearing water and higher water pressure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643050A (en) * 2018-05-22 2018-10-12 宁夏路桥工程股份有限公司 A kind of method for blocking in wall-through pull rod hole
CN108643050B (en) * 2018-05-22 2020-02-11 宁夏路桥工程股份有限公司 Plugging method for through-wall pull rod hole
CN114809592A (en) * 2022-05-19 2022-07-29 中建五局第三建设(深圳)有限公司 Post-cast strip wall formwork structure and construction method for advanced water stop of outer wall post-cast strip
CN114809592B (en) * 2022-05-19 2024-03-29 中建五局第三建设(深圳)有限公司 Construction method for advanced water stop of post-pouring strip of outer wall

Similar Documents

Publication Publication Date Title
CN101914917B (en) Anti-seepage and leak-blocking construction method for excavation of subway foundation pit in soft soil area
CN107387123B (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece leakage phenomenon
CN106320353B (en) A kind of construction method of basement construction Yield rainfall relation device
CN207193996U (en) A kind of precipitation pipe well well-sealing device
CN105735364B (en) Concrete joint waterproof system, construction method and the protection component for the system
CN108166517A (en) For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
CN104963324B (en) A kind of diversion tunnel block head exhaust structure and its method for exhausting
CN103321255A (en) Underground concrete structural engineering joint waterproof construction method
CN107338816A (en) A kind of high artesian post-cast strip is depressured leak-blocking construction method
CN112900512A (en) Basement bottom plate crack punching, reinforcing and repairing construction method
CN114109442B (en) Tunnel karst crushing belt sliding collapse half-section curtain progressive grouting reinforcement treatment method
CN207469277U (en) The quick slip casting plugging device of diaphram wall leakage point in a kind of foundation pit
CN105220700B (en) Foundation pit waterproof curtain reinforcement
CN109056734A (en) Diaphram wall defect grouting mending construction method
CN206385557U (en) The water-impervious plugging mechanism of dewatering well on deep basal pit raft plate
CN203795482U (en) Piping handling device at foundation pit bottom
CN205475710U (en) Steel -pipe column concrete jacking interface turnover device
CN110284908B (en) Circumferential grouting plugging method in shield receiving well
CN104964121B (en) A kind of sleeve water leakage plugging method
CN105134223B (en) A kind of construction method for improving shield launching steel case sealing
CN206477349U (en) Stifled, the water blockoff structure of drainpipe through walls
CN108755776A (en) A kind of underground structure bottom plate leak Integrated Processing Unit and its processing method
CN209227571U (en) Plugging dewatering well tool during a kind of dewatering construction
CN211395718U (en) Plugging device for dewatering well
CN103132536A (en) Drainage technology of geologic chemistry before grouting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171110

RJ01 Rejection of invention patent application after publication