CN107908905A - A kind of device that construction simulation is carried out by BIM - Google Patents
A kind of device that construction simulation is carried out by BIM Download PDFInfo
- Publication number
- CN107908905A CN107908905A CN201711313741.5A CN201711313741A CN107908905A CN 107908905 A CN107908905 A CN 107908905A CN 201711313741 A CN201711313741 A CN 201711313741A CN 107908905 A CN107908905 A CN 107908905A
- Authority
- CN
- China
- Prior art keywords
- data
- construction
- module
- bim
- modeling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Civil Engineering (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Architecture (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of device that construction simulation is carried out by BIM of construction simulation engineering device technique field, and the device of construction simulation should be carried out by BIM to be included:Data acquisition end, data conversion module, memory, processing center, database, modeling, database population module, data regulation and control module and display;The data acquisition end is used to be acquired the parameter of construction site, and the object of collection includes geographical location, construction point, construction progress image, and the output terminal at the data acquisition end is coupled with the input terminal of data conversion module;This can subsequently be adjusted while not influencing normally to simulate by the BIM devices for carrying out construction simulation, inputs operation, pass through the adjustment of data, input, so that its real-time status is more accurate, it can be anticipated that the duration of a project, by being measured to the service condition of material, so that its dosage is accurate, and being capable of real-time variation call.
Description
Technical field
The present invention relates to construction simulation engineering device technique field, is specially a kind of device that construction simulation is carried out by BIM.
Background technology
BIM (Building Information Modeling, i.e. Building Information Model) is that (area of computer aided is set after CAD
Meter) appear in the another important Computer Applied Technology of engineering construction industry after technology, triggering history of building trade without
The thorough revolution of precedent.The technology utilizes digital modeling software, improves Project design, construction and the efficiency of management, and to use
The building enterprise of the technology brings great newly-increased value, dosage monitoring, duration and work of original analog form for raw material
Change in journey is difficult to change, and causes it to be deviated with actual conditions, for this reason, being applied we have proposed one kind by BIM
The device of work simulation.
The content of the invention
It is an object of the invention to provide a kind of device that construction simulation is carried out by BIM, to solve above-mentioned background technology
Change in dosage monitoring of the original analog form of middle proposition for raw material, duration and engineering is difficult to change, cause its with
The problem of actual conditions are deviated.
To achieve the above object, the present invention provides following technical solution:A kind of device that construction simulation is carried out by BIM,
The device that construction simulation is carried out by BIM includes:Data acquisition end, data conversion module, memory, processing center, data
Storehouse, modeling, database population module, data regulation and control module and display;
The data acquisition end is used to be acquired the parameter of construction site, and the object of collection includes geographical location, applies
Work point, construction carry out image, and the output terminal at the data acquisition end is coupled with the input terminal of data conversion module;
The data that data acquisition end gathers are converted to the electric signal of system identification, the data by the data conversion module
Modular converter is by electric signal transmission to memory;
The data terminal of the memory is connected by the transmission port of data cable and processing center, and the processing center passes through
Reception electric signal to memory is obtained and handled, and the processing center is by by the electric signal and database of reception
In pre-stored data contrast;
The information to prestore in the database to the arrangement and method for construction, by the way that the information of acquisition and the information that prestores are carried out pair
According to finding out and the position of prestored information deviation, and carry out feedback adjustment;
The modeling is BIM simulation softwares, the data of collection is carried out construction data model, and carry out solid and fill out
Fill, the modeling is Real-time running system, and when the information at the data acquisition end changes, modeling is made accordingly
Adjustment;
The database population module carries out module filling to some spaces of modeling as needed, after filled object is
Phase addition construction thing is deleted not by the construction object of progress, is fed back to after adding construction object by way of information feedback
Construction end;
The data regulation and control module includes construction progress data metering end, material quantity data metering end and rdu remaining duration and reminds
Module, data regulation and control module regulate and control the data of modeling, increase modeling display mode or according to
Real progress finely tunes its data parameters;
Pattern reality after modeling is added information, modification information and builds full pattern and shown by the display.
Preferably, the data acquisition end includes GPS positioning module, high-definition night-viewing photographing module and communication module.
Preferably, the processing center is manually-operated control terminal.
Preferably, the output terminal of the processing center is also associated with warning device.
Preferably, the display is light-emitting diode display.
Compared with prior art, the beneficial effects of the invention are as follows:The device that construction simulation is carried out by BIM can be not
Influence subsequently be adjusted while normal simulation, input operation, pass through the adjustment of data, input so that its real-time shape
State is more accurate, it can be anticipated that the duration of a project, by being measured to the service condition of material so that its dosage is accurate, and energy
Enough real-time variation calls.
Brief description of the drawings
Fig. 1 is present system block diagram;
Fig. 2 is the system block diagram that data of the present invention regulate and control module.
In figure:1 data acquisition end, 2 data conversion modules, 3 memories, 4 processing centers, 5 databases, 6 modelings, 7
Database population module, 8 data regulation and control module, 81 construction progress data metering ends, 82 material quantity data metering ends, 83 rdu remaining durations
Reminding module, 9 displays.
Embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other without making creative work
Embodiment, belongs to the scope of protection of the invention.
- 2 are please referred to Fig.1, the present invention provides a kind of technical solution:A kind of device that construction simulation is carried out by BIM, this is logical
Crossing the device of BIM progress construction simulations includes:Data acquisition end 1, data conversion module 2, memory 3, processing center 4, data
Storehouse 5, modeling 6, database population module 7, data regulation and control module 8 and display 9;
Data acquisition end 1 is used to be acquired the parameter of construction site, and the object of collection includes geographical location, construction
Point, construction carry out image, and the output terminal at data acquisition end 1 is coupled with the input terminal of data conversion module 2;
The data that data acquisition end 1 gathers are converted to the electric signal of system identification, data conversion mould by data conversion module 2
Block 2 is by electric signal transmission to memory 3;
The data terminal of memory 3 is connected by data cable with the transmission port of processing center 4, and processing center 4 is by depositing
The reception electric signal of reservoir 3 is obtained and handled, and processing center 4 passes through in the electric signal of reception and database 5
Pre-stored data contrasts;
The information to prestore in database 5 to the arrangement and method for construction, by the way that the information of acquisition is compareed with the information to prestore,
Find out and the position of prestored information deviation, and carry out feedback adjustment;
Modeling 6 is BIM simulation softwares, and the data of collection are carried out construction data model, and carries out three-dimensional filling, is built
Modular system 6 is Real-time running system, and when the information at data acquisition end 1 changes, modeling 6 makes corresponding adjustment;
Database population module 7 carries out module filling to some spaces of modeling 6 as needed, and filled object is the later stage
Addition construction thing is deleted not by the construction object of progress, is fed back to and applied by way of information feedback after addition construction object
Work end;
Data regulation and control module 8 is carried including construction progress data metering end 81, material quantity data metering end 82 and rdu remaining duration
Awake module 83, data regulation and control module 8 regulate and control the data of modeling 6, increase the display mode or root of modeling 6
Its data parameters is finely tuned according to real progress;
Pattern reality after modeling is added information, modification information and builds full pattern and shown by display 9.
Wherein, data acquisition end 1 includes GPS positioning module, high-definition night-viewing photographing module and communication module, can be determined
The transmission of position, Image Acquisition and data, processing center 4 is manually-operated control terminal, can carry out the same of voluntarily data control
When can also by artificial control, calculate, the output terminal of processing center 4 be also associated with warning device, and display 9 shows for LED
Show device.
Operation principle:In use, data acquisition end 1 is installed on engineering construction end, positional information to engineering construction point,
Construction image information is gathered in real time, collection information is converted to electric signal by data conversion module 2, in database 5
Prestore the positional information for needing to build, and positional information is compareed with the information gathered, passes through feedback if there is deviation
Mode feed back to construction point and be modified, the information of acquisition is exported to modeling 6 and is modeled, passes through data fill mould
Block 7, data regulate and control module 8 and are added, delete and correct, so as to reach the effect identical with practical application, will finally build
Model after mould is shown by display 9, passes through construction progress data metering end 81, material quantity data metering end 82, remaining work
Phase reminding module 83 carries out man-hour calculation and raw material dosage metering, and when there is the excessive situation of raw material dosage, processing center 4 passes through
Warning device is reminded, and construction point is required.
Although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of changes, modification, replace
And modification, the scope of the present invention is defined by the appended.
Claims (5)
- A kind of 1. device that construction simulation is carried out by BIM, it is characterised in that:This carries out the device bag of construction simulation by BIM Include:Data acquisition end (1), data conversion module (2), memory (3), processing center (4), database (5), modeling (6), Database population module (7), data regulation and control module (8) and display (9);The data acquisition end (1) is used to be acquired the parameter of construction site, and the object of collection includes geographical location, construction Point, construction carry out image, and the output terminal of the data acquisition end (1) is coupled with the input terminal of data conversion module (2);The data that data acquisition end (1) gathers are converted to the electric signal of system identification, the number by the data conversion module (2) According to modular converter (2) by electric signal transmission to memory (3);The data terminal of the memory (3) is connected by data cable with the transmission port of processing center (4), the processing center (4) by the way that the reception electric signal of memory (3) is obtained and handled, the processing center (4) is by by reception Electric signal is contrasted with the pre-stored data in database (5);The information to prestore to the arrangement and method for construction in the database (5), by the way that the information of acquisition and the information to prestore are carried out pair According to finding out and the position of prestored information deviation, and carry out feedback adjustment;The modeling (6) is BIM simulation softwares, and the data of collection are carried out construction data model, and carries out three-dimensional filling, The modeling (6) is Real-time running system, and when the information of the data acquisition end (1) changes, modeling (6) is made Go out corresponding adjustment;The database population module (7) carries out module filling to some spaces of modeling (6) as needed, and filled object is Later stage addition construction thing is deleted not by the construction object of progress, is fed back after adding construction object by way of information feedback To construction end;The data regulation and control module (8) includes construction progress data metering end (81), material quantity data metering end (82) and residue Duration reminding module (83), the data regulation and control module (8) regulate and control the data of modeling (6), increase modeling (6) display mode finely tunes its data parameters according to real progress;Pattern reality after modeling is added information, modification information and builds full pattern and shown by the display (9).
- A kind of 2. device that construction simulation is carried out by BIM according to claim 1, it is characterised in that:The data are adopted Collection end (1) includes GPS positioning module, high-definition night-viewing photographing module and communication module.
- A kind of 3. device that construction simulation is carried out by BIM according to claim 1, it is characterised in that:In the processing The heart (4) is manually-operated control terminal.
- A kind of 4. device that construction simulation is carried out by BIM according to claim 1, it is characterised in that:In the processing The output terminal of the heart (4) is also associated with warning device.
- A kind of 5. device that construction simulation is carried out by BIM according to claim 1, it is characterised in that:The display (9) it is light-emitting diode display.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711313741.5A CN107908905A (en) | 2017-12-12 | 2017-12-12 | A kind of device that construction simulation is carried out by BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711313741.5A CN107908905A (en) | 2017-12-12 | 2017-12-12 | A kind of device that construction simulation is carried out by BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107908905A true CN107908905A (en) | 2018-04-13 |
Family
ID=61865226
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711313741.5A Pending CN107908905A (en) | 2017-12-12 | 2017-12-12 | A kind of device that construction simulation is carried out by BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107908905A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109544102A (en) * | 2018-10-26 | 2019-03-29 | 中交第航务工程局有限公司 | A kind of engineering ship construction management system and application method based on BIM model |
CN110200402A (en) * | 2019-06-20 | 2019-09-06 | 四川省劲腾环保建材有限公司 | One kind being based on BIM platform construction Ground arrangement simulator |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102819621A (en) * | 2011-06-10 | 2012-12-12 | 上海市电力公司 | Device for conducting construction simulation through building information model (BIM) |
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN106682373A (en) * | 2017-03-17 | 2017-05-17 | 江苏省建筑科学研究院有限公司 | Construction simulation device working through BIM (building information modeling) |
CN106886848A (en) * | 2017-01-17 | 2017-06-23 | 中铁上海工程局集团有限公司 | Bridge construction information acquisition management system |
CN106920049A (en) * | 2017-03-28 | 2017-07-04 | 内蒙古科技大学 | A kind of Project Management System platform based on BIM network technologies |
CN106934852A (en) * | 2017-02-16 | 2017-07-07 | 西安科技大学 | A kind of Project Management System platform based on BIM network technologies |
CN107229802A (en) * | 2017-06-14 | 2017-10-03 | 成都智建新业建筑设计咨询有限公司 | Construction techniques based on BIM |
CN107423865A (en) * | 2017-03-10 | 2017-12-01 | 中铁四局集团有限公司 | BIM-based high-speed railway informatization management system |
-
2017
- 2017-12-12 CN CN201711313741.5A patent/CN107908905A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102819621A (en) * | 2011-06-10 | 2012-12-12 | 上海市电力公司 | Device for conducting construction simulation through building information model (BIM) |
US20130335413A1 (en) * | 2012-06-13 | 2013-12-19 | National Chiao Tung University | System and method for estimating construction duration |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN106886848A (en) * | 2017-01-17 | 2017-06-23 | 中铁上海工程局集团有限公司 | Bridge construction information acquisition management system |
CN106934852A (en) * | 2017-02-16 | 2017-07-07 | 西安科技大学 | A kind of Project Management System platform based on BIM network technologies |
CN107423865A (en) * | 2017-03-10 | 2017-12-01 | 中铁四局集团有限公司 | BIM-based high-speed railway informatization management system |
CN106682373A (en) * | 2017-03-17 | 2017-05-17 | 江苏省建筑科学研究院有限公司 | Construction simulation device working through BIM (building information modeling) |
CN106920049A (en) * | 2017-03-28 | 2017-07-04 | 内蒙古科技大学 | A kind of Project Management System platform based on BIM network technologies |
CN107229802A (en) * | 2017-06-14 | 2017-10-03 | 成都智建新业建筑设计咨询有限公司 | Construction techniques based on BIM |
Non-Patent Citations (4)
Title |
---|
夏贞勇: "基于BIM的实时施工模型应用实现", 《工业建筑》 * |
张康照: "基于BIM实时模型的施工进度监测系统研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑(月刊)建筑科学与工程》 * |
杨永刚: "BIM 技术在建筑设计中的实际应用", 《工程设计》 * |
王雪青 等: "基于BIM实时施工模型的4D模拟", 《广西大学学报:自然科学版》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109544102A (en) * | 2018-10-26 | 2019-03-29 | 中交第航务工程局有限公司 | A kind of engineering ship construction management system and application method based on BIM model |
CN110200402A (en) * | 2019-06-20 | 2019-09-06 | 四川省劲腾环保建材有限公司 | One kind being based on BIM platform construction Ground arrangement simulator |
CN110200402B (en) * | 2019-06-20 | 2024-05-10 | 四川省劲腾环保建材有限公司 | BIM platform-based construction site layout simulation device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107870600B (en) | A kind of transparent monitoring method in intelligence workshop and system | |
CN109412829A (en) | A kind of prediction technique and equipment of resource distribution | |
CN104572213B (en) | A kind of reconstructing method of spaceborne control computer | |
CN102867091B (en) | The quantitation modification method of a kind of electric network current diagram | |
CN109557934A (en) | A kind of control method and device of the unmanned plane cruise based on assembled architecture platform | |
CN103646348B (en) | Method for saving factory station wiring diagram panoramic inversion context | |
CN107908905A (en) | A kind of device that construction simulation is carried out by BIM | |
CN114201799A (en) | Visual tunnel construction progress management analysis system | |
CN108052311A (en) | A kind of metrical information system based on general system frame | |
CN110287567A (en) | The BIM fast modeling method driven based on parameterized units by design parameter | |
CN107066500A (en) | A kind of electrical network mass data quality indicator method based on PMS models | |
CN105893655A (en) | Physical simulation method for petroleum reservoir architecture | |
CN113705143B (en) | Automatic simulation system and automatic simulation method | |
CN112417562A (en) | Dynamo-based earthwork construction modeling method and device | |
CN104537168B (en) | The comprehensively monitoring simulation training system model data management method of equipment oriented function | |
CN107368972A (en) | It is a kind of that work platform and its application method are sent based on BIM technology | |
CN113128041A (en) | Digital factory MES system development method based on digital twin virtual technology | |
CN116030210A (en) | Carbon emission data statistics method, electronic device and storage medium | |
CN109344439A (en) | A kind of modeling of building block formula and its simulative construction method based on BIM | |
CN109766090B (en) | Integrated configuration method for program logic and secondary circuit | |
CN104463462A (en) | Power grid future state model maintenance tool | |
CN105679375A (en) | Automatic test system of storage equipment, and method thereof | |
CN109214015B (en) | Building element management method, device, terminal equipment and readable storage medium | |
CN102663159B (en) | Layered automatic configuration and optimization method of single line diagram outside power distribution network | |
CN111857015B (en) | Power transmission and transformation cloud intelligent controller |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180413 |
|
RJ01 | Rejection of invention patent application after publication |