CN107288352A - The transport of the closed shed dormer roof boarding of overlarge area and installation method - Google Patents

The transport of the closed shed dormer roof boarding of overlarge area and installation method Download PDF

Info

Publication number
CN107288352A
CN107288352A CN201610193812.1A CN201610193812A CN107288352A CN 107288352 A CN107288352 A CN 107288352A CN 201610193812 A CN201610193812 A CN 201610193812A CN 107288352 A CN107288352 A CN 107288352A
Authority
CN
China
Prior art keywords
roof boarding
skylight
installation
travelling bogie
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610193812.1A
Other languages
Chinese (zh)
Other versions
CN107288352B (en
Inventor
李佰西
林锡森
郭微微
谭星
黄晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610193812.1A priority Critical patent/CN107288352B/en
Publication of CN107288352A publication Critical patent/CN107288352A/en
Application granted granted Critical
Publication of CN107288352B publication Critical patent/CN107288352B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention is specifically transport and the installation method of a kind of closed shed dormer roof boarding of overlarge area;It is included in and lays groined type guide rail on the peripheral factory building roof plate of skylight frame and configure truck crane;Installation carriage and travelling bogie are set up on groined type guide rail;Travelling bogie is pushed into truck crane side along groined type guide rail;Skylight roof boarding is hoisted on travelling bogie using truck crane;Travelling bogie is elapsed to installation carriage;Installation carriage slings lightweight concrete skylight roof boarding;The installation carriage for being lifted with skylight roof boarding is elapsed to the installation site of roof boarding, is transferred using jack tune to skylight frame and carries out being welded and fixed operation.This transport and installation method need not use large-scale crane or tower crane that the installation rate of skylight roof boarding is accelerated in construction, effectively reduce substantial amounts of work high above the ground, reduce the generation of site safety accident.

Description

The transport of the closed shed dormer roof boarding of overlarge area and installation method
Technical field
The present invention relates to the realm of building construction, the transport of specifically a kind of closed shed dormer roof boarding of overlarge area and installation method.
Background technology
Construction market is become increasingly prosperous in recent years, to the requirement more and more higher in terms of building products energy-saving and environmental protection.Lightweight concrete steel framework plate can be met in the material requirements in terms of the energy-saving and environmental protection that construction market is increasingly improved, the wallboard and roof boarding that are widely used in the buildings such as industrial premises and residential houses.Because most of industrial premises and civil buildings are respectively provided with big roof system area, height height and substantially totally enclosed feature, its skylight roof boarding installation problem is increasingly highlighted, and how to overcome the high-altitude of this special construction environment to install problem has turned into the problem of current construction must be solved.
At this stage, traditional truck crane and tower crane can not solve the above problems well on traditional ground large hanging device and roofing, there is co-ordination amount big, security is poor, and boundary of works area is limited, and the construction period is long, large-scale crane machine-team wastes serious, mounting cost is big, and because lightweight concrete roof boarding bearing capacity is poor, can not also carry the weight of large-scale crane.
The content of the invention
It is an object of the present invention to provide a kind of operational method for being easy to the closed shed dormer roof boarding of overlarge area to install and transport.
In order to achieve the above object, the present invention is realized in:
A kind of transport of closed shed dormer roof boarding of overlarge area and installation method, including
Step 1, groined type guide rail laid on the factory building roof plate of skylight frame periphery according to the size of femerell size, skylight the size of the cover plate and skylight frame;
Step 2, erection installation carriage and travelling bogie on groined type guide rail;Wherein, the jack of four rectangular distributions is set on installation carriage, and the jack is used to lift skylight roof boarding;
Step 3, travelling bogie along groined type guide rail pushed into truck crane side;
Step 4, using truck crane lightweight concrete skylight roof boarding is hoisted on travelling bogie;
Step 5, travelling bogie elapsed to below installation carriage;
Step 6, installation carriage are sling lightweight concrete skylight roof boarding using jack;
Step 7, the installation carriage for being lifted with lightweight concrete skylight roof boarding elapsed to the installation site of lightweight concrete skylight roof boarding, adjust the gradient of lightweight concrete skylight roof boarding using jack and transfer to skylight frame progress and be welded and fixed operation.
The transport of the closed shed dormer roof boarding of described overlarge area and installation method, installation carriage described in step 3, travelling bogie in tower structure and are provided with roller in its bottom.
The transport of the closed shed dormer roof boarding of described overlarge area and installation method, groined type guide rail are made using channel-section steel, are attached between track using angle steel, the handing-over of track longitudinally, laterally goes out for cross connectivity structure.
The simple in construction, easy to process of transport, installation carriage and the track that this transport and installation method are used makes and large-scale crane or tower crane need not be used in construction, and then saves lifting cost use;Also so that the installation rate of skylight roof boarding is accelerated, contracted short installation period;Substantial amounts of work high above the ground is effectively reduced, the generation of site safety accident is reduced.
Brief description of the drawings
Fig. 1 is skylight roof boarding lifting schematic diagram in this method.
Fig. 2 is the combining structure schematic diagram of travelling bogie, installation carriage and track in this method.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
As shown in Figure 1 and Figure 2, a kind of transport of the closed shed dormer roof boarding of overlarge area and installation method, including
Step 1, according to the size of femerell size, skylight the size of the cover plate and skylight frame 1 on the factory building roof plate 2 of the periphery of skylight frame 1 laying groined type guide rail 4;
Step 2, erection installation carriage 5 and travelling bogie 6 on groined type guide rail 4;Wherein, the jack 7 of four rectangular distributions is set on installation carriage 5, and the jack 7 is used to lift skylight roof boarding 8;
Step 3, travelling bogie 6 along groined type guide rail 4 pushed into truck crane side;
Step 4, using truck crane lightweight concrete skylight roof boarding 8 is hoisted on travelling bogie 6;
Step 5, travelling bogie 6 elapsed to the lower section of installation carriage 5;
Step 6, installation carriage 5 are sling lightweight concrete skylight roof boarding 8 using jack 7;
Step 7, the installation carriage 5 for being lifted with lightweight concrete skylight roof boarding 8 elapsed to the installation site of lightweight concrete skylight roof boarding 8, adjust the gradient of lightweight concrete skylight roof boarding 8 using jack 7 and transfer to skylight frame 1 progress and be welded and fixed operation.
In above-mentioned construction method,
As shown in Fig. 2 the steel-pipe welding that job site is respectively adopted in the main body of installation carriage 5 and travelling bogie 6 is formed, including four steel pipe posts, up and down two layers of horizontal tube and support tube.Depending on the length, width and height size of installation carriage main body is according to skylight frame size and the gradient, it is wider than skylight frame go out 500mm, ensure that walking gauge both sides are uniform simultaneously, depending on the length, width and height size of travelling bogie main body is according to skylight the size of the cover plate and the skylight frame gradient, length height is significantly less than installation car, width is with installing car with width, and such travelling bogie can be placed in below installation carriage and then be easy to the carry and hoist of skylight roof boarding.
For ease of the walking of installation carriage 5, travelling bogie 6, in installation carriage 5, the root weld roller groove of the main body of travelling bogie 6 and roller 9 is installed, footbrake is made on race to ensure safety, roller widths are slightly less than groove steel rail width, it is ensured that roller accessible walking in orbit.
Groined type guide rail for being advanced for installation carriage, travelling bogie is made using channel-section steel, is attached between track using angle steel, the handing-over of track longitudinally, laterally goes out for cross connectivity structure.
The body top face of the travelling bogie is provided with skid-prevention button, prevents from being arranged on the skylight roof boarding at the top of travelling bogie and is slided because of the gradient.
The simple in construction, easy to process of transport, installation carriage and the track that this transport and installation method are used makes and large-scale crane or tower crane need not be used in construction, and then saves lifting cost use;Also so that the installation rate of skylight roof boarding is accelerated, contracted short installation period;Substantial amounts of work high above the ground is effectively reduced, the generation of site safety accident is reduced.

Claims (3)

1. transport and the installation method of a kind of closed shed dormer roof boarding of overlarge area, it is characterized in that:Also include
Step 1, groined type guide rail laid on the factory building roof plate of skylight frame periphery according to the size of femerell size, skylight the size of the cover plate and skylight frame;
Step 2, erection installation carriage and travelling bogie on groined type guide rail;Wherein, the jack of four rectangular distributions is set on installation carriage, and the jack is used to lift skylight roof boarding;
Step 3, travelling bogie along groined type guide rail pushed into truck crane side;
Step 4, using truck crane lightweight concrete skylight roof boarding is hoisted on travelling bogie;
Step 5, travelling bogie elapsed to below installation carriage;
Step 6, installation carriage are sling lightweight concrete skylight roof boarding using jack;
Step 7, the installation carriage for being lifted with lightweight concrete skylight roof boarding elapsed to the installation site of lightweight concrete skylight roof boarding, adjust the gradient of lightweight concrete skylight roof boarding using jack and transfer to skylight frame progress and be welded and fixed operation.
2. transport and the installation method of the closed shed dormer roof boarding of overlarge area according to claim 1, it is characterized in that:Installation carriage described in step 2, travelling bogie in tower structure and are provided with roller in its bottom.
3. transport and the installation method of the closed shed dormer roof boarding of overlarge area according to claim 1, it is characterized in that:Groined type guide rail is made using channel-section steel, is attached between track using angle steel, the handing-over of track longitudinally, laterally goes out for cross connectivity structure.
CN201610193812.1A 2016-03-31 2016-03-31 The transport of the closed shed dormer roof boarding of overlarge area and installation method Active CN107288352B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610193812.1A CN107288352B (en) 2016-03-31 2016-03-31 The transport of the closed shed dormer roof boarding of overlarge area and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610193812.1A CN107288352B (en) 2016-03-31 2016-03-31 The transport of the closed shed dormer roof boarding of overlarge area and installation method

Publications (2)

Publication Number Publication Date
CN107288352A true CN107288352A (en) 2017-10-24
CN107288352B CN107288352B (en) 2019-07-30

Family

ID=60087850

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610193812.1A Active CN107288352B (en) 2016-03-31 2016-03-31 The transport of the closed shed dormer roof boarding of overlarge area and installation method

Country Status (1)

Country Link
CN (1) CN107288352B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109256736A (en) * 2018-09-14 2019-01-22 中国冶集团有限公司 A kind of wire box built-in process and positioning device
CN109838055A (en) * 2017-11-24 2019-06-04 中建安装工程有限公司 High-altitude is installed by steel frame and light concrete face-board for room special mounting vehicle
CN111336314A (en) * 2020-04-26 2020-06-26 中国二十二冶集团有限公司 Large-caliber pipeline roof installation device and construction method thereof
CN115538790A (en) * 2022-09-02 2022-12-30 广州市机电安装有限公司 Installation method of long and narrow hyperboloid steel roof
CN115596217A (en) * 2022-11-28 2023-01-13 中国二十二冶集团有限公司(Cn) Integral installation method for three-hinged arch skylight frame of steel structure factory building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08333813A (en) * 1995-06-07 1996-12-17 Takenaka Komuten Co Ltd Building method of building unit for vertical and horizontal conveying
CN201560539U (en) * 2009-09-30 2010-08-25 中太建设集团股份有限公司 Tool car for long-span net rack roof space plate
CN201857761U (en) * 2010-08-10 2011-06-08 中建五局工业设备安装有限公司 Hoisting and sliding device and hoisting and sliding equipment
CN202324662U (en) * 2011-12-02 2012-07-11 中国建筑第七工程局有限公司 Installation device for foam cement composites
CN203393923U (en) * 2013-07-15 2014-01-15 中国二冶集团有限公司 Mobile transportation trolley for color plates
CN203821720U (en) * 2014-05-14 2014-09-10 中建八局第三建设有限公司 High-altitude large roof panel installing tool trolley

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08333813A (en) * 1995-06-07 1996-12-17 Takenaka Komuten Co Ltd Building method of building unit for vertical and horizontal conveying
CN201560539U (en) * 2009-09-30 2010-08-25 中太建设集团股份有限公司 Tool car for long-span net rack roof space plate
CN201857761U (en) * 2010-08-10 2011-06-08 中建五局工业设备安装有限公司 Hoisting and sliding device and hoisting and sliding equipment
CN202324662U (en) * 2011-12-02 2012-07-11 中国建筑第七工程局有限公司 Installation device for foam cement composites
CN203393923U (en) * 2013-07-15 2014-01-15 中国二冶集团有限公司 Mobile transportation trolley for color plates
CN203821720U (en) * 2014-05-14 2014-09-10 中建八局第三建设有限公司 High-altitude large roof panel installing tool trolley

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838055A (en) * 2017-11-24 2019-06-04 中建安装工程有限公司 High-altitude is installed by steel frame and light concrete face-board for room special mounting vehicle
CN109256736A (en) * 2018-09-14 2019-01-22 中国冶集团有限公司 A kind of wire box built-in process and positioning device
CN111336314A (en) * 2020-04-26 2020-06-26 中国二十二冶集团有限公司 Large-caliber pipeline roof installation device and construction method thereof
CN115538790A (en) * 2022-09-02 2022-12-30 广州市机电安装有限公司 Installation method of long and narrow hyperboloid steel roof
CN115596217A (en) * 2022-11-28 2023-01-13 中国二十二冶集团有限公司(Cn) Integral installation method for three-hinged arch skylight frame of steel structure factory building

Also Published As

Publication number Publication date
CN107288352B (en) 2019-07-30

Similar Documents

Publication Publication Date Title
LU102302B1 (en) Steel reinforcement cage for use in ventilation shaft diaphragm wall, and usage method
CN107288352A (en) The transport of the closed shed dormer roof boarding of overlarge area and installation method
CN108019076B (en) Construction method of large-diameter reinforced concrete silo and device for conical shell construction
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN103572699A (en) Novel road bridge girder erection machine
CN107447973B (en) Unilateral suspension type air mobile steel platform
CN103899093A (en) Step-by-step hoisting construction method of mega-frame steel truss beam
CN106948604A (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
CN203334695U (en) Curtain wall glass installation and suspending system
CN105621304A (en) Building material elevator
CN102677907A (en) Method for manually installing steel beam at top of silo
CN103291078B (en) A kind of steel girder erection equipment
CN205654127U (en) Portable operation protective platform of assembly type structure stairwell
CN108194111A (en) A kind of umbrella arch splash guard, reinforced mesh are laid with ancillary equipment
CN204609308U (en) A kind of passage limited position concrete rail transporter
CN105625732A (en) Supporting-free construction method of ultrahigh overhung steel-structure truss
CN215291562U (en) Device for high-rise building construction by adopting cantilever crane
CN204402001U (en) For the mobile operating platform system that structure for steel structure roof inner slab is installed
CN204174850U (en) High-altitude stereo cross-operation chassis
CN102733644A (en) Super-altitude roof super-long antenna hoisting construction method and system
CN107447931A (en) The closed factory building roof skylight frame installation method of overlarge area
CN207658895U (en) Working at height glass hanging equipment
CN203307770U (en) Transverse-joint rubber waterstop climbing device for concrete dam
CN107558742A (en) Large area two layers of Steel Structure Installation method of closed factory building
CN207228604U (en) A kind of unilateral suspension type aerial movement steel platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant