CN107317257A - 4 × " one leads 2 " wires-erecting pulley hangers - Google Patents

4 × " one leads 2 " wires-erecting pulley hangers Download PDF

Info

Publication number
CN107317257A
CN107317257A CN201710691296.XA CN201710691296A CN107317257A CN 107317257 A CN107317257 A CN 107317257A CN 201710691296 A CN201710691296 A CN 201710691296A CN 107317257 A CN107317257 A CN 107317257A
Authority
CN
China
Prior art keywords
connecting plate
liang
succession
wires
leads
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710691296.XA
Other languages
Chinese (zh)
Inventor
韩启云
朱立明
黄成云
桂和怀
朱冠昱
单长孝
李凯
徐鹏飞
杨泰朋
关绍峰
赵杰
姚永先
田新宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Anhui Power Transmission and Transformation Engineering Co Ltd
Original Assignee
State Grid Corp of China SGCC
Anhui Power Transmission and Transformation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Anhui Power Transmission and Transformation Engineering Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710691296.XA priority Critical patent/CN107317257A/en
Publication of CN107317257A publication Critical patent/CN107317257A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Electric Cable Installation (AREA)

Abstract

4 × " one leads 2 " wires-erecting pulley hangers, and it is related to work transmission line apparatus technical field;V-type insulator chain is won in succession with pendency to be fixedly connected, and dangles and gold utensil is fixed with winning in succession, and the both sides won in succession of dangling are connected by channel-section steel with first liang of connecting plate respectively, and two first liang of connecting plate are connected by crossbeam, and two second liang of connecting plate are fixed with crossbeam;First liang of described connecting plate and the bottom of second liang of connecting plate have been bolted right angle hanging plate respectively, and the lower end of right angle hanging plate is fixed with three-fold block.Of the present invention 4 × " one leads 2 " wires-erecting pulley hangers, avoid the work for needing to adjust coaster height under independent suspension coaster mode, advantageously ensure that Construction of Tension Stringing sag observation quality, avoid the problem of independent suspension coaster mode needs a large amount of rope slings, hanger, Work tool simultaneously, multiple coaster arrangements and the complicated problem of hang are efficiently solved, facilitates postorder Construction of Tension Stringing and annex installation operation.

Description

4 × " one leads 2 " wires-erecting pulley hangers
Technical field
The present invention relates to work transmission line apparatus technical field, and in particular to 4 × " one leads 2 " wires-erecting pulley hangers.
Background technology
Because steel tower will hang 4 or 8 three wheel line tackles per pole, prior art uses independent suspension coaster mode, Pulley suspension workload is big, and coaster arrangement and hang are complicated, and postorder Construction of Tension Stringing and annex installation operation are inconvenient.
The content of the invention
In view of the defects and deficiencies of the prior art, the present invention intends to provide one kind is simple in construction, reasonable in design, make With convenient 4 × " one leads 2 " wires-erecting pulley hangers.
To achieve the above object, the technical solution adopted by the present invention is:It wins in succession comprising V-type insulator chain, pendency, gold Tool, crossbeam, channel-section steel, first liang of connecting plate, second liang of connecting plate, right angle hanging plate, bolt, three-fold block;Described V-type insulator chain with Pendency, which is won in succession, to be fixedly connected, and dangles and gold utensil is fixed with winning in succession, and the both sides won in succession of dangling are respectively by channel-section steel and first liang of connecting plate Connection, two first liang of connecting plate are connected by crossbeam, and two second liang of connecting plate are fixed with crossbeam;Described first liang of connecting plate and The bottom of second liang of connecting plate has been bolted right angle hanging plate respectively, and the lower end of right angle hanging plate is fixed with three-fold block.
Preferably, first liang of described connecting plate and second liang of connecting plate are by the first connecting plate and the connection of the second connecting plate Into the second connecting plate vertically plugs the bottom for being fixed on the first connecting plate;Divide on first liang of described connecting plate and second liang of connecting plate Four eyelets and three eyelets are not provided with.
Preferably, the middle part that described pendency is won in succession is fixedly connected by bolt with crossbeam middle part.
Preferably, described two first liang of connecting plate and two second liang of connecting plate are uniformly fixed on crossbeam by bolt On.
Preferably, described channel-section steel is reinforced channel-section steel.
During present invention operation, V-type insulator chain, gold utensil, three-fold block are synchronized into installation and hung, construction is reduced Fixing link, so as to improve the overall efficiency of construction of tension stringing, advantageously ensures that the good stress of steel tower;Utilize coaster hanger 4 three-fold blocks are suspended on same support body, 4 contour, straight and even purposes of releasing pulley are reached;Due to first liang of company Plate or two second liang of connecting plate are plugged in the groove of right angle hanging plate, and are connected by screw bolts, and three-fold block is along unwinding direction Can swing, ensure that wire crosses the stability of coaster, it is to avoid situation about mutually colliding with occurs in work progress in coaster.
After said structure, what the present invention was produced has the beneficial effect that:Of the present invention 4 × " one leads 2 " wires-erecting pulley Hanger, it is to avoid need to adjust the work of coaster height under independent suspension coaster mode, advantageously ensure that Construction of Tension Stringing sag observation Quality, while avoiding the problem of independent suspension coaster mode needs a large amount of rope slings, hanger, Work tool, efficiently solves multiple cunnings Car arranges and the complicated problem of hang, facilitates postorder Construction of Tension Stringing and annex installation operation, the present invention have it is simple in construction, Set rationally, low manufacture cost the advantages of.
Brief description of the drawings
Fig. 1 is the structure chart of the present invention;
Fig. 2 is the structure chart of first liang of connecting plate of the invention;
Fig. 3 is Fig. 2 side view;
Fig. 4 is the structure chart of second liang of connecting plate of the invention;
Fig. 5 is Fig. 4 side view.
Description of reference numerals:
V-type insulator chain 1, pendency are won in succession 2, gold utensil 3, crossbeam 4, channel-section steel 5, first liang of connecting plate 6, second liang of connecting plate 7, right angle hanging plate 8th, bolt 9, three-fold block 10, the first connecting plate 11, the second connecting plate 12.
Embodiment
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also To obtain other accompanying drawings according to these accompanying drawings.
Referring to such as Fig. 1 --- shown in Fig. 5, present embodiment is adopted the following technical scheme that:It includes V-type insulator chain 1st, pendency is won in succession 2, gold utensil 3, crossbeam 4, channel-section steel 5, first liang of connecting plate 6, second liang of connecting plate 7, right angle hanging plate 8, bolt 9, three skiddings Car 10;Described V-type insulator chain 1 and pendency, which are won in succession, 2 to be fixedly connected, and pendency, which is won in succession, is fixed with gold utensil 3 on 2, and pendency wins 2 in succession Both sides are connected by channel-section steel 5 with first liang of connecting plate 6 respectively, and two first liang of connecting plate 6 are connected by crossbeam 4, are fixed with crossbeam 4 Two second liang of connecting plate 7;First liang of described connecting plate 6 and the bottom of second liang of connecting plate 7 are connected with right angle by bolt 9 respectively and hung Plate 8, the lower end of right angle hanging plate 8 is fixed with three-fold block 10.
Preferably, first liang of described connecting plate 6 and second liang of connecting plate 7 are by the first connecting plate 11 and the second connecting plate 12 It is formed by connecting, the second connecting plate 12 vertically plugs the bottom for being fixed on the first connecting plate 11;Described first liang of connecting plate 6 and second Four eyelets and three eyelets are respectively arranged with two connecting plates 7.
Preferably, described pendency is won in succession, 2 middle part is fixedly connected by the middle part of bolt and crossbeam 4.
Preferably, described two first liang of connecting plate 6 and two second liang of connecting plate 7 are uniformly fixed on crossbeam by bolt On 4.
Preferably, described channel-section steel 5 is reinforced channel-section steel.
When present embodiment is operated, V-type insulator chain 1, gold utensil 3, three-fold block 10 are synchronized into installation and outstanding Hang, reduce construction and installation link, so as to improve the overall efficiency of construction of tension stringing, advantageously ensure that steel tower it is good by Power;4 three-fold blocks 10 are suspended on same support body using coaster hanger, 4 releasing pulleys are reached contour, straight and even Purpose;Connected because first liang of connecting plate 6 or two second liang of connecting plate 7 are plugged in the groove of right angle hanging plate 8, and using bolt 9, Three-fold block 10 along unwinding direction can swing, ensure that wire crosses the stability of coaster, it is to avoid coaster is in work progress There is situation about mutually colliding with.
The hanger of present embodiment three-fold block 10 long 3040mm, high 785mm, the hanging hole spacing of hanger lower end 4 is 900mm.Adjacent 2 apparatus for suspension body space is 320mm after suspension, meets the gap between two adjacent coasters.
Overall structure uniform force.Overall structure utilizes back-to-back angle steel, and centre plus steel plate combination are formed, and all materials are Q345 Zinc-coated angle steels and steel plate, angle steel are the angle steel being commonly used in engineering, draw materials and process and be more convenient.Add according to steel tower Work standard, is produced in batches, it is ensured that overall structure uniform force, entirety is most after being assembled in strict accordance with design manuscript setting-out examination Big bearing load is more than 720kN.
Present embodiment hanger versatility preferably, can be quickly connected with whole hardware strings.
Present embodiment is all connected using 8.8 grade bolts, splits combination conveniently, is easy to mountain area split transport.
Present embodiment is applied to 4 × and " one leads in 2 " unwrapping wire modes and hangs releasing pulley.
After said structure, what present embodiment was produced has the beneficial effect that:Described in present embodiment 4 × " one lead 2 " wires-erecting pulley hangers, it is to avoid needs to adjust the work of coaster height under independent suspension coaster mode, advantageously ensures that tight Line construction sag observation quality, while avoiding the problem of independent suspension coaster mode needs a large amount of rope slings, hanger, Work tool, has Effect solves multiple coaster arrangements and the complicated problem of hang, facilitates postorder Construction of Tension Stringing and annex installation operation, this tool Body embodiment have the advantages that it is simple in construction, set rationally, low manufacture cost.
The general principle and principal character and advantages of the present invention of the present invention has been shown and described above.The skill of the industry Art personnel are it should be appreciated that the present invention is not limited to the above embodiments, and described in above-described embodiment and specification is explanation The principle of the present invention, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these Changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and Its equivalent thereof.

Claims (5)

1.4 × " one leads 2 " wires-erecting pulley hangers, it is characterised in that:It comprising V-type insulator chain, pendency win in succession, gold utensil, crossbeam, Channel-section steel, first liang of connecting plate, second liang of connecting plate, right angle hanging plate, bolt, three-fold block;Described V-type insulator chain is won in succession with pendency It is fixedly connected, dangles and gold utensil is fixed with winning in succession, the both sides won in succession of dangling is connected by channel-section steel with first liang of connecting plate respectively, two First liang of connecting plate is connected by crossbeam, and two second liang of connecting plate are fixed with crossbeam;First liang of described connecting plate and second liang of company The bottom of plate has been bolted right angle hanging plate respectively, and the lower end of right angle hanging plate is fixed with three-fold block.
2. according to claim 14 × " one leads 2 " wires-erecting pulley hangers, it is characterised in that:Described first liang of connecting plate and Second liang of connecting plate is formed by connecting by the first connecting plate and the second connecting plate, and the second connecting plate, which is vertically plugged, is fixed on the first connection The bottom of plate;Four eyelets and three eyelets are respectively arranged with first liang of described connecting plate and second liang of connecting plate.
3. according to claim 14 × " one leads 2 " wires-erecting pulley hangers, it is characterised in that:During described pendency is won in succession Portion is by bolt with being fixedly connected in the middle part of crossbeam.
4. according to claim 14 × " one leads 2 " wires-erecting pulley hangers, it is characterised in that:Two described first liang of company Plate and two second liang of connecting plate are uniformly fixed on crossbeam by bolt.
5. according to claim 14 × " one leads 2 " wires-erecting pulley hangers, it is characterised in that:Described channel-section steel is reinforced Channel-section steel.
CN201710691296.XA 2017-08-14 2017-08-14 4 × " one leads 2 " wires-erecting pulley hangers Pending CN107317257A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710691296.XA CN107317257A (en) 2017-08-14 2017-08-14 4 × " one leads 2 " wires-erecting pulley hangers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710691296.XA CN107317257A (en) 2017-08-14 2017-08-14 4 × " one leads 2 " wires-erecting pulley hangers

Publications (1)

Publication Number Publication Date
CN107317257A true CN107317257A (en) 2017-11-03

Family

ID=60175698

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710691296.XA Pending CN107317257A (en) 2017-08-14 2017-08-14 4 × " one leads 2 " wires-erecting pulley hangers

Country Status (1)

Country Link
CN (1) CN107317257A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202142826U (en) * 2011-07-22 2012-02-08 湖北省输变电工程公司 Electric pulley yoke plate
CN106300129A (en) * 2015-12-10 2017-01-04 国家电网公司 Great span device for suspending line tackles
CN107453273A (en) * 2017-08-14 2017-12-08 青海送变电工程公司 One kind eight divides large-section lead coaster hanger
CN207069439U (en) * 2017-08-14 2018-03-02 安徽送变电工程公司 4 × " one leads 2 " wires-erecting pulley hangers

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202142826U (en) * 2011-07-22 2012-02-08 湖北省输变电工程公司 Electric pulley yoke plate
CN106300129A (en) * 2015-12-10 2017-01-04 国家电网公司 Great span device for suspending line tackles
CN107453273A (en) * 2017-08-14 2017-12-08 青海送变电工程公司 One kind eight divides large-section lead coaster hanger
CN207069439U (en) * 2017-08-14 2018-03-02 安徽送变电工程公司 4 × " one leads 2 " wires-erecting pulley hangers

Similar Documents

Publication Publication Date Title
CN103715633A (en) Clamping device and method for replacing single-hole connecting plate strain insulator string
CN103594976B (en) Combination stringing instrument for line conductor stringing
CN105305317B (en) Live wire hangs the instrument of insulated flexible ladder
CN102916367A (en) Maintenance block for vertical twin bundled conductors
CN205170156U (en) Heavy object lift -over device
CN207069439U (en) 4 × " one leads 2 " wires-erecting pulley hangers
CN107317257A (en) 4 × " one leads 2 " wires-erecting pulley hangers
CN101582571A (en) Multi-supporting point self balancing paying-off tackle
CN206060035U (en) A kind of releasing pulley hanger
CN203562695U (en) Pulley suspension device of power transmission tower cross-arm angle iron
CN203536865U (en) Combined wire-tightening tool for tightening line wire
CN203377535U (en) Self-adaptive type paying-off tackle
CN103350947B (en) Suspension system and suspension method both special for boiler heating surface pipe rack
CN203475318U (en) Cable-clamp-free hanging appliance used for anchoring stay cable at tower end in cable bent tower steel anchor beam area
CN103579952B (en) Bulb fixing-line device for overhead transmission line stringing
CN102208777A (en) Construction method for parallel suspension of lead trolleys by using V-shaped strings
CN203004051U (en) Bracket chain block mold emptier for prefabricated part horizontal moldboard
CN205829038U (en) A kind of eight division 1250mm2device for suspending line tackles
CN104242143A (en) Self-adaptive wire-releasing pulley
CN210693259U (en) Porcelain insulator anti-collision device for large crossing rack line and pulley rack
CN103594974A (en) Yoke plate tightener for overhead line stringing
CN106641452A (en) Suspension frame for overhead operation
CN203553772U (en) Yoke plate line tightening device used for tightening overhead lines
CN203553770U (en) Ball head wire clamping device applied to overhead line stringing
CN208022591U (en) Track girder suspender

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181101

Address after: 230011 Hongyuan building, 1599 Huaining Road, Hefei, Anhui

Applicant after: Anhui transmission and Transformation Engineering Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: 230011 Hongyuan building, 1599 Huaining Road, Hefei, Anhui

Applicant before: Anhui Power Transmission & Transformation Company

Applicant before: State Grid Corporation of China

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171103