CN107227740A - The construction method that limestone cave cell wall is closed in construction of diaphragm wall - Google Patents

The construction method that limestone cave cell wall is closed in construction of diaphragm wall Download PDF

Info

Publication number
CN107227740A
CN107227740A CN201710602537.9A CN201710602537A CN107227740A CN 107227740 A CN107227740 A CN 107227740A CN 201710602537 A CN201710602537 A CN 201710602537A CN 107227740 A CN107227740 A CN 107227740A
Authority
CN
China
Prior art keywords
grouting
hole
solution cavity
wall
diaphragm wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710602537.9A
Other languages
Chinese (zh)
Inventor
谢志杰
张润德
唐武兴
黄茂兴
蔡凯祥
罗海腾
梁何龙
谢宝如
萧敏权
王殷杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuan Tian Engineering Co Ltd Of Guangdong Province
Guangdong Yuantian Engineering Co Ltd
Original Assignee
Yuan Tian Engineering Co Ltd Of Guangdong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuan Tian Engineering Co Ltd Of Guangdong Province filed Critical Yuan Tian Engineering Co Ltd Of Guangdong Province
Priority to CN201710602537.9A priority Critical patent/CN107227740A/en
Publication of CN107227740A publication Critical patent/CN107227740A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/24Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing alkyl, ammonium or metal silicates; containing silica sols
    • C04B28/26Silicates of the alkali metals
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/70Grouts, e.g. injection mixtures for cables for prestressed concrete

Abstract

The present invention proposes the construction method that limestone cave cell wall is closed in a kind of construction of diaphragm wall, and it includes step:(One)Solution cavity condition survey;(Two)Set grout hole:Single liquid grout hole is set at nearly continuous wall displacement both sides interval;Two-shot grouting hole is set in single liquid grout hole outside spacers;(Three)By two-shot grouting hole toward irrigating two fluid grouting in solution cavity:The two fluid grouting is cement:Water:Enclosed in waterglass mixed serum, solution cavity and cover continuous curtain wall area;(Four)By double single liquid grout holes toward irrigating single fluid grouting in solution cavity:The single fluid grouting is cement mortar, and area can be dug by forming diaphragm wall in diaphragm wall area;(Five)Note oar effect detection.The present invention is for the deeper solution cavity in position, it is only necessary to prospecting hole is set in diaphragm wall periphery, the potential safety hazard of landslide is not caused because arranging excessive exploration hole;The present invention only need to diaphragm wall location-appropriate expanded scope be in the milk, without whole solution cavity is evacuated and grout filling handle, with short time limit, difficulty is small, cost is low, effect is good the features such as.

Description

The construction method that limestone cave cell wall is closed in construction of diaphragm wall
Technical field
The present invention relates to a kind of construction method of construction engineering technical field, and in particular to a kind of karst strata underground is continuous The construction method of wall chase wall closing.
Background technology
General underground connects more than wall work progress mid-early stage using segmentation grooving, then inserts reinforcing bar the groove section dug is interior Cage and concrete perfusion, during segmentation grooving, such as limestone cave then will first be filled processing to solution cavity, current public affairs It is first for detection solution cavity to recognize preferable karst cave treatment process(The long wide * of * are high)Position, then takes the throwing block into solution cavity The methods such as stone, backfill plain concrete, pressure slurry.This karst cave treatment method needs to arrange that solution cavity is verified in many geology detecting holes Specific size, exploration hole disturbance solution cavity mostly occurs landslide potential safety hazard greatly, takes long, costly, long in time limit, difficulty of construction Greatly, work efficiency is low, and the karst cave treatment deeper to depth brings very big difficulty.
The content of the invention
The purpose of the present invention is to propose in a kind of construction of diaphragm wall limestone cave cell wall close construction method, its Only continuous wall displacement locally carry out cell wall closing, with easy construction, it is quick, efficient and cost-effective the characteristics of.
The purpose of the present invention can be realized by following technical solution:
The construction method that limestone cave cell wall is closed in a kind of construction of diaphragm wall, comprises the following steps.
Step one, solution cavity condition survey
Prospecting hole is set in diaphragm wall axis and periphery using boring method, the distributing position and size of limestone cave is determined, sentences Groundwater environment and watery residing for disconnected solution cavity.
Step 2, sets grout hole
Single liquid grout hole is set by interval of 2~3m in nearly continuous wall displacement both sides, some single liquid grout holes surround single liquid grouting Circle;Single liquid grouting circle outside sets two-shot grouting hole by interval of 2~3m, and some two-shot grouting holes surround two-shot grouting circle;It is double Liquid grouting circle is separated by 2~2.5m with single liquid grouting circle.
Step 3, toward the interior perfusion two fluid grouting of solution cavity
Toward the two-shot grouting hole insertion Grouting Pipe of two-shot grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging;
Two fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the two fluid grouting is cement:Water:Waterglass is with 10: 10 ~15:2~4 quality uses 42.5 grades of portland cements or Portland cement, waterglass mould than mixed serum, cement Number m=2.4~3.2(Concentration Be=30~40), injection speed is:30~70L/min.
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, can be formed after the completion of dual slurry slip casting together Curtain wall, is enclosed in solution cavity and covers continuous curtain wall area, after the completion of slip casting, extracts Grouting Pipe, and biliquid is blocked with M7.5 cement mortar Grout hole.
Step 4, toward the interior perfusion single fluid grouting of solution cavity
Toward single liquid grout hole insertion Grouting Pipe of list liquid grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging;
Single fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the single fluid grouting is cement mortar, and cement uses 42.5 Level portland cement or Portland cement, the ratio of mud=1.0~1.5, injection speed is:30~70L/min.
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, in diaphragm wall area after the completion of single slurry slip casting Area can be dug by forming diaphragm wall, after the completion of slip casting, extract Grouting Pipe, and single liquid grout hole is blocked with M7.5 cement mortar.
Step 5, notes oar effect detection
Detection drilling is set by the 5% of hole number, 1 detection drilling should pass through test point no less than 3 marks, by detecting drilling to molten Hole note oar effect enters rower and passes through detection, and SPT blow count is hit by 8<100mm is qualified.
Compared with prior art, the present invention is with substantial effect prominent as follows and significantly progressive:
1. the present invention is for the deeper solution cavity in position, it is only necessary to prospecting hole is set in diaphragm wall periphery, whole without detecting The specific size of solution cavity, does not cause the potential safety hazard of landslide because arranging excessive exploration hole.
2. the present invention only needs to be in the milk in diaphragm wall location-appropriate expanded scope, without being evacuated to whole solution cavity And grout filling processing, with short time limit, difficulty is small, cost is low, effect is good the features such as.
Brief description of the drawings
Fig. 1 CAVE DETECTIONs hole and injected hole horizontal layout schematic diagram.
Embodiment
With specific embodiment, the invention will be further described below:
With reference to Fig. 1, the construction method that limestone cave cell wall is closed in a kind of construction of diaphragm wall comprises the following steps.
Step one, solution cavity condition survey
Set prospecting hole 1 in the axis of diaphragm wall 10 and periphery using boring method, determine the distributing position of limestone cave with it is big It is small, judge the groundwater environment and watery residing for solution cavity.
Step 2, sets grout hole
Single liquid grout hole 2 is set by interval of 2m in the nearly position both sides of diaphragm wall 10, some single liquid grout holes 2 surround single liquid grouting Circle;Single liquid grouting circle outside sets two-shot grouting hole 3 by interval of 2m, and some two-shot grouting holes 3 surround two-shot grouting circle;Biliquid Grouting circle is separated by 2m with single liquid grouting circle, as shown in Figure 1.
Step 3, toward the interior perfusion two fluid grouting of solution cavity
Toward the insertion of two-shot grouting hole 3 Grouting Pipe of two-shot grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging.
Two fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the two fluid grouting is cement:Water:Waterglass with 10: 14:3 quality is than mixed serum, and cement is using 42.5 grades of Portland cements, modulus of water glass m=2.4~3.2 (Concentration Be=30~40), injection speed is:30~70L/min.
Grouting pressure is controlled in 0.2~0.5MPa, and each hole slip casting time determines according to pressure size, if grouting pressure 0.3MPa is not reached always, then each grouting amount in each hole must not exceed 30m3, slip casting be not up to 0.3MPa require interval 24h after Continue slip casting, so repeatedly untill slip casting reaches whole hole condition.If grouting pressure reaches 0.3MPa and on the rise, Then continue slip casting, when grouting pressure reaches 0.5MPa final grouting pressure, continue more than slip casting 10min, then can whole hole.
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, only just enters after the completion of each group of slip casting The slip casting operation of next group of row, can form one of curtain wall, be enclosed in solution cavity and cover continuous curtain wall area after the completion of dual slurry slip casting, note After the completion of slurry, Grouting Pipe is extracted, two-shot grouting hole 3 is blocked with M7.5 cement mortar.
Step 4, toward the interior perfusion single fluid grouting of solution cavity
Toward single liquid grout hole 2 insertion Grouting Pipe of list liquid grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging.
Single fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the single fluid grouting is cement mortar, and cement is used 42.5 grades of Portland cements, the ratio of mud=1.0~1.5, injection speed is:30~70L/min:
Grouting pressure control method irrigates two fluid grouting with step 3.
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, under being carried out again after the completion of each group of slip casting One group of slip casting operation, area can be dug by forming diaphragm wall in diaphragm wall area after the completion of single slurry slip casting, after the completion of slip casting, extract slip casting Pipe, single liquid grout hole is blocked with M7.5 cement mortar.
Step 5, notes oar effect detection
Detection drilling is set by the 5% of hole number, 1 detection drilling should pass through test point no less than 3 marks, by detecting drilling to molten Hole note oar effect enters rower and passes through detection, and SPT blow count is hit by 8<100mm is qualified.

Claims (1)

1. the construction method that limestone cave cell wall is closed in a kind of construction of diaphragm wall, it is characterised in that including following step Suddenly:
Step one, solution cavity condition survey
Prospecting hole is set in diaphragm wall axis and periphery using boring method, the distributing position and size of limestone cave is determined, sentences Groundwater environment and watery residing for disconnected solution cavity;
Step 2, sets grout hole
Single liquid grout hole is set by interval of 2~3m in nearly continuous wall displacement both sides, some single liquid grout holes surround single liquid grouting Circle;Single liquid grouting circle outside sets two-shot grouting hole by interval of 2~3m, and some two-shot grouting holes surround two-shot grouting circle;It is double Liquid grouting circle is separated by 2~2.5m with single liquid grouting circle;
Step 3, toward the interior perfusion two fluid grouting of solution cavity
Toward the two-shot grouting hole insertion Grouting Pipe of two-shot grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging;
Two fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the two fluid grouting is cement:Water:Waterglass is with 10: 10 ~15:2~4 quality uses 42.5 grades of portland cements or Portland cement, waterglass mould than mixed serum, cement Number m=2.4~3.2(Concentration Be=30~40), injection speed is:30~70L/min;
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, and one act can be formed after the completion of dual slurry slip casting Wall, encloses in solution cavity and covers continuous curtain wall area, after the completion of slip casting, extracts Grouting Pipe, is filled with M7.5 cement mortar closure biliquid Starch hole;
Step 4, toward the interior perfusion single fluid grouting of solution cavity
Toward single liquid grout hole insertion Grouting Pipe of list liquid grouting circle, Grouting Pipe, which is located at solution cavity section, has distribution injected hole, Grouting Pipe End blocking closure, injected hole adhesive plaster temporary plugging;
Single fluid grouting is irrigated toward solution cavity by Grouting Pipe with grouting pump, the single fluid grouting is cement mortar, and cement uses 42.5 Level portland cement or Portland cement, the ratio of mud=1.0~1.5, injection speed is:30~70L/min;
Grouting mode first notes odd number hole using note method is jumped, then notes even hole, is formed after the completion of single slurry slip casting in diaphragm wall area Diaphragm wall can dig area, after the completion of slip casting, extract Grouting Pipe, and single liquid grout hole is blocked with M7.5 cement mortar;
Step 5, notes oar effect detection
Detection drilling is set by the 5% of hole number, 1 detection drilling should pass through test point no less than 3 marks, by detecting drilling to molten Hole note oar effect enters rower and passes through detection, and SPT blow count is hit by 8<100mm is qualified.
CN201710602537.9A 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall Pending CN107227740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710602537.9A CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710602537.9A CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Publications (1)

Publication Number Publication Date
CN107227740A true CN107227740A (en) 2017-10-03

Family

ID=59956128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710602537.9A Pending CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Country Status (1)

Country Link
CN (1) CN107227740A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
CN112664193A (en) * 2021-01-12 2021-04-16 北京天地华泰矿业管理股份有限公司 Coal mining method under high-voltage transmission line
WO2021248872A1 (en) * 2020-06-11 2021-12-16 中铁一局集团第二工程有限公司 Method for determining safe thickness of side wall in karst area of foundation pit, and grouting device
CN115419047A (en) * 2022-09-13 2022-12-02 中铁二十局集团南方工程有限公司 Karst cave grouting process

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
US20160169435A1 (en) * 2015-02-09 2016-06-16 SAFEKEY Engineering Technology(Zhengzhou), Ltd. Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
US20160169435A1 (en) * 2015-02-09 2016-06-16 SAFEKEY Engineering Technology(Zhengzhou), Ltd. Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜普;: "岩溶发育地区控制范围溶(土)洞处理施工技术研究", 建材与装饰, vol. 1, no. 20, pages 245 - 247 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
WO2021248872A1 (en) * 2020-06-11 2021-12-16 中铁一局集团第二工程有限公司 Method for determining safe thickness of side wall in karst area of foundation pit, and grouting device
CN112664193A (en) * 2021-01-12 2021-04-16 北京天地华泰矿业管理股份有限公司 Coal mining method under high-voltage transmission line
CN115419047A (en) * 2022-09-13 2022-12-02 中铁二十局集团南方工程有限公司 Karst cave grouting process

Similar Documents

Publication Publication Date Title
CN102705005B (en) Technology for plugging water bursting in mine by directional diversion grouting
CN111119940B (en) Grouting construction treatment method
CN204112308U (en) A kind of simple and easy sleeve valve grouting device based on bowlder stone, Thief zone coefficient stratum
CN107227740A (en) The construction method that limestone cave cell wall is closed in construction of diaphragm wall
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN110130936B (en) Construction method for sudden encountering untreated karst cave or crack in shield tunneling process
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN103437339A (en) Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN103835729A (en) Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN102660952B (en) Controllable clay paste slurry grouting technique
CN108166483A (en) Bored pile construction method
CN110469332B (en) Advanced support consolidation method for tunnel penetrating through debris flow accumulation body
CN106837382B (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN103321233B (en) The preparation method of groundwater resources retracting device in landslide deep layer draining and sliding mass
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN108756893B (en) A kind of city shallow tunnel vault soil stabilization method
CN105804107A (en) High-pressure-jetting and anti-seepage treatment method for triple tube of joint of underground diaphragm wall
CN104790982B (en) A kind of bored tunnel superdeep holes grouting sleeve shell material
CN108442378A (en) A kind of diversion tunnel reinforced concrete lining layer section consolidation grouting engineering method
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN102912789A (en) Mechanical hole forming technology applied to karst landform
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN110241837A (en) A kind of construction method for preventing basement bottom board from cracking under high artesian geological conditions
CN106638606B (en) A kind of quick grouting method of deep covering layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination