CN107191198A - The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes - Google Patents
The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes Download PDFInfo
- Publication number
- CN107191198A CN107191198A CN201710216531.8A CN201710216531A CN107191198A CN 107191198 A CN107191198 A CN 107191198A CN 201710216531 A CN201710216531 A CN 201710216531A CN 107191198 A CN107191198 A CN 107191198A
- Authority
- CN
- China
- Prior art keywords
- cast
- oriented
- wall
- situ bored
- bored pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 12
- 230000001629 suppression Effects 0.000 title claims abstract description 7
- 238000011065 in-situ storage Methods 0.000 claims abstract description 20
- 238000005266 casting Methods 0.000 claims abstract description 5
- 230000008676 import Effects 0.000 claims abstract description 5
- 230000006835 compression Effects 0.000 claims abstract description 4
- 238000007906 compression Methods 0.000 claims abstract description 4
- 239000007787 solid Substances 0.000 claims description 2
- 239000011435 rock Substances 0.000 description 13
- 238000010276 construction Methods 0.000 description 9
- 239000002689 soil Substances 0.000 description 3
- 238000005553 drilling Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000010410 layer Substances 0.000 description 2
- 230000002265 prevention Effects 0.000 description 2
- 238000010008 shearing Methods 0.000 description 2
- 235000007926 Craterellus fallax Nutrition 0.000 description 1
- 240000007175 Datura inoxia Species 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 210000000481 breast Anatomy 0.000 description 1
- 230000009918 complex formation Effects 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000011229 interlayer Substances 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710216531.8A CN107191198A (en) | 2017-04-05 | 2017-04-05 | The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710216531.8A CN107191198A (en) | 2017-04-05 | 2017-04-05 | The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107191198A true CN107191198A (en) | 2017-09-22 |
Family
ID=59871407
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710216531.8A Pending CN107191198A (en) | 2017-04-05 | 2017-04-05 | The retaining structure and method of a kind of horizontal creep of suppression tunnel light and shade hole intersection slopes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107191198A (en) |
Citations (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH505943A (en) * | 1968-02-28 | 1971-04-15 | Kunz Alfred & Co | Method for producing a tunnel body |
FR2727447A1 (en) * | 1994-11-28 | 1996-05-31 | Matiere Soc Civ De Brevets | Construction of tunnel under embankment in soft soils or areas prone to flooding |
KR100711576B1 (en) * | 2005-11-08 | 2007-04-27 | 삼성물산 주식회사 | Reinforcement structure for entrance of tunnel and construction method thereof |
CN202039859U (en) * | 2011-02-24 | 2011-11-16 | 湖南省交通规划勘察设计院 | Door type composite pipe shed cover arch structure for tunnel portal |
CN102444405A (en) * | 2011-10-19 | 2012-05-09 | 重庆大学 | Anti-slide pile and frame arch combined structure and construction method |
CN202493274U (en) * | 2012-03-23 | 2012-10-17 | 重庆中设工程设计股份有限公司 | Structure of striding large across-section tunnel on existing tunnel through shallow underground excavation |
CN103205957A (en) * | 2013-03-19 | 2013-07-17 | 天津市市政工程设计研究院 | Method of estimation on underlying tunnel and foundation rebound in excavation of foundation pit |
CN203189032U (en) * | 2013-03-28 | 2013-09-11 | 中铁十五局集团有限公司 | Advance support large pipe shed guide wall with pile foundation |
CN103375170A (en) * | 2013-07-26 | 2013-10-30 | 中铁六局集团石家庄铁路建设有限公司 | Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway |
CN203308470U (en) * | 2013-05-28 | 2013-11-27 | 山西省交通科学研究院 | Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section |
CN103967504A (en) * | 2014-05-21 | 2014-08-06 | 中国能源建设集团广东省电力设计研究院 | Supporting structure of tunnel opening of power plant circulating water system and construction method |
CN204000900U (en) * | 2014-07-17 | 2014-12-10 | 陕西路桥集团第一工程有限公司 | A kind of ruggedized construction that is applied to the landslide of unsymmetrial loading tunnel hole |
CN104389628A (en) * | 2014-11-21 | 2015-03-04 | 山西省交通科学研究院 | Landslide section tunnel reinforcing device and reinforcing construction method |
CN204457791U (en) * | 2015-02-04 | 2015-07-08 | 北京市政建设集团有限责任公司 | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station |
CN204609899U (en) * | 2015-05-14 | 2015-09-02 | 贵州省公路工程集团有限公司 | A kind of supporting and protection structure for soft soil layer tunnel |
CN105133625A (en) * | 2015-09-16 | 2015-12-09 | 中南大学 | Reinforced structure of tunnel transversely penetrating through sliding slope and construction method |
CN205189886U (en) * | 2015-12-10 | 2016-04-27 | 中铁二十局集团第二工程有限公司 | Tunnel transverse passage -way changes main cave construction structures |
CN205277434U (en) * | 2016-01-19 | 2016-06-01 | 重庆电讯职业学院 | Tunnel portal pre -reinforcing structure |
CN205422731U (en) * | 2016-03-21 | 2016-08-03 | 长安大学 | Excavation structure of subway shield zone hard rock changeover portion |
CN105839643A (en) * | 2016-05-23 | 2016-08-10 | 浙江省交通规划设计研究院 | Tunnel in-hole construction method adopting foundation pit support |
CN205576940U (en) * | 2016-04-06 | 2016-09-14 | 武汉理工大学 | Compound retaining structure of friction pile that pile bolck is connected entirely |
CN106499413A (en) * | 2016-11-19 | 2017-03-15 | 中铁十二局集团有限公司 | A kind of Shallow-buried section tunnel stratum consolidation construction method |
-
2017
- 2017-04-05 CN CN201710216531.8A patent/CN107191198A/en active Pending
Patent Citations (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CH505943A (en) * | 1968-02-28 | 1971-04-15 | Kunz Alfred & Co | Method for producing a tunnel body |
FR2727447A1 (en) * | 1994-11-28 | 1996-05-31 | Matiere Soc Civ De Brevets | Construction of tunnel under embankment in soft soils or areas prone to flooding |
KR100711576B1 (en) * | 2005-11-08 | 2007-04-27 | 삼성물산 주식회사 | Reinforcement structure for entrance of tunnel and construction method thereof |
CN202039859U (en) * | 2011-02-24 | 2011-11-16 | 湖南省交通规划勘察设计院 | Door type composite pipe shed cover arch structure for tunnel portal |
CN102444405A (en) * | 2011-10-19 | 2012-05-09 | 重庆大学 | Anti-slide pile and frame arch combined structure and construction method |
CN202493274U (en) * | 2012-03-23 | 2012-10-17 | 重庆中设工程设计股份有限公司 | Structure of striding large across-section tunnel on existing tunnel through shallow underground excavation |
CN103205957A (en) * | 2013-03-19 | 2013-07-17 | 天津市市政工程设计研究院 | Method of estimation on underlying tunnel and foundation rebound in excavation of foundation pit |
CN203189032U (en) * | 2013-03-28 | 2013-09-11 | 中铁十五局集团有限公司 | Advance support large pipe shed guide wall with pile foundation |
CN203308470U (en) * | 2013-05-28 | 2013-11-27 | 山西省交通科学研究院 | Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section |
CN103375170A (en) * | 2013-07-26 | 2013-10-30 | 中铁六局集团石家庄铁路建设有限公司 | Underground excavation construction deformation control method for three-hole small clear distance tunnel underpass trunk railway |
CN103967504A (en) * | 2014-05-21 | 2014-08-06 | 中国能源建设集团广东省电力设计研究院 | Supporting structure of tunnel opening of power plant circulating water system and construction method |
CN204000900U (en) * | 2014-07-17 | 2014-12-10 | 陕西路桥集团第一工程有限公司 | A kind of ruggedized construction that is applied to the landslide of unsymmetrial loading tunnel hole |
CN104389628A (en) * | 2014-11-21 | 2015-03-04 | 山西省交通科学研究院 | Landslide section tunnel reinforcing device and reinforcing construction method |
CN204457791U (en) * | 2015-02-04 | 2015-07-08 | 北京市政建设集团有限责任公司 | A kind ofly meet the interim air channel structure that large-diameter shield first passes through subway station |
CN204609899U (en) * | 2015-05-14 | 2015-09-02 | 贵州省公路工程集团有限公司 | A kind of supporting and protection structure for soft soil layer tunnel |
CN105133625A (en) * | 2015-09-16 | 2015-12-09 | 中南大学 | Reinforced structure of tunnel transversely penetrating through sliding slope and construction method |
CN205189886U (en) * | 2015-12-10 | 2016-04-27 | 中铁二十局集团第二工程有限公司 | Tunnel transverse passage -way changes main cave construction structures |
CN205277434U (en) * | 2016-01-19 | 2016-06-01 | 重庆电讯职业学院 | Tunnel portal pre -reinforcing structure |
CN205422731U (en) * | 2016-03-21 | 2016-08-03 | 长安大学 | Excavation structure of subway shield zone hard rock changeover portion |
CN205576940U (en) * | 2016-04-06 | 2016-09-14 | 武汉理工大学 | Compound retaining structure of friction pile that pile bolck is connected entirely |
CN105839643A (en) * | 2016-05-23 | 2016-08-10 | 浙江省交通规划设计研究院 | Tunnel in-hole construction method adopting foundation pit support |
CN106499413A (en) * | 2016-11-19 | 2017-03-15 | 中铁十二局集团有限公司 | A kind of Shallow-buried section tunnel stratum consolidation construction method |
Non-Patent Citations (13)
Title |
---|
丰逍野等: "高铁隧道洞口浅埋段浅层蠕动滑坡体综合治理技术", 《中国港湾建设》 * |
丰逍野等: "高铁隧道洞口浅埋段浅层蠕动滑坡体综合治理技术", 《中国港湾建设》, no. 11, 25 November 2016 (2016-11-25), pages 1 - 4 * |
唐朝松: "客运专线铁路隧道地震区Ⅴ级偏弱围岩病害整治方法研究", 《铁道标准设计》 * |
唐朝松: "客运专线铁路隧道地震区Ⅴ级偏弱围岩病害整治方法研究", 《铁道标准设计》, no. 04, 20 April 2009 (2009-04-20), pages 1 - 5 * |
张民庆等: "宜万线隧道洞口滑坍分析与治理", 《铁道工程学报》 * |
张民庆等: "宜万线隧道洞口滑坍分析与治理", 《铁道工程学报》, no. 02, 15 February 2008 (2008-02-15), pages 1 - 7 * |
袁东: "工布江达隧道洞口滑塌处理方案", 《山西建筑》 * |
袁东: "工布江达隧道洞口滑塌处理方案", 《山西建筑》, no. 07, 1 March 2016 (2016-03-01), pages 1 - 2 * |
陈智强;: "城市连拱隧道下穿挡墙段出洞方案优化与监测分析", 现代隧道技术, vol. 1, no. 03, pages 163 - 169 * |
韩华轩等: "高速铁路隧道洞口工程设计研究", 《石家庄铁道大学学报(自然科学版)》 * |
韩华轩等: "高速铁路隧道洞口工程设计研究", 《石家庄铁道大学学报(自然科学版)》, 30 September 2013 (2013-09-30), pages 1 - 5 * |
黄河清等: "抗滑桩综合支护在某隧道进口治理中的应用", 《山西建筑》 * |
黄河清等: "抗滑桩综合支护在某隧道进口治理中的应用", 《山西建筑》, no. 22, 1 August 2013 (2013-08-01), pages 1 - 2 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103306687B (en) | Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method | |
CN109826667A (en) | The I-shaped checkdam of coal mine underground reservoir | |
CN104847362B (en) | Ground consisting of hard rock construction method across underground digging in subway station greatly | |
CN105839643A (en) | Tunnel in-hole construction method adopting foundation pit support | |
CN108204240A (en) | Newly built tunnels closely on across existing tunnel anti-floating reinforcement system and its reinforcement means | |
CN103967504B (en) | A kind of supporting construction and construction method of electric power plant circulating water system tunnel mouth | |
CN103898916B (en) | Mini stake Composite Braced Retaining Structure and construction method | |
CN106121659B (en) | The narrow-bore tunnel excavation method of major urban arterial highway upper-soft lower-hard ground is worn under one kind | |
CN109630195B (en) | Strong-wall seepage-blocking water retaining dam for coal mine underground reservoir | |
CN103206219A (en) | Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method | |
CN107503257A (en) | One kind is close to mountain high-filled subgrade stabilization and Deformation control structure and construction method | |
CN108487911A (en) | The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition | |
CN105370289B (en) | A kind of existing pipeline overlength Dryopteris sublaetaChing et Hsu method of complex environment | |
CN109098733A (en) | Quick grouting strengthening method of the large cross-section tunnel in fracture belt rock stratum | |
CN109595034B (en) | Checkdam is seeped in the I-shaped strong side resistance of coal mine underground reservoir | |
CN207109475U (en) | It is close to mountain high-filled subgrade stabilization and Deformation control structure | |
CN110043264A (en) | A kind of construction method of jacking prefabricated rectangle shaft structure pattern | |
CN109611103B (en) | Method for reinforcing shield section suspended boulder group | |
CN206174963U (en) | Cross shallow undercut tunnel supporting construction of burying of ground fissure crushed zone | |
CN106988760A (en) | Facility-sliding strata tunnel portal reinforcing construction and construction method | |
CN109578007B (en) | Pass through that high angle is inverse to rush rich water richness sand tomography tunnel excavation and drainage and construction method | |
CN109441456A (en) | A kind of the tunnel structure and its construction method of weakness Facility-sliding strata | |
CN102839980A (en) | Highway tunnel structure and construction method thereof | |
CN108222951A (en) | Pass through fine sand layer tunnel portal weak surrounding rock section constructing method | |
CN110230273A (en) | A kind of safeguard structure of small-sized rockfall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: No. 113 West Street, Nangang District, Harbin City, Heilongjiang Province, 150001 Applicant after: CHINA RAILWAY 22ND CONSTRUCTION BUREAU 1ST ENGINEERING Co.,Ltd. Applicant after: China Railway 22nd Bureau Group Co.,ltd. Applicant after: Lanzhou Jiaotong University Address before: No. 113 West Street, Nangang District, Harbin City, Heilongjiang Province, 150001 Applicant before: HARBIN RAILWAY CONSTRUCTION GROUP CO.,LTD. OF CHINA RAILWAY 22ND CONSTRUCTION BUREAU CO.,LTD. Applicant before: China Railway 22nd Bureau Group Co.,ltd. Applicant before: Lanzhou Jiaotong University |