CN102912789A - Mechanical hole forming technology applied to karst landform - Google Patents

Mechanical hole forming technology applied to karst landform Download PDF

Info

Publication number
CN102912789A
CN102912789A CN2012104104477A CN201210410447A CN102912789A CN 102912789 A CN102912789 A CN 102912789A CN 2012104104477 A CN2012104104477 A CN 2012104104477A CN 201210410447 A CN201210410447 A CN 201210410447A CN 102912789 A CN102912789 A CN 102912789A
Authority
CN
China
Prior art keywords
hole
karst landform
mechanical
holes
mechanical hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012104104477A
Other languages
Chinese (zh)
Other versions
CN102912789B (en
Inventor
郭腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongse No12 Metallurgy Construction Co Ltd
Original Assignee
Zhongse No12 Metallurgy Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongse No12 Metallurgy Construction Co Ltd filed Critical Zhongse No12 Metallurgy Construction Co Ltd
Priority to CN201210410447.7A priority Critical patent/CN102912789B/en
Publication of CN102912789A publication Critical patent/CN102912789A/en
Application granted granted Critical
Publication of CN102912789B publication Critical patent/CN102912789B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a mechanical hole forming technology applied to karst landform. The technology comprises the following steps of: laying off and positioning; digging a mud pit; burying a pile casing; arranging a drill in place and making mud; forming holes by using an impact machine, wherein when a karst cave is greater than or equal to 3m in depth during construction, a steel pile casing dado is arranged; pumping out sediment and supplementing mud; checking the sediment; clearing off the holes by using a home-made hole cleaning device; checking the holes; arranging a steel reinforcement cage; arranging guide pipes; and pouring underwater concrete. By the mechanical hole forming technology, the probability of occurrence of hole collapse, overfilling of concrete and the like can be lowered, karst cave areas can be effectively protected, the effect of saving concrete is achieved and the cost is further reduced; moreover, by the mechanical hole forming technology, a unit in charge of construction can be effectively helped to clear off sediment from the bottoms of holes, hole piles in collapsed holes can be cleared quickly, the specific depth of a hole pipe can be measured by construction workers.

Description

Mechanical hole building technology under the karst landform
Technical field
The present invention relates to the mechanical hole building technology under a kind of special geology, particularly relate to the mechanical hole building technology under a kind of karst landform that is applied to complicated geology, many solution cavities.
Background technology
For the processing under the karst landform, the most of mud off method that adopts of China is constructed now.But for the complicated especially zone of the more zone of solution cavity, geological conditions, adopt mud off still can't play good support action, will produce the phenomenons such as the hole of collapsing, the super filling of concrete; And, in the actual machine pore forming process, if the hole number of times that collapses is more, and after causing sand setting, mud especially behind the hole of collapsing, can't measure concrete hole depth, in the prior art, with traditional mud flush, sand setting etc. thoroughly can not be cleared, can't measure the concrete hole stake degree of depth.
Summary of the invention
The object of the invention is to overcome the defective that the mechanical hole building technology exists under the existing karst landform, and provide mechanical hole building technology under a kind of new karst landform, technical problem to be solved is for the complicated especially zone of the more zone of solution cavity under the karst landform, geological conditions, improve the defective that the mud off method can't play good support action, reduce the probability that the phenomenons such as the hole of collapsing, the super filling of concrete occur; And the cleaning that effectively helps unit in charge of construction to solve hole bed mud sand, accelerate the clear hole speed to hole, the hole stake of collapsing, and can make the constructor measure the concrete hole stake degree of depth.
The object of the invention to solve the technical problems realizes by the following technical solutions.According to mechanical hole building technology under the karst landform of the present invention's proposition, it comprises following processing step: setting-out; The stock tank of dredging; Bury casing underground; Rig is in place, mud is made; The impact machine pore-forming; Take out slag and mend slurry; Check sediment; Clear hole; Verify; Lay reinforcing cage; Downcomer; Pouring underwater concrete; Wherein: carry out clearly hole with homemade hole cleaning device; And during impact holing, when the solution cavity degree of depth that runs in the work progress 〉=3 meters, steel is set protects a barrel retaining wall.
The object of the invention to solve the technical problems also can be applied to the following technical measures to achieve further.
Mechanical hole building technology under the aforesaid karst landform, wherein when impact holing, this solution cavity degree of depth during less than 3 meters, is taked steel to protect a barrel retaining wall method and is carried out bore operation apart from ground less than 10 meters and solution cavity.
Mechanical hole building technology under the aforesaid karst landform, wherein said hole cleaning device is comprised of movable hinge and conically shaped.
Mechanical hole building technology under the aforesaid karst landform, wherein this movable hinge is comprised of hinge and movable axis, at the affixed movable axis that is provided with of the big end surface of this tapered barrel, hinge is installed above the movable axis.
By technique scheme, the mechanical hole building technology has following advantages and beneficial effect at least under the karst landform of the present invention:
1, for large-scale solution cavity zone, the way that adopts steel to protect barrel retaining wall can reduce the probability that the phenomenons such as the hole of collapsing, the super filling of concrete occur, and can effectively protect the solution cavity zone, plays and saves concrete effect, thereby reach the purpose of saving cost.
2, utilize the device of impurity in this removing small holes, can effectively accelerate the husky cleaning of hole bed mud, the probability that the hole phenomenon that prevents from collapsing occurs guarantees the hole quality of pile and effectively builds, and can make the constructor measure the concrete hole stake degree of depth.
Above-mentioned explanation only is the general introduction of technical solution of the present invention, for can clearer understanding technological means of the present invention, and can be implemented according to the content of manual, and for above and other purpose of the present invention, feature and advantage can be become apparent, below especially exemplified by preferred embodiment, and the cooperation accompanying drawing, be described in detail as follows.
Description of drawings
Fig. 1 is mechanical hole building technical matters flow chart under the karst landform of the present invention.
Fig. 2 is that the mechanical hole building technology is implemented illustration under the karst landform of the present invention.
Fig. 3 is the structural representation of the device of impurity in the removing small holes of mechanical hole building technology under the karst landform of the present invention.
Fig. 4 is the application implementation illustration of the device of impurity in the removing small holes of mechanical hole building technology under the karst landform of the present invention.
Fig. 5 is the Another Application enforcement illustration that the present invention removes the device of impurity in the small holes.
The specific embodiment
Reach technological means and the effect that predetermined goal of the invention is taked for further setting forth the present invention, below in conjunction with accompanying drawing and preferred embodiment, to its specific embodiment of mechanical hole building technology, step, feature and effect thereof under the karst landform of foundation the present invention proposition, be described in detail as follows.
As shown in Figure 1, be mechanical hole building technical matters flow chart under the karst landform of the present invention, setting-out, the stock tank of dredging is buried casing underground, rig is in place, mud is made, and impact holing is taken out slag and mended slurry, checks sediment, clear hole, verify is laid reinforcing cage, downcomer, pouring underwater concrete.Wherein, this clear hole process can adopt the device of impurity in the self-control hole cleaning device removing small holes to carry out clearly hole.As shown in Figure 3, be the structural representation of the device of impurity in the removing small holes of mechanical hole building technology under the karst landform of the present invention, the device 10 of removing impurity in the small holes is comprised of conically shaped 1 and hinge 2, and this hinge 2 is comprised of movable hinge 3 and movable axis 4.At the affixed movable axis 4 that is provided with of the big end surface of this tapered barrel 1, movable hinge 3 is installed above the movable axis 4.See also Fig. 4, in work progress, the device 10 that to remove impurity in the small holes with the stake machine puts down fast, utilize himself gravity that it is descended in the stake of hole fast, in the time of at the bottom of it arrives the hole stake, because this movable hinge 3 of Water Pressure is opened, at this moment, water at the bottom of this hole stake and silt particle enter in the device 10 of impurity in this removing small holes together, afterwards, and as shown in Figure 5, to remove the device 10 of impurity in the small holes at the uniform velocity mentions with this machine, this movable hinge 3 is subjected to influence of hydraulic pressure and silt particle effect of weight and closes, and pours out the silt particle in the device 10 of impurity in this removing small holes, reaches the clearly effect in hole.
Please consult again Fig. 1, wherein, during impact holing, on the basis of mud off, such as the large-scale solution cavity zone of the solution cavity degree of depth above 3 meters, then divide into the steel casing.For example, in practical operation, ground is surveyed and is reported that being presented at the stake of 40# hole sees middle decomposed rock at 23 meters, satisfy 5 meters bearing stratum requirements below 23 meters, this hole is large-scale solution cavity zone at 10 meters to 18 meters, then at this solution cavity region division steel casing, namely from aperture to 18 meter, as shown in Figure 2.
If surveying on ground has long solution cavity in the report, and in practice of construction, the solution cavity degree of depth≤10 meter and solution cavity apart from ground≤3 meters, and this solution cavity degree of depth 〉=3 meter all can adopt the way of dividing into the steel casing effectively to protect the solution cavity zone, save concrete amount.
If during the impact machine pore-forming, lower deviation large (because drill bit is run into larger petrographic province, during boring the hole up and down with irregular) can't be divided into the steel casing on the position, hole, at this moment divide into the steel casing for more shallow solution cavity position, save concrete purpose to reach.For example, one 14 meters hole stake, it is the solution cavity zone at-4 meters to-11 meters, and boulder is arranged at-9 meters, at this moment the steel casing is divided into from the aperture to-9 meters,-9 meters to-11 places owing to having boulder to exist may to cause inclined to one side stake, sliding pile, therefore this part no longer arranges the steel casing, namely to divide into the steel casing and will divide into to the zone that can divide into from the aperture.
The above, it only is preferred embodiment of the present invention, be not that the present invention is done any pro forma restriction, although the present invention discloses as above with preferred embodiment, yet be not to limit the present invention, any those skilled in the art, within not breaking away from the technical solution of the present invention scope, when the technology contents that can utilize above-mentioned announcement is made a little change or is modified to the equivalent embodiment of equivalent variations, in every case be not break away from the technical solution of the present invention content, any simple modification that foundation technical spirit of the present invention is done above embodiment, equivalent variations and modification all still belong in the scope of technical solution of the present invention.

Claims (4)

1. mechanical hole building technology under the karst landform comprises following processing step:
Setting-out; The stock tank of dredging; Bury casing underground; Rig is in place, mud is made; The impact machine pore-forming; Take out slag and mend slurry; Check sediment; Clear hole; Verify; Lay reinforcing cage; Downcomer; Pouring underwater concrete; It is characterized in that:
Carry out clearly hole with homemade hole cleaning device; And
During impact holing, when the solution cavity degree of depth that runs in the work progress 〉=3 meters, steel is set protects a barrel retaining wall.
2. mechanical hole building technology under the karst landform according to claim 1 is characterized in that when impact holing, and this solution cavity degree of depth during less than 3 meters, is taked steel to protect a barrel retaining wall method and carried out bore operation apart from ground less than 10 meters and solution cavity.
3. mechanical hole building technology under the karst landform according to claim 1 and 2 is characterized in that described hole cleaning device is comprised of movable hinge and conically shaped.
4. mechanical hole building technology under the karst landform according to claim 3 is characterized in that this movable hinge is comprised of hinge and movable axis, at the affixed movable axis that is provided with of the big end surface of this tapered barrel, hinge is installed above the movable axis.
CN201210410447.7A 2012-10-24 2012-10-24 Mechanical hole forming technology applied to karst landform Active CN102912789B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210410447.7A CN102912789B (en) 2012-10-24 2012-10-24 Mechanical hole forming technology applied to karst landform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210410447.7A CN102912789B (en) 2012-10-24 2012-10-24 Mechanical hole forming technology applied to karst landform

Publications (2)

Publication Number Publication Date
CN102912789A true CN102912789A (en) 2013-02-06
CN102912789B CN102912789B (en) 2014-12-10

Family

ID=47611339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210410447.7A Active CN102912789B (en) 2012-10-24 2012-10-24 Mechanical hole forming technology applied to karst landform

Country Status (1)

Country Link
CN (1) CN102912789B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195058A (en) * 2013-04-03 2013-07-10 四川川交路桥有限责任公司 Multi-casing structure capable of facilitating bridge-pile construction in cavern development areas and construction method thereof
CN104141311A (en) * 2014-04-29 2014-11-12 中建四局第五建筑工程有限公司 Mechanical holing method for protecting wall and structure formed with method
CN104947672A (en) * 2015-07-01 2015-09-30 北京天润建设有限公司 Prefabricating tubular pile core clearing device
CN105672309A (en) * 2016-02-22 2016-06-15 北龙建设集团有限公司 Encasing method for hole forming of socketed piles at karst terrain through recoverable extra-long steel pile casings
CN106351575A (en) * 2016-11-07 2017-01-25 赵宽学 Hole-protecting and pile-drilling method
CN112030956A (en) * 2020-07-15 2020-12-04 中交第一航务工程局有限公司 Karst stratum bored pile construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4364441A (en) * 1980-11-12 1982-12-21 States Engineering Corporation Hole cleaning device for augers
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN201605577U (en) * 2009-12-28 2010-10-13 中国核工业华兴建设有限公司 Borehole cleaning device for mechanical-boring cast-in-place pile
CN102094419A (en) * 2011-03-09 2011-06-15 中铁六局集团有限公司 Method for forming drilled pile in foundation with silty sand layer
CN102146672A (en) * 2011-03-15 2011-08-10 中铁六局集团有限公司 Method for constructing pile foundation in karst area
CN102605768A (en) * 2012-03-31 2012-07-25 中建三局建设工程股份有限公司 Bore cleaning device for cast-in-place bored piles

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4364441A (en) * 1980-11-12 1982-12-21 States Engineering Corporation Hole cleaning device for augers
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN201605577U (en) * 2009-12-28 2010-10-13 中国核工业华兴建设有限公司 Borehole cleaning device for mechanical-boring cast-in-place pile
CN102094419A (en) * 2011-03-09 2011-06-15 中铁六局集团有限公司 Method for forming drilled pile in foundation with silty sand layer
CN102146672A (en) * 2011-03-15 2011-08-10 中铁六局集团有限公司 Method for constructing pile foundation in karst area
CN102605768A (en) * 2012-03-31 2012-07-25 中建三局建设工程股份有限公司 Bore cleaning device for cast-in-place bored piles

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103195058A (en) * 2013-04-03 2013-07-10 四川川交路桥有限责任公司 Multi-casing structure capable of facilitating bridge-pile construction in cavern development areas and construction method thereof
CN103195058B (en) * 2013-04-03 2015-08-19 四川川交路桥有限责任公司 Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct
CN104141311A (en) * 2014-04-29 2014-11-12 中建四局第五建筑工程有限公司 Mechanical holing method for protecting wall and structure formed with method
CN104947672A (en) * 2015-07-01 2015-09-30 北京天润建设有限公司 Prefabricating tubular pile core clearing device
CN105672309A (en) * 2016-02-22 2016-06-15 北龙建设集团有限公司 Encasing method for hole forming of socketed piles at karst terrain through recoverable extra-long steel pile casings
CN106351575A (en) * 2016-11-07 2017-01-25 赵宽学 Hole-protecting and pile-drilling method
CN112030956A (en) * 2020-07-15 2020-12-04 中交第一航务工程局有限公司 Karst stratum bored pile construction method

Also Published As

Publication number Publication date
CN102912789B (en) 2014-12-10

Similar Documents

Publication Publication Date Title
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN108560541B (en) Rotary drilling full-casing follow-up rock face drilling construction method
CN102912789B (en) Mechanical hole forming technology applied to karst landform
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN106320333B (en) Combined drainage type water filling pile device and construction method
CN107130592B (en) construction method for long spiral drill and impact drill double-machine composite hole-forming cast-in-place pile
CN104947690A (en) Grooving construction method for embedding underground continuous wall into rock
CN108166483A (en) Bored pile construction method
CN103321233B (en) The preparation method of groundwater resources retracting device in landslide deep layer draining and sliding mass
CN113668527A (en) Construction method for inserting long steel pile casing under rotary digging pile construction of deep rockfill silt stratum
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN212336250U (en) Pipe jacking connection guide row structure
CN207538090U (en) A kind of externally reinforced structure of Urban underground Tunnel
CN105804203A (en) Plugging method of deep-buried large-diameter waste water pipeline
CN203320538U (en) Water resource recycling and deep drainage device for landslides and underground water inside landslides
CN203113361U (en) Deep foundation pit sealing precipitation device
CN205100226U (en) Underground continuous wall goes into rock grooving construction equipment
CN211735404U (en) Anti-over-irrigation system for long spiral bored pile
CN109113054A (en) A kind of reclaimation area complex geological condition cast-in-situ bored pile multimachine combined construction method
CN107975376A (en) Tunneling shield push pipe and vertical duct connection structure and construction method
CN211113598U (en) Karst cave handling system for deep foundation pit pile foundation construction in karst area
CN113481971A (en) Construction method for forming hole of cast-in-place pile under complex geological condition
CN111894103A (en) Pipe jacking connection guide row structure and pipe jacking connection method
CN202970549U (en) Hole cleaning device for mechanical hole forming under karst landform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant