CN112878500A - Jacking construction method for recycling concrete pump pipe - Google Patents

Jacking construction method for recycling concrete pump pipe Download PDF

Info

Publication number
CN112878500A
CN112878500A CN201911200294.1A CN201911200294A CN112878500A CN 112878500 A CN112878500 A CN 112878500A CN 201911200294 A CN201911200294 A CN 201911200294A CN 112878500 A CN112878500 A CN 112878500A
Authority
CN
China
Prior art keywords
column
pump pipe
concrete
pipe joint
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911200294.1A
Other languages
Chinese (zh)
Inventor
唐启旭
刘明路
范业翔
赵和庆
于成龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Shanghai Steel Structure Technology Co Ltd
Original Assignee
MCC Shanghai Steel Structure Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shanghai Steel Structure Technology Co Ltd filed Critical MCC Shanghai Steel Structure Technology Co Ltd
Priority to CN201911200294.1A priority Critical patent/CN112878500A/en
Publication of CN112878500A publication Critical patent/CN112878500A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3505Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by the in situ moulding of large parts of a structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3522Extraordinary methods of construction, e.g. lift-slab, jack-block characterised by raising a structure and then adding structural elements under it
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention relates to a jacking construction method for recycling a concrete pump pipe; the method is characterized in that: the method comprises the steps that a column built-in reinforcing plate is welded at a column body feeding port in a processing stage, a bolt is built in advance, and the inner side of a bolt column is firmly welded and fixed; the joint of the pump pipe outside the column is leaned against the column body and is fastened through a bolt fixed on a built-in reinforcing plate of the column, so that the lateral displacement of the pump pipe is reduced; connecting the stop valve and the pump pipe joint with the pump pipe joint outside the column; dismantling: disconnecting the connection between the concrete at the column side and the pump workshop; disconnecting the connection between the concrete in the column and the pump pipe joint; the pump pipe joint and the stop valve are detached; the pump pipe joint outside the column is separated from the column body. The two-stage stop valve is arranged, so that the joint pump pipe can be recycled; the pump pipe cutting head does not need to be cut off any more, and the contact surface can be separated by disassembling the bolt and knocking with a steel hammer, so that the construction difficulty is reduced, and the manual input is reduced; the concrete of the joint surface of the column body is formed when the concrete inside and outside the column is separated, and the surface is smoother and more beautiful after solidification.

Description

Jacking construction method for recycling concrete pump pipe
Technical Field
The invention relates to the field of concrete construction, in particular to a jacking construction method for recycling a concrete pump pipe.
Background
The jacking construction process of the traditional concrete filled steel tubular column approximately comprises the following steps: (1) welding a joint pump pipe on the steel pipe concrete column, and arranging a stop valve; (2) after the concrete is jacked to a specified elevation, the stop valve is closed, and the joint pump pipe is cut off after the concrete is initially set. In the process, the joint pump pipe cannot be reused because the concrete is solidified in the joint pump pipe, and only can be discarded. When the number of the steel tube concrete columns is large, the material waste is large, and the cutting and polishing operation amount of the pump tubes of the column bodies is large.
Disclosure of Invention
The invention aims to overcome the defects and provide a construction method which enables the joint pump pipe to be repeatedly recycled, enables the surface of the column body to be smoother and reduces the workload of processing the appearance of the column body.
In order to achieve the above object, the present invention is realized by:
a jacking construction method for recycling a concrete pump pipe comprises the following steps: the device comprises an external column pump pipe joint, a stop valve, a pump pipe joint and a column built-in reinforcing plate; the jacking construction method comprises the following steps
Step 1, welding a column built-in reinforcing plate at a column body feeding port part in a processing stage, building a bolt in advance, and firmly welding and fixing the inner side of a bolt column;
before the concrete jacking construction, the joint of the pump pipe outside the column is leaned against the column body and is fastened through a bolt fixed on a built-in reinforcing plate of the column, so that the lateral displacement of the pump pipe is reduced;
step 3, connecting the stop valve and the pump pipe joint with the pump pipe joint outside the column in sequence;
step 4, the dismantling step comprises:
step 4.1, knocking the stop valve downwards after the concrete is jacked to a specified elevation, and disconnecting the connection between the concrete on the column side and the pump workshop;
step 4.2, knocking the pump pipe joint outside the column to enable the joint round hole and the column body round hole to be completely staggered, and disconnecting the connection between the concrete in the column and the pump pipe joint;
4.3, sequentially detaching the pump pipe joint and the stop valve, and cleaning concrete in the pipe;
step 4.4, cleaning concrete in the pipe joint of the pump pipe outside the column;
4.5, after the concrete is initially set, removing nuts on the built-in bolts of the built-in reinforcing plates of the columns to separate the pump pipe joints outside the columns from the column bodies;
wherein,
the end plate of the external concrete pump pipe joint is provided with an L-shaped groove, during the concrete jacking, the bolt is fixedly embedded in the transverse groove, after the concrete is jacked to a specified elevation, the end plate is knocked, so that the bolt is transferred to the top of the vertical groove, and the external concrete pump pipe joint and the hole of the column body are completely staggered.
In the traditional concrete jacking construction process, the joint pump pipe is scrapped after being used once, the joint pump pipe is cut, time is consumed, and concrete on the joint surface of the column body is not smooth. According to the invention, the two-stage stop valve is arranged, so that the joint pump pipe can be recycled, and the resource waste is reduced; the pump pipe cutting head does not need to be cut off any more, and the contact surface can be separated by disassembling the bolt and knocking with a steel hammer, so that the construction difficulty is reduced, and the manual input is reduced; the concrete of the joint surface of the column body is formed when the concrete inside and outside the column is separated, and the surface is smoother and more beautiful after the concrete is solidified.
Drawings
Fig. 1 is a schematic view of the connection structure of the respective components of the present invention.
FIG. 2 is a first schematic view of the construction sequence of the present invention.
FIG. 3 is a schematic view of the construction sequence of the present invention.
FIG. 4 is a schematic illustration of the outer column pump tube of the present invention removed.
FIG. 5 is a construction effect diagram of the method.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1, a jacking construction method for recycling a concrete pump pipe includes: the device comprises an external column pump pipe joint 1, a stop valve 2, a pump pipe joint 3 and an internal column reinforcing plate 4.
As shown in fig. 2, 3 and 5, the jacking construction method includes
Step 1, welding a column built-in reinforcing plate 4 at a column body feeding port part in a machining stage, building a bolt in advance, and firmly welding and fixing the inner side of a bolt column;
before the concrete jacking construction, the pump pipe joint 1 outside the column is leaned against the column body and fastened through bolts fixed on the built-in reinforcing plate of the column, so that the lateral displacement of the pump pipe joint is reduced;
step 3, connecting the stop valve 2 and the pump pipe joint 3 with the pump pipe joint 1 outside the column in sequence;
step 4, the dismantling step comprises:
step 4.1, knocking the stop valve 2 downwards after the concrete is jacked to a specified elevation, and disconnecting the connection between the concrete on the column side and the pump workshop;
step 4.2, knocking the pump pipe joint 1 outside the column to enable the joint round hole and the column body round hole to be completely staggered, and disconnecting the connection between the concrete in the column and the pump pipe joint;
4.3, sequentially detaching the pump pipe joint 3 and the stop valve 2, and cleaning concrete in the pipe;
4.4, cleaning concrete in the pipe of the pump pipe joint 1 outside the column;
step 4.5, after the concrete is initially set, removing nuts on the built-in bolts of the built-in reinforcing plate 4 of the column, and separating the pump pipe joint 1 outside the column from the column body;
as shown in fig. 4, in which,
the end plate of the external column concrete pump pipe joint 1 is provided with an L-shaped groove, during the concrete jacking, a bolt is fixedly embedded in the transverse groove, after the concrete is jacked to a specified elevation, the end plate is knocked, the bolt is transferred to the top of the vertical groove, and therefore the external column concrete pump pipe joint 1 and the column body are completely staggered.
In the traditional concrete jacking construction process, the joint pump pipe is scrapped after being used once, the joint pump pipe is cut, time is consumed, and concrete on the joint surface of the column body is not smooth. According to the invention, the two-stage stop valve is arranged, so that the joint pump pipe can be recycled, and the resource waste is reduced; the pump pipe cutting head does not need to be cut off any more, and the contact surface can be separated by disassembling the bolt and knocking with a steel hammer, so that the construction difficulty is reduced, and the manual input is reduced; the concrete of the joint surface of the column body is formed when the concrete inside and outside the column is separated, and the surface is smoother and more beautiful after the concrete is solidified.

Claims (1)

1. A jacking construction method for recycling a concrete pump pipe comprises the following steps: the device comprises an external column pump pipe joint (1), a stop valve (2), a pump pipe joint (3) and a built-in column reinforcing plate (4); the method is characterized in that: the jacking construction method comprises the following steps
Step 1, welding a column built-in reinforcing plate (4) at a column body feeding port part in a processing stage, building a bolt in advance, and firmly welding and fixing the inner side of a bolt column;
before the concrete jacking construction, the pump pipe joint (1) outside the column is leaned against the column body and fastened through bolts fixed on the built-in reinforcing plate of the column, so that the lateral displacement of the pump pipe joint is reduced;
step 3, connecting the stop valve (2) and the pump pipe joint (3) with the pump pipe joint (1) outside the column in sequence;
step 4, the dismantling step comprises:
step 4.1, knocking the stop valve (2) downwards after the concrete is jacked to a specified elevation, and disconnecting the connection between the concrete on the column side and a pump workshop;
step 4.2, knocking the pump pipe joint (1) outside the column to enable the joint round hole and the column body round hole to be completely staggered, and disconnecting the connection between the concrete in the column and the pump pipe joint;
4.3, sequentially dismounting the pump pipe joint (3) and the stop valve (2) and cleaning concrete in the pipe;
4.4, cleaning concrete in the pipe of the external pump pipe joint (1) of the column;
step 4.5, after the concrete is initially set, removing nuts on the built-in bolts of the built-in reinforcing plate (4) of the column, and separating the pump pipe joint (1) outside the column from the column body;
wherein,
the end plate of the external column concrete pump pipe joint (1) is provided with an L-shaped groove, during the concrete jacking, a bolt is embedded and fixed in the transverse groove, after the concrete is jacked to a specified elevation, the end plate is knocked, the bolt is transferred to the top of the vertical groove, and therefore the external column concrete pump pipe joint (1) and the hole of the column body are completely staggered.
CN201911200294.1A 2019-11-29 2019-11-29 Jacking construction method for recycling concrete pump pipe Pending CN112878500A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911200294.1A CN112878500A (en) 2019-11-29 2019-11-29 Jacking construction method for recycling concrete pump pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911200294.1A CN112878500A (en) 2019-11-29 2019-11-29 Jacking construction method for recycling concrete pump pipe

Publications (1)

Publication Number Publication Date
CN112878500A true CN112878500A (en) 2021-06-01

Family

ID=76039053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911200294.1A Pending CN112878500A (en) 2019-11-29 2019-11-29 Jacking construction method for recycling concrete pump pipe

Country Status (1)

Country Link
CN (1) CN112878500A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114109042A (en) * 2022-01-12 2022-03-01 山东三箭建设工程股份有限公司 Check valve for construction of concrete filled steel tubular column by jacking method and application method thereof
CN114673261A (en) * 2022-03-31 2022-06-28 上海宝冶集团有限公司 Closed inclined steel pipe column concrete jacking construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2474383A1 (en) * 1980-01-30 1981-07-31 Wolf Johann Gmbh Kg Pumping for feeding concrete into wall forms of circular silo - is horizontal and pivots about vertical axis supported by centre post core frame (AT 15.2.81)
JPH0726726A (en) * 1993-05-14 1995-01-27 Mitsubishi Heavy Ind Ltd Zone module construction method for constructing steel structure
CN202899301U (en) * 2012-11-16 2013-04-24 中建八局第三建设有限公司 Hold hoop device for jacking steel pipe concrete
CN202925675U (en) * 2012-10-15 2013-05-08 中天建设集团有限公司天津分公司 Non-return device use for pouring of steel column core concrete in lift-up method
CN103883126A (en) * 2014-03-31 2014-06-25 武汉一冶建筑安装工程有限责任公司 Plugboard non-return flow type concrete jacking filling construction method
CN104153464A (en) * 2014-08-26 2014-11-19 中冶天工集团有限公司 Steel pipe concrete jacking inserting plate type control device and method for connecting steel pipe concrete jacking inserting plate type control device to steel pipe column
CN104989103A (en) * 2015-05-15 2015-10-21 甘肃第六建设集团股份有限公司 Concrete filled steel tube pumping lifting-up stop valve installation method
CN105442707A (en) * 2015-12-30 2016-03-30 中国二十二冶集团有限公司 Jacking and connecting device for steel pipe column concrete
CN205475710U (en) * 2016-04-13 2016-08-17 中国建筑第八工程局有限公司 Steel -pipe column concrete jacking interface turnover device
CN209145295U (en) * 2018-09-28 2019-07-23 李孝贤 A kind of steel pipe column concrete lifting device

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2474383A1 (en) * 1980-01-30 1981-07-31 Wolf Johann Gmbh Kg Pumping for feeding concrete into wall forms of circular silo - is horizontal and pivots about vertical axis supported by centre post core frame (AT 15.2.81)
JPH0726726A (en) * 1993-05-14 1995-01-27 Mitsubishi Heavy Ind Ltd Zone module construction method for constructing steel structure
CN202925675U (en) * 2012-10-15 2013-05-08 中天建设集团有限公司天津分公司 Non-return device use for pouring of steel column core concrete in lift-up method
CN202899301U (en) * 2012-11-16 2013-04-24 中建八局第三建设有限公司 Hold hoop device for jacking steel pipe concrete
CN103883126A (en) * 2014-03-31 2014-06-25 武汉一冶建筑安装工程有限责任公司 Plugboard non-return flow type concrete jacking filling construction method
CN104153464A (en) * 2014-08-26 2014-11-19 中冶天工集团有限公司 Steel pipe concrete jacking inserting plate type control device and method for connecting steel pipe concrete jacking inserting plate type control device to steel pipe column
CN104989103A (en) * 2015-05-15 2015-10-21 甘肃第六建设集团股份有限公司 Concrete filled steel tube pumping lifting-up stop valve installation method
CN105442707A (en) * 2015-12-30 2016-03-30 中国二十二冶集团有限公司 Jacking and connecting device for steel pipe column concrete
CN205475710U (en) * 2016-04-13 2016-08-17 中国建筑第八工程局有限公司 Steel -pipe column concrete jacking interface turnover device
CN209145295U (en) * 2018-09-28 2019-07-23 李孝贤 A kind of steel pipe column concrete lifting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114109042A (en) * 2022-01-12 2022-03-01 山东三箭建设工程股份有限公司 Check valve for construction of concrete filled steel tubular column by jacking method and application method thereof
CN114673261A (en) * 2022-03-31 2022-06-28 上海宝冶集团有限公司 Closed inclined steel pipe column concrete jacking construction method

Similar Documents

Publication Publication Date Title
CN112878500A (en) Jacking construction method for recycling concrete pump pipe
CN102409851B (en) Method and system for reinforcing telescopic supporting system for deformation joint template of shear wall structure
CN104074352A (en) Wall body template supporting method in position with narrow space
CN102431088B (en) Decomposable type spring die assembling bolt
CN111395175B (en) Pier column template for road and bridge building
CN204357448U (en) Tunnel lining cutting movement joint red copper waterstop end template reinforcement processing apparatus
CN204277898U (en) Relief valve overhauls device
CN113585764B (en) Concrete pouring device for jacking pump of tall steel pipe concrete column and construction method of concrete pouring device
KR20090091895A (en) A tie for architecture
CN215407372U (en) Quick detach formula aluminum alloy template
CN211849566U (en) Roughing mill body reserved bolt hole support-free template
CN201162346Y (en) Pore-creating device for box beam ventilating openings
CN208379576U (en) A kind of filling pile head processing unit
CN210164591U (en) Drilling site mud pump piston repairing device
CN210880204U (en) Spiral force transmission type embedded tool
CN111112947A (en) Engine expansion section II section milling flutes device
CN107891521B (en) Construction method for prefabricated comprehensive pipe gallery tensioning box
CN201442167U (en) Special work automobile brake drum fast-disassembling device
CN220117125U (en) Fender built-in fitting reuse fixing device
CN109555005A (en) A kind of concrete box girder maintenance people hole template and its application method
CN218668568U (en) Quick dismounting device suitable for pressurizing concrete-filled steel tube member
CN104260046A (en) Disassembling tool for pistons of petroleum drilling pumps
CN103223569A (en) Method for repairing moving cone of cone crushing machine
CN216515166U (en) Quick detachable bridge hollow beam steel system centre form
CN213329974U (en) Steel pipe fixing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210601