CN107254925A - Vertical prestressing loam wall and its construction method - Google Patents

Vertical prestressing loam wall and its construction method Download PDF

Info

Publication number
CN107254925A
CN107254925A CN201710600596.2A CN201710600596A CN107254925A CN 107254925 A CN107254925 A CN 107254925A CN 201710600596 A CN201710600596 A CN 201710600596A CN 107254925 A CN107254925 A CN 107254925A
Authority
CN
China
Prior art keywords
wall
connection
capping beam
foundation
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710600596.2A
Other languages
Chinese (zh)
Inventor
杨新磊
赵子良
张建新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Chengjian University
Original Assignee
Tianjin Chengjian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Chengjian University filed Critical Tianjin Chengjian University
Priority to CN201710600596.2A priority Critical patent/CN107254925A/en
Publication of CN107254925A publication Critical patent/CN107254925A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

Vertical prestressing loam wall and its construction method, loam wall include foundation of wall, rammed earth main body and vertical prestressing and apply structure;Vertical prestressing, which applies structure, includes two constructional columns, multigroup prestressed component and capping beam;Two constructional column branch are connected by the two set constructor post connection pre-embedded bolts and foundation of wall at two ends in foundation of wall respectively, and the loam wall tip position and constructional column that capping beam is located between two constructional columns are connected;Every group of prestressed component includes base connection, outer tube and deformed bar, base connection is connected by correspondence prestressing force connection pre-embedded bolt in foundation of wall and foundation of wall, the bottom of deformed bar is connected with corresponding base connection, and the upper end of deformed bar is connected through capping beam and the billet of capping beam upper end with capping beam;Outer tube is set in outside deformed bar;Rammed earth main body building is between two ends constructional column, foundation of wall and capping beam.Invention enhances the shearing strength between rammed earth layer, the globality of wall is improved.

Description

Vertical prestressing loam wall and its construction method
Technical field
The invention belongs to civil engineering earth building reinforcement technique field, more particularly to a kind of vertical prestressing loam wall and Its construction method.
Background technology
Traditional cob has cheap, and building technology is simple, the advantages of thermal and insulating performance is good, is typical green Color environment protection architecture.But because traditional loam wall construction technology is generally using successively tamping, causes cohesive force at layering relatively low, destroy Form is similar with sheared destruction situation at masonry structure horizontal mortar joint.Therefore, loam wall under action of horizontal seismic due to point Layer place shear-carrying capacity is not enough and easily occurs failure by shear, how to improve one of shearing strength at intersection performance as rammed earth construction improvement Individual important directions.
In order to improve wall shearing strength at intersection performance, it is usually taken at building layering and horizontal shear connector is set, but by Snap-in force is smaller between shear connector and levels rammed earth, and shearing resistance effect is not notable.Understood according to Coulomb theory, work as stress When shear stress τ in a certain plane of cell cube reaches a certain limit value, along the plane sliding rupture occurs for material.Make material edge flat The maximum shear stress τ of face slidinguIt can be calculated as follows by acting on direct stress σ on this plane:
τ≤τu=c- μ σ
In formula:σ is that by the direct stress (setting tension as just) on the face of cutting, cohesive strength C and coefficient of internal friction μ are and material Relevant parameter.Therefore in the case where cutting pressure composite stress state, when the direct stress value on interlayer is bigger, material is less susceptible to along interlayer Section produces slip.Therefore, the positive pressure value (namely the vertically active force in direction) of loam wall is improved, loam wall can be improved and existed Shear-carrying capacity at layering.
The content of the invention
Present invention technical problem present in solution known technology provides a kind of vertical prestressing loam wall and its applied Work method, this loam wall can strengthen rammed earth layer between shearing strength, the shear-carrying capacity of wall can be improved, so as to effective The formation for avoiding horizontal straight joint, and then the anti-seismic performance of loam wall can be strengthened;The construction method of this loam wall is simple, operability By force.
The present invention is adopted the technical scheme that to solve technical problem present in known technology:
Vertical prestressing loam wall, it is characterised in that:Apply structure including foundation of wall, rammed earth main body and vertical prestressing;
One end to another extreme direction is provided with multigroup pre-embedded bolt protruded upward in foundation of wall, wherein positioned at two ends Two groups of pre-embedded bolts be constructional column connection pre-embedded bolt, remaining pre-embedded bolt be prestressed member connection pre-embedded bolt;
The vertical prestressing, which applies structure, includes two constructional columns, multigroup prestressed component and capping beam;Two constructions Post is supported in the position close to two ends in foundation of wall, and passes through two set constructor post connection pre-embedded bolts and pre-embedded bolt respectively The nut of cooperation is formed a fixed connection with foundation of wall, and vertically arranged connection is each provided with the upper end of two constructional columns and is slitted Mouthful;The capping beam sets the loam wall tip position between two constructional columns, and prepared screw-bolt hole is provided with the two ends of capping beam, By being installed on the connection gap of two constructional columns with the connecting bolt in the prepared screw-bolt hole of capping beam corresponding end, with being connected spiral shell The nut that bolt coordinates makes the constructional column at capping beam and two ends be fixed with one;The group number of prestressed component is connected with prestressing force with pre- Bury the group number of bolt unanimously and above and below being formed to correspond, every group of prestressed component includes base connection, outer tube and two ends Deformed bar provided with connection screw thread, the middle part of base connection is provided with downward opening U-shaped raised connecting portion, basis connection The nut and foundation of wall that part is coordinated by the prestressing force connection of correspondence position with pre-embedded bolt, with pre-embedded bolt form fixed company Connect, connecting hole is provided with the U-shaped raised connecting portion of base connection, the bottom of deformed bar is connected through correspondence basis The connecting hole of part and by connected lower nuts, makes the bottom of deformed bar be formed with corresponding base connection It is fixedly connected, the upper end of deformed bar passes through the vertical through holes being arranged on capping beam and the steel pad for being arranged on capping beam upper end Plate, and by connected upper nut, the upper end and capping beam for making deformed bar form a fixed connection;The overcoat Pipe sleeve is located at outside correspondence deformed bar, the lower end of outer tube and the upper-end contact of base connection, the upper end of outer tube and pressure Leave gap in the lower end of back timber;
Rammed earth main body building shape between two ends constructional column, the foundation of wall positioned at bottom and superposed capping beam Into space in, and make rammed earth main body generally in vertical pressured state.
It is preferred that:The capping beam is precast concrete capping beam, and two are embedded with inside capping beam in the horizontal direction The connection reinforcing bar of setting, every connection reinforcing bar two ends are provided with connection sleeve pipe, connection sleeve pipe and are provided with internal thread, form described Prepared screw-bolt hole;The tubing of multiple vertically insertions is also embedded with the inside of capping beam, the endoporus of tubing forms described Vertical through holes.
It is preferred that:It is welded with and is set with connecting hole in coaxial in the upper end of the U-shaped lug boss and the position that connecting hole is aligned The short set of positioning put, positions short set and is plugged in corresponding outer tube, form outer tube spacing.
It is preferred that:Two constructional columns are made of thin-wall steel tube, and section is square, and constructional column inner chamber is filled out provided with concrete Body is filled, the bottom of constructional column is welded with the end plate being connected with foundation of wall.
It is preferred that:The deformed bar uses finish rolling deformed bar.
The construction method of vertical prestressing loam wall, it is characterised in that loam wall is applied using above-mentioned vertical prestressing Structure, its construction procedure is as follows:
S1 Construction in Preparatory Stage
C. each constituting parts that composition of preparation vertical prestressing applies structure is shifted to an earlier date:Applied according to required building wall size and plan Prestressing force size, determines model, quantity, length and the installation site of deformed bar;According to wall size, design and make structure Make post;According to the size of wall size and constructional column, prefabricating coping beam in advance;Prepare base connection, the overcoat of respective numbers Pipe, billet, connecting bolt, packing ring and nut;
D. foundation of wall is poured:During foundation of wall is poured, in two constructional columns and the predetermined installation of multigroup base connection Pre-embedded bolt at position, the constructional column connection pre-embedded bolt and prestressed member connection for forming subsequent construction respectively uses pre-buried spiral shell Bolt;
The S2 building stages
C. the nut for locking connection with pre-embedded bolt and mutually by multigroup prestressed member connection is solid one by one by base connection It is scheduled on the position set in foundation of wall;The nut of connection is locked with pre-embedded bolt and mutually by two structures by two set constructor post connections Make the end positions that post is fixed in foundation of wall;By multiple outer tubes be placed in one by one multiple basis connections by upper end, and make many Individual outer tube is aligned one by one with the connecting hole on multiple base connections, and the situation for positioning short set is provided with base connection Under, the lower end of outer tube and the short set of the positioning of correspondence position form inserting connection, to realize positioning;
D. installation form, after model sheetinstallat in place after, according to loam wall construction technology successively building rammed earth master from the bottom to top Body portion, until design height value;Use artificial building as far as possible in building outer tube surrounding soil, it is ensured that outer tube is protected all the time Hold vertical state;
S3 prestressed reinforcement of tensioning, produces vertical prestressing
D. many deformed bars are from top to bottom penetrated in multiple outer tubes one by one, make the bottom of deformed bar from The connecting hole of base connection is passed, and mounting gasket and lower nuts carry out anchor connection;
E. in the upper ends capping beam of rammed earth main body, the upper end of many vertical prestressed reinforcements is made from capping beam Multiple vertical through holes are passed, and form top revealed section;After rammed earth main body thoroughly parches and reaches setting intensity, in every prestressing force Billet, packing ring and upper nut are installed at the top revealed section of reinforcing bar, deformed bar carried out by tightening upper nut Upward tensioning, tensioning need to be carried out symmetrically, it is ensured that wall loading process is uniform;
When tensioning reaches the vertical prestressing of setting, tensioning terminates, after prestressing force in deformed bar is stable, The two ends prepared screw-bolt hole of capping beam, by nut check, makes with installing connecting bolt in the connection gap on the constructional column of two ends Capping beam and the constructional column at two ends are connected as the work progress of entirety, so far completion vertical prestressing loam wall.
The present invention has the advantages and positive effects of:
1st, this loam wall is that in loam wall body, multiple tracks vertical prestressed reinforcement, prestressing force are set along wall length direction Reinforcing bar bottom is connected by base connection with foundation of wall, and capping beam and billet are run through at the top of deformed bar, and by twisting Tight nut carries out upward tensioning to reinforcing bar.Deformed bar provides vertical precompression for wall, is in loam wall vertical equal Even pressured state, enhances the cohesive force at loam wall layering, improves the shear-carrying capacity of wall, can effectively avoid horizontal stroke To the formation of straight joint, the anti-seismic performance of loam wall is enhanced.Simultaneously capping beam after the completion of prestress application with both sides constructional column Entirety is linked to be by bolt, coordinates the deformation between constructional column and wall, shared lateral displacement helps and improves the whole of wall Body.
2nd, this rammed earth wall construction method produces three techniques of vertical prestressing by Construction in Preparatory Stage, building stage and tensioning Stage is constituted, and construction technology is simple, be easy to operate and control.
Brief description of the drawings
Fig. 1 is the whole structure figure of the present invention;
Fig. 2 is the design sketch that Fig. 1 removes rammed earth main part;
Fig. 3 is the partial schematic diagram that base connection is connected with deformed bar in Fig. 2;
Fig. 4 is the partial schematic diagram that deformed bar is connected with capping beam in Fig. 2;
Fig. 5 is the partial schematic diagram that is connected with corresponding constructional column of end of capping beam in Fig. 2;
Fig. 6 is the structural representation of base connection of the present invention;
Fig. 7 is the structural representation of constructional column of the present invention;
Fig. 8 is the structural representation that capping beam main body of the present invention is connected reinforcing bar cooperation with two.
In figure:1st, foundation of wall;2nd, rammed earth main body;3rd, vertical prestressing applies structure;3-1, constructional column;3-1-1, connection are slitted Mouthful;3-2, prestressed component;3-2-1, base connection;3-2-1a, U-shaped raised connecting portion;3-2-1b, the short set of positioning;3-2- 2nd, outer tube;3-2-3, deformed bar;3-2-4, lower nuts;3-2-5, steel plate washer;3-2-6, upper nut;3-3, bear down on one Beam;3-3-1, connection reinforcing bar;3-3-2, connection sleeve pipe;3-4, connecting bolt;4th, constructional column connection pre-embedded bolt;5th, prestressing force Part connection pre-embedded bolt.
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows:
Fig. 1-8, vertical prestressing loam wall are referred to, inventive point is:In advance should including foundation of wall 1, rammed earth main body 2 and vertically Power applies structure 3.
One end to another extreme direction is provided with multigroup pre-embedded bolt protruded upward in foundation of wall, wherein positioned at two ends Two groups of pre-embedded bolts be constructional column connection pre-embedded bolt 4, remaining pre-embedded bolt be prestressed member connection pre-embedded bolt 5.
The vertical prestressing, which applies structure, includes two constructional column 3-1, multigroup prestressed component 3-2 and capping beam 3-3. Vertical prestressing applies the concrete structure of three parts of structure and connected as follows:
Two constructional columns be supported in foundation of wall close to two ends position and respectively by the connection of two set constructor posts with pre-buried Bolt, the nut and foundation of wall that coordinate with pre-embedded bolt form a fixed connection, specifically, in the lower end welded end plate of constructional column, The multiple bolts hole for being connected and being coordinated with pre-embedded bolt with the constructional column of correspondence position, multiple bolts hole and structure are reserved on end plate Make post connection and install connection one by one with pre-embedded bolt formation, by the nut being tightened on constructional column connection pre-embedded bolt, make Constructional column forms a fixed connection with foundation of wall.Vertically arranged connection gap 3-1- is each provided with the upper end of two constructional columns 1。
The capping beam is arranged on the loam wall tip position between two constructional columns, specifically, capping beam size should be covered All rammed earth main parts of lid wall and it can not be overlapped with constructional column, it is ensured that vertical prestressing only produces work to soil body part With without being impacted to constructional column.Prepared screw-bolt hole is provided with the two ends of capping beam, by being installed on two constructional columns The nut that connection gap coordinates with the connecting bolt 3-4 in the prepared screw-bolt hole of capping beam corresponding end, with connecting bolt makes to bear down on one Beam and the constructional column at two ends are fixed with one, shared horizontal comparison.
The group number of prestressed component it is consistent with the group number of prestressing force connection pre-embedded bolt and formed above and below correspond. Every group of prestressed component includes the deformed bar 3- that base connection 3-2-1, outer tube 3-2-2 and two ends are provided with connection screw thread 2-3.The middle part of base connection is provided with opening down U-shaped raised connecting portion 3-2-1a, and base connection passes through correspondence position The nut and foundation of wall that prestressing force connection coordinates with pre-embedded bolt, with pre-embedded bolt form a fixed connection, specifically, on basis even Bolt hole is reserved with two rim portions of the U-shaped raised connecting portion of fitting, the prestressing force connection of bolt hole and correspondence position is with advance Bury bolt formation install connection one by one, by the nut being tightened on prestressing force connection pre-embedded bolt, make base connection and Foundation of wall forms a fixed connection.Connecting hole, the bottom of deformed bar are provided with the U-shaped raised connecting portion of base connection Through the connecting hole for corresponding to base connection and by connected lower nuts 3-2-4, make the bottom of deformed bar Formed a fixed connection with corresponding base connection.The upper end of deformed bar passes through the vertical through holes being arranged on capping beam and set The billet 3-2-5 in capping beam upper end is put, and by connected upper nut 3-2-6, makes the upper end of deformed bar Portion forms a fixed connection with capping beam.The outer tube is set in outside correspondence deformed bar, and lower end and the basis of outer tube connect The upper end that gap, i.e. outer tube are left in the upper-end contact of fitting, the upper end of outer tube and the lower end of capping beam can not be with capping beam Lower end dieback.
Rammed earth main body building shape between two ends constructional column, the foundation of wall positioned at bottom and superposed capping beam Into space in, and make rammed earth main body generally in vertical pressured state.
Above-mentioned capping beam can be using structures such as girder steel, concreting beams, and in the present invention, the capping beam is further excellent Elect precast concrete capping beam as, two horizontally disposed connection reinforcing bar 3-3-1, every are embedded with inside capping beam Connection reinforcing bar two ends, which are respectively provided with connection sleeve pipe 3-3-2, connection sleeve pipe, is provided with internal thread, forms the prepared screw-bolt hole. The inside of capping beam is also embedded with the tubing of multiple vertically insertions, and tubing is not shown in the accompanying drawings, the endoporus of tubing Form the vertical through holes.
On above-mentioned base connection, the position aligned in the upper end of the U-shaped lug boss with connecting hole is further welded with With connecting hole in the short set 3-2-1b of positioning being coaxially disposed, position short set and be plugged in corresponding outer tube, form outer tube It is spacing.So, it is to avoid in building rammed earth main body, in addition it is also necessary to manually align outside outer tube and the position of connecting hole and righting Sleeve pipe, in the case where being easy to ensure outer tube position, while saving artificial.
The above-mentioned further preferred structure of constructional column is:Two constructional columns are made of thin-wall steel tube, and section is square, structure Post inner chamber is made provided with Concrete Filled body, the bottom of constructional column is welded with the end plate being connected with foundation of wall.
Above-mentioned deformed bar further preferably uses finish rolling deformed bar, and bar gauge applies prestressing force size according to plan And rammed earth wall size is determined.
The construction method of vertical prestressing loam wall, inventive point is:Loam wall applies structure using above-mentioned vertical prestressing, Its construction procedure is as follows:
S1:Construction in Preparatory Stage
A, in advance composition of preparation vertical prestressing apply each constituting parts of structure:Applied according to required building wall size and plan Prestressing force size, determines model, quantity, length and the installation site of deformed bar.According to wall size, design and make structure Post is made, when constructional column uses above-mentioned thin-walled rectangular steel tube structure, connection through hole is reserved on the end plate of constructional column lower end.According to According to the size of wall size and constructional column, prefabricating coping beam in advance, when capping beam is beared down on one girder construction using above-mentioned precast concrete When, according to wall size assembling reinforcement and casting concrete, pre-buried two elongated connection reinforcing bars in beam, and connect steel at two Muscle two ends are respectively mounted connection sleeve pipe, and the vertically pre-buried tubing at the presstressed reinforcing steel position of setting.Prepare respective numbers Base connection, outer tube, billet, connecting bolt, packing ring and nut, wherein base connection by plurality of steel plates weld and Into, and reserve on the plain plate on U-shaped lug boss both sides connection through hole.
B, pour foundation of wall:During foundation of wall is poured, in two constructional columns and the predetermined installation of multigroup base connection Pre-embedded bolt at position, the constructional column connection pre-embedded bolt and prestressed member connection for forming subsequent construction respectively uses pre-buried spiral shell Bolt.
S2:The building stage
A, the nut for locking by multigroup prestressed member connection connection with pre-embedded bolt and mutually are solid one by one by base connection It is scheduled on the position set in foundation of wall;The nut of connection is locked with pre-embedded bolt and mutually by two structures by two set constructor post connections Make the end positions that post is fixed in foundation of wall;By multiple outer tubes be placed in one by one multiple basis connections by upper end, and make many Individual outer tube is aligned one by one with the connecting hole on multiple base connections, and the situation for positioning short set is provided with base connection Under, the lower end of outer tube and the short set of the positioning of correspondence position form inserting connection, to realize positioning.
B, installation form, after model sheetinstallat in place after, according to loam wall construction technology successively building rammed earth master from the bottom to top Body portion, until design height value, artificial building is used in building outer tube surrounding soil, it is ensured that outer tube is protected all the time as far as possible Hold vertical state.
S3:Prestressed reinforcement of tensioning, produces vertical prestressing
A, many deformed bars are from top to bottom penetrated in multiple outer tubes one by one, make the bottom of deformed bar from The connecting hole of base connection is passed, and mounting gasket and lower nuts carry out anchor connection.
B, the upper ends capping beam in rammed earth main body, make the upper end of many vertical prestressed reinforcements from capping beam Multiple vertical through holes are passed, and form top revealed section;After rammed earth main body thoroughly parches and reaches setting intensity, in every prestressing force Billet, packing ring and upper nut are installed at the top revealed section of reinforcing bar, deformed bar carried out by tightening upper nut Upward tensioning, tensioning need to be carried out symmetrically, it is ensured that wall loading process is uniform.
F. when tensioning reaches the vertical prestressing of setting, tensioning terminates, after prestressing force in deformed bar is stable, Connecting bolt is installed in connection gap on the two ends prepared screw-bolt hole and two ends constructional column of capping beam, by nut check, Capping beam and the constructional column at two ends is connected for entirety, so far complete the work progress of vertical prestressing loam wall.
To sum up, there are following features using the loam wall of above method building:
1st, by applying vertical prestressing to loam wall, the shearing strength between rammed earth layer is enhanced, wall is improved whole Body, improves the anti-seismic performance of loam wall.
2nd, rammed earth surface contraction fissure caused by humiture changes can be suppressed.
3rd, capping beam of the invention, which can both have been played, evenly distributes vertical prestressing effect, again can be after the completion of prestress application It is linked to be the overall coupling beam that plays by bolt with both sides constructional column to act on, so as to coordinate to deform between constructional column and wall, is total to it With lateral displacement is undertaken, the globality of wall is improved.
4th, deformed bar is connected by the present invention by base connection with foundation of wall, and base connection is by deformed bar Anchored end is separated with foundation of wall, and the construction space of abundance is provided for anchoring, is easy to post-tensioned construction, has both improved operable Property, construction technology is simplified, the security of construction is improved again.

Claims (6)

1. vertical prestressing loam wall, it is characterised in that:Apply structure including foundation of wall, rammed earth main body and vertical prestressing;
One end to another extreme direction is provided with multigroup pre-embedded bolt protruded upward in foundation of wall, wherein two positioned at two ends Group pre-embedded bolt is constructional column connection pre-embedded bolt, and remaining pre-embedded bolt is prestressed member connection pre-embedded bolt;
The vertical prestressing, which applies structure, includes two constructional columns, multigroup prestressed component and capping beam;Two constructional column branch Support in the position in foundation of wall close to two ends, and coordinate respectively by two set constructor post connection pre-embedded bolts, with pre-embedded bolt Nut formed a fixed connection with foundation of wall, vertically arranged connection gap is each provided with the upper end of two constructional columns;Institute The loam wall tip position between capping beam two constructional columns of setting is stated, prepared screw-bolt hole is provided with the two ends of capping beam, passes through The connection gap of two constructional columns is installed on the connecting bolt in the prepared screw-bolt hole of capping beam corresponding end, with connecting bolt to match somebody with somebody The nut of conjunction makes the constructional column at capping beam and two ends be fixed with one;The group number of prestressed component is connected with prestressing force uses pre-buried spiral shell The group number of bolt unanimously and above and below being formed is corresponded, and every group of prestressed component is provided with including base connection, outer tube and two ends The deformed bar of connection screw thread, the middle part of base connection is provided with downward opening U-shaped raised connecting portion, and base connection leads to Nut and foundation of wall of the prestressing force connection of correspondence position with pre-embedded bolt, with pre-embedded bolt cooperation is crossed to form a fixed connection, The U-shaped raised connecting portion of base connection is provided with connecting hole, and the bottom of deformed bar passes through correspondence base connection Connecting hole and by connected lower nuts, makes the bottom of deformed bar form fixation with corresponding base connection Connection, the upper end of deformed bar passes through the vertical through holes being arranged on capping beam and the billet for being arranged on capping beam upper end, And by connected upper nut, the upper end and capping beam for making deformed bar form a fixed connection;The outer tube It is set in outside correspondence deformed bar, the lower end of outer tube and the upper-end contact of base connection, the upper end of outer tube is with bearing down on one Leave gap in the lower end of beam;
What the rammed earth main body building was formed between two ends constructional column, the foundation of wall positioned at bottom and superposed capping beam In space, and make rammed earth main body generally in vertical pressured state.
2. vertical prestressing loam wall according to claim 1, it is characterised in that:The capping beam is concrete soil pressure Back timber, is embedded with two horizontally disposed connection reinforcing bars inside capping beam, and every connection reinforcing bar two ends are provided with Internal thread is provided with connection sleeve pipe, connection sleeve pipe, the prepared screw-bolt hole is formed;Multiple edges are also embedded with the inside of capping beam Vertically communicated tubing, the endoporus of tubing forms the vertical through holes.
3. vertical prestressing loam wall according to claim 1, it is characterised in that:The upper end of the U-shaped lug boss with The position that connecting hole is aligned is welded with connecting hole in the short set of positioning being coaxially disposed, and is positioned short set and is plugged in corresponding outer tube It is interior, form outer tube spacing.
4. vertical prestressing loam wall according to claim 1, it is characterised in that:Two constructional columns use Steel Thin-Wall control Into section is square, and constructional column inner chamber is provided with Concrete Filled body, and the bottom of constructional column is welded with the end being connected with foundation of wall Plate.
5. vertical prestressing loam wall according to claim 1, it is characterised in that:The deformed bar uses finish rolling spiral shell Line reinforcing bar.
6. the construction method of vertical prestressing loam wall, it is characterised in that loam wall uses any described in claim 1-5 Vertical prestressing applies structure, and its construction procedure is as follows:
S1 Construction in Preparatory Stage
A. each constituting parts that composition of preparation vertical prestressing applies structure is shifted to an earlier date:Pre- answer is applied according to required building wall size and plan Power size, determines model, quantity, length and the installation site of deformed bar;According to wall size, design and make construction Post;According to the size of wall size and constructional column, prefabricating coping beam in advance;Prepare the base connections of respective numbers, outer tube, Billet, connecting bolt, packing ring and nut;
B. foundation of wall is poured:During foundation of wall is poured, in two constructional columns and the predetermined installation site of multigroup base connection Locate pre-embedded bolt, form the constructional column connection of subsequent construction respectively with pre-embedded bolt and prestressed member connection pre-embedded bolt;
The S2 building stages
Base connection is fixed on by the nut that connection is a. locked with pre-embedded bolt and mutually by multigroup prestressed member connection one by one The position set in foundation of wall;The nut of connection is locked with pre-embedded bolt and mutually by two constructional columns by two set constructor post connections It is fixed on the end positions in foundation of wall;By multiple outer tubes be placed in one by one multiple basis connections by upper end, and make multiple outer Sleeve pipe is aligned one by one with the connecting hole on multiple base connections, in the case of the short set of positioning is provided with base connection, The lower end of outer tube and the short set of the positioning of correspondence position form inserting connection, to realize positioning;
B. installation form, after model sheetinstallat in place after, according to loam wall construction technology successively building rammed earth main part from the bottom to top Point, until design height value;Use artificial building as far as possible in building outer tube surrounding soil, it is ensured that outer tube remains perpendicular Straight state;
S3 prestressed reinforcement of tensioning, produces vertical prestressing
A. many deformed bars are from top to bottom penetrated in multiple outer tubes one by one, makes the bottom of deformed bar from basis The connecting hole of connector is passed, and mounting gasket and lower nuts carry out anchor connection;
B. in the upper ends capping beam of rammed earth main body, the upper ends of many vertical prestressed reinforcements is made from multiple on capping beam Vertical through holes are passed, and form top revealed section;After rammed earth main body thoroughly parches and reaches setting intensity, in every deformed bar Top revealed section at billet, packing ring and upper nut are installed, by tighten upper nut deformed bar is carried out it is upward Tensioning, tensioning need to be carried out symmetrically, it is ensured that wall loading process is uniform;
C. when tensioning reaches the vertical prestressing of setting, tensioning terminates, after prestressing force in deformed bar is stable, in pressure The two ends prepared screw-bolt hole of back timber, by nut check, makes pressure with installing connecting bolt in the connection gap on the constructional column of two ends Back timber and the constructional column at two ends are connected as the work progress of entirety, so far completion vertical prestressing loam wall.
CN201710600596.2A 2017-07-21 2017-07-21 Vertical prestressing loam wall and its construction method Pending CN107254925A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710600596.2A CN107254925A (en) 2017-07-21 2017-07-21 Vertical prestressing loam wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710600596.2A CN107254925A (en) 2017-07-21 2017-07-21 Vertical prestressing loam wall and its construction method

Publications (1)

Publication Number Publication Date
CN107254925A true CN107254925A (en) 2017-10-17

Family

ID=60026467

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710600596.2A Pending CN107254925A (en) 2017-07-21 2017-07-21 Vertical prestressing loam wall and its construction method

Country Status (1)

Country Link
CN (1) CN107254925A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
CN108412081A (en) * 2018-01-30 2018-08-17 天津城建大学 It is applied with the building construction method of horizontal prestressed masonry structure and masonry
CN108412087A (en) * 2018-05-08 2018-08-17 天津城建大学 Improve the prefabricated reinforcement structure and loam wall of loam wall globality
CN108643395A (en) * 2018-07-24 2018-10-12 华北理工大学 A kind of prefabricated prestressing Self-resetting shear wall structure and its construction method
CN109623977A (en) * 2018-11-22 2019-04-16 华侨大学 A kind of soil property metope hammers into the number determination method of nail needed for drawing a picture
CN109695290A (en) * 2019-01-04 2019-04-30 国住人居工程顾问有限公司 A kind of prefabricated foundation and its construction method for tensioning construction building
CN109797888A (en) * 2019-01-04 2019-05-24 国住人居工程顾问有限公司 A kind of wall/rod structure and its construction method for tensioning construction building
CN110685404A (en) * 2019-09-16 2020-01-14 浙江绿筑集成科技有限公司 Construction method of prefabricated combined structure constructional column
CN110818346A (en) * 2019-10-28 2020-02-21 北京建筑大学 Preparation method of decorative thin-wall rammed earth wall
CN111472471A (en) * 2020-04-29 2020-07-31 南宁学院 Multifunctional composite wall
CN111910767A (en) * 2020-07-16 2020-11-10 中铁武汉勘察设计研究院有限公司 Be applied to assembled structure of removal transfer island
CN112482881A (en) * 2020-12-03 2021-03-12 中国建筑股份有限公司 Enclosure system of landscape building and construction method thereof
CN114908900A (en) * 2022-03-31 2022-08-16 西安建筑科技大学 Swing laminated wood frame-rammed earth wall mixed wall and construction process

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273246A (en) * 1996-04-04 1997-10-21 Oriental Constr Co Ltd Construction method of prestress assembly structure
CN101851970A (en) * 2010-05-14 2010-10-06 北京工业大学 Horizontal seamed energy dissipation prestressed shear wall structure
CN201679114U (en) * 2010-05-14 2010-12-22 北京工业大学 Horizontal seam dissipating energy prestress shear wall structure
CN104895224A (en) * 2015-06-30 2015-09-09 郑州大学 Prestressed loam wall and construction process thereof
CN105275222A (en) * 2015-11-24 2016-01-27 郑州大学 Immature soil coil-filling type traditional folk house wall reinforcing structure and reinforcing method
CN105696733A (en) * 2016-04-11 2016-06-22 天津城建大学 Rammed earth wall with precast concrete constructional columns
CN105804293A (en) * 2016-05-09 2016-07-27 天津城建大学 Prefabricated concrete-filled steel tube construction column rammed earth wall
CN205638802U (en) * 2016-04-20 2016-10-12 广东明阳风电产业集团有限公司 Formula precast concrete pylon structure is made up in segmentation
CN207211435U (en) * 2017-07-21 2018-04-10 天津城建大学 A kind of vertical prestressing loam wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273246A (en) * 1996-04-04 1997-10-21 Oriental Constr Co Ltd Construction method of prestress assembly structure
CN101851970A (en) * 2010-05-14 2010-10-06 北京工业大学 Horizontal seamed energy dissipation prestressed shear wall structure
CN201679114U (en) * 2010-05-14 2010-12-22 北京工业大学 Horizontal seam dissipating energy prestress shear wall structure
CN104895224A (en) * 2015-06-30 2015-09-09 郑州大学 Prestressed loam wall and construction process thereof
CN105275222A (en) * 2015-11-24 2016-01-27 郑州大学 Immature soil coil-filling type traditional folk house wall reinforcing structure and reinforcing method
CN105696733A (en) * 2016-04-11 2016-06-22 天津城建大学 Rammed earth wall with precast concrete constructional columns
CN205638802U (en) * 2016-04-20 2016-10-12 广东明阳风电产业集团有限公司 Formula precast concrete pylon structure is made up in segmentation
CN105804293A (en) * 2016-05-09 2016-07-27 天津城建大学 Prefabricated concrete-filled steel tube construction column rammed earth wall
CN207211435U (en) * 2017-07-21 2018-04-10 天津城建大学 A kind of vertical prestressing loam wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中国科学技术咨询服务中心预应力技术专家组 等: "《预应力工程实例应用手册》", 31 January 1994 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108412081A (en) * 2018-01-30 2018-08-17 天津城建大学 It is applied with the building construction method of horizontal prestressed masonry structure and masonry
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
CN108412087A (en) * 2018-05-08 2018-08-17 天津城建大学 Improve the prefabricated reinforcement structure and loam wall of loam wall globality
CN108643395A (en) * 2018-07-24 2018-10-12 华北理工大学 A kind of prefabricated prestressing Self-resetting shear wall structure and its construction method
CN108643395B (en) * 2018-07-24 2023-05-26 华北理工大学 Prefabricated assembly type prestress self-resetting shear wall structure and construction method thereof
CN109623977B (en) * 2018-11-22 2021-03-09 华侨大学 Method for determining number of nails to be driven into soil wall painting
CN109623977A (en) * 2018-11-22 2019-04-16 华侨大学 A kind of soil property metope hammers into the number determination method of nail needed for drawing a picture
CN109695290A (en) * 2019-01-04 2019-04-30 国住人居工程顾问有限公司 A kind of prefabricated foundation and its construction method for tensioning construction building
CN109797888A (en) * 2019-01-04 2019-05-24 国住人居工程顾问有限公司 A kind of wall/rod structure and its construction method for tensioning construction building
CN110685404A (en) * 2019-09-16 2020-01-14 浙江绿筑集成科技有限公司 Construction method of prefabricated combined structure constructional column
CN110818346A (en) * 2019-10-28 2020-02-21 北京建筑大学 Preparation method of decorative thin-wall rammed earth wall
CN110818346B (en) * 2019-10-28 2022-03-15 北京建筑大学 Preparation method of decorative thin-wall rammed earth wall
CN111472471A (en) * 2020-04-29 2020-07-31 南宁学院 Multifunctional composite wall
CN111910767A (en) * 2020-07-16 2020-11-10 中铁武汉勘察设计研究院有限公司 Be applied to assembled structure of removal transfer island
CN111910767B (en) * 2020-07-16 2024-08-13 中铁大桥勘测设计院集团有限公司武汉分公司 Be applied to assembled structure of removal transfer island
CN112482881A (en) * 2020-12-03 2021-03-12 中国建筑股份有限公司 Enclosure system of landscape building and construction method thereof
CN114908900A (en) * 2022-03-31 2022-08-16 西安建筑科技大学 Swing laminated wood frame-rammed earth wall mixed wall and construction process

Similar Documents

Publication Publication Date Title
CN107254925A (en) Vertical prestressing loam wall and its construction method
CN207211435U (en) A kind of vertical prestressing loam wall
CN100577923C (en) Prestressed concrete steel pipe congruent pile and its manufacture and construction method
WO2019149270A1 (en) Assembled pier for mixed reinforcement of normal steel rebar and finished threaded steel bar
CN111705795B (en) Prefabricated anchor pier for slope reinforcement and post-cast lattice beam assembly integral construction method
CN106948549B (en) A kind of prefabricated special-shaped side column
CN105275222A (en) Immature soil coil-filling type traditional folk house wall reinforcing structure and reinforcing method
CN109853849A (en) A kind of embedded column base node and its construction method equipped with fashioned iron short beam
CN114592688B (en) Construction method of oblique reinforced concrete shear wall based on equivalent rod model
JPH08333714A (en) Constructing method of columnar structure used with hybrid prefabricated segments
CN110924291A (en) Prefabricated stiffened concrete-filled steel tube and reinforced concrete assembled pier and construction process
CN110424548A (en) A kind of steel core concrete column-arch without beam connecting node and its construction method
CN209873809U (en) Foundation pit limb platform system
CN208219689U (en) Prefabricated components concrete tower fan foundation structure
CN108798681B (en) Underpinning system for zero-distance crossing existing subway station by middle-hole method and construction method thereof
JP2007277910A (en) Block for lightweight fill, lightweight fill structure, and its construction method
CN216713017U (en) Prefabricated stock waist rail
CN107060212B (en) Prefabricated abnormity center pillar, assembled beam-column node and its construction method
CN113638506A (en) Precast concrete ground beam-frame column connecting joint and construction method thereof
CN114045750A (en) Construction method of high pier column tie beam
CN207633583U (en) A kind of connection structure of prefabricated post and prefabricated partition wall
CN105888282A (en) Seismic strengthening structure and method for enlarging opening of substation masonry wall
CN112359978A (en) Connecting node of prefabricated module and cast-in-place structure and construction method
CN221030629U (en) Anti-torsion waist-bar-slurry anchor lapping device for girder in core area of beam column node and beam column structure
CN220365043U (en) Steel pipe column foundation combined with beam column joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171017

RJ01 Rejection of invention patent application after publication