CN107558742A - Large area two layers of Steel Structure Installation method of closed factory building - Google Patents
Large area two layers of Steel Structure Installation method of closed factory building Download PDFInfo
- Publication number
- CN107558742A CN107558742A CN201610498826.4A CN201610498826A CN107558742A CN 107558742 A CN107558742 A CN 107558742A CN 201610498826 A CN201610498826 A CN 201610498826A CN 107558742 A CN107558742 A CN 107558742A
- Authority
- CN
- China
- Prior art keywords
- steel
- installation
- armed
- elevator sling
- construction piece
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The present invention relates to Construction of Steel Structure.A kind of closed two layers of Steel Structure Installation method of factory building of large area, it includes:A kind of one-armed elevator sling cart is made, the one-armed elevator sling cart includes:The lower dress vehicle seat of roller, the weighted areas at vehicle seat rear portion, the assembly pulley at the top of the vertical rod and electrical hoist and vertical rod that set on vehicle seat;The steel wire rope of the hoist engine goes to the free end with clasp of connection lifting steel construction piece by the assembly pulley at the top of vertical rod;The good elevator sling cart steel wire rope free end of counterweight is fastened into steel construction piece;Control electrical hoist operating lifting, after post position and erect by one-armed elevator sling cart by the steel column one of steel construction piece, installation column bolt is completed to install;The steel girder erection of steel construction piece is lifted by two independence for Taiwan arm elevator sling carts, is in place afterwards positioned beam and is laterally fixed, and installation connecting bolt completes installation.The present invention need not use large-scale crane or tower crane, save lifting cost and use;Reduce the generation of site safety accident.
Description
Technical field
The present invention relates to Construction of Steel Structure, more particularly to a kind of closed workshop steel structure construction method of large area.
Background technology
Generally two layers of Air Conditioning Facilities are all provided with the industrial premises roofing of overlarge area, the Air Conditioning Facilities span is big, easily 20 ~ 30 meters, and Air Conditioning Facilities are substantially disposed among roofing or center, ground large hanging device can not visit at all and, and factory building roof plate bearing capacity is all relatively low, tower crane can not be also installed on roofing or truck crane is set, because roof area is big, height height and one layer of totally enclosed feature of ceiling, based on span and structure and scale requirement, two-layer structure girder steel, transport be present in steel column, the problem of installation, existing Minitype manual installs stroller, also can not be applicable.Therefore the installation problem of large area two layers of Air Conditioning Facilities structure of closed factory building increasingly highlights, how overcoming the high-altitude of this special construction environment to install problem must solve the problems, such as current construction.
The content of the invention
A kind of present invention seek to address that drawbacks described above, there is provided closed two layers of Steel Structure Installation method of factory building of large area.The present invention need not use large-scale crane or tower crane, save lifting cost and use;Installation rate is fast, shortens installation period;Substantial amounts of work high above the ground is effectively reduced, reduces the generation of site safety accident.
To solve the above problems, a kind of closed two layers of Steel Structure Installation method of factory building of large area, it includes:
Step 1, according to two-layer structure height, span and girder steel, steel column scale, a kind of one-armed elevator sling cart is made, the one-armed elevator sling cart includes:The lower dress vehicle seat of roller, the weighted areas at vehicle seat rear portion, the assembly pulley at the top of the vertical rod and electrical hoist and vertical rod that set on vehicle seat;The steel wire rope of the hoist engine goes to the free end with clasp of connection lifting steel construction piece by the assembly pulley at the top of vertical rod;
Step 2, two layers of steel construction are transported to installation position by travelling bogie, the good elevator sling cart steel wire rope free end of counterweight is fastened into steel construction piece;
Speed and positioning are controlled in step 3, control electrical hoist operating lifting in lifting process, and after post position and erect by one-armed elevator sling cart by the steel column of steel construction piece one, installation column bolt is completed to install;
Step 4, the steel girder erection of steel construction piece are lifted by two independence for Taiwan arm elevator sling carts, are in place afterwards positioned beam and are laterally fixed, and installation connecting bolt completes installation.
In the present invention, the one-armed elevator sling cart designed and produced is simple in construction, easy to operate, conducts oneself with dignity and small, combination is flexible, multidirectional conveniently moving, position adjustment is easy, and lifting effect is good, it is safe, hoisting process does not need high-altitude application, and making material can gather materials on the spot, with many-sided advantage such as making easy to process, cheap.Its installation principle is simple, easily operation;Large-scale crane or tower crane need not be used, lifting cost is saved and uses;Meanwhile installation rate of the present invention is fast, shorten installation period;Substantial amounts of work high above the ground is effectively reduced, reduces the generation of site safety accident;Applicability is wide, and generalization is strong.
Brief description of the drawings
Below, with reference to accompanying drawing, the present invention is further illustrated:
Fig. 1 is the schematic diagram of the present invention;
Fig. 2 is the schematic diagram of step 4.
Embodiment
A kind of closed two layers of Steel Structure Installation method of factory building of large area as shown in Figure 1, it includes:
Step 1, according to two-layer structure height, span and girder steel, steel column scale, a kind of one-armed elevator sling cart is made, the one-armed elevator sling cart includes:The lower dress vehicle seat 1 of roller, the weighted areas 2 at vehicle seat rear portion, the assembly pulley 5 at the top of the vertical rod 3 and electrical hoist 4 and vertical rod that set on vehicle seat;The steel wire rope of the hoist engine goes to the free end with clasp of connection lifting steel construction piece by the assembly pulley at the top of vertical rod;
Step 2, two layers of steel construction are transported to installation position by travelling bogie, the good elevator sling cart steel wire rope free end of counterweight is fastened into steel construction piece 6;
Speed and positioning are controlled in step 3, control electrical hoist operating lifting in lifting process, and after post position and erect by one-armed elevator sling cart by the steel column of steel construction piece one, installation column bolt is completed to install;
As shown in Figure 2:Step 4, the steel girder erection of steel construction piece are lifted by two independence for Taiwan arm elevator sling carts, are in place afterwards positioned beam and are laterally fixed, and installation connecting bolt completes installation.
Claims (1)
- A kind of 1. closed two layers of Steel Structure Installation method of factory building of large area, it is characterised in that it includes:Step 1, according to two-layer structure height, span and girder steel, steel column scale, a kind of one-armed elevator sling cart is made, the one-armed elevator sling cart includes:The lower dress vehicle seat of roller, the weighted areas at vehicle seat rear portion, the assembly pulley at the top of the vertical rod and electrical hoist and vertical rod that set on vehicle seat;The steel wire rope of the hoist engine goes to the free end with clasp of connection lifting steel construction piece by the assembly pulley at the top of vertical rod;Step 2, two layers of steel construction are transported to installation position by travelling bogie, the good elevator sling cart steel wire rope free end of counterweight is fastened into steel construction piece;Speed and positioning are controlled in step 3, control electrical hoist operating lifting in lifting process, and after post position and erect by one-armed elevator sling cart by the steel column of steel construction piece one, installation column bolt is completed to install;Step 4, the steel girder erection of steel construction piece are lifted by two independence for Taiwan arm elevator sling carts, are in place afterwards positioned beam and are laterally fixed, and installation connecting bolt completes installation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610498826.4A CN107558742A (en) | 2016-06-30 | 2016-06-30 | Large area two layers of Steel Structure Installation method of closed factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610498826.4A CN107558742A (en) | 2016-06-30 | 2016-06-30 | Large area two layers of Steel Structure Installation method of closed factory building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107558742A true CN107558742A (en) | 2018-01-09 |
Family
ID=60969199
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610498826.4A Pending CN107558742A (en) | 2016-06-30 | 2016-06-30 | Large area two layers of Steel Structure Installation method of closed factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107558742A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110725550A (en) * | 2019-10-18 | 2020-01-24 | 上海宝冶集团有限公司 | Hanger and construction method of additional layer of steel structure of factory building |
CN111719564A (en) * | 2020-06-29 | 2020-09-29 | 中国建筑第八工程局有限公司 | Method for installing steel column in limited space |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203295071U (en) * | 2013-05-07 | 2013-11-20 | 李政泽 | Multifunctional concrete stirring and conveying sling cart with auger device |
CN203807014U (en) * | 2014-05-13 | 2014-09-03 | 福建省威盛机械发展有限公司 | Telescopic arm sling cart more stable to run |
CN203820328U (en) * | 2014-05-20 | 2014-09-10 | 中建八局第三建设有限公司 | Movable slingcart for minitype prefabricated part and steel form |
CN205259073U (en) * | 2015-12-23 | 2016-05-25 | 中铁十二局集团第二工程有限公司 | Multi -functional transportation sling cart on bridge roof beam |
-
2016
- 2016-06-30 CN CN201610498826.4A patent/CN107558742A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203295071U (en) * | 2013-05-07 | 2013-11-20 | 李政泽 | Multifunctional concrete stirring and conveying sling cart with auger device |
CN203807014U (en) * | 2014-05-13 | 2014-09-03 | 福建省威盛机械发展有限公司 | Telescopic arm sling cart more stable to run |
CN203820328U (en) * | 2014-05-20 | 2014-09-10 | 中建八局第三建设有限公司 | Movable slingcart for minitype prefabricated part and steel form |
CN205259073U (en) * | 2015-12-23 | 2016-05-25 | 中铁十二局集团第二工程有限公司 | Multi -functional transportation sling cart on bridge roof beam |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110725550A (en) * | 2019-10-18 | 2020-01-24 | 上海宝冶集团有限公司 | Hanger and construction method of additional layer of steel structure of factory building |
CN111719564A (en) * | 2020-06-29 | 2020-09-29 | 中国建筑第八工程局有限公司 | Method for installing steel column in limited space |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201228206Y (en) | Self-made small-sized hoisting machine | |
CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
CN205772984U (en) | A kind of hanging apparatus of monolithic steel truss | |
CN205653058U (en) | Harbour wind -force monitoring auto -lock protection type hoist | |
CN107060349A (en) | A kind of large-span steel girder upper air installing system in place and its construction | |
CN103899093A (en) | Step-by-step hoisting construction method of mega-frame steel truss beam | |
CN106638688B (en) | Purlin vehicle type closure construction system and its construction method | |
CN107288352B (en) | The transport of the closed shed dormer roof boarding of overlarge area and installation method | |
CN107558742A (en) | Large area two layers of Steel Structure Installation method of closed factory building | |
CN103086276B (en) | Construction method for hoisting bridge type crane in high-rise well tower type building | |
JP2008248664A (en) | Curtain wall lifting method | |
CN103161350A (en) | Large span heavy steel structure mast hoisting construction method | |
CN104973517A (en) | Electric gantry platform for installing sintering machine head equipment and application method thereof | |
CN104291222A (en) | Rigid protection and crane integration system inside super high-rise building core tube | |
CN204057758U (en) | A kind of hoisting device for overhaul of the equipments in large height industrial building | |
CN203834369U (en) | Device capable of being rotated by 360 degrees and vertically lifted for bridge | |
CN206273951U (en) | The hoisting apparatus of attachment type raise scaffold | |
CN203582307U (en) | Novel crane | |
CN206069208U (en) | A kind of bridging crane main beam body structure | |
CN111232849A (en) | Tower crane dismantling method | |
CN206693641U (en) | The irregular alien invasion glass curtain wall positioning apparatus of high-rise building | |
CN202729645U (en) | Tower crane with elevator | |
CN206279555U (en) | Purlin vehicle type closure construction system | |
CN205653067U (en) | Gantry crane is prevented rocking by special rope in harbour | |
CN201433051Y (en) | Large-scale rack lower boom double-track single-beam lifting crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180109 |
|
RJ01 | Rejection of invention patent application after publication |