CN107246145B - Concrete floor slab placement equipment and construction method for preserved pipeline hole - Google Patents

Concrete floor slab placement equipment and construction method for preserved pipeline hole Download PDF

Info

Publication number
CN107246145B
CN107246145B CN201710356796.8A CN201710356796A CN107246145B CN 107246145 B CN107246145 B CN 107246145B CN 201710356796 A CN201710356796 A CN 201710356796A CN 107246145 B CN107246145 B CN 107246145B
Authority
CN
China
Prior art keywords
module
support bar
bolt
hole
lower module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710356796.8A
Other languages
Chinese (zh)
Other versions
CN107246145A (en
Inventor
蔡庆军
赵红
蒋启诚
王彩明
何嘉骏
王玉飞
李华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201710356796.8A priority Critical patent/CN107246145B/en
Publication of CN107246145A publication Critical patent/CN107246145A/en
Application granted granted Critical
Publication of CN107246145B publication Critical patent/CN107246145B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G15/00Forms or shutterings for making openings, cavities, slits, or channels
    • E04G15/06Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
    • E04G15/063Re-usable forms
    • E04G15/068Re-usable forms for channels open towards the surface
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G25/06Shores or struts; Chocks telescopic with parts held together by positive means
    • E04G25/065Shores or struts; Chocks telescopic with parts held together by positive means by a threaded nut

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a kind of concrete floor slab placement equipment and construction method for preserved pipeline hole, wherein, concrete floor slab placement equipment includes upper module, lower module, upper support bar, lower support bar, and casing preformed hole is offered on the upper module, is placed with casing on the lower module;The upper support bar is equipped with pin hole, it is hollow setting inside the lower support bar, the top of the lower support bar is threaded portion, vertical bolt seam corresponding with the pin hole of upper support bar is offered on the threaded portion of the lower support bar, an adjustable seats are arranged on the threaded portion, upper support bar is mounted on the top of lower support bar by bolt insertion pin hole and bolt seam, and adjustable seats limit bolt, and can be moved along the threaded portion of lower support bar, thus adjust the length of support rod.The upper module top surface is equipped with the positioning column being arranged for lower support bar bottom;The bottom surface of the lower module is equipped with the positioning tube for plugging at the top of upper support bar.The bottom surface of the lower module is equipped with the positioning support column for positioning support upper module.

Description

Concrete floor slab placement equipment and construction method for preserved pipeline hole
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of concrete floor slab placement equipment for preserved pipeline hole and Construction method.
Background technique
In civil engineering work, the construction and installation of later period pipeline are always the heavy difficult point of engineering, due to building interior conduit Setting, need to open up the pipe hole passed through for pipeline on floor, tradition is there are two types of the construction method of pipe hole, and one is floors After the completion of pouring, aperture passes through for pipeline on floor, and another kind is the preserved pipeline hole in concrete floor slab placement.The first is applied Work method can destroy floor, cause the security risk of engineering, second method, and the reserved pipe hole between floor and floor is deposited In deviation, pipeline is caused possibly can not to install.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of for the concrete floor slab placement equipment in preserved pipeline hole and construction Method is not necessarily to later period aperture on floor, while solving different floor pipeline hole perpendicularities deficiencies, when leading to later period pipe laying There is the problem of dislocation inclination.
In order to realize the above technical effect, the invention discloses a kind of concrete floor slab placement equipment for preserved pipeline hole, in building Template is cooperated to use when plate pours comprising including upper module, lower module, support rod and casing, the periphery of the lower module Equipped with the birdsmouth for agreeing with installation with the template, in which:
The upper module is formed with a top surface and a bottom surface, and the casing through the upper module is offered on the upper module Preformed hole, the top surface of the upper module are equipped with first fixing piece fixed for the support rod bottom;
The lower module is formed with a top surface and a bottom surface, and the bottom surface of the lower module, which is equipped with, supplies the support bar top The second fixed fixing piece is additionally provided with the positioning support column for positioning support upper module on the top surface of the lower module;
Described sleeve pipe is placed on the top surface of the lower module.
The improvement of concrete floor slab placement equipment of the present invention for preserved pipeline hole be, the support rod include upper support bar, Lower support bar and a bolt, the upper support bar are equipped with pin hole, are hollow setting, the lower branch inside the lower support bar The top of strut is threaded portion, is offered on the threaded portion of the lower support bar corresponding with the pin hole of the upper support bar Vertical bolt stitches, and is arranged with an adjustable seats on the threaded portion, the upper support bar is plugged in the lower support bar, described Bolt is plugged in the pin hole of the upper support bar and the bolt seam of lower support bar upper support bar being mounted on lower support bar Top, the adjustable seats fix bolt, and the adjustable seats can be moved along the threaded portion of the lower support bar It is dynamic, thus adjust the length of support rod.
The present invention for preserved pipeline hole concrete floor slab placement equipment further improvement lies in that, first fixing piece is fixed Position column, the bottom of the lower support bar is set on the positioning column of the upper module top surface.
The present invention for preserved pipeline hole concrete floor slab placement equipment further improvement lies in that, second fixing piece is fixed Position cylinder, is plugged in the positioning tube of the lower module bottom surface at the top of the upper support bar.
The present invention for preserved pipeline hole concrete floor slab placement equipment further improvement lies in that, on the bottom surface of the upper module It equipped with mounting groove corresponding with the positioning support column, is plugged for the positioning support column of the lower module, thus the positioning branch Dagger is supported upper module, and when preventing concrete floor slab placement, upper module causes to squeeze to the concrete poured, makes Floor Slab Deformation not It is smooth, and can also play the role of positioning upper module and lower module.
The present invention for preserved pipeline hole concrete floor slab placement equipment further improvement lies in that, further include a bolt, it is described Upper module is equipped with the first bolt hole matched with the bolt, and the lower module is equipped with the second spiral shell matched with the bolt Keyhole, the first bolt hole of the upper module and the position of the second bolt hole of the lower module are corresponding, and bolt is plugged in In one bolt hole and the second bolt hole, guarantee that upper module connects fastening with lower module.
The present invention for preserved pipeline hole concrete floor slab placement equipment further improvement lies in that, on the periphery of the support rod It is installed with socket, side lever is provided between adjacent supports bar, the side lever is installed in the support rod periphery by bolt On socket.
The present invention separately provides a kind of construction method of concrete floor slab placement equipment for preserved pipeline hole, which is characterized in that packet Include following steps:
A., one lower module is provided, and the lower module is aligned with the formwork for placing of first layer floor and is connect, the lower module A top and bottom are formed with, the bottom surface of the lower module is equipped with the second fixing piece, and it is fixed that the top surface of the lower module is equipped with Position support column;
B. according to pipe design position, casing is placed on the top surface of lower module, and pours the first floor in casing periphery The concrete of plate;
C. a upper module is provided, the upper module is formed with a top surface and a bottom surface, offers and run through on the upper module The bottom surface of the casing preformed hole of the upper module, the upper module is equipped with and the positioning support column phase on the lower module top surface The upper module is placed in above the lower module, and the positioning support column of lower module is made to be plugged in institute by corresponding mounting groove It states in the mounting groove of upper module, adjusting sleeve pipe position, makes to wear at the top of casing in the casing preformed hole of upper module;On described The top surface of module is equipped with the first fixing piece;
D., one support rod is provided, to the end of the concrete initial set of first layer floor, the bottom of the support rod is passed through into institute The first fixing piece for stating upper module is installed on the upper module;
E. the lower module for placing second layer floor, makes the lower module of second layer floor and the formwork for placing pair of second layer floor Its connect, and by the top of the support rod above first layer floor by the second fixing piece of the lower module be installed in it is described under Below module, then repeatedly step b, c;
F. step d, e is then repeated, the pouring construction of each floor plate is sequentially completed.
Improvement of the present invention for the construction method of the concrete floor slab placement equipment of pipeline preformed hole is that the support rod is by upper Support rod and lower support bar connect and compose, and step d further comprises:
To the end of the concrete initial set of floor, the lower support bar and a bolt that an inside is hollow setting are provided, under described The top of support rod is threaded portion, and vertical bolt seam corresponding with the bolt, the threaded portion are offered on the threaded portion Periphery is arranged with an adjustable seats, the bottom of the lower support bar is installed in by the first fixing piece of the upper module described On upper module;
A upper support bar is provided, the upper support bar is equipped with pin hole, and the lower part of the upper support bar is worn into described In the top of lower support bar, and bolt is inserted into the bolt seam of the lower support bar and the pin hole of the upper support bar, And adjustable seats are adjusted, the height for the support rod for constituting upper support bar and lower support bar corresponds to the interval distance of adjacent floor deck From;
The present invention for pipeline preformed hole concrete floor slab placement equipment construction method further improvement lies in that, further include with Lower step:
After the concrete of floor reaches design strength, support rod above the floor plate and the floor plate are removed Upper module and lower module.
The present invention is used for the concrete floor slab placement equipment and construction method in preserved pipeline hole, by the way that support rod is arranged, makes adjacent building Layer upper module and lower module it is co-located, i.e., concrete floor slab placement when, the casing of different floors is co-located, thus Guarantee that deviation is not present in vertical direction in reserved pipe hole, convenient for the installation of later period pipeline.Also, in placing installation of the present invention Support rod adjustable in length, meet the high requirement of different floor layers, it is applied widely.
Detailed description of the invention
Fig. 1 is top surface structure schematic diagram of the present invention for upper module in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 2 is bottom surface structure schematic diagram of the present invention for upper module in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 3 is top surface structure schematic diagram of the present invention for lower module in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 4 is bottom surface structure schematic diagram of the present invention for lower module in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 5 is structural schematic diagram of the present invention for upper support bar in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 6 is partial enlargement diagram of the present invention for upper support bar in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 7 is structural schematic diagram of the present invention for lower support bar in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 8 is partial enlargement diagram of the present invention for lower support bar in the concrete floor slab placement equipment in preserved pipeline hole;
Fig. 9,10,11 are the step schematic diagram that first layer lower module of the present invention and upper module are installed;
Figure 12,13,14,16 are the step schematic diagram of first layer support rod of the present invention installation;
Figure 15 is the schematic diagram of upper support bar of the present invention and lower support bar junction;
Figure 17,18,19 are the step schematic diagram that second layer lower module of the present invention and upper module are installed;
Figure 20 is the schematic diagram that the present invention is installed for the concrete floor slab placement equipment in preserved pipeline hole.
Specific embodiment
With reference to the accompanying drawing and specific embodiment the present invention is described in further detail.
In conjunction with shown in Fig. 1 to Fig. 8, the present invention is used for the concrete floor slab placement equipment in preserved pipeline hole, cooperates in concrete floor slab placement Formwork for placing uses, and when concrete floor slab placement, and casing 40 is placed at pipeline through-flooring position, pre- on floor by the casing 40 Stay the through-hole of pipeline.The present invention is used for the concrete floor slab placement equipment in preserved pipeline hole, including upper module 10, lower module 20, support rod 30 and casing 40, described sleeve pipe 40 be placed on the lower module 20.Wherein, the upper module 10 is formed with a top surface and a bottom Face offers the casing preformed hole 104 through the upper module 10 on the upper module 10, for being limited to casing 40, Preferably, the height of casing 40 is greater than the thickness of floor, thus when casing 40 is placed on lower module 20, upper part is from upper module 10 Casing preformed hole 104 be pierced by, casing 40 is accurately positioned convenient for casing preformed hole 104.The top surface of the upper module 10 It is equipped with first fixing piece fixed for the bottom of the support rod 30;The lower module 20 is formed with a top surface and a bottom surface, The bottom surface of the lower module 20 is equipped with second fixing piece fixed for the top of the support rod 30, the top of the lower module 20 The positioning support column 203 for positioning support upper module 10 is additionally provided on face;Preferably, the periphery of the lower module 20 be equipped with Concrete floor slab placement template agrees with the birdsmouth 207 of installation.
In the present embodiment, it is arranged due to upper module 10 by wall, therefore is equipped with side plate against the side of wall in upper module 10 107, in other embodiments, setting side plate 107 can be chosen whether as needed.
In the present embodiment, using the lowest level for needing preserved pipeline hole build floor to be poured as first layer floor, with this First floor plate is adjacent and what is be positioned above needs the build floor to be poured in preserved pipeline hole as second layer floor, remaining upper floor Plate successively defines.As shown in figure 20, upper module 10 and lower module 20, second layer floor location are installed at first layer floor location Place is installed with upper module 10a and lower module 20a, the lower module 20a of the upper module 10 of the first layer floor and second layer floor it Between be installed with support rod 30, the support rod 30 be used for the lower module 20 of the upper module 10 of first layer floor and second layer floor into Row positioning, guarantees that the preserved pipeline hole of different floors meets the allowed band of pipeline construction in the offset of vertical direction.
Further, in conjunction with Fig. 5 to Fig. 8, support rod 30 includes upper support bar 31, lower support bar 33 and bolt 35, institute It states upper support bar 31 and is equipped with the pin hole 311 matched with bolt 35;It is hollow setting inside the lower support bar 33, it is described The top of lower support bar 33 is spire 330, and 311 phase of pin hole with the upper support bar 31 is offered on the spire 330 Corresponding vertical bolt seam 331, and an adjustable seats 333, the adjustable supporting are also arranged on the spire 330 of lower support bar 33 333 inner circumferentials of seat are equipped with the screw thread matched with spire 330, and can move up and down along the spire 330 of lower support bar 33.It is described The top of the lower support bar 33 is inserted into the lower part of upper support bar 31, and bolt 35 is inserted into the pin hole 311 of upper support bar 31 And in the bolt seam 331 of lower support bar 33, and the adjustable seats 333 on the spire 330 of lower support bar 33 are located at bolt 35 Lower section, for bolt 35 to be limited and is supported, thus form support rod 30.Also, as adjustable seats 333 are in lower branch Movement on the spire 330 of strut 33, bolt 35 is also vertically movable along 331 progress of bolt seam, and then upper support bar 31 is under It carries out vertically movable in support rod 33, is achieved in the length adjustment of support rod 30.It in other embodiments, can also on bolt 35 Screw thread is set, so that its end is secured with nuts, and then bolt 35 is effectively prevent to take off from pin hole 311 and bolt seam 331 Out.
Preferably, in the present embodiment, the inside of the upper support bar 31 is also hollow setting;Preferably, in this implementation In example, the upper module 10 and lower module 20 are made of steel plate, the upper support bar 31 and the lower support bar 33 by Steel pipe is made.
Preferably, as shown in Figure 1, in the present embodiment, first fixing piece is positioning column 101, the lower support bar 33 bottom is set on the positioning column 101 on 10 top surface of upper module;In other embodiments, first fixing piece can also be Positioning tube, the bottom of the lower positioning support column 33 are plugged in the positioning tube on 10 top surface of upper module.Preferably, such as Fig. 4 Shown, in the present embodiment, second fixing piece is positioning tube 201, and the top of the upper support bar 31 is plugged in lower module In the positioning tube 201 of 20 bottom surfaces;In other embodiments, second fixing piece can also be positioning column, the upper support bar 31 Top be set on the positioning column of 20 bottom surface of lower module.As a result, support rod 30 be fixed on the lower modules 20 of adjacent two layers with Between upper module 10, the fixation to different floors casting module is realized, guarantee that different floor preserved pipelines hole is accurately positioned.
Further, in conjunction with Fig. 2 and Fig. 3, the top surface of the lower module 20 is equipped with positioning support column 203, the upper mold The top surface of block 10 is equipped with mounting groove 103 corresponding with the positioning support column 203 on the lower module 20, thus for the lower die Positioning support column 203 on block 20 plugs, and is supported positioning support column 203 to upper module 10, prevents upper module to pouring Concrete generate extruding, cause Floor Slab Deformation out-of-flatness;And the positioning support column 203 can also be to upper module 10 and lower die Block 20 plays positioning action, and avoiding upper module 10 from occurring with lower module 20, horizontal displacement is poor, and the reserved location of pipeline is caused to occur Deviation.In the present embodiment, mounting groove 103 does not penetrate upper module 10, the design thickness of the height of positioning support column 203 than floor High 2mm, thus the groove depth of mounting groove 203 is 2mm, is matched with positioning support column 203, real to upper module 10 and lower module 20 While now positioning, upper module 10 is avoided to impact the flatness of floor.
Preferably, concrete floor slab placement equipment of the present invention for preserved pipeline hole further includes a bolt 15, described in conjunction with Figure 11 Upper module 10 is equipped with the first bolt hole 105 matched with the bolt 15, and the lower module 20 is equipped with and the bolt 15 match and second bolt hole 205 corresponding with first bolt hole 105, the bolt 15 are plugged in the upper mold It in first bolt hole 105 of block 10 and the second bolt hole 205 of lower module 20, and is tightened with nut, further to upper module 10 and lower module 20 positioned, guarantee upper module 10 and lower module 20 position consistency, and then guarantee pipe hole reserved matter Amount.
Further, socket, i.e., the upper periphery of the described upper support bar 31 are installed on the periphery of the support rod 30 It is installed with socket 315, the lower, outer perimeter of the lower support bar 33 is installed with socket 335, is arranged between adjacent supports bar 30 There is side lever 50, the both ends of the side lever 50 pass through bolt and are respectively installed on the socket 315,335 of adjacent supports bar 30, into And improve the stability of the support system of the composition of support rod 30.
Preferably, the top surface of the upper module 10 is equipped with handle 109, the bottom of the lower module 20 in conjunction with Fig. 1 and Fig. 4 Face is equipped with handle 209, and the setting of handle 109,209 moves upper module 10 and lower module 20 convenient for construction personnel, i.e., Convenient for the disassembly of upper module 10 and lower module 20.
In the present embodiment, using the lowest level for needing preserved pipeline hole build floor to be poured as first layer floor, with this First floor plate is adjacent and what is be positioned above needs the build floor to be poured in preserved pipeline hole as second layer floor, remaining upper floor Plate successively defines.In conjunction with Fig. 9 to Figure 20, construction method of the present invention for the concrete floor slab placement equipment in preserved pipeline hole, including with Lower construction procedure:
A. a lower module 20 is provided, it is preferable that the periphery of the lower module 20, which is equipped with, agrees with installation with concrete floor slab placement template The lower module 20 is aligned by its birdsmouth 207 with the formwork for placing of first layer floor and is connect, makes lower module by birdsmouth 207 20 upper plane is concordant with the upper plane of formwork for placing, and floor is smooth after the completion of guarantee pours, without difference of height.The lower module 20 are formed with a top surface and a bottom surface, and the bottom surface of the lower module 20 is equipped with the second fixing piece, on the top surface of the lower module Equipped with positioning support column 203.
B. according to pipe design position, casing 40 is placed on the top surface of lower module 20, casing 40 is made to be located substantially at pipeline Design position;The concrete of first layer floor is then poured in casing periphery, until first layer floor specified altitude assignment.Preferably Ground, the height of casing 40 are greater than the thickness of first layer floor.
C. a upper module 10 is provided, the upper module 10 is formed with a top surface and a bottom surface, opens up on the upper module 10 There is the casing preformed hole 104 through the upper module 10, the bottom surface of the upper module 10 is equipped with and 20 top surface of lower module On the corresponding mounting groove 103 of positioning support column 203, after concreting, by the upper module 10 be placed in it is described under 20 top of module, and it is plugged in the positioning support column 203 of lower module 20 in the mounting groove 103 of the upper module, make positioning branch Dagger 203 carries out positioning support to upper module 10, prevents upper module 10 from generating excessive compression to the concrete poured, causes to pour Floor Slab Deformation out-of-flatness after the completion, and positioning action can also be played to upper module 10 and lower module 20.In the present embodiment In, mounting groove 103 does not penetrate upper module 10, and the height of positioning support column 203 is 2mm higher than the design thickness of floor, thus installs The groove depth of slot 203 is 2mm, is matched with positioning support column 203, while realizing positioning to upper module 10 and lower module 20, Upper module 10 is avoided to impact the flatness of floor.Then the position of casing 40 is finely adjusted, makes the top of casing 40 It wears in the casing preformed hole 104 of upper module 10, thereby guarantees that the accurate positionin of casing 40;On the top surface of the upper module 10 Equipped with the first fixing piece.
Preferably, concrete floor slab placement equipment of the present invention for preserved pipeline hole further includes a bolt 15, the upper module 10 Be equipped with the first bolt hole 105 for matching with the bolt 15, the lower module 20 be equipped with matched with the bolt 15, And second bolt hole 205 corresponding with first bolt hole 105.In the mounting groove 103 and lower module 20 of upper module 10 Casing 40 in the alignment of positioning support column 203 and lower module 20 is directed at positioning with the casing preformed hole 104 of upper module 10 and completes Afterwards, the bolt hole 105 of upper module 10 is aligned with the bolt hole 205 of lower module 20, is inserted into bolt hole 105 and bolt hole 205 High-strength bolt 15, and tightened with nut, further upper module 10 and lower module 20 are positioned, guarantee upper module 10 and lower die The position consistency of block 20, and then guarantee the reserved quality of pipe hole.And make the difference in height between upper module 10 and lower module 20 Furthermore the exactly design thickness of floor passes through the extruding of the upper module 10 and lower module 20, makes the floor table after the completion of pouring Face is smooth.
D., one support rod 30 is provided, to the end of the concrete initial set of first layer floor, the bottom of the support rod 30 is led to The first fixing piece for crossing the upper module 10 is installed on the upper module 10 of the first layer floor.
Further, the support rod is connected and composed by upper support bar and lower support bar, and step d further comprises:
To the end of the concrete initial set of first layer floor, the lower support bar 33 and a bolt that an inside is hollow setting are provided 35, the top of the lower support bar 33 is threaded portion 330, is offered on the threaded portion 330 corresponding with the bolt 35 perpendicular To bolt seam 331, the periphery of the threaded portion 330 is also arranged with an adjustable seats 333, and the bottom of the lower support bar 33 is led to The first fixing piece for crossing the upper module 10 is installed on the upper module 10 of the first layer floor;Preferably, described first is solid Determining part is positioning column 101, and the bottom of the lower support bar 33 is set in the positioning of 10 top surface of upper module of the first layer floor On column 101.
Preferably, the lower, outer perimeter of the lower support bar 33 is installed with socket 335, first is mounted on to lower support bar 33 After on the upper module 10 of floor plate, side lever 50 is installed between adjacent lower support bar 33, the both ends of side lever 50 are separately mounted to phase On the socket 335 of adjacent lower support bar 33, which is connect with the socket 335 of lower support bar 33 by bolt.The side The setting of bar 50 can promote the stability between lower support bar 33, it is ensured that lower support bar 33 can accurately determine casing 40 Position is communicated up.
A upper support bar 31 is provided, the upper support bar 31 is equipped with pin hole 311, the lower part of the upper support bar 31 is worn If in the top for entering the lower support bar 33, the bolt of the pin hole 311 and lower support bar 33 that make upper support bar 31 stitches 331 pairs Bolt 35 is then inserted into the bolt seam 331 of the lower support bar 33 and the pin hole 311 of the upper support bar 31 by standard, So that the adjustable seats 333 on the spire 330 of lower support bar 33 is located at the lower section of bolt 35, for bolt 35 carry out limit and Support.In the present embodiment, the inner circumferential of adjustable seats 333 is equipped with the screw thread matched with the spire 330 of lower support bar 33, and Adjustable seats 333 are adjusted afterwards, and with movement of the adjustable seats 333 on the spire 330 of lower support bar 33, bolt 35 is also along slotting Eyelet 331 carry out it is vertically movable, and then upper support bar 31 carried out in lower support bar 33 it is vertically movable, thus to support rod 30 Length is adjusted, and the height for the support rod 30 for constituting upper support bar 31 and lower support bar 33 corresponds to the interval of adjacent floor deck Distance.Preferably, it may also set up screw thread on bolt 35, so that its end can be secured with nuts, further prevent bolt 35 from inserting Deviate from pin hole 311 and bolt seam 331.
Preferably, the upper periphery of the upper support bar 31 is installed with socket 315, lower branch is mounted on to upper support bar 33 The top of strut 33, and after completing the height adjustment of support rod 30, side lever 50 is installed between adjacent upper support bar 31, side lever 50 Both ends are separately mounted on the socket 315 of adjacent upper support bar 31, and the socket 315 of the side lever 50 and upper support bar 31 passes through Bolt connection.The setting of the side lever 50, can promote the stability between upper support bar 31, it is ensured that upper support bar 31 can be accurate The positioning of casing 40 is communicated up by ground.
E. according to the placement process of the lower module 20 of first layer floor in abovementioned steps a, the lower die of second layer floor is placed Block 20a connect the lower module 20a of second layer floor with the formwork for placing of second layer floor to it by its birdsmouth 207a, And the top of the support rod 30 above first layer floor is installed in described second by the second fixing piece of the lower module 20a Below the lower module 20a of floor plate, preferably, second fixing piece is positioning tube 201a, i.e., the top of the described upper support bar 31 Portion is plugged in the positioning tube 201a of the bottom surface lower module 20a of second layer floor.Step b, c is then repeated, the second floor is completed The installation of the upper module 10a of the placement of the casing 40a of plate, positioning and second layer floor;
F. step d, e is then repeated, the installation of the support rod, lower module, casing and upper module of lower first floor plate is carried out Construction, until being sequentially completed the pouring construction of each floor plate.
Construction method of the present invention for the concrete floor slab placement equipment in preserved pipeline hole, further includes that the concrete to floor reaches To after design strength, the upper module 10 and lower module 20 of the support rod 30 and the floor plate above the floor plate are removed, and is had There is following removal step:
Side lever 50 is removed, takes out the bolt 35 for fixing upper support bar 31 later, then upper support bar 31 is due to bolt 35 taking-up no longer supports fixed and falls and be inserted into inside lower support bar 33 by adjustable seats 333, or is taking out bolt 35 Meanwhile upper support bar 31 is fixed, after the taking-up of bolt 35, directly upper support bar 31 is taken out;Then by lower support bar 33 from It is extracted on the positioning column 103 of the upper module 10 of first layer floor, thus completes the dismounting of support rod 30;
After support rod 30 is removed, the bolt 15 in the first bolt hole 105 and the second bolt hole 205 is taken out, and by first The upper module 10 of floor plate is extracted;After the taking-up of upper module 10, the lower module 20 of first layer floor is extracted, thus completes first The demoulding of floor plate, i.e. a working cycles terminate.
In above-mentioned steps b, when casing 40 is placed on lower module 20, upper module 10 can be placed in 20 top of lower module, And be directed at the positioning support column 203 of lower module 20 and be plugged in the mounting groove 103 of upper module 10, so as to adjust the position of casing 40 It sets, is directed at the casing 40 on lower module 20 with the casing preformed hole 104 of upper module 10, thereby determines that the position of casing 40.To After casing 40 on lower module 20 substantially positions, upper module 10 is removed, pouring for concrete can be carried out.
When construction, construction personnel can according to actual needs, can with the upper module of the multiple floors of once mounting, lower module and Support rod, after the concrete of first layer floor reaches some strength, by the upper module, lower module and support of first layer floor Bar is removed, and the placing installation that the first layer is removed is continued installation into upper layer build floor to be poured, to make the placing installation It can recycle.In the present embodiment, casing is matched with line size, and casing without removing, directly splice with pipeline by the later period ?;Or the internal diameter of casing can be greater than outer diameter tube, and casing is without dismounting, directly through casing when Pipe installing, and Waterproof material etc. is filled between casing and pipeline.In other embodiments, if casing needs to remove, which uses plastics It is made, after concrete reaches intensity, which is broken into pieces or is taken out using other way.
Concrete floor slab placement equipment and construction method of the present invention for preserved pipeline hole have the advantages that
1) in concrete floor slab placement, advance reservation goes out the hole location of later period pipeline, aperture is abolished after avoiding floor from forming, to floor It damages;
2) by support bar group at support system setting, accurately control the position of different floor gap pipeline preformed holes Verticality makes the offset in different floor gap preserved pipelines hole within a certain error range, guarantees the smooth installation of later period pipeline;
3) adjustable in length of support rod, so that the present invention can be applicable in the construction of different story height buildings, it can week Turn to use.

Claims (10)

1. a kind of concrete floor slab placement equipment for preserved pipeline hole, it is characterised in that including upper module, lower module, support rod and Casing, in which:
The support rod is fixed between the lower module of adjacent two layers and upper module;
The upper module is formed with a top surface and a bottom surface, and the casing offered on the upper module through the upper module is reserved Hole, the top surface of the upper module are equipped with first fixing piece fixed for the support rod bottom;
The lower module is formed with a top surface and a bottom surface, and the bottom surface of the lower module is equipped with to be fixed for the support bar top The second fixing piece, the positioning support column for positioning support upper module is additionally provided on the top surface of the lower module;
Described sleeve pipe is placed on the top surface of the lower module.
2. the concrete floor slab placement equipment according to claim 1 for preserved pipeline hole, it is characterised in that: the support rod packet Upper support bar, lower support bar and a bolt are included, it is hollow set inside the lower support bar that the upper support bar, which is equipped with pin hole, It sets, the top of the lower support bar is threaded portion, is offered on the threaded portion of the lower support bar slotting with the upper support bar The corresponding vertical bolt seam of pin hole, is arranged with an adjustable seats on the threaded portion, the upper support bar be plugged in it is described under In support rod, the bolt is plugged in the pin hole of the upper support bar and the bolt seam of lower support bar, and by described The fixed bolt of adjustable seats limit.
3. the concrete floor slab placement equipment according to claim 2 for preserved pipeline hole, it is characterised in that: described first is fixed Part is positioning column, and the bottom of the lower support bar is set on the positioning column of the upper module top surface.
4. the concrete floor slab placement equipment according to claim 2 for preserved pipeline hole, it is characterised in that: described second is fixed Part is positioning tube, is plugged in the positioning tube of the lower module bottom surface at the top of the upper support bar.
5. the concrete floor slab placement equipment according to claim 1 for preserved pipeline hole, it is characterised in that: the upper module Bottom surface is equipped with mounting groove corresponding with the positioning support column, plugs for the positioning support column of the lower module.
6. the concrete floor slab placement equipment according to claim 1 for preserved pipeline hole, it is characterised in that: further include a spiral shell Bolt, the upper module are equipped with the first bolt hole matched with the bolt, and the lower module is equipped with and matches with the bolt The second bolt hole, the first bolt hole of the upper module and the position of the second bolt hole of the lower module are corresponding.
7. the concrete floor slab placement equipment according to claim 1 for preserved pipeline hole, it is characterised in that: the support rod It is installed with socket on periphery, side lever is provided between adjacent supports bar, the side lever is installed in the support rod by bolt On the socket of periphery.
8. a kind of construction method of the concrete floor slab placement equipment for preserved pipeline hole, which comprises the following steps:
A., one lower module is provided, and the lower module is aligned with the formwork for placing of first layer floor and is connect, the lower module is formed There are a top and bottom, the bottom surface of the lower module is equipped with the second fixing piece, and the top surface of the lower module is equipped with positioning branch Dagger;
B. according to pipe design position, casing is placed on the top surface of lower module, and pours first layer floor in casing periphery Concrete;
C. a upper module is provided, the upper module is formed with a top surface and a bottom surface, is offered on the upper module through described The casing preformed hole of upper module, the bottom surface of the upper module are equipped with corresponding with the positioning support column on the lower module top surface Mounting groove, the upper module is placed in above the lower module, and be plugged in the positioning support column of lower module on described In the mounting groove of module, adjusting sleeve pipe position makes to wear at the top of casing in the casing preformed hole of upper module;The upper module Top surface be equipped with the first fixing piece;
D., one support rod is provided, to the end of the concrete initial set of first layer floor, the bottom of the support rod is passed through on described First fixing piece of module is installed on the upper module;
E. the lower module for placing second layer floor, connects the lower module of second layer floor and the formwork for placing of second layer floor to it It connects, and the top of the support rod above first layer floor is installed in the lower module by the second fixing piece of the lower module Lower section, then repeatedly step b, c;
F. step d, e is then repeated, the pouring construction of each floor plate is sequentially completed.
9. the construction method of the concrete floor slab placement equipment according to claim 8 for pipeline preformed hole, which is characterized in that institute It states support rod to be connected and composed by upper support bar and lower support bar, step d further comprises:
To the end of the concrete initial set of floor, the lower support bar and a bolt that an inside is hollow setting, the lower support are provided The top of bar is threaded portion, and vertical bolt seam corresponding with the bolt, the threaded portion periphery are offered on the threaded portion An adjustable seats are arranged with, the bottom of the lower support bar is installed in the upper mold by the first fixing piece of the upper module On block;
A upper support bar is provided, the upper support bar is equipped with pin hole, the lower part of the upper support bar is worn into the lower branch In the top of strut, and bolt is inserted into the bolt seam of the lower support bar and the pin hole of the upper support bar, and adjust Adjustable seats are saved, the height for the support rod for constituting upper support bar and lower support bar corresponds to the spacing distance of adjacent floor deck.
10. the construction method of the concrete floor slab placement equipment according to claim 8 for pipeline preformed hole, which is characterized in that It is further comprising the steps of:
After the concrete of floor reaches design strength, the upper mold of the support rod and the floor plate above the floor plate is removed Block and lower module.
CN201710356796.8A 2017-05-19 2017-05-19 Concrete floor slab placement equipment and construction method for preserved pipeline hole Active CN107246145B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710356796.8A CN107246145B (en) 2017-05-19 2017-05-19 Concrete floor slab placement equipment and construction method for preserved pipeline hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710356796.8A CN107246145B (en) 2017-05-19 2017-05-19 Concrete floor slab placement equipment and construction method for preserved pipeline hole

Publications (2)

Publication Number Publication Date
CN107246145A CN107246145A (en) 2017-10-13
CN107246145B true CN107246145B (en) 2019-06-14

Family

ID=60017115

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710356796.8A Active CN107246145B (en) 2017-05-19 2017-05-19 Concrete floor slab placement equipment and construction method for preserved pipeline hole

Country Status (1)

Country Link
CN (1) CN107246145B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20190383039A1 (en) * 2018-09-04 2019-12-19 Sien Han Charlene Chong Height-Adjustable Jack and Vertical Modular Component Support using the same
CN110905187B (en) * 2019-12-09 2021-10-01 国网新疆电力有限公司建设分公司 Template structure for transformer substation main body construction
CN111335562B (en) * 2019-12-12 2021-04-09 孟凡林 Stair construction method applying precast concrete stair platform plate and support system

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03500191A (en) * 1987-09-02 1991-01-17 ラケンヌスパルベル・ヘイッキ・リンキネン・オイ Penetrating structural element
FR2712330B1 (en) * 1993-11-10 1998-12-24 Michel Destouches Lost formwork plate for reservations in the floors of all fluid pipelines.
CN103806646B (en) * 2014-02-18 2016-04-27 中国建筑股份有限公司 The early-dismantling construction method that a kind of three-dimensional space is adjustable
CN205000639U (en) * 2015-09-08 2016-01-27 中建八局第四建设有限公司 Modular wear floor cover
CN205502577U (en) * 2016-01-28 2016-08-24 京鑫建设集团有限公司 A thimble assembly for buried sleeve one shot forming construction in piping shaft
CN206071038U (en) * 2016-08-31 2017-04-05 中国建筑第七工程局有限公司 A kind of aluminum alloy pattern plate flooring and beam support system

Also Published As

Publication number Publication date
CN107246145A (en) 2017-10-13

Similar Documents

Publication Publication Date Title
CN105220874B (en) The construction method of basement superelevation exterior wall self-supporting single side formwork system
CN107246145B (en) Concrete floor slab placement equipment and construction method for preserved pipeline hole
KR101745242B1 (en) Bariable beam form and construction method thereof
CN111979882B (en) Template device and template system
CN106150055A (en) Concrete embedded part essence flat hanging installment work stand and the installation method of built-in fitting
CN113374245B (en) Construction method for temporary support of post-cast strip of beam plate
CN205243006U (en) Side form supports top and holds in palm
CN105421781A (en) Synchronous pouring construction method and formwork system for concrete ridge platform and structural floor slab
CN113123597B (en) Assembled laminated slab splicing seam suspension type formwork structure and construction method thereof
CN113006377B (en) Constructional column steel bar construction method
KR20110010248A (en) Multi u-head bracket apparatus for bridge construction
CN205822792U (en) A kind of regulation support for masonry direct-burried
CN109537606B (en) Slope protection retaining wall masonry template structure
CN110409320A (en) A kind of the concrete cast-in-situ bracket and its construction method of adjustable slope
KR20180057380A (en) Supporting and connecting apparatus for foamwork
CN205791363U (en) A kind of electrical engineering positioning installation apparatus
CN205026208U (en) Pipeline positioning installation device
CN208918294U (en) The baffle plate assembly that segmentation for concrete pours
KR101673907B1 (en) Roof building construction methods and construction materials used him
KR101639311B1 (en) Manhole height adjustment implement and manhole construction method using the same
CN106013779A (en) Positioning method for early-dismantling supporting system
CN113481823A (en) Adjustable beam bottom wedge-shaped device and beam body installation process
CN217054323U (en) Adjustable post-cast strip temporary support system
CN114562105B (en) Plastering-free aluminum template for building wall
CN217079670U (en) A building reinforcing apparatus for city planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant