CN107229802A - Construction techniques based on BIM - Google Patents

Construction techniques based on BIM Download PDF

Info

Publication number
CN107229802A
CN107229802A CN201710447149.8A CN201710447149A CN107229802A CN 107229802 A CN107229802 A CN 107229802A CN 201710447149 A CN201710447149 A CN 201710447149A CN 107229802 A CN107229802 A CN 107229802A
Authority
CN
China
Prior art keywords
bim
building
bim models
models
skeleton
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710447149.8A
Other languages
Chinese (zh)
Inventor
周江峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Original Assignee
Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Zhi Jian New Architectural Design Consulting Co Ltd filed Critical Chengdu Zhi Jian New Architectural Design Consulting Co Ltd
Priority to CN201710447149.8A priority Critical patent/CN107229802A/en
Publication of CN107229802A publication Critical patent/CN107229802A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Architecture (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Civil Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Structural Engineering (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • Strategic Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Mechanical Engineering (AREA)
  • General Business, Economics & Management (AREA)
  • Primary Health Care (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses the construction techniques based on BIM, comprise the following steps:1) the framework information feature of building, is collected, BIM models are set up according to framework information feature;2), to step 1) obtain BIM models analyze, the defect to presence is repaired, the BIM models after then being repaired;3), according to step 2) obtain BIM models carry out building skeleton build;4) skeleton fill material information, the BIM models set up according to fill material information after the filling of building, are collected;5) the BIM models of material transport system, are set up, and the BIM models are carried out to repair the optimal material transport system of establishment, to realize safety to the high-rise conveying material of building.The present invention sets up related BIM models, the problem of solving the building existing defects that existing building mode is easily caused after building by BIM technology.

Description

Construction techniques based on BIM
Technical field
The present invention relates to technical field of building construction, and in particular to the construction techniques based on BIM.
Background technology
Urban development be unable to do without the construction of building.
Existing building, which is built, includes layout design, then carries out building for building according to layout design, due to building Designer is in design, and dependence is theoretical foundation and empirical value, successively, it is impossible to completely being asked present in actual construction process Topic is all taken into account, and therefore, is easily caused the building existing defects built, it is impossible to reach most satisfied effect so that visitor Family is unsatisfied with.
The content of the invention
It is an object of the invention to provide the construction techniques based on BIM, it is easily caused with to solve existing building mode and is repaiied The problem of building existing defects after building.
The present invention is achieved through the following technical solutions:
Construction techniques based on BIM, comprises the following steps:
1) the framework information feature of building, is collected, BIM models are set up according to framework information feature;
2), to step 1) obtain BIM models analyze, the defect to presence is repaired, after then being repaired BIM models;
3), according to step 2) obtain BIM models carry out building skeleton build;
4) skeleton fill material information, the BIM models set up according to fill material information after the filling of building, are collected;
5) the BIM models of material transport system, are set up, and the BIM models are carried out to repair the optimal material transportation of establishment System, to realize safety to the high-rise conveying material of building.
At present, existing construction pattern can not modify according to defect information to architectural design, cause after building Building existing defects the problem of.
The present invention sets up related BIM models by BIM technology, and architectural design is actually being repaiied in advance by BIM models Have before building it is directly perceived understand, then BIM models are modified until satisfaction according to the defect of presence, then according to final BIM models are designed modification, and are constructed according to final BIM models, in this way, the present invention solves existing building side The problem of formula is easily caused the building existing defects after building.
Further, the detailed process that the skeleton is built:Skeleton is built with reinforcing bar, then first is poured with mixed mud Layer, then up pours rest layers successively, after pouring one layer when the defect that occurs when being poured with preceding layer BIM models are carried out Repair, obtain more excellent BIM models.
Further, by BIM models and repair process input database.
The present invention compared with prior art, has the following advantages and advantages:
The present invention sets up related BIM models by BIM technology, and architectural design is actually being repaiied in advance by BIM models Have before building it is directly perceived understand, then BIM models are modified until satisfaction according to the defect of presence, then according to final BIM models are designed modification, and are constructed according to final BIM models, in this way, the present invention solves existing building side The problem of formula is easily caused the building existing defects after building.
Embodiment
For the object, technical solutions and advantages of the present invention are more clearly understood, with reference to embodiment, to present invention work Further to describe in detail, exemplary embodiment and its explanation of the invention is only used for explaining the present invention, is not intended as to this The restriction of invention.
Embodiment:
Construction techniques based on BIM, comprises the following steps:
1) the framework information feature of building, is collected, BIM models are set up according to framework information feature;
2), to step 1) obtain BIM models analyze, the defect to presence is repaired, after then being repaired BIM models;
3), according to step 2) obtain BIM models carry out building skeleton build;The specific mistake that the skeleton is built Journey:Skeleton is built with reinforcing bar, then first layer is poured with mixed mud, rest layers are then up poured successively, one layer after pouring When the defect that occurs when being poured with preceding layer BIM models are repaired, obtain more excellent BIM models;
4) skeleton fill material information, the BIM models set up according to fill material information after the filling of building, are collected;
5) the BIM models of material transport system, are set up, and the BIM models are carried out to repair the optimal material transportation of establishment System, to realize safety to the high-rise conveying material of building;
By all BIM models and repair process input database.
Above-described embodiment, has been carried out further to the purpose of the present invention, technical scheme and beneficial effect Describe in detail, should be understood that the embodiment that the foregoing is only the present invention, be not intended to limit the present invention Protection domain, within the spirit and principles of the invention, any modification, equivalent substitution and improvements done etc. all should be included Within protection scope of the present invention.

Claims (3)

1. the construction techniques based on BIM, it is characterised in that comprise the following steps:
1) the framework information feature of building, is collected, BIM models are set up according to framework information feature;
2), to step 1) obtain BIM models analyze, the defect to presence is repaired, the BIM after then being repaired Model;
3), according to step 2) obtain BIM models carry out building skeleton build;
4) skeleton fill material information, the BIM models set up according to fill material information after the filling of building, are collected;
5) the BIM models of material transport system, are set up, and the BIM models are carried out to repair the optimal material transport system of establishment, To realize safety to the high-rise conveying material of building.
2. the construction techniques according to claim 1 based on BIM, it is characterised in that it is specific that the skeleton is built Process:Skeleton is built with reinforcing bar, then first layer is poured with mixed mud, rest layers are then up poured successively, after pouring one The defect occurred when being poured during layer with preceding layer is repaired to BIM models, obtains more excellent BIM models.
3. the construction techniques according to claim 1 based on BIM, it is characterised in that by BIM models and repair process Input database.
CN201710447149.8A 2017-06-14 2017-06-14 Construction techniques based on BIM Pending CN107229802A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710447149.8A CN107229802A (en) 2017-06-14 2017-06-14 Construction techniques based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710447149.8A CN107229802A (en) 2017-06-14 2017-06-14 Construction techniques based on BIM

Publications (1)

Publication Number Publication Date
CN107229802A true CN107229802A (en) 2017-10-03

Family

ID=59935026

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710447149.8A Pending CN107229802A (en) 2017-06-14 2017-06-14 Construction techniques based on BIM

Country Status (1)

Country Link
CN (1) CN107229802A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107908905A (en) * 2017-12-12 2018-04-13 东华理工大学 A kind of device that construction simulation is carried out by BIM
CN108763619A (en) * 2018-04-02 2018-11-06 中国十七冶集团有限公司 A kind of analyzing methods of architectural energy saving based on BIM
CN109726445A (en) * 2018-12-07 2019-05-07 佛山科学技术学院 Assembled architecture concrete pouring procedure based on BIM
CN110206167A (en) * 2019-06-17 2019-09-06 中国十七冶集团有限公司 A kind of assembly concrete building element tenon riveting formula design and construction method
CN112214824A (en) * 2020-10-28 2021-01-12 东阳市鼎元建设有限公司 Building construction method
CN115048710A (en) * 2022-08-15 2022-09-13 中建八局发展建设有限公司 Holographic visualization model construction and interaction system and method based on BIM technology

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103544556A (en) * 2013-09-06 2014-01-29 上海大学 Life-cycle management system and method for tunnels
CN104657510A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing rapid steel truss arch bridge modeling by utilizing BIM
CN106013798A (en) * 2016-06-12 2016-10-12 江苏宜安建设有限公司 Marker bed construction method based on building information modeling (BIM)
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN106202648A (en) * 2016-06-29 2016-12-07 铁道第三勘察设计院集团有限公司 Tunnel portal position automatization is than the BIM method for designing of choosing
US20160357881A1 (en) * 2010-03-02 2016-12-08 Illinois Tool Works, Inc. Method, computer program product and apparatus for providing a building options configurator

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160357881A1 (en) * 2010-03-02 2016-12-08 Illinois Tool Works, Inc. Method, computer program product and apparatus for providing a building options configurator
CN103544556A (en) * 2013-09-06 2014-01-29 上海大学 Life-cycle management system and method for tunnels
CN104657510A (en) * 2015-03-19 2015-05-27 中铁二局第五工程有限公司 Method and device for realizing rapid steel truss arch bridge modeling by utilizing BIM
CN106013535A (en) * 2016-05-31 2016-10-12 上海宝冶集团有限公司 BIM-based pre-assembling method for double-curved glass curtain wall
CN106013798A (en) * 2016-06-12 2016-10-12 江苏宜安建设有限公司 Marker bed construction method based on building information modeling (BIM)
CN106202648A (en) * 2016-06-29 2016-12-07 铁道第三勘察设计院集团有限公司 Tunnel portal position automatization is than the BIM method for designing of choosing

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
赵永任: "虚拟施工的作用", 《工程项目管理》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107908905A (en) * 2017-12-12 2018-04-13 东华理工大学 A kind of device that construction simulation is carried out by BIM
CN108763619A (en) * 2018-04-02 2018-11-06 中国十七冶集团有限公司 A kind of analyzing methods of architectural energy saving based on BIM
CN109726445A (en) * 2018-12-07 2019-05-07 佛山科学技术学院 Assembled architecture concrete pouring procedure based on BIM
CN110206167A (en) * 2019-06-17 2019-09-06 中国十七冶集团有限公司 A kind of assembly concrete building element tenon riveting formula design and construction method
CN112214824A (en) * 2020-10-28 2021-01-12 东阳市鼎元建设有限公司 Building construction method
CN115048710A (en) * 2022-08-15 2022-09-13 中建八局发展建设有限公司 Holographic visualization model construction and interaction system and method based on BIM technology
CN115048710B (en) * 2022-08-15 2022-10-25 中建八局发展建设有限公司 Holographic visualization model construction and interaction system and method based on BIM technology

Similar Documents

Publication Publication Date Title
CN107229802A (en) Construction techniques based on BIM
Tam et al. Prefabrication as a mean of minimizing construction waste on site
Liu et al. Retracted: Using BIM to improve the design and construction of bridge projects: A case study of a long-span steel-box arch bridge project
CN108763710A (en) A kind of assembled architecture forward direction Deepen Design method based on BIM
CN109753672A (en) Prefabricated concrete structure engineering optimization method based on BIM technology
CN103336856A (en) Virtual steel structure pre-assembly method based on visual model
Buitrago et al. Structural failures in cast-in-place reinforced concrete building structures under construction
Golzarpoor et al. A green-lean simulation model for assessing environmental and production waste in construction
CN104573254A (en) Pre-construction technical disclosure method based on BIM
CN107299762A (en) A kind of concrete pouring procedure based on BIM
CN108086323A (en) A kind of concrete construction control method
CN110750823A (en) BIM visual display method
CN107489277B (en) Novel steel-hybrid beam column node construction structure and comprehensive construction method
CN106088598A (en) A kind of BIM technology is used to carry out the method led the way of model of constructing
CN107255981A (en) A kind of super high rise building transport of materials management system based on BIM
CN103485370A (en) Concrete construction control method for preventing harmful cracks of wallboard
CN107092764A (en) A kind of concrete assembled construction method based on BIM
CN108979205B (en) Staggered floor flow construction method for super high-rise residential structure
CN205444903U (en) Shear force wall wind -tunnel bush board
CN107386637A (en) A kind of shear wall negative and positive angle construction mould and operating method
CN206397129U (en) Build aluminum alloy mould plate corner upright and wall panel assemblies structure
CN206397130U (en) Build aluminum alloy mould plate wall panel assemblies structure
CN106639344A (en) Concrete exposed reinforcing bar and hole repairing scheme
CN107671242A (en) A kind of smokeless pouring technology of gravity casting mold
CN103878316A (en) Process for effectively preventing sand inclusion defect caused by process water blocking hole of air cylinder body

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171003

RJ01 Rejection of invention patent application after publication