CN107227740A - The construction method that limestone cave cell wall is closed in construction of diaphragm wall - Google Patents

The construction method that limestone cave cell wall is closed in construction of diaphragm wall Download PDF

Info

Publication number
CN107227740A
CN107227740A CN201710602537.9A CN201710602537A CN107227740A CN 107227740 A CN107227740 A CN 107227740A CN 201710602537 A CN201710602537 A CN 201710602537A CN 107227740 A CN107227740 A CN 107227740A
Authority
CN
China
Prior art keywords
grouting
liquid
holes
double
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710602537.9A
Other languages
Chinese (zh)
Inventor
谢志杰
张润德
唐武兴
黄茂兴
蔡凯祥
罗海腾
梁何龙
谢宝如
萧敏权
王殷杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuan Tian Engineering Co Ltd Of Guangdong Province
Guangdong Yuantian Engineering Co Ltd
Original Assignee
Yuan Tian Engineering Co Ltd Of Guangdong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuan Tian Engineering Co Ltd Of Guangdong Province filed Critical Yuan Tian Engineering Co Ltd Of Guangdong Province
Priority to CN201710602537.9A priority Critical patent/CN107227740A/en
Publication of CN107227740A publication Critical patent/CN107227740A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/24Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing alkyl, ammonium or metal silicates; containing silica sols
    • C04B28/26Silicates of the alkali metals
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/70Grouts, e.g. injection mixtures for cables for prestressed concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention proposes the construction method that limestone cave cell wall is closed in a kind of construction of diaphragm wall, and it includes step:(One)Solution cavity condition survey;(Two)Set grout hole:Single liquid grout hole is set at nearly continuous wall displacement both sides interval;Two-shot grouting hole is set in single liquid grout hole outside spacers;(Three)By two-shot grouting hole toward irrigating two fluid grouting in solution cavity:The two fluid grouting is cement:Water:Enclosed in waterglass mixed serum, solution cavity and cover continuous curtain wall area;(Four)By double single liquid grout holes toward irrigating single fluid grouting in solution cavity:The single fluid grouting is cement mortar, and area can be dug by forming diaphragm wall in diaphragm wall area;(Five)Note oar effect detection.The present invention is for the deeper solution cavity in position, it is only necessary to prospecting hole is set in diaphragm wall periphery, the potential safety hazard of landslide is not caused because arranging excessive exploration hole;The present invention only need to diaphragm wall location-appropriate expanded scope be in the milk, without whole solution cavity is evacuated and grout filling handle, with short time limit, difficulty is small, cost is low, effect is good the features such as.

Description

地下连续墙施工中石灰岩溶洞槽壁封闭的施工方法Construction method of limestone karst cave wall closure in construction of underground diaphragm wall

技术领域technical field

本发明涉及一种建筑工程技术领域的施工方法,具体涉及一种岩溶地层地下连续墙槽壁封闭的施工方法。The invention relates to a construction method in the technical field of construction engineering, in particular to a construction method for sealing the groove wall of an underground diaphragm wall in a karst formation.

背景技术Background technique

一般的地下连墙施工过程中前期多采用分段挖槽,然后在挖好的槽段内插入钢筋笼并灌注混凝土,在分段挖槽过程中,如遇石灰岩溶洞则要先对溶洞进行填充处理,目前公认较好的溶洞处理工艺方法是首先为探测溶洞(长*宽*高)位置,然后采取向溶洞内抛填块石、回填素混凝土、压力液浆等方法。这种溶洞处理方法需要布置很多地质探测孔探明溶洞具体大小,探测孔扰动溶洞多发生塌方安全隐患大,耗时过长,费用高、工期长、施工难度大、工效低,对深度较深的溶洞处理带来很大困难。In the general construction process of underground connecting walls, segmental excavation is often used in the early stage, and then steel cages are inserted into the excavated slots and concrete is poured. In the process of segmental excavation, if limestone caves are encountered, the caves must be filled first. At present, it is recognized that the better treatment method of karst caves is to first detect the position of karst caves (length*width*height), and then adopt methods such as throwing and filling blocks into the karst caves, backfilling plain concrete, and pressure slurry. This method of karst cave treatment needs to arrange many geological detection holes to find out the specific size of the karst caves. The detection holes disturb the karst caves and often cause landslides. It is very difficult to deal with the caves.

发明内容Contents of the invention

本发明的目的是提出一种地下连续墙施工中石灰岩溶洞槽壁封闭的施工方法,其只在连续墙位置局部进行槽壁封闭,具有施工方便、快捷、高效及节约成本的特点。The object of the present invention is to propose a construction method for sealing the groove wall of limestone karst cave in the construction of underground diaphragm wall, which only partially seals the groove wall at the position of the diaphragm wall, and has the characteristics of convenient, fast, efficient and cost-saving construction.

本发明的目的可通过如下技术方案来实现:The purpose of the present invention can be achieved through the following technical solutions:

一种地下连续墙施工中石灰岩溶洞槽壁封闭的施工方法,包括如下步骤。The invention discloses a construction method for sealing the groove wall of a limestone karst cave in the construction of an underground diaphragm wall, comprising the following steps.

步骤一,溶洞情况调查Step 1: Investigation of cave conditions

利用钻孔法在连续墙轴线和外围打设勘察孔,确定石灰岩溶洞的分布位置与大小,判断溶洞所处的地下水环境及富水性。Use the drilling method to drill survey holes on the axis and periphery of the diaphragm wall to determine the distribution position and size of the limestone caves, and judge the groundwater environment and water-richness of the caves.

步骤二,打设灌浆孔Step 2: Drill the grouting holes

在近连续墙位置两侧以2~3m为间隔打设单液灌浆孔,若干单液灌浆孔围成单液灌浆圈;单液灌浆圈外侧以2~3m为间隔打设双液灌浆孔,若干双液灌浆孔围成双液灌浆圈;双液灌浆圈与单液灌浆圈相隔2~2.5m。Set single-liquid grouting holes at intervals of 2-3m on both sides of the near continuous wall, and several single-liquid grouting holes form a single-liquid grouting circle; set double-liquid grouting holes at intervals of 2-3m outside the single-liquid grouting circle, A number of double-liquid grouting holes are surrounded to form a double-liquid grouting circle; the distance between the double-liquid grouting circle and the single-liquid grouting circle is 2-2.5m.

步骤三,往溶洞内灌注双液注浆Step 3: Pour double-liquid grouting into the cave

往双液灌浆圈的双液灌浆孔插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵;Insert the grouting pipe into the double-liquid grouting hole of the double-liquid grouting ring. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape;

用注浆泵通过注浆管往溶洞灌注双液注浆,所述双液注浆是水泥:水:水玻璃以10: 10~15: 2~4的质量比混合浆液,水泥采用42.5级硅酸盐水泥或普通硅酸盐水泥,水玻璃模数m=2.4~3.2(浓度Be=30~40),注浆速度为:30~70L/min。Use a grouting pump to pour double-liquid grouting into the cave through the grouting pipe. The double-liquid grouting is cement: water: water glass with a mass ratio of 10: 10-15: 2-4. The cement uses 42.5 grade silicon Salt cement or ordinary Portland cement, water glass modulus m=2.4~3.2 (concentration Be=30~40), grouting speed: 30~70L/min.

注浆方式采用跳注法,即先注奇数孔,再注偶数孔,双液浆注浆完成后会形成一道幕墙,在溶洞内围蔽出连续幕墙区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵双液灌浆孔。The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. After the double-liquid grouting is completed, a curtain wall will be formed, and a continuous curtain wall area will be enclosed in the cave. After the grouting is completed, pull out the grouting Pipe, use M7.5 cement mortar to seal the double-liquid grouting hole.

步骤四,往溶洞内灌注单液注浆Step 4, pour single-liquid grouting into the cave

往单液灌浆圈的单液灌浆孔插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵;Insert the grouting pipe into the single-liquid grouting hole of the single-liquid grouting ring. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape;

用注浆泵通过注浆管往溶洞灌注单液注浆,所述单液注浆即是水泥浆,水泥采用42.5级硅酸盐水泥或普通硅酸盐水泥,水灰比=1.0~1.5,注浆速度为:30~70L/min。Use a grouting pump to pour single-liquid grouting into the cave through the grouting pipe. The single-liquid grouting is cement slurry. The cement is 42.5 grade Portland cement or ordinary Portland cement, and the water-cement ratio is 1.0-1.5. The grouting speed is: 30~70L/min.

注浆方式采用跳注法,即先注奇数孔,再注偶数孔,单液浆注浆完成后在连续墙区形成连续墙可挖区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵单液灌浆孔。The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. After the single-liquid grouting is completed, the diaphragm wall can be excavated in the diaphragm wall area. After the grouting is completed, pull out the grouting pipe and use M7 .5 cement mortar to seal the single liquid grouting hole.

步骤五,注桨效果检测Step 5, check the effect of paddle injection

按钻孔数的5%设检测钻孔,1个检测钻孔应不少于3个标贯检测点,通过检测钻孔对溶洞注桨效果进行标贯检测,标贯击数按8击<100mm为合格。According to 5% of the number of drilled holes, set the inspection drill holes. One inspection drill hole should have no less than 3 standard penetration inspection points. Through the inspection drill holes, the standard penetration inspection of the grouting effect in the karst cave is carried out. The number of standard penetration strokes is 8 strokes< 100mm is qualified.

与现有技术相比,本发明具有如下突出的实质性效果和显著的进步:Compared with the prior art, the present invention has the following prominent substantive effects and remarkable progress:

1. 本发明针对位置较深的溶洞,只需要在连续墙外围打设勘察孔,而不需要探测整个溶洞的具体尺寸,不因布置过多探测孔而引起塌方的安全隐患。1. For deep karst caves, the present invention only needs to drill survey holes on the periphery of the diaphragm wall, without detecting the specific size of the entire karst cave, and does not cause potential safety hazards of landslides due to the arrangement of too many detection holes.

2. 本发明只需要在连续墙位置适当扩大范围灌浆,而不需要对整个溶洞作抽空及灌浆填充处理,具有工期短、难度小、成本低、效果好等特点。2. The present invention only needs to appropriately expand the scope of grouting at the position of the diaphragm wall, and does not need to evacuate and fill the entire cave with grouting. It has the characteristics of short construction period, low difficulty, low cost, and good effect.

附图说明Description of drawings

图1 溶洞探测孔和注浆孔平面布置示意图。Fig. 1 Schematic diagram of the plane layout of detection holes and grouting holes in the cave.

具体实施方式detailed description

下面用具体实施例对本发明作进一步说明:The present invention will be further described below with specific embodiment:

参考图1,一种地下连续墙施工中石灰岩溶洞槽壁封闭的施工方法,包括如下步骤。With reference to Fig. 1, a kind of construction method of limestone karst cave groove wall closure in the construction of underground diaphragm wall, comprises the following steps.

步骤一,溶洞情况调查Step 1: Investigation of cave conditions

利用钻孔法在连续墙10的轴线和外围打设勘察孔1,确定石灰岩溶洞的分布位置与大小,判断溶洞所处的地下水环境及富水性。Drill survey holes 1 on the axis and periphery of the diaphragm wall 10 by using the drilling method to determine the distribution position and size of the limestone karst caves, and judge the groundwater environment and water-richness of the karst caves.

步骤二,打设灌浆孔Step 2: Drill the grouting holes

在近连续墙10位置两侧以2m为间隔打设单液灌浆孔2,若干单液灌浆孔2围成单液灌浆圈;单液灌浆圈外侧以2m为间隔打设双液灌浆孔3,若干双液灌浆孔3围成双液灌浆圈;双液灌浆圈与单液灌浆圈相隔2m,如图1所示。On both sides of the near continuous wall 10, single-liquid grouting holes 2 are drilled at intervals of 2m, and several single-liquid grouting holes 2 form a single-liquid grouting circle; the outer side of the single-liquid grouting circle is drilled with double-liquid grouting holes 3 at intervals of 2m. A number of double-liquid grouting holes 3 are surrounded to form a double-liquid grouting circle; the double-liquid grouting circle is separated from the single-liquid grouting circle by 2m, as shown in Figure 1.

步骤三,往溶洞内灌注双液注浆Step 3: Pour double-liquid grouting into the cave

往双液灌浆圈的双液灌浆孔3插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵。Insert the grouting pipe into the double-liquid grouting hole 3 of the double-liquid grouting circle. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape.

用注浆泵通过注浆管往溶洞灌注双液注浆,所述双液注浆是水泥:水:水玻璃以10: 14: 3的质量比混合浆液,水泥采用42.5级普通硅酸盐水泥,水玻璃模数m=2.4~3.2(浓度Be=30~40),注浆速度为:30~70L/min。 Use a grouting pump to pour double-liquid grouting into the cave through the grouting pipe. The double-liquid grouting is cement: water: water glass mixed with a mass ratio of 10: 14: 3. The cement uses 42.5 grade ordinary Portland cement , water glass modulus m=2.4~3.2 (concentration Be=30~40), grouting speed: 30~70L/min.

注浆压力控制在0.2~0.5MPa,每个孔注浆时间根据压力大小决定,如果注浆压力一直达不到0.3MPa,则每个孔每次注浆量不得超过30m3,注浆未达到0.3MPa要求间隔24h后继续注浆,如此反复直至注浆达到终孔条件为止。如果注浆压力达到0.3MPa并有上升趋势,则继续注浆,当注浆压力达到0.5MPa的注浆终压时,继续注浆10min以上,则可终孔。The grouting pressure is controlled at 0.2-0.5MPa, and the grouting time for each hole is determined according to the pressure. If the grouting pressure does not reach 0.3MPa, the amount of grouting for each hole shall not exceed 30m 3 . 0.3MPa requires continuous grouting after an interval of 24 hours, and so on until the grouting reaches the final hole condition. If the grouting pressure reaches 0.3MPa and has an upward trend, continue grouting. When the grouting pressure reaches the final grouting pressure of 0.5MPa, continue grouting for more than 10 minutes, and the hole can be finalized.

注浆方式采用跳注法,即先注奇数孔,再注偶数孔,只有在每一组注浆完成后才进行下一组的注浆作业,双液浆注浆完成后会形成一道幕墙,在溶洞内围蔽出连续幕墙区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵双液灌浆孔3。The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. Only after each group of grouting is completed, the next group of grouting operations will be carried out. After the double-liquid grouting is completed, a curtain wall will be formed. Enclose the continuous curtain wall area in the cave. After the grouting is completed, pull out the grouting pipe, and seal the double-liquid grouting hole 3 with M7.5 cement mortar.

步骤四,往溶洞内灌注单液注浆Step 4, pour single-liquid grouting into the cave

往单液灌浆圈的单液灌浆孔2插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵。Insert the grouting pipe into the single-liquid grouting hole 2 of the single-liquid grouting ring. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape.

用注浆泵通过注浆管往溶洞灌注单液注浆,所述单液注浆即是水泥浆,水泥采用42.5级普通硅酸盐水泥,水灰比=1.0~1.5,注浆速度为:30~70L/min:Use a grouting pump to pour single-liquid grouting into the cave through the grouting pipe. The single-liquid grouting is the cement slurry. The cement is made of 42.5 grade ordinary Portland cement, the water-cement ratio=1.0-1.5, and the grouting speed is: 30~70L/min:

注浆压力控制方法同步骤三灌注双液注浆。The grouting pressure control method is the same as that of step three for double-fluid grouting.

注浆方式采用跳注法,即先注奇数孔,再注偶数孔,在每一组注浆完成后再进行下一组的注浆作业,单液浆注浆完成后在连续墙区形成连续墙可挖区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵单液灌浆孔。The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. After each group of grouting is completed, the next group of grouting operations is performed. After the single-liquid grouting is completed, a continuous wall is formed in the continuous wall area. In the excavable area of the wall, after the grouting is completed, pull out the grouting pipe, and seal the single-liquid grouting hole with M7.5 cement mortar.

步骤五,注桨效果检测Step 5, check the effect of paddle injection

按钻孔数的5%设检测钻孔,1个检测钻孔应不少于3个标贯检测点,通过检测钻孔对溶洞注桨效果进行标贯检测,标贯击数按8击<100mm为合格。According to 5% of the number of drilled holes, set the inspection drill holes. One inspection drill hole should have no less than 3 standard penetration inspection points. Through the inspection drill holes, the standard penetration inspection of the grouting effect in the karst cave is carried out. The number of standard penetration strokes is 8 strokes< 100mm is qualified.

Claims (1)

1.一种地下连续墙施工中石灰岩溶洞槽壁封闭的施工方法,其特征在于包括如下步骤:1. a construction method of limestone karst cave tank wall sealing in underground diaphragm wall construction, it is characterized in that comprising the steps: 步骤一,溶洞情况调查Step 1: Investigation of cave conditions 利用钻孔法在连续墙轴线和外围打设勘察孔,确定石灰岩溶洞的分布位置与大小,判断溶洞所处的地下水环境及富水性;Use the drilling method to drill reconnaissance holes on the axis and periphery of the diaphragm wall to determine the distribution position and size of the limestone caves, and judge the groundwater environment and water-richness of the caves; 步骤二,打设灌浆孔Step 2: Drill the grouting holes 在近连续墙位置两侧以2~3m为间隔打设单液灌浆孔,若干单液灌浆孔围成单液灌浆圈;单液灌浆圈外侧以2~3m为间隔打设双液灌浆孔,若干双液灌浆孔围成双液灌浆圈;双液灌浆圈与单液灌浆圈相隔2~2.5m;Set single-liquid grouting holes at intervals of 2-3m on both sides of the near continuous wall, and several single-liquid grouting holes form a single-liquid grouting circle; set double-liquid grouting holes at intervals of 2-3m outside the single-liquid grouting circle, A number of double-liquid grouting holes are surrounded to form a double-liquid grouting circle; the distance between the double-liquid grouting circle and the single-liquid grouting circle is 2-2.5m; 步骤三,往溶洞内灌注双液注浆Step 3: Pour double-liquid grouting into the cave 往双液灌浆圈的双液灌浆孔插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵;Insert the grouting pipe into the double-liquid grouting hole of the double-liquid grouting ring. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape; 用注浆泵通过注浆管往溶洞灌注双液注浆,所述双液注浆是水泥:水:水玻璃以10: 10~15: 2~4的质量比混合浆液,水泥采用42.5级硅酸盐水泥或普通硅酸盐水泥,水玻璃模数m=2.4~3.2(浓度Be=30~40),注浆速度为:30~70L/min;Use a grouting pump to pour double-liquid grouting into the cave through the grouting pipe. The double-liquid grouting is cement: water: water glass with a mass ratio of 10: 10-15: 2-4. The cement uses 42.5 grade silicon Salt cement or ordinary Portland cement, water glass modulus m=2.4~3.2 (concentration Be=30~40), grouting speed: 30~70L/min; 注浆方式采用跳注法,即先注奇数孔,再注偶数孔,双液浆注浆完成后会形成一道幕墙,在溶洞内围蔽出连续幕墙区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵双液灌浆孔;The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. After the double-liquid grouting is completed, a curtain wall will be formed, and a continuous curtain wall area will be enclosed in the cave. After the grouting is completed, pull out the grouting Pipe, use M7.5 cement mortar to seal the double-liquid grouting hole; 步骤四,往溶洞内灌注单液注浆Step 4, pour single-liquid grouting into the cave 往单液灌浆圈的单液灌浆孔插入注浆管,注浆管位于溶洞段具有分布注浆孔,注浆管端用堵塞封堵,注浆孔用胶布临时封堵;Insert the grouting pipe into the single-liquid grouting hole of the single-liquid grouting ring. The grouting pipe is located in the cave section and has distributed grouting holes. The end of the grouting pipe is blocked with a plug, and the grouting hole is temporarily blocked with adhesive tape; 用注浆泵通过注浆管往溶洞灌注单液注浆,所述单液注浆即是水泥浆,水泥采用42.5级硅酸盐水泥或普通硅酸盐水泥,水灰比=1.0~1.5,注浆速度为:30~70L/min;Use a grouting pump to pour single-liquid grouting into the cave through the grouting pipe. The single-liquid grouting is cement slurry. The cement is 42.5 grade Portland cement or ordinary Portland cement, and the water-cement ratio is 1.0-1.5. Grouting speed: 30~70L/min; 注浆方式采用跳注法,即先注奇数孔,再注偶数孔,单液浆注浆完成后在连续墙区形成连续墙可挖区,注浆完成后,拔出注浆管,用M7.5号水泥砂浆封堵单液灌浆孔;The grouting method adopts the jump injection method, that is, the odd-numbered holes are injected first, and then the even-numbered holes are injected. After the single-liquid grouting is completed, the diaphragm wall can be excavated in the diaphragm wall area. After the grouting is completed, pull out the grouting pipe and use M7 .5 cement mortar to block the single liquid grouting hole; 步骤五,注桨效果检测Step 5, check the effect of paddle injection 按钻孔数的5%设检测钻孔,1个检测钻孔应不少于3个标贯检测点,通过检测钻孔对溶洞注桨效果进行标贯检测,标贯击数按8击<100mm为合格。According to 5% of the number of drilled holes, set the inspection drill holes. One inspection drill hole should have no less than 3 standard penetration inspection points. Through the inspection drill holes, the standard penetration inspection of the grouting effect in the karst cave is carried out. The number of standard penetration strokes is 8 strokes< 100mm is qualified.
CN201710602537.9A 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall Pending CN107227740A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710602537.9A CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710602537.9A CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Publications (1)

Publication Number Publication Date
CN107227740A true CN107227740A (en) 2017-10-03

Family

ID=59956128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710602537.9A Pending CN107227740A (en) 2017-07-21 2017-07-21 The construction method that limestone cave cell wall is closed in construction of diaphragm wall

Country Status (1)

Country Link
CN (1) CN107227740A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
CN112664193A (en) * 2021-01-12 2021-04-16 北京天地华泰矿业管理股份有限公司 Coal mining method under high-voltage transmission line
WO2021248872A1 (en) * 2020-06-11 2021-12-16 中铁一局集团第二工程有限公司 Method for determining safe thickness of side wall in karst area of foundation pit, and grouting device
CN115419047A (en) * 2022-09-13 2022-12-02 中铁二十局集团南方工程有限公司 Karst cave grouting process

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
US20160169435A1 (en) * 2015-02-09 2016-06-16 SAFEKEY Engineering Technology(Zhengzhou), Ltd. Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103437339A (en) * 2013-07-29 2013-12-11 中铁十六局集团北京轨道交通工程建设有限公司 Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
US20160169435A1 (en) * 2015-02-09 2016-06-16 SAFEKEY Engineering Technology(Zhengzhou), Ltd. Polymer composite grouting method for blocking leaking and sand inrush of underground pipelines

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜普;: "岩溶发育地区控制范围溶(土)洞处理施工技术研究", 建材与装饰, vol. 1, no. 20, pages 245 - 247 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
WO2021248872A1 (en) * 2020-06-11 2021-12-16 中铁一局集团第二工程有限公司 Method for determining safe thickness of side wall in karst area of foundation pit, and grouting device
CN112664193A (en) * 2021-01-12 2021-04-16 北京天地华泰矿业管理股份有限公司 Coal mining method under high-voltage transmission line
CN115419047A (en) * 2022-09-13 2022-12-02 中铁二十局集团南方工程有限公司 Karst cave grouting process

Similar Documents

Publication Publication Date Title
CN105422170B (en) Middle deep goaf grouting reinforcing and processing method under a kind of building foundation
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN103075149B (en) Method and device for quickly determining gas pressure of coal bed in downward superdeep borehole
CN103075148B (en) On to the method for remotely drilling Fast Measurement coal-bed gas pressure and device thereof
CN105298518B (en) A kind of profound cavern bridging of hidden-type blocks the administering method of water burst
CN105887886B (en) A kind of strong karsts developing area stratum Curtain Grouting Construction method
CN104099943B (en) Diaphram wall and discarded underground civil defense engineering intersection processing method
CN105696550B (en) A kind of three axes agitating pile construction method of additional reinforcement continuous wall trench underground
CN107761753A (en) A kind of foundation ditch water burst rapid rescue slip casting method for blocking
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN103437339A (en) Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN107227740A (en) The construction method that limestone cave cell wall is closed in construction of diaphragm wall
CN209636826U (en) Water-stop structure of foundation pit in water-rich sand and gravel stratum
CN107339108A (en) The layer of sand location subway pipe shed construction method of underground water enrichment
CN109322699A (en) An underground pollution isolation and plugging technology
CN103195477A (en) Gravity drainage system for underground roadway high-pressure water inrush
CN106567714A (en) Grouting material for underground mine roadway and grouting water control method
CN103147741B (en) Coal bed roadside pressure relief zone width measuring method based on drill hole gas leakage
CN108915705B (en) A kind of baffle grouting construction method blocked for shield export &amp; import leak
CN202644538U (en) A grouting device used for a water-rich quicksand stratum
CN106837411A (en) The arrangement and method of a kind of buried shield tunnel filling and injecting slurry
CN108005662A (en) A kind of processing method of underground water seal cave depot bank area geology crushed zone
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN114108609A (en) A kind of construction technology and method for multi-level subsection precise filling and filling of deep piles in goaf
CN113266417A (en) Construction method of karst cave pile foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171003