CN205475710U - Steel -pipe column concrete jacking interface turnover device - Google Patents

Steel -pipe column concrete jacking interface turnover device Download PDF

Info

Publication number
CN205475710U
CN205475710U CN201620304861.3U CN201620304861U CN205475710U CN 205475710 U CN205475710 U CN 205475710U CN 201620304861 U CN201620304861 U CN 201620304861U CN 205475710 U CN205475710 U CN 205475710U
Authority
CN
China
Prior art keywords
pipe column
steel pipe
pump line
concrete
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620304861.3U
Other languages
Chinese (zh)
Inventor
高辉
裴鸿斌
唐祖锡
杨晨
肖大伟
康晋宇
汤淼
齐轩
李享
林涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620304861.3U priority Critical patent/CN205475710U/en
Application granted granted Critical
Publication of CN205475710U publication Critical patent/CN205475710U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a steel -pipe column concrete jacking interface turnover device, include: the concrete feeding structure includes the pump line, locates pump line stop valve and concrete feeding pump, and will the pump line rigid coupling in the fixed knot of steel -pipe column constructs, the pump line passes through the steel -pipe column the jacking mouth and communicate in the inside of steel -pipe column. The utility model discloses steel -pipe column concrete jacking interface turnover device constructs the jacking mouth department of being fixed in the steel -pipe column with the pump line through fixed knot to when transporting the concrete through external device to the pump line, through jacking mouth entering steel -pipe column, to pressure notes, the jacking of carrying out the concrete in the steel -pipe column, the incision injustice that the mode of the welding of pump line and steel -pipe column, cutting when solving traditional concreting was brought, the drawback of damage concrete, and this device can have enough to meet the need the use, the saving environmental protection.

Description

Steel pipe column concrete lifting interface turnover device
Technical field
This utility model relates to building engineering field, particularly relates to a kind of steel pipe column concrete lifting interface Turnover device.
Background technology
Along with scientific and technological progress and the raising of material property, high-rise building gets more and more, and Super High is built The version building the use concrete filled steel tube combination of middle housing is the most universal.
The mode that pours many employings jacking technique of housing steel pipe column interior concrete in current domestic Super High Construct.Steel pipe column jacking concrete construction principle is: 1) offer jacking hole on steel pipe column;2) Pump line is welded at jacking hole;3) pump line external concrete stop valve;4) concrete stop valve is with mixed The pump line of solidifying soil delivery pump connects;5) under a certain pressure, by concrete pump by concrete Jacking is in steel pipe column;6) after jacking completes, concrete stop valve is closed;7) mix in treating steel pipe column Solidifying soil removes stop valve after reaching some strength, and is carried out by the concrete pump pipe being welded on steel pipe column Cut off;8) the former steel pipe column steel plate cut off in jacking hole of offering is welded.
On steel pipe column, welding pump line is as the mode in jacking hole, need to adopt when later stage concrete pump pipe cuts off Cutting off with flame, this way is more serious to the concrete damage at jacking mouth, and uses flame Causing cut surface uneven when cutting off, the welding quality of steel plate is unfavorable for ensureing.
Utility model content
In view of the foregoing, it would be desirable to provide a kind of and carry out steel pipe column in application jack-up construction method Concreting turnover device when inner concrete pours, solve tradition casting concrete time pump line with The otch that steel pipe column welding, the mode of cutting are brought is uneven, damage the drawback of concrete.
For achieving the above object, this utility model adopts the technical scheme that:
A kind of steel pipe column concrete lifting interface turnover device, is applied to bottom steel pipe column at jacking mouth, To carrying out concrete press-casting and jacking in described steel pipe column, it is characterised in that described steel pipe column concrete Jacking interface turnover device includes:
Concrete conveyance structure, including pump line, is located at described pump line stop valve and concrete conveyance Pump;
Described pump line is fixed in the fixed structure of described steel pipe column, and described pump line passes through described steel pipe column Described jacking mouth and be communicated in the inside of described steel pipe column.
The beneficial effects of the utility model are, this utility model steel pipe column concrete lifting interface has enough to meet the need Pump line is fixed at the jacking mouth of steel pipe column by device by fixed structure, and by external device to pump When pipe transports concrete, by jacking mouth enter steel pipe column, to carry out in steel pipe column concrete pressure injection, Jacking, the otch that when solving tradition casting concrete, pump line welds with steel pipe column, the mode cut is brought Uneven, damage the drawback of concrete, and this device can have enough to meet the need use, economical environment-protective.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described Fixed structure includes that fixed plate and weld bolt, described fixed plate are welded in institute by described weld bolt Stating on the described steel pipe column at jacking mouth edge, described fixed plate is provided with for the close-connected company of described pump line Connecing hole, described pump line is arranged in described connecting hole and is connected to described jacking mouth.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described The connected mode of pump line and described connecting hole is for welding.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described Fixed plate fits tightly in the edge of described jacking mouth.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described Fixed structure includes the one or more steel sections being arranged at described pump line one end, and described steel section one end is fixed In described pump line outer tube wall, the other end is welded in the described steel pipe column at described jacking mouth edge so that institute State pump line and be connected to described jacking mouth.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described On described pump line between jacking mouth, described fixed structure and described pump line circle be provided with stress buffering, close The packing ring of envelope effect.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described Being provided with jacking pipe at described jacking mouth within steel pipe column, the concrete transporting described pump line connects Receive, and pour in described steel pipe column.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described The connected mode at jacking pipe and described jacking mouth edge is for welding.
Further improvement is that of this utility model steel pipe column concrete lifting interface turnover device, described Jacking pipe is mouth of pipe swan-neck upwards.
Accompanying drawing explanation
Fig. 1 is the structure chart of this utility model steel pipe column concrete lifting interface turnover device.
Fig. 2 is the A line profile of this utility model steel pipe column concrete lifting interface turnover device.
Detailed description of the invention
For the benefit of the understanding to structure of the present utility model, says below in conjunction with drawings and Examples Bright.
Refer to Fig. 1, Fig. 2, Fig. 1 shows this utility model steel pipe column concrete lifting interface week The structure chart of rotary device;Fig. 2 shows this utility model steel pipe column concrete lifting interface turnover device A line profile.
The otch that the mode weld with steel pipe column for pump line during solution tradition casting concrete, cut is brought Uneven, the drawback of damage concrete, this utility model provides a kind of steel pipe column concrete lifting interface Turnover device, including: concrete conveyance structure, including pump line 1, it is located on pump line 1 pump line 1 Inner concrete carry out the stop valve 2 that dams and concrete pump (concrete conveyance power set, not Illustrated);Fixed structure, described fixed structure is fixed in described pump line and described jacking mouth edge Described steel pipe column 6 on so that described pump line 1 is communicated in described jacking mouth.
Hereinafter said modules is described in detail:
This utility model steel pipe column concrete lifting interface turnover device is by fixed structure by pump line 1 admittedly At the jacking mouth of steel pipe column 6, and when pump line 1 being transported concrete by external device, pass through Jacking mouth enters steel pipe column 6, pours carrying out concrete in steel pipe column 6.
For reaching above-mentioned purpose, concrete conveyance structure of the present utility model includes a pump line 1 and to pump Pipe 1 inner concrete carries out the stop valve 2 dammed, by stop valve 2 control concrete circulation and Cut-off.When constructing in construction site, the transport to concrete is all to use concrete pump to enter Row pressure delivery, so pump line needs to meet certain intensity, it is preferable that pump line 1 is steel pipe.? The stop valve 2 of flow control effect is set on steel pipe.
In jacking technique is constructed, the typically sidepiece at steel pipe column 6 offers jacking mouth in advance, by top Rising mouth and carry out concreting to steel pipe column 6 is internal, concrete conveyance structure is fixed on jacking mouth, and Make pump line 1 be communicated in jacking mouth, steel pipe column 6 is carried out concreting, defeated for reaching concrete Sending fixing this purpose of structure and steel pipe column 6, pump line 1 connects fixed structure, fixed structure bag Including fixed plate 4 and weld bolt 3, fixed plate 4 is fixed in jacking mouth by weld bolt 3, fixing Plate 4 is provided with the connecting hole (diagram does not gives label) closely interted for pump line 1, and pump line 1 is by wearing Cross connecting hole to be docking together with jacking mouth, again because fixed plate 4 is fixed on steel pipe column 6, further Pump line 1 be fixed on steel pipe column 6 and connect with jacking mouth.Preferably, pump line 1 welds with connecting hole Ensure the stability of structure together.
In order to strengthen the bonding strength between fixed plate 4 and steel pipe column 6, fixed plate 4 and steel pipe column 6 Between contact surface should be the most identical, concrete shape should determine according to Specific construction, such as, Large circular Shape steel pipe column, then fixed plate 4 should have certain radian;Large-scale square bar tubing string, fixed plate 4 Should be smooth.This should not be used as the restriction in this utility model structure.
For the damage preventing being rigidly connected between fixed plate 4 and steel pipe column 6 from bringing, in fixed plate Being provided with one layer of packing ring 5 between 4 and steel pipe column 6, an effect of packing ring 5 is stress buffering, prevents Structural damage, on the other hand also functions to the sealing function of pump line 1 and jacking mouth.Preferably, packing ring 5 Select the preferable rubber washer of ductility.
Fixed structure is in addition to for fixed plate 4 and weld bolt 3, it is also possible to be usual technological means The solder technology used, i.e. fixed structure are one or more steel section (not giving accompanying drawing explanation), The outer tube wall of pump line 1 is fixed in steel section one end, and the other end is fixed on the steel pipe column 6 of jacking mouth edge On, equally, packing ring 5 can also be set between pump line 1 and steel pipe column 6, utilize steel section to fix, Wherein the concrete shape of steel section can be long and straight type, oblique is welded between pump line 1 and steel pipe column 6;Also Can be L-type, depending on its concrete shape is according to practice of construction, not as restriction of the present utility model.
Concrete by pump line 1 enter inside steel pipe column 6 can to steel pipe column 6 avoid produce bigger Impulsive force, in order to prevent the generation of this situation, arranges a top at the jacking mouth inside steel pipe column 6 Riser 7, jacking pipe 7 receives the mixed earth of pump line 1 and pours steel pipe column 6, it is preferable that Jacking pipe 7 is bending swan-neck upwards, and swan-neck 7 is selected steel swan-neck, and welded with jacking mouth It is connected together.Receiving the concrete in pump line 1 for convenience, the diameter of jacking pipe 7 should be greater than jacking The diameter of mouth, finds through the operation of repeatedly practice of construction, the diameter of jacking pipe 7 should be greater than jacking mouth 80mm 100mm is optimal.
The practical operation of this utility model steel pipe column concrete lifting interface turnover device is:
First, according to practice of construction needs, the sidepiece at steel pipe column 6 cuts with jacking mouth, under cutting The steel plate come retains, and welds jacking pipe 7 at the inside jacking mouth of steel pipe column 6;Then incite somebody to action this The pump line 1 of utility model is welded on one and has in the fixed plate 4 of connecting hole, by fixed plate 4 by weldering Connecting bolt 3 is welded on steel pipe column 6, and arranges between steel pipe column 6 and fixed plate 4 before welding Rubber washer 5 (pump line to be made alignment jacking mouth), then opens stop valve 2, passes through concrete Delivery pump high-pressure delivery concrete, pour complete after, close stop valve 2, wait concrete coagulation; After concrete coagulation to some strength, remove weld bolt 3, concrete is picked chisel, enters And remove this utility model, and after concrete at jacking mouth is picked chisel, the steel that will cut down before Plate repair welding is at jacking mouth.
The beneficial effects of the utility model are, this utility model steel pipe column concrete lifting interface has enough to meet the need Pump line 1 is fixed at the jacking mouth of steel pipe column 6 by device by fixed structure, and passes through external device When pump line 1 is transported concrete, enter steel pipe column 6 by jacking mouth, mix in steel pipe column 6 Pouring of solidifying soil, when solving tradition casting concrete, pump line welds with steel pipe column, the mode cut is brought Otch uneven, damage the drawback of concrete, and this device can have enough to meet the need use, economical environment-protective.
Above in association with accompanying drawing embodiment, this utility model is described in detail, common skill in this area This utility model can be made multiple change by art personnel according to the above description.Thus, do not violating this reality On the premise of novel claim objective, some details in embodiment should not be constituted this practicality Novel restriction, this utility model by the scope that defines using appended claims as protection domain.

Claims (9)

1. a steel pipe column concrete lifting interface turnover device, is applied to jacking mouth bottom steel pipe column Place, to carrying out concrete press-casting and jacking in described steel pipe column, it is characterised in that described steel pipe column mixes Solidifying soil jacking interface turnover device includes:
Concrete conveyance structure, stop valve and the concrete of including pump line, being located at described pump line are defeated Send pump;
Described pump line is fixed in the fixed structure of described steel pipe column, and described pump line passes through described steel pipe column Described jacking mouth and be communicated in the inside of described steel pipe column.
Steel pipe column concrete lifting interface turnover device the most according to claim 1, its feature Being: described fixed structure includes fixed plate and weld bolt, described fixed plate is by described welding spiral shell Bolt is welded on the described steel pipe column at described jacking mouth edge, and described fixed plate is provided with for described pump line tight The connecting hole of close connection, described pump line is arranged in described connecting hole and is connected to described jacking mouth.
Steel pipe column concrete lifting interface turnover device the most according to claim 2, its feature It is: the connected mode of described pump line and described connecting hole is for welding.
Steel pipe column concrete lifting interface turnover device the most according to claim 2, its feature It is: described fixed plate fits tightly in the edge of described jacking mouth.
Steel pipe column concrete lifting interface turnover device the most according to claim 1, its feature It is: described fixed structure includes being arranged at one or more steel sections of described pump line one end, described steel Duan Yiduan is fixed on described pump line outer tube wall, and the other end is welded in the described steel pipe at described jacking mouth edge Post so that described pump line is connected to described jacking mouth.
Steel pipe column concrete lifting interface turnover device the most according to claim 1, its feature It is: on the described pump line between described jacking mouth, described fixed structure and described pump line, circle is provided with and is subject to Power buffering, the packing ring of sealing function.
Steel pipe column concrete lifting interface turnover device the most according to claim 1, its feature It is: be provided with jacking pipe at the described jacking mouth within described steel pipe column, described pump line is transported Concrete receives, and pours in described steel pipe column.
Steel pipe column concrete lifting interface turnover device the most according to claim 7, its feature It is: the connected mode at described jacking pipe and described jacking mouth edge is for welding.
Steel pipe column concrete lifting interface turnover device the most according to claim 7, its feature It is: described jacking pipe is mouth of pipe swan-neck upwards.
CN201620304861.3U 2016-04-13 2016-04-13 Steel -pipe column concrete jacking interface turnover device Expired - Fee Related CN205475710U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620304861.3U CN205475710U (en) 2016-04-13 2016-04-13 Steel -pipe column concrete jacking interface turnover device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620304861.3U CN205475710U (en) 2016-04-13 2016-04-13 Steel -pipe column concrete jacking interface turnover device

Publications (1)

Publication Number Publication Date
CN205475710U true CN205475710U (en) 2016-08-17

Family

ID=56640749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620304861.3U Expired - Fee Related CN205475710U (en) 2016-04-13 2016-04-13 Steel -pipe column concrete jacking interface turnover device

Country Status (1)

Country Link
CN (1) CN205475710U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469329A (en) * 2018-10-30 2019-03-15 浙江中南建设集团有限公司 One kind can have enough to meet the need steel pipe column pumping Lifting Equipment and jacking interface construction method
CN111749467A (en) * 2020-06-29 2020-10-09 中冶天工集团有限公司 Jacking device for steel pipe concrete and construction method thereof
CN112878500A (en) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 Jacking construction method for recycling concrete pump pipe

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469329A (en) * 2018-10-30 2019-03-15 浙江中南建设集团有限公司 One kind can have enough to meet the need steel pipe column pumping Lifting Equipment and jacking interface construction method
CN109469329B (en) * 2018-10-30 2021-04-23 浙江中南建设集团有限公司 Recyclable steel pipe column pumping jacking equipment and jacking interface construction method
CN112878500A (en) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 Jacking construction method for recycling concrete pump pipe
CN111749467A (en) * 2020-06-29 2020-10-09 中冶天工集团有限公司 Jacking device for steel pipe concrete and construction method thereof

Similar Documents

Publication Publication Date Title
CN101914917B (en) Anti-seepage and leak-blocking construction method for excavation of subway foundation pit in soft soil area
CN205475710U (en) Steel -pipe column concrete jacking interface turnover device
CN103233481B (en) A kind of jacket support structure connected that is in the milk
CN103321255A (en) Underground concrete structural engineering joint waterproof construction method
CN109630151A (en) Rectangular top pipe tunneling construction method
WO2020248702A1 (en) Bidirectional overall stirring apparatus and method for reinforcing shallow soft foundation using same
CN105862872B (en) A kind of deep footing groove enclosing structure joint seal construction method
CN208763204U (en) A kind of vertical connecting structure of low layer assembled architecture prefabricated panel
CN103410529B (en) A kind of support of tunnel arch springing ruggedized construction for weak surrounding rock and construction method
CN211144384U (en) High-pressure rotary jet drill bit for geological drilling machine
CN101205718A (en) Method and equipment for seepage-proofing construction of dam and foundation pit
CN101709577A (en) Quick-thawing method of frozen soil foundation
CN208105923U (en) A kind of existing pond increases the connecting joint structure of water string
CN104153464A (en) Steel pipe concrete jacking inserting plate type control device and method for connecting steel pipe concrete jacking inserting plate type control device to steel pipe column
CN204024068U (en) A kind of hoisting steel pipe pillar concrete connection control device
CN207392205U (en) Pile foundation post-grouting device
CN106836215B (en) Inside and outside hydraulic pressure autobalance steel pile casting
CN205206784U (en) Colliery water damage prevention and cure device
CN205501988U (en) Stake of binocular shape hasp
CN107338816A (en) A kind of high artesian post-cast strip is depressured leak-blocking construction method
CN205917988U (en) Anchor bar bundle structure
CN204825912U (en) Defeated material drilling tool of composite pile dual circuit
CN205314085U (en) A biliquid slip casting system that is used for cement and water glass solution
CN206607586U (en) A kind of self-balancing grouting under pressure steel tube for soil-nail structure
CN104018475B (en) A kind of embedded penstock backfill grouting structure and grouting process thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160817